Prefiled testimony
Witness: Melissa Whited
Files3
Synapse - Eversource COS and Rate Design Testimony Final.pdf
PDF · 829 KB · 48 pagesText searchable
Download Synapse - Eversource COS and Rate Design Testimony Final.pdfRead the text of Synapse - Eversource COS and Rate Design Testimony Final.pdf
MW-2- Synapse Attachment.pdf
PDF · 4.6 MB · 276 pagesText searchable
Download MW-2- Synapse Attachment.pdfRead the text of MW-2- Synapse Attachment.pdf
MW-1 - Synapse Attachment.pdf
PDF · 734 KB · 13 pagesText searchable
Download MW-1 - Synapse Attachment.pdfRead the text of MW-1 - Synapse Attachment.pdf
Page 157 of 276
REGULATORY ASSISTANCE PROJECT (RAP)® ELECTRIC COST ALLOCATION FOR A NEW ERA | and Account 595 for transformers) should be classified and Table 30. Residential shared transformer example allocated in the same manner as associated equipment. Other With multiple residences per transformer With single residence per transformer Total drops (accounts 583, 584, 593 and 594) or include services to Number of transformers 197,503 47,699 245,202 a range of equipment (accounts 580 and 590). These costs Number of customers 1,054,296 47,699 1,101,995 5.3 1 4.5 Customers per transformer 155 accounts serve both primary and secondary lines and service normally should be classified and allocated in proportion Sources: Levin, A. (2017, June 30). Prefiled response testimony on behalf of NW Energy Coalition, Renewable Northwest and Natural Resources Defense Council. Washington Utilities and Transportation Commission Docket No. UE-170033; additional calculations by the authors individual transformers may need to pay to obtain service that is more expensive than their line extension allowances (see Section 11.2 or Section 15.2). Small customers will have similar, but lower, diversity to the plant in service, for the plant accounts they support, subfunctionalized as appropriate. For example, typical utility tree-trimming activities are almost entirely related to primary overhead lines, with very little cost driven by secondary distribution and no costs for protecting service lines (see, for example, Entergy Corp., n.d.). 11.3.5 Multifamily Housing and Distribution Allocation One common error in distribution cost allocation is treating the residential class as if all customers were in single- on secondary conductors, which generally serve multiple family structures, with one service drop per customer and a customers but not as many as a transformer. A transformer relatively small number of customers on each transformer.163 that serves a dozen customers may serve two of them directly For multifamily customers, one or a few transformers may without secondary lines, four customers from one stretch of serve 100 or more customers through a single service line.164 secondary line and six from another stretch of secondary line Treating multifamily customers as if they were single-family running in the opposite direction or across the street. customers would overstate their contribution to distribution Where no detailed data are available on the number of customers per transformer in each class, a reasonable costs, particularly line transformers and secondary service lines.165 approximation might be to allocate transformer demand This problem can be resolved in either of two ways. costs on a simple average of class NCP and customer NCP The broadest solution is to separate residential customers for residential and small commercial customers and just into two allocation classes: single-family residential and customer NCP for larger nonresidential customers. multifamily residential, as we discuss in Section 5.2.166 Alternatively, the allocation of transformer and service costs 11.3.4 Distribution Operations and Maintenance Allocators Distribution O&M accounts associated with a single type to a combined residential class (as well as residential rate design) should take into account the percentage of customers who are in multifamily buildings, and only components that of equipment (FERC accounts 582, 591 and 592 for substations are not shared should be considered customer-related. 163 One large service drop is much less expensive than the multiple drops needed to serve the same number of customers in single-customer buildings. Small commercial customers may also share service drops, although probably to a more limited extent than residential customers. 165 Allocating transformer costs on demand eliminates the bias for that cost category. 164 Similarly, if the cost of service study includes any classification of shared distribution plant as customer-related (such as from a minimum system), each multifamily building should be treated as a single location, rather than a large number of dispersed customers. For utilities without remote meter reading, the labor cost for that activity per multifamily customer will be lower than for single-family customers. 166 If any sort of NCP allocator is used in the cost of service study, the multifamily class load generally should be combined with the load of the type of customers that tend to surround the multifamily buildings in the particular service territory, which may be single-family residential or medium commercial customers.Page 158 of 276
156 | ELECTRIC COST ALLOCATION FOR A NEW ERA 11.3.6 Direct Assignment of Distribution Plant Direct cost assignment may be appropriate for equip- REGULATORY ASSISTANCE PROJECT (RAP)® analysis of the specific lines in use for each class. Many utilities have performed bottom-up analyses, selecting a typical customer or an arguably representative ment required for particular customers, not shared with sample of customers in each class, pricing out those custom- other classes, and not double-counted in class allocation of ers’ service lines and extrapolating to the class. Since the costs common costs. Examples include distribution-style poles are estimated in today’s dollars, the result of these studies is that support streetlights and are not used by any other class; the ratio of each class’s cost of services to the total cost, or a the same may be true for spans of conductor to those poles. set of weights for service costs per customer. Either approach Short tap lines from a main primary voltage line to serve a should reflect the sharing of services in multifamily buildings. single primary voltage customer’s premises may be another example, as they are analogous to a secondary distribution service drop. Beyond some limited situations, it is not practical or useful to determine which distribution equipment (such as 11.5 Classification and Allocation for Advanced Metering and Smart Grid Costs Traditional meters are often discussed as part of the lines and poles) was built for only one class or currently serves distribution system but are primarily used for billing only one class and to ensure that the class is properly credited purposes.167 These meters typically record energy and, for for not using the other distribution equipment jointly used by some classes, customer NCP demand for periodic manual other classes in those locations. or remote reading and generally are classified as customer- 11.4 Allocation Factors for Service Drops The cost of a service drop clearly varies with a number related. Meter costs are then typically allocated on a basis that reflects the higher costs of meters for customers who take power at higher voltage or three phases, for demandrecording meters, for TOU meters and for hourly-recording of factors that vary by class: customer load (which affects energy meters. The weights may be developed from the the capacity of the service line), the distance from the current costs of installing the various types of meters, but as distribution line to the customer, underground versus technology changes, those costs may not be representative of overhead service, the number of customers sharing a service the costs of equipment in rates. (or the number of services required by a single customer) and whether customers require three-phase service. Some utilities, including Baltimore Gas & Electric, In many parts of the country, this traditional metering has been replaced with advanced metering infrastructure. AMI investments were funded in many cases by the attempt to track service line costs by class over time American Recovery and Reinvestment Act of 2009, the (Chernick, 2010, p. 7). This approach is ideal but economic stimulus passed during the Great Recession, complicated. Although assigning the costs of new and but in other cases ratepayers are paying for them in full replacement service lines just requires careful cost in the traditional method. In many jurisdictions, AMI has accounting, determining the costs of services that are retired been accompanied by other complementary “smart grid” and tracking changes in the class or classes in a building (which may change over time from manufacturing to office space to mixed residential and retail) is much more complex. Other utilities allocate service lines on the sum of customer maximum demands in each class. This has the advantage of reflecting the fact that larger customers require larger (and often longer) service lines, without requiring a detailed 167 Some customers who are small or have extremely consistent load patterns are not metered; instead, their bills are estimated based on known load parameters. The largest group of these customers is street lighting customers, but some utilities allow unmetered loads for various small loads that can be easily estimated or nearly flat loads with very high load factors (such as traffic signals). An example of an unmetered customer from the past was a phone booth. Unmetered customers should not be allocated costs of traditional metering and meter reading.Page 159 of 276
REGULATORY ASSISTANCE PROJECT (RAP)® ELECTRIC COST ALLOCATION FOR A NEW ERA | 157 Table 31. Smart grid cost classification Legacy approach Smart grid element Equivalent cost FERC account Classification Smart grid classification Meters 370 Customer Demand, energy and customer Station equipment and devices 362, 365, 367 Demand Demand and energy Data collection system Meter readers 902 Customer Demand, energy and customer Meter data management system Customer accounting and general plant 903, 905, 391 Customer and overhead Demand, energy and customer Smart meters Distribution control devices investments. On the whole, these investments include: • • Smart meters, which are usually defined to include the • factor and phase balancing. • Reduced energy costs due to load shifting. measure voltage and power factor, and allow for remote • Reliability benefits, saving time and money on service connection and disconnection of the customer. restoration after outages, since the utility can determine Distribution system improvements, such as equipment to which meters do not have power and can determine remotely monitor power flow on feeders and substations, whether a customer’s loss of service is due to a problem open and close switches and breakers and otherwise inside the premises or on the distribution system. • Voltage control equipment on substations to allow modulation of input voltage in response to measured • Distribution line loss savings from improved power ability to record and remotely report granular load data, control the distribution system. • • Allowing utilities to determine maximum loads on individual transformers. • Retail service benefits, by reducing meter reading costs voltage at the end of each feeder. compared with manual meter reads and even automated Power factor control equipment to respond to signals meter reading and by reducing the cost of disconnecting from the meters. and reconnecting customers.168 Data collection networks for the meters and line The installations have also been very expensive, running monitors. into the hundreds of millions of dollars for some utilities, and Advanced data processing hardware and software to the cost-effectiveness of the AMI projects has been a matter handle the additional flood of data. of dispute in many jurisdictions. Since these new systems are Supporting overhead costs to make the new system work. much more expensive than the older metering systems and The potential benefits of the smart grid, depending are largely justified by services other than billing, their costs on how it is designed and used, include reduced costs for must be allocated over a wider range of activities, either by generation, transmission, distribution and customer service, functionalizing part of the costs to generation, distribution as described in Subsection 7.1.1. A smart meter is much more and so on or reflecting those functions in classification or the than a device to measure customer usage to assure an accu- allocation factor. • • rate bill — it is the foundation of a system that may provide Special attention must be given to matching costs and some or all of the following: benefits associated with smart grid deployment. The expected • Benefits at every level of system capacity, by enabling benefits spread across the entire spectrum of utility costs, peak load management since the communication from lower labor costs for meter reading to lower energy system can be used to control compatible end uses, and because customer response to calls for load reduction can be measured and rewarded. 168 The data systems can also be configured to provide systemwide Wi-Fi internet access, although they usually are not. See Burbank Water and Power (n.d.).Page 160 of 276
158 | ELECTRIC COST ALLOCATION FOR A NEW ERA REGULATORY ASSISTANCE PROJECT (RAP)® Table 32. Summary of distribution allocation approaches Element Method Comments Hourly allocation Substations Functionalization: Entirely primary Classification: Demand and energy Allocator: Loads on substations in hours at or near peaks Reflect effect of energy near peak and preceding peak on sizing and aging Allocate by substation cost or capacity, then to hours that stress that substation with peak and heating Poles Functionalization: Entirely primary Classification: Demand and energy* Energy allocator: Energy or revenue Demand allocator: Loads in hours at or near peaks Pole costs driven by revenue expectation As primary lines Primary conductors Functionalization: Entirely primary Classification: Demand and energy* Energy allocator: Energy or revenue Demand allocator: Loads in hours at or near peaks • • Line transformers Functionalization: Entirely secondary Classification: Demand and energy* Energy allocator: Secondary energy Demand allocator: Diversified secondary loads in peak and near-peak hours Reflect diversity Distribution of transformer peaks and high-load hours Secondary conductors Functionalization: Entirely secondary Classification: Demand and energy* Energy allocator: Energy or revenue Demand allocator: Loads in hours at or near peaks Energy is more important for underground than overhead Distribution of line peaks and highload hours Meters Functionalization: Advanced metering infrastructure to generation, transmission and distribution, as well as metering Allocator for customer-related costs: Weighted customer Allocation of generation, transmission and distribution components depends on use of advanced metering infrastructure N/A • Distribution network is installed due to revenue potential Sizing determined by loads in and near peak hours • Cost associated with revenuedriven line extension to all hours Cost associated with peak loads and overloads on distribution of line peaks and high-load hours * Except some to customer, where a significant portion of plant serves only one customer costs due to load shifting and line loss reduction. Legacy methods for allocating metering costs as primarily customerrelated would place the vast majority of these costs onto the residential rate class, but many of the benefits are typically shared across all rate classes. In other words, the legacy method would give commercial and industrial rate classes substantial benefits but none of the costs. Table 31 identifies some of the key elements of smart grid cost and how these would be appropriately treated in an embedded cost of service study. These approaches match smart grid cost savings to the enabling expenditures. 11.6 Summary of Distribution Classification and Allocation Methods and Illustrative Examples The preceding discussion identifies a variety of methods used to functionalize, classify and allocate distribution plant. Table 32 summarizes the application of some of those methods, including the hourly allocations that may be applicable for modern distribution systems with: • A mix of centralized and distributed resources, conventional and renewable, as well as storage. • The ability to measure hourly usage on the substations and feeders. • The ability to estimate hourly load patterns on transformers and secondary lines.Page 161 of 276
REGULATORY ASSISTANCE PROJECT (RAP)® ELECTRIC COST ALLOCATION FOR A NEW ERA | 159 Table 33. Illustrative allocation of distribution substation costs by different methods Residential Secondary commercial Primary industrial Street lighting Total Class NCP: substation (legacy) $9,730,000 $9,730,000 $7,297,000 $3,243,000 $30,000,000 Average and peak $10,056,000 $10,056,000 $8,100,000 $1,788,000 $30,000,000 Hourly $9,939,000 $10,533,000 $9,009,000 $519,000 $30,000,000 Note: Numbers may not add up to total because of rounding. Where the available data or analytical resources will not support more sophisticated analyses of distribution Substations Table 33 shows three methods for allocating costs of cost causation, the following simple rules of thumb may be distribution substations. The first of these is a legacy method, helpful. relying solely on the class NCP at the substation level.169 The • The only costs that should be classified as customer- second is an average-and-peak method, a weighted average related are those specific to individual customers: between class NCP and energy usage. The third uses the • Basic metering costs, not including the additional hourly composite allocator, which includes higher costs for costs of advanced meters incurred for system hours in which substations are highly loaded. benefits. • Service lines, adjusting for shared services in buildings with multiple tenants. • • • Primary Circuits Distribution circuits are built where there is an expecta- For very rural systems, where most transformers and tion of significant electricity usage and must be sized to meet large stretches of primary line serve only a single peak demands, including the peak hour and other high-load customer (and those costs are not recovered from hours that contribute to heating of the relevant elements of contributions in aid of construction), a portion of the system. Table 34 on the next page illustrates the effect of transformer and primary costs. four alternative methods. The first, based on the class NCP at Other costs should be classified as a mix of energy and the circuit level, again produces unreasonable results for the demand, such as using the average-and-peak allocator. street lighting class. The second, the legacy minimum system The peak demand allocation factor should reflect the method, is not recommended, as discussed above. The third distribution of hours in which various portions of and fourth use a simple (average-and-peak) and more sophis- distribution system equipment experience peak or ticated (hourly) approach to assigning costs based on how heavy loads. If the utility has data only on the time of much each class uses the lines and how that usage correlates substation peaks, the load-weighted peaks can be used to with high-load hours. distribute the demand-related distribution costs to hours and hence to classes. 11.6.1 Illustrative Methods and Results Transformers Line transformers are needed to serve all secondary voltage customers, typically all residential, small general The following discussion and tables show illustrative methods and results for several of the key distribution accounts, focused only on the capital costs. The same principles should be applied to O&M costs and depreciation expense. These examples use inputs from tables 5, 6, 7 and 27. 169 The street lighting class NCP occurs in the night, and street lighting is a small portion of load on any substation, so the street lighting class NCP load rarely contributes to the sizing of summer-peaking substations. The NCP method treats off-peak class loads as being as important as those that are on-peak. This is particularly inequitable for street lighting, which is nearly always a load caused by the presence of other customers who collectively justify the construction of a circuit.Page 162 of 276
160 | ELECTRIC COST ALLOCATION FOR A NEW ERA REGULATORY ASSISTANCE PROJECT (RAP)® Table 34. Illustrative allocation of primary distribution circuit costs by different methods Residential Secondary commercial Primary industrial Street lighting Total Class NCP: circuit (legacy) $69,565,000 $69,565,000 $43,478,000 $17,391,000 $200,000,000 Minimum system (legacy) $113,783,000 $51,783,000 $24,739,000 $9,696,000 $200,000,000 Average and peak $67,041,000 $67,041,000 $53,997,000 $11,921,000 $200,000,000 Hourly $66,258,000 $70,221,000 $60,059,000 $3,462,000 $200,000,000 Note: Numbers may not add up to total because of rounding. service and street lighting customers and often other by class at 20% and the class sum of customer NCP customer classes as well. We present four methods in (recognizing that the diversity is not perfect) at 80%. Table 35: two archaic and two more reflective of dynamic The last is an hourly energy method but excluding the systems and more granular data. All of these apportion primary voltage class of customers. no cost to the primary voltage class, which does not use Customer-Related Costs distribution transformers supplied by the utility. The final illustration shows two techniques for the The first method is to apportion transformers in proportion to the class sum of customer noncoincident apportionment of customer-related costs, based on a peaks. This method is not recommended because it fails to traditional customer count and a weighted customer count. recognize that there is great diversity between customers Even for simple meters used solely for billing purposes, at the transformer level; as noted in Subsection 11.3.3, each larger customers require different and more expensive transformer in an urban or suburban system may serve meters. There are fewer of them per customer class, but the anywhere from five to more than 50 customers. The second billing system programming costs do not vary by number of is the minimum system method, also not recommended customers. In addition, a weighted customer account is also because it fails to recognize the drivers of circuit relevant to customer service, discussed in the next chapter, construction, as discussed in Section 11.2. The third is the because the larger use customers typically have access to weighted transformers allocation factor we derive in superior customer service through “key accounts” specialists Section 5.3 (Table 7), weighting the number of transformers who are trained for their needs. Table 35. Illustrative allocation of distribution line transformer costs by different methods Residential Secondary commercial Primary industrial Street lighting Total Customer NCP (legacy) $32,258,000 $16,129,000 $0 $1,613,000 $50,000,000 Minimum system (legacy) $32,461,000 $14,773,000 $0 $2,766,000 $50,000,000 Weighted transformers factor $29,806,000 $14,903,000 $0 $5,290,000 $50,000,000 Hourly $23,810,000 $23,810,000 $0 $2,381,000 $50,000,000 Note: Numbers may not add up to total because of rounding.Page 163 of 276
REGULATORY ASSISTANCE PROJECT (RAP)® ELECTRIC COST ALLOCATION FOR A NEW ERA | 161 Table 36. Illustrative allocation of customer-related costs by different methods Residential Secondary commercial Primary industrial Street lighting Customer count 100,000 20,000 2,000 50,000 172,000 Customer factor 58% 12% 1% 29% 100% Customer costs $58,140,000 $11,628,000 $1,163,000 $29,070,000 $100,000,000 Weighting factor 1 3 20 0.05 Customer count 100,000 60,000 40,000 2,500 202,500 Customer factor 49% 30% 20% 1% 100% Customer costs $49,383,000 $29,630,000 $19,753,000 $1,235,000 $100,000,000 Total Unweighted Weighted Note: Numbers may not add up to total because of rounding. Table 36 first shows a traditional calculation based on treated as a tiny fraction of one customer; although there the actual number of customers. Then it shows an illustrative are tens of thousands of individual lights, the bills typically customer weighting and a simple allocation of customer- include hundreds or thousands of individual lights, billed to a related costs based on that weighting. Each street light is city, homeowners association or other responsible party.170 170 In some locales, street lighting is treated as a franchise obligation of the utility and is not billed. In this situation, there are no customer service or billing and collection expenses.Page 164 of 276
162 | ELECTRIC COST ALLOCATION FOR A NEW ERA REGULATORY ASSISTANCE PROJECT (RAP)® 12. Billing and Customer Service in Embedded Cost of Service Studies M any utilities classify billing and customer service allocated according to appropriate measures of usage, rather costs, often termed retail service costs, as almost than customer count. entirely customer-related and allocate these Manual reading of the meters of large customers typically costs across classes based on the number of customers. This takes longer than for small customers, both because of chapter describes how these costs can be allocated in a more travel distance among larger customers and the complexity granular and detailed way. of metering typical of large customers (TOU or demand- 12.1 Billing and Meter Reading metered). In some cases, small customer meters are read manually but large customers are remotely metered; the Most utilities bill customers either monthly or additional costs of the equipment for that remote metering bimonthly. The reason for this is relatively simple: If should be assigned to the classes that use remote metering. billed less frequently, the bills would be very large and As noted in Section 11.5, unmetered customers such as unmanageable for some consumers; if billed more frequently, streetlights should not be allocated meter reading costs. the billing costs would be an unacceptable part of the total For utilities with AMI, any meter reading costs arising cost. As noted in Subsection 3.1.5, billing closer to the time of from customers opting out of AMI should be recovered either consumption provides customers with a better understanding from the opt-out customers or functionalized, classified and of their usage patterns from month to month, which may allocated in proportion to the AMI costs, because opt-outs are assist them in increasing efficiency. There are exceptions: part of the cost of obtaining the benefits of AMI. Many water, sewer and even electric utilities serving seasonal properties may render bills only once or twice a year.171 The costs of billing, payment processing and collections for special services (e.g., line extensions and relocations) can It is important to recognize these cost drivers in the clas- end up in Account 903 for some utilities. These are overhead sification of billing costs. From a cost causation perspective, costs, not customer costs, and should be either classified or the reason for frequent billing is that usage drives the size of allocated as an overhead expense.172 the bill. We receive annual bills for magazine subscriptions Some utilities provide on-bill financing for energy because the quantity we will use (one per week or month) efficiency, renewable energy or demand response investments is very small and predictable. In some states, rules of the that the utility (or a third party) makes at the customer prem- regulatory commission require billing on a specified interval. ises. Where this occurs, a portion of the billing cost should be For example, in Washington state, the rules require billing assigned to the nonservice cost element. not less than bimonthly (Washington Administrative Code Title 480, Chapter 100, § 178[1][a]). In this situation, billing frequency in excess of that required by law or regulation is driven by consumption. The portion of the costs of reading meters and billing more frequently should be classified and 171 This is also the case for California customers who opt out of AMI (California Public Utilities Commission, 2014). 172 The same is true for any uncollectible charges for special services. If there 12.2 Uncollectible Accounts Expenses Uncollectible accounts expenses are the expenses from customers who have not paid their bills, due to financial is direct assignment of uncollectibles, charges related to non-energy billings or claims should be segregated from the remainder of Account 904 and directly assigned as overhead expenses.Page 165 of 276
REGULATORY ASSISTANCE PROJECT (RAP)® ELECTRIC COST ALLOCATION FOR A NEW ERA | 163 distress, bankruptcy or departure from the service territory.173 on the cost of service study, because direct-assigned late Some analyses erroneously allocate the costs of former payment revenues and deposits partly offset direct-assigned customers to the classes of current customers on a per- uncollectible accounts expenses. customer basis or by direct assignment. However, these costs The worst cost allocation outcome is inconsistency: are not caused by any current customer in any particular assigning uncollectible accounts expenses largely to class.174 Although certain accounts have unpaid electric bills, residential customers using direct assignment or a those accounts are former customers who are no longer per-customer allocation while using a broad allocation members of any class. method for late payment charges and customer deposits, Uncollectible accounts are related to class revenue in two ways. First, the higher the bills of a particular class, the more revenue is at risk of becoming uncollectible. Second, if the customer had shut down or left before rates were set, most of the costs reflected in the uncollectible bills would have been allocated to the remaining customers, in all classes. even though both of these items are also largely paid by residential customers. 12.3 Customer Service and Assistance Utilities frequently classify customer service and in- Hence, uncollectible revenues should be classified as revenue- formation expenses as customer-related and allocate them related and allocated in proportion to revenues, not customer in proportion to customer number. This approach is not number.175 reasonable, because these expenses are more likely to vary The treatment of four elements should be coordinated in the cost of service study: with class energy consumption and revenues. In general, larger customers have more complicated • Uncollectible accounts expenses. installations, metering and billing and warrant more time and • Late payment revenues if charged to all classes (some- attention from a utility. A utility customer service staff does times called forfeited discounts, often recorded in FERC not spend as much time and attention on each residential Account 450 in the Uniform System of Accounts). customer as on each large commercial or industrial customer, Customer deposits, which protect utilities against considering the fact that the larger customers may have bills uncollectibles and which offset rate base for most utilities 100 or 1,000 times that of the average residential customer. in North America. Indeed, most utilities have key accounts specialists — highly Interest paid to customers on customer deposits. trained customer service personnel who concentrate on the If uncollectible accounts expenses are assigned as an needs of the largest customers. Large customers may also • • overhead expense based on revenue, then all of these four have more complex billing arrangements, multiple delivery items should be allocated based on revenue. points, demand charges, campus billing, interruptible rates On the other hand, if uncollectible accounts expenses are and credits, transformer ownership credits and additional directly assigned to the originating class or using a customer complications that require more time from engineering, allocator, then late payment revenues and customer deposits legal and rate staff, supervisors and higher management, so should be assigned in the same manner. the billing costs should be weighted proportionately to the Although an allocation based on revenue is more appropriate, the consistent allocation of these four items by either customer classes with complex arrangements. The alternative to a simple customer allocator for revenue or direct assignment may not have a large effect customer service costs may be to use a weighted customer 173 For most utilities, the residential class produces most of the uncollectible accounts expenses, in part because large customers are more often required to post deposits or demonstrate good financial standing. However, when large customers’ bills are uncollectible, often due to bankruptcy, the amounts can be very large. 174 Texas has one of the strongest precedents on this issue for utilities not in ERCOT and therefore not subject to competition. See Public Utility Commission of Texas (2018, p. 47, findings of fact 303-305). 175 Texas and California have treated these costs as overhead costs, allocated by revenue to all customer classes.Page 166 of 276
164 | ELECTRIC COST ALLOCATION FOR A NEW ERA allocator — in which larger customers are assigned a multiple of the costs assigned to smaller customers — or a combination of customer number and class revenue. The retail allocators should be derived from the relative cost or effort required per customer for each class. Most utilities can segregate costs for key accounts and identify the customer classes for which these services are provided. Although these costs should be recorded in customer service costs (accounts 907 to 910), they can appear in other accounts. Wherever they appear, they should be assigned to the classes that use them. The costs should be assigned mostly to the largest commercial and industrial customers who receive the services, perhaps with a small amount allocated to classes with smaller nonresidential customers.176 Account 908, which FERC identifies as customer assistance expenses, contains general advice and education on electrical safety and energy conservation. Account 909 involves informational advertising. Those activities are generally not extensive (or expensive), and allocation is not REGULATORY ASSISTANCE PROJECT (RAP)® 12.4 Sales and Marketing Sales and marketing costs are often erroneously allocated by the number of customers rather than the purpose of sales and marketing expenses: to increase electric loads (e.g., by economic development or load retention). Since the purpose of these costs is to increase contributions to margin from new or existing customers, thereby reducing the need for future rate increases, the costs should be allocated by base rate revenue or another broad allocation factor such as rate base. Some sales and marketing funds are used to promote important public policy programs (such as energy efficiency or electric vehicles, discussed further in sections 14.1 and 7.1.3, respectively). Other sales and marketing efforts, however, may promote programs that ratepayers arguably should not fund at all (e.g., promotion of inefficient electric resistance heating by a utility that is almost entirely fossil fuel-based, through sponsorships and advertising) and should be examined closely in revenue requirements cases. usually controversial. But many utilities also book to this account energy efficiency expenditures, which can represent a few percent of consumer bills. If there are significant costs in this account, they are likely to be dominated by energy efficiency programs, which should be allocated as described in Section 14.1. 176 A few large customers billed on multiple small or medium commercial tariffs may receive key-customer services, such as franchisees, government agencies and small accounts attached to large ones.
As listed on the current system
Prefiled testimony: 10/21/2026 - Sponsor: TBD / Witness: Melissa Whited [26-05-10]