MW-1 - Synapse Attachment.pdf
PDF · 734 KB · 13 pagesText searchable
Download MW-1 - Synapse Attachment.pdfRead the text of MW-1 - Synapse Attachment.pdf
Page 117 of 276
REGULATORY ASSISTANCE PROJECT (RAP)® ELECTRIC COST ALLOCATION FOR A NEW ERA | 115 Figure 32. Cost of combustion turbine plant in service in 2011 $600 Gross plant cost per kilowatt of capacity Average for year $500 Five-year rolling average $400 $300 $200 $100 $0 1960 1965 1970 1975 1980 1985 1990 1995 Plant in-service year Data source: Federal Energy Regulatory Commission Form 1 database developed more expensive and more efficient designs, • Comparing recent or current net plant (gross plant minus accumulated depreciation) costs for nonpeaking generators including steam injection. with the corresponding net plant costs of contempora- For comparison, coal plants built in this period generally cost from several hundred dollars per kW to more than neous peakers. This comparison is theoretically the most $2,000 per kW; the latest vintage coal plants cost as much appropriate basis for classifying generation rate base, which as $3,000 per kW. Steam plants fired by gas and oil (and not is based on net plant. Unfortunately, net plant is not gener- converted from coal) tend to have a wide range of gross plant ally publicly reported by plant or unit, so most cost analysts costs, from the prices of contemporaneous combustion will have a difficult time implementing this approach. turbines to perhaps twice those costs. Nuclear plants In addition, many utilities have depreciated peakers at a generally have gross plant costs well above $1,000 per kW, faster rate than steam plants, resulting in lower net plant up to $8,000 per kW. Combined cycle plants have usually for a peaker than for a steam plant with the same initial been 20% to 50% more expensive than contemporaneous cost, additions and retirements. This results in a higher combustion turbines.100 percentage of the steam plant costs being classified as energy-related based on net plant than gross plant. It is not The capital costs of various types of generating capacity can be compared with the costs of peakers in several ways, obvious whether the additional classification to energy is including the following: more equitable than the result of the gross plant allocation. • Comparing recent or current gross plant costs for other • Comparing the cost of building the actual mix of generators with the corresponding cost of peakers, as generation today with the cost of building a peaking-only discussed above. system today.101 This approach avoids the problem of 100 These cost ratios are provided to explain the importance of identifying the demand-related portion of generation investment. Any application of the equivalent peaker method should compare the costs of the utility’s existing plants to the costs of contemporaneous peakers, using the most comparable estimates of the costs of peakers, reflecting geographical and other differences. 101 The peaking-only system might include combustion turbines, demand response and storage resources.Page 118 of 276
116 | ELECTRIC COST ALLOCATION FOR A NEW ERA estimating the cost of building peakers at various times in the past. But many existing plants could not be built REGULATORY ASSISTANCE PROJECT (RAP)® Table 14. Equivalent peaker method analysis using replacement cost estimates today as they currently exist — a new coal plant may Cost per kW Capacityrelated share of cost Peaking $770 100% 0% gas-fired boiler units, no longer make economic sense Nuclear $3,689 20.9% 79.1% and would not be built today. Determining the cost of Fossil* $1,976 39.0% 61.0% building a new 1970s-style coal plant or a gas-fired steam Combined cycle $1,020 75.4% 24.6% plant may be much more difficult than determining the Hydro $4,519 17.0% 83.0% require scrubbers, nitrogen oxide reduction, closedsystem cooling and other features that the existing coal plant does not have.102 Other plant types, such as oil- and cost of peakers in the 1970s. And for some technologies, the costs of new construction do not meaningfully reflect the costs of the plants currently embedded in rates. For example, as expensive as the nuclear units of the 1980s were, the nuclear units currently under construction Resource type Energyrelated share of cost *The “fossil” resource type appears to be coal- or gas-fired steam. Source: Peppin, M. (2013, November 4). Direct testimony on behalf of Northern States Power Co.-Minnesota. Minnesota Public Utilities Commission Docket No. E002/GR-13-868 This is not a very realistic comparison, for reasons are much more expensive. Conversely, the costs of discussed above. Many of the plants could not be built wind turbines have fallen dramatically since the 1980s. today, and some have complicated histories of retrofits and Comparing today’s costs for those resources to the costs repowering. The nuclear replacement cost appears to be of new peakers would probably overstate the energy- particularly optimistic compared with the cost of nuclear related portion of the costs of an old nuclear unit and power plants under construction today. understate the energy-related portion of the costs of an Table 15 on the next page shows an alternative analysis old wind farm. based on the Xcel Energy Minnesota subsidiary’s actual Whether the comparison uses gross plant in service, net investments in each plant type at the end of 2017, from plant in service or hypothetical new construction, the data Page 402 of its FERC Form 1 report (Federal Energy sources should be as consistent as possible. It would not be Regulatory Commission, n.d.). appropriate to compare the current book value of an actual The results of the two analyses are generally consistent, plant with the cost of a hypothetical plant in today’s dollars except for the classification of the combined cycle resources. (Nova Scotia Utility and Review Board, 1995, p. 18). These plants are of more recent vintage than the others; a Table 14 shows the equivalent peaker method analysis fairer comparison, using peaker costs contemporaneous with that Northern States Power Co.-Minnesota (a subsidiary of the in-service dates of each of the other resources, probably Xcel Energy) used in its 2013 rate case filing (Peppin, 2013, would result in a lower energy classification of the combined Schedule 2, p. 4).103 The capacity portion for each plant type cycle resources and higher energy classification for the coal is the ratio of the peaking cost ($770 per kW) to the plant and nuclear units. type cost. For example, the peaking cost is 20.9% of the cost The equivalent peaker method does have limitations. of the nuclear plant, so 20.9% of the nuclear investment is Perhaps most importantly, it requires cost comparisons of treated as capacity-related. The company uses its estimates of individual generation units with peakers of the same vintage. the replacement costs of each type of generation and applies Utilities installed combustion turbines as far back as the early the results to each capital cost component (gross plant, 1950s, but the technology was widely installed only in the accumulated depreciation, deferred taxes, etc.). late 1960s. The oldest remaining combustion turbine owned 102 Many hydroelectric projects could not be licensed if they were proposed today. 103 The company calls this a plant stratification analysis.Page 119 of 276
REGULATORY ASSISTANCE PROJECT (RAP)® ELECTRIC COST ALLOCATION FOR A NEW ERA | 117 Table 15. Equivalent peaker method analysis using 2017 gross plant in service Excess over combustion turbine Plant in service Capacity (MWs) Combustion turbine Energy-related share of cost Cost Cost per kW Cost Cost per kW 1,114 $291,000,000 $261 N/A N/A 0% Nuclear 1,657 $3,448,000,000 $2,081 $3,016,000,000 $1,820 87% Coal 2,390 $2,156,000,000 $902 $1,532,000,000 $641 71% Combined cycle 1,266 $939,000,000 $742 $609,000,000 $481 65% All resources 6,427 $6,834,000,000 $1,063 $5,157,000,000 $802 75% Resource type Data source: Federal Energy Regulatory Commission Form 1 database records for Northern States Power Co.-Minnesota by a utility filing cost data (Madison Gas and Electric’s Nine usually ignores the higher accumulated depreciation of Springs) entered service in 1964. The paucity of earlier data peakers compared with the accumulated depreciation for complicates the use of the equivalent peaker method for other generation resources of the same vintage (which tends classifying the costs of older plants. This problem is gradually to overstate the demand-related portion of generation rate fading away, as all pre-1970 nuclear is gone and much of the base), it is also generally symmetrical to classify generation pre-1970 fossil-fueled steam capacity has been retired or depreciation expense as proportional to the demand-related is nearing retirement, but the issue remains for classifying portion of gross plant (which will tend to understate the hydro plant costs and the few remaining old fossil fuel plants demand-related portion). If classification of one of these cost (U.S. Energy Information Administration, 1992). components is refined to reflect the difference in depreciation One solution to the problem of classifying the rates, the other cost component should be similarly adjusted. investment in very old, little-used steam plants is to treat As is true for plant in service, the nonfuel O&M costs that cost as entirely demand-related. Since these units often of steam plants are generally much higher than the nonfuel represent a very small portion of generation rate base, this O&M costs of combustion turbines. Typical O&M costs per solution may be reasonable. kW-year are $1 to $10 for combustion turbines, $10 to $15 for A full equivalent peaker analysis would compare the combined cycle plants, $10 to $20 for oil- and gas-fired steam product of the actual depreciation charges for the nonpeaking plants, $40 to $80 for coal plants and more than $100 for plants with the product of the peaker depreciation rate nuclear plants. Table 16 shows how the capacity-related O&M and the peaker-equivalent gross investment for the same for conventional generation might be classified between reliability contribution. Since the classification of rate base energy and demand, using the utility’s actual nonfuel O&M Table 16. Equivalent peaker method classification of nonfuel operations and maintenance costs Resource type Capacity (MWs) Nonfuel operations and maintenance Cost per kW-year Cost Excess over combustion turbine Cost Cost per kW-year Energy-related share of cost Combustion turbine 1,114 $4,170,000 $3.74 N/A N/A 0% Nuclear 1,657 $215,880,000 $130.28 $209,680,000 $126.54 97% Coal 2,390 $33,490,000 $14.01 $24,550,000 $10.27 73% Combined cycle 1,266 $16,380,000 $12.94 $11,650,000 $9.20 71% Data source: Federal Energy Regulatory Commission Form 1 database records for Northern States Power Co.-MinnesotaPage 120 of 276
118 | ELECTRIC COST ALLOCATION FOR A NEW ERA costs; the data are 2017 numbers from FERC Form 1, Page 402, for Northern States Power Co.-Minnesota (Federal Energy Regulatory Commission, n.d.). Table 16 does not include the company’s wind resources, REGULATORY ASSISTANCE PROJECT (RAP)® 9.1.3 Joint Classification and Allocation Methods Although most cost of service studies classify capital investments and capacity-related O&M as either demand- which average about $30 per kW-year in O&M, since MISO related or energy-related, classify power and short-term credits wind with unforced capacity value at only about variable costs as energy-related, and then allocate 15% of rated capacity, or about 17% of the value of an installed energy-related and demand-related costs in separate MW of typical conventional generation. The demand-related steps, two approaches accomplish both at once. These are portion of the wind capacity is thus less than $1 per kW-year, the probability-of-dispatch (POD) and decomposition and the wind O&M is almost all energy-related.104 approaches. Operational Characteristics Methods Probability of Dispatch The operational characteristics methods classify The POD approach is the better of the two.105 Methods generation resources (units, resource types, purchases) based using this approach are generically referred to as probability on their capacity factors or operating factors. Newfoundland of dispatch, even for versions that do not explicitly Hydro classifies as energy-related a portion of the cost of incorporate probability computations.106 A simplified each oil-fueled steam plant equal to the plant’s capacity illustrative example of power plant dispatch is shown in factor (Parmesano, Rankin, Nieto and Irastorza, 2004, p. 22). Figure 33 on the next page, under the utility load duration At first blush, this approach appears to roughly follow the use curve. The example uses only four types of generation: of the resource, with plants that are used rarely being treated nuclear, coal, gas combined cycle and a peaking resource as primarily demand-related and those used in most hours consisting of a mix of demand response, storage and classified as predominantly energy-related. Unfortunately, combustion turbines. An actual POD analysis might break the use of capacity factor effectively classifies more of the the generation data down to the plant or even unit level and cost to demand as the reliability of the resource declines. may need to include load management and demand response A better approach would be to use the resource’s as resources. This simplified example also does not illustrate operating factor, which is the ratio of its output to its equivalent availability (that is, its potential output, if it were maintenance, forced outages or ramping constraints. Off-system sales and purchases can be added or used whenever available). This approach would classify any subtracted from the load duration curve when they occur, or resource that is dispatched whenever it is available (e.g., they can be subtracted or added to the generation available in nuclear, wind and solar) as essentially 100% energy-related. each hour or period. Similar adjustments may be needed to That may be seen as an overstatement, since those resources reflect the charging of storage and operation of behind-the- generally provide some demand-related benefits and are meter generation. sometimes built to increase generation reliability, as well as to produce energy with little or no fuel cost. Figure 34 shows the composition of demand in each hour for the same illustrative system, divided among three customer classes. In this example, the residential class peak load occurs when load is high but not near the system peak. 104 The nonfuel O&M costs per kW for Northern States Power’s two small waste-burning plants and its small run-of-river hydro plant are even higher than the nuclear O&M and hence are effectively entirely energy-related, even if the hydro plant provides firm capacity. 105 The Massachusetts Department of Public Utilities explained its preference for this method as follows: “The modified peaker POD results in a fair allocation of embedded capacity costs because this method recognizes the factors that cause the utility to incur power plant capital costs and because this method allocates to the beneficiaries of fuel savings the capitalized energy costs that produce those savings” (1989, p. 113). 106 For an example of the POD method, see La Capra (1992).Page 121 of 276
REGULATORY ASSISTANCE PROJECT (RAP)® ELECTRIC COST ALLOCATION FOR A NEW ERA | 119 Figure 33. Simplified generation dispatch duration illustrative example 7,000 Demand response/storage/combustion turbines Combined cycle 6,000 System total megawatts Coal 5,000 Nuclear 4,000 3,000 2,000 1,000 0 1,000 2,000 3,000 4,000 5,000 6,000 7,000 8,000 Hour of the year, sorted by load Higher load Lower load This situation might arise for a winter-peaking residential industrial class might peak in the morning, the secondary class in a summer-peaking system, or an evening-peaking commercial class at 1 p.m., and the residential class in the residential class in a midday-peaking system. evening. Large commercial buildings typically experience Note that the three customer classes need not peak at the same time. On a high-load summer day, the primary their peak load in the summer, since large buildings require cooling in most climates. If a large percentage of home Figure 34. Illustrative customer class load in each hour 7,000 Residential Secondary commercial 6,000 Primary industrial Total megawatts 5,000 4,000 3,000 2,000 1,000 0 1,000 2,000 3,000 4,000 5,000 6,000 7,000 8,000 Hour of the year, sorted by load Higher load Lower loadPage 122 of 276
120 | ELECTRIC COST ALLOCATION FOR A NEW ERA REGULATORY ASSISTANCE PROJECT (RAP)® outages, hydro output, natural gas price, off-system purchases Table 17. Class share of each generation type under probability-of-dispatch allocation and sales), actual hourly output (reflecting planned and random outages and unit ramping constraints) and other Generation source Nuclear Coal 34% 34% 32% 31% available data to match costs with usage as realistically as Secondary commercial 28% 29% 39% 42% possible. 38% 37% 29% 27% Customer class Residential Primary industrial Peaking resources variants. The POD method is thus one approach to hourly Combined cycle allocation. Ideally, dispatch and class loads should use the The POD approach has some limitations. Most importantly, it does not consider the reason that investments were heating is electric, the residential class is likely to experience incurred, only the way they are currently used. The costs its highest load in the winter, even in places like Florida. The of an expensive coal plant no longer needed for baseload industrial class loads may peak in a variety of seasons, driven service and converted to burn natural gas and operating at by vacation and maintenance schedules, variation in inputs a 10% capacity factor to meet peak loads might be allocated (e.g., agricultural products) and demand, and other factors. in exactly the same way as the costs of a much less expensive The system peak may occur at a time different from all of the combustion turbine operating at 10% capacity factor.108 The customer class NCP demands. excess costs of the converted coal plant are due to its historical Table 17 shows how the costs of each generation resource role of providing large amounts of energy at then-attractive would be allocated to the classes in the illustrative example fuel costs; those costs were not incurred for the 10% of hours in Figure 34. In the lowest-load hours, when nuclear is with highest demand. The same considerations arise for other serving 80% of the energy load, the industrial class uses half steam plants that operate at much lower capacity factors than the system energy and hence half the nuclear output; in the they were planned for and justified by. Some hydro plants highest-load hours, when nuclear is serving about 29% of the have also changed operating patterns from their original load, the industrial class uses about 27% of the system energy. use, either running for more hours to maintain downstream Averaged over the year, the industrial class uses 38% of the flow or for fewer hours due to reduced water supply. Peaking nuclear output. In the hours that the combustion turbines capacity is used to provide a range of ancillary services at are running, the industrial class uses only 27% of the peaking many load levels, including upward ramping services (when resources’ output, since the residential and commercial load surges during the day or wind and solar output falls) and classes dominate loads in that period. operating reserves (especially to back up large generation and The commercial class is responsible for the largest share transmission facilities). Reflecting these considerations may of the summer peak and hence of the combustion turbine require modification of the inputs to the POD analysis, which costs but the smallest part of the low-load hours and hence considers only current use, not historical causation. the lowest share of the nuclear and coal costs. Every class pays for a share of each type of generation.107 The POD method has been applied with a wide range of Second, the POD method spreads the cost of each resource equally to all hours or energy output, assigning the same cost of a totally baseload plant (with a 100% capacity detail. The generation “dispatch” over the year may represent factor) to the lowest-load off-peak hour as to the system peak historical or forecast operation, equivalent availability or hour. That approach comports with some concepts of equity capacity factor, seasonal variation (due to maintenance and cost responsibility: The cost of each resource is allocated 107 If this example had included a street lighting class, that class might not have been allocated any combustion turbine costs if the lights would not be on in the summer peak hours. In a more realistic example, including outages of the baseload plants, the combustion turbines probably would operate in some hours with street lighting loads and the lighting class would be allocated some combustion turbine costs. 108 In the simpler forms of POD, the costs of both plants would be spread over the top 10% of hours. In more sophisticated approaches that map generation to actual operating hours, the steam plant would generate in many hours with load lower than the top 10%, while missing some of the top 10%, due to limits on load following.Page 123 of 276
REGULATORY ASSISTANCE PROJECT (RAP)® ELECTRIC COST ALLOCATION FOR A NEW ERA | 121 proportionately to the classes that use it. On the other hand, whether classes are paying for enough capacity to cover their it can be argued that the hours with higher marginal energy energy and reliability requirements. costs contribute more of the rationale for investing in that In the context of resources stacked under a load resource and that, in a sense, each kWh of usage at high-load duration curve, such as that shown in Figure 33 on Page 119, times should bear more of the resource’s investment-related the decomposition approach allocates the resource mix costs than should each kWh in the off-peak hours. This horizontally, rather than the vertical allocation used in the concern can be addressed by weighting the energy over the POD method. Figure 35 on the next page illustrates the hours, such as in proportion to some measure of hourly decomposition approach. market price. Third, it is important that the load and dispatch data be In essence, the decomposition method treats the utility as if it were multiple separate utilities. In the case of Figure 35, representative of the cost causation or resource usage the utility system is decomposed into an all-nuclear system in the years for which the cost allocation will be in place. with enough capacity to meet the industrial peak load, and For example, a baseload plant may have operated at only a utility with a little nuclear and all the other resources to 40% capacity factor in the most recent year because of major serve all other load. Whether the industrial customers would maintenance or availability of economic energy imports. support this allocation would usually depend on the cost of Or load and dispatch in the last 12 months of data may the nuclear resources compared with the system average. be atypical because of an extremely cold winter and mild The decomposition approach conflicts with reality in summer. The POD allocation should be based on weather- many ways, including: normalized dispatch and load, just as the rate case costs 1. The reserve requirements for the decomposed systems allowed by the regulator and included in the cost of service would be driven by their noncoincident class peaks or study should reflect weather-normalized load. high loads (if they are assumed to be fully free-standing), requiring additional hypothetical capacity for utilities Decomposition that are not already extensively overbuilt. If the decom- Class obligations for generation costs have occasionally position assumes that the multiple class-specific systems been addressed by dividing the generation resource into would operate in a power pool, contribution to the separate generation systems serving hypothetical loads for system peaks would drive capacity requirements. portions of the utility’s customers, such as just the residential 2. A system with a high load factor and relatively few customers, just the commercial customers and just the large units would require a very high reserve margin industrial customers. For example, industrial customers in (as discussed in Subsection 5.1.1) to cover fixed outages Nova Scotia have argued that their high-load-factor demands and even maintenance outages. The reserve units would could be served by the capacity and energy of some set of operate in many hours (since the system load would baseload plants, where those costs are lower than the average always be near the allocated baseload capacity). generation cost per kWh (Drazen and Mikkelsen, 2013, 3. A baseload-only system would require a large amount of pp. 11-16). The industrial advocates for this approach assume backup supply energy, either from hypothetical units or that the flat industrial load would be served exclusively by as purchases from the other classes. baseload plants and that all other costs should be allocated to other classes.109 A similar approach might inappropriately 4. The decomposition approach is usually designed to assign the lowest-cost resources to the industrial class, be suggested to justify allocating the highest-cost resources to customers with behind-the-meter solar generation and lower-cost resources to nonsolar customers whose load does not dip in midday. The method might also be used to test 109 A decomposition method that accounts for all relevant factors may not show an advantage for industrial customers. In Alberta, a related method to the decomposition method was presented to demonstrate that baseload power for industrial customers would be considerably more expensive than the demand-based cost allocation of the existing system for the industrial class (Marcus, 1987).Page 124 of 276
122 | ELECTRIC COST ALLOCATION FOR A NEW ERA REGULATORY ASSISTANCE PROJECT (RAP)® Figure 35. Illustration of decomposition approach to allocating resource mix Demand response/storage/combustion turbines 7,000 Combined cycle Other-class generation allocation Coal System total megawatts Nuclear 5,000 Maximum industrial load Industrial load 4,000 3,000 2,000 1,000 0 1,000 2,000 3,000 4,000 5,000 6,000 7,000 8,000 Industrial generation allocation 6,000 Hour of the year, sorted by load Higher load 5. Lower load shifting all the costs of mistakes and market changes onto needed to deal with allocating nonhydro renewable costs; the other classes. That includes excess capacity (even a few utilities already have significant costs for nonhydro excess baseload and capacity made excess by decline storage (mostly batteries) and most will need to deal with in industrial loads), the costs of fuel conversion and those costs in the future. As technologies change, new the high costs of plants built as baseload but currently cost allocation challenges will arise — for new resources, operated as peakers. repurposed existing assets and newly obsolete resources. It is not clear how variable renewables and other unconventional resources would be incorporated into Fuel Switching and Pollution Control Costs Many fuel conversion investments have been the decomposed utility systems. It is possible (if not certain) that the decomposition undertaken to reduce fuel costs or increase the reliability approach could be expanded and revised to create a viable of fuel supply for high-capacity-factor power plants. classification and allocation method, but at this point no This category includes: such model has been developed. • Conversion of oil-fired steam plants to burn coal in the 1970s and 1980s (most of which have since been retired). 9.1.4 Other Technologies and Issues • when the supply of gas was limited. Several types of generation costs do not fit neatly into the classification methods discussed in the previous sections. Conversion of gas-fired plants to burn oil in the 1970s, • Conversion of oil-fired plants to co-firing or dual firing Some of those costs, such as hydro resources and purchased with gas since the 1990s to achieve environmental power, have been part of utility cost structures since before compliance and reduce fuel costs. the development of formal cost of service studies. Others, • on gas to achieve environmental compliance. such as excess capacity and uneconomic investments, became prominent in recent decades. More recently, utilities have Conversion of coal-fired plants to partial or full operation • Conversion of coal-fired plants to partial or fullPage 125 of 276
REGULATORY ASSISTANCE PROJECT (RAP)® • ELECTRIC COST ALLOCATION FOR A NEW ERA | 123 operation on biomass to achieve environmental capacity has vanished and the value of its energy output has compliance and RPS credit.110 decreased dramatically. One or both of those outcomes befell Conversion of coal-fired plants to partial or full operation many of the nuclear plants and some coal plants in the late on petroleum coke, tire-derived fuel or other waste to 1970s and 1980s. The long lead times are generally the result reduce fuel costs. of choices to build plants to produce large amounts of energy These investments and resulting longer-term operating at low variable costs; in those cases, there is a reasonable costs may reasonably be classified as 100% energy-related. Most pollution control retrofit costs are incurred to comply with regulatory requirements to reduce the presumption that the costs of the excess capacity are due to anticipated or actual energy requirements.112 Excess capacity can be priced at the costs of environmental effects of fossil-fueled plants and to allow contemporaneous peaking capacity and allocated among them to continue burning low-cost fuel at high capacity classes in proportion to the differences between projected factors. Peaking units that are needed only in a few high-load class contribution to peak loads (at the time commitments hours annually can afford to burn expensive clean fuels and were undertaken) and actual current class loads. Excess are often allowed to have higher emissions rates since they capitalized energy costs (net of equivalent peaking capacity operate so little. Hence, the need for the pollution control costs and any fuel savings) similarly can be allocated in is driven primarily by the energy-serving function of the proportion to the differences between class projected energy nonpeaking fossil plants. These environmental costs are requirements and their actual energy requirements. most often related to emissions standards for air pollutants, Table 18 on the next page provides an illustration of but some substantial costs are driven by the need to protect the allocation of excess capacity among classes to reflect water quality and aquatic life and to meet other health responsibility for the excess. In this illustration, the actual and environmental standards. As a result, the identifiable load in the rate case test year is 600 MWs lower than the capital investment and nondispatch O&M costs of pollution load forecast at the time the utility committed to the excess controls may reasonably be classified as 100% energy-related capacity. Because of other adjustments in supply planning, or allocated in proportion to class usage of energy during the the utility has about 480 MWs of excess capacity, which times that the plant is operated, to recognize the causes of the would support about 400 MWs more load than the actual environmental retrofits.111 need. That 400-MW excess is allocated among the classes in proportion to their shortfalls in load.113 Excess Capacity and Excess Costs Utilities sometimes add generation that is not needed to This adjusted peak load could be used in allocating peaking resources or the peaking-equivalent portion of maintain adequate reliability. Some of that excess capacity all generation resource costs. A similar approach could be may result from the lumpiness of generation additions or applied to allocate the additional costs of having a baseload- declining load, with no clear connection to the classification heavy resources mix resulting from actual energy use being of the additional costs. Other times the excess is the result of lower than the forecast usage. the long lead times for certain baseload generation (especially Another source of excess capacity is the addition of clean nuclear, but also some coal and hydro facilities), which resources to allow the reduced use of dirty older generation, can result in a plant being completed after the need for its which thus allows the utility to meet environmental 110 In principle, biomass conversion might also reduce fuel costs, although that is not necessarily the case. 112 Accounting for a suboptimal system resource mix (and other inefficiencies) is also discussed in detail in Chapter 18. 111 Nova Scotia Power uses this adjustment to the average-and-peak approach (Nova Scotia Power, 2013a, p. 37). 113 Any load shortfall due to increased utility efficiency efforts since the commitment to build the capacity should generally be excluded from the shortfall.Page 126 of 276
124 | ELECTRIC COST ALLOCATION FOR A NEW ERA REGULATORY ASSISTANCE PROJECT (RAP)® Table 18. Allocation of 400 MWs excess capacity to reflect load risk Allocated excess (MWs) Load for allocation (MWs) 0% 0 1,500 -300 43% 171 2,171 2,300 -400 57% 229 2,529 5,800 +600 100% 400 6,200 Forecast load (MWs) Actual load (MWs) Load differential Residential 1,400 1,500 +100 Secondary commercial 2,300 2,000 Primary industrial 2,700 Total 6,400 Share of load shortfall requirements, reduce fuel costs or meet portfolio standards.114 the plant, long before the plant’s costs and benefits were clear. Even though these new clean resources may raise the Many nuclear plants were canceled after the utility spent reliability of generation supply (usually above an existing more on the plant than the entire original expected cost, adequate level), their costs were incurred as a result of energy most recently the Summer plant in South Carolina. A number loads; in these cases, the excess capacity should be recognized of coal plants were also canceled after the commitment of as energy-related.115 substantial funds. Aside from excess capacity, changing economic, technological and regulatory conditions can result in a facility providing a service different from its original purpose. For Hydroelectric Generation The classification of hydroelectric generation presents example, a previously baseload generation plant may run on some issues that differ from those of thermal generation.117 only a few days annually or may house a distribution service First, many large generation facilities installed prior to 1960 center. The plant may still have unrecovered capital costs, are still in operation, so their costs are difficult to classify environmental cleanup obligations or other burdens. If the using the equivalent peaker method. Most of them could full cost of the repurposed facility exceeds its value in its new not be built today, given environmental siting constraints, use, the excess costs should be allocated based on its former so comparing new construction costs with new peaker costs use as a baseload generating plant.116 may not be practical. Second, each conventional hydro Finally, the amortization of a canceled generation plant facility consists of turbines and dams (and other civil works), is attributable to the reason the utility spent the money on which have different and varying effects on the energy and 114 MidAmerican Energy, for example, will have added over 6,000 MWs of wind in the period 2004-2020 to reduce fuel costs to its retail customers but has kept most of its fossil generation in operation (Hammer, 2018). This could result in a MISO-recognized reserve margin of 26% in unforced capacity terms in certain areas (Hammer, 2018, Table 3). This is nearly three times the typical MISO-required unforced capacity reserve around 8% (Midcontinent Independent System Operator, 2018, p. 23). 116 Excess costs can also be associated with underutilized or repurposed facilities. For example, a retired steam power plant may be used to warehouse distribution equipment; the generator may be operated as a synchronous condenser to support the transmission system; or a portion of the plant site may remain in service to house a combustion turbine, a transmission switching station or a control center. Sometimes this is intentionally done to avoid (or evade) a rate base disallowance for a unit retired prior to being fully depreciated. Most of those costs continue to be attributable to the original purpose of the steam plant and hence to energy and demand. Similarly, the utility may face cleanup costs for a former coal gasification site or any site contaminated by hazardous materials (e.g., heavy metals, waste lubricating oil or PCB-contaminated transformer oil). Regardless of how that site is used today or was most recently used, the cleanup costs are attributable to the activity that generated the contamination, not the current use. 115 Texas and Iowa established their initial renewable portfolio standards in terms of installed capacity, rather than the more common energy percentage requirement, and several jurisdictions have established targets for specific renewables (e.g., solar, offshore wind). See Texas Utilities Code § 39.904 and Iowa Code Ch. 476 §§ 41-44. The motivations for these targets, however they are formulated, have been primarily related to reducing fuel costs and emissions. Both Texas and Iowa have exceeded their requirements and continue to add renewables to reduce fuel and other energy costs. 117 The treatment of pumped storage, where water is pumped uphill off-peak and released to produce electricity during peak periods, is addressed with other storage technologies in Subsection 9.1.4.
As listed on the current system