Prefiled testimony
Witness: Melissa Whited
Files3
Synapse - Eversource COS and Rate Design Testimony Final.pdf
PDF · 829 KB · 48 pagesText searchable
Download Synapse - Eversource COS and Rate Design Testimony Final.pdfRead the text of Synapse - Eversource COS and Rate Design Testimony Final.pdf
MW-2- Synapse Attachment.pdf
PDF · 4.6 MB · 276 pagesText searchable
Download MW-2- Synapse Attachment.pdfRead the text of MW-2- Synapse Attachment.pdf
MW-1 - Synapse Attachment.pdf
PDF · 734 KB · 13 pagesText searchable
Download MW-1 - Synapse Attachment.pdfRead the text of MW-1 - Synapse Attachment.pdf
Page 182 of 276
180 | ELECTRIC COST ALLOCATION FOR A NEW ERA REGULATORY ASSISTANCE PROJECT (RAP)® Figure 46. Class loads for illustrative hourly allocation example 2,500 Street lighting Industrial Commercial Megawatts 2,000 Residential 1,500 1,000 500 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 Hour of day worth of hourly dispatch of four resources: a baseload The generation cost allocation for a class would be: resource (perhaps nuclear), solar, a peaker (perhaps a Lh combustion turbine) and storage (both as charging load below the axis and generation above the line). In this example, the storage charges from excess base capacity in the early morning and then from solar, and discharges in the evening to replace the waning solar. The actual application of hourly allocation would include 8,760 hours from an actual or typical year, with a wide range of load levels, availability of the base resource and solar output patterns. Figure 46 provides hourly energy requirements by class (including losses) for the same day as in Figure 45. Table 39 on the next page provides two types of data from Figure 45 and Figure 46: each class’s share of the load in each hour, and the portion of each resource’s daily generation that occurs in the hour. r,h r r,h Where Lh = class share of load in hour h Sr,h = share of resource r output that occurred in hour h Cr = cost of resource (in this example, for the day) Table 40 shows the result of this computation for the data in Table 39. The lighting class, for example, would pay for 1.8% of the base resource, 2.2% of the peakers and just 0.6% of the solar. Table 40 also shows each class’s share of total load, for reference.Page 183 of 276
REGULATORY ASSISTANCE PROJECT (RAP)® ELECTRIC COST ALLOCATION FOR A NEW ERA Table 39. Hourly class load share and resource output Class share of load Resource output: Percentage occurring by hour Hour Residential Commercial Industrial Street lighting 1 39.0% 35.3% 22.5% 3.2% 4% 0% 0% 0% 2 37.0% 36.2% 23.5% 3.3% 4% 0% 0% 0% 3 36.4% 36.7% 23.5% 3.4% 4% 0% 0% 0% 4 36.7% 37.0% 23.1% 3.3% 4% 0% 0% 0% 5 37.5% 36.6% 22.7% 3.2% 4% 0% 0% 0% 6 38.4% 37.2% 21.4% 3.0% 4% 0% 3% 0% 7 39.7% 37.1% 20.6% 2.6% 4% 0% 8% 0% 8 39.8% 39.2% 19.5% 1.6% 4% 0% 9% 0% 9 38.8% 42.6% 18.4% 0.2% 4% 0% 9% 0% 10 36.7% 44.8% 18.2% 0.2% 4% 0% 8% 0% 11 36.6% 45.1% 18.1% 0.2% 4% 0% 11% 0% 12 35.9% 45.8% 18.1% 0.2% 4% 0% 10% 0% 13 36.7% 44.8% 18.3% 0.2% 4% 0% 7% 1% 14 37.5% 44.0% 18.2% 0.2% 4% 0% 13% 0% 15 36.3% 44.7% 18.8% 0.2% 4% 0% 12% 0% 16 37.4% 43.5% 18.8% 0.2% 4% 0% 7% 0% 17 41.5% 40.6% 17.4% 0.4% 4% 5% 1% 25% 18 44.7% 37.3% 16.1% 2.0% 4% 13% 0% 25% 19 45.2% 35.8% 16.8% 2.2% 4% 13% 0% 18% 20 44.2% 36.1% 17.4% 2.3% 4% 15% 0% 12% 21 44.4% 35.4% 17.8% 2.3% 4% 15% 0% 10% 22 45.9% 33.8% 17.9% 2.4% 4% 19% 0% 5% 23 42.8% 35.1% 19.4% 2.6% 4% 12% 0% 1% 24 41.6% 35.5% 20.1% 2.8% 4% 6% 0% 3% All hours 39.7% 39.6% 19.1% 1.6% 100% 100% 100% 100% Note: Percentages may not add up to 100 because of rounding. Table 40. Class shares of resource cost responsibilities and load Residential Secondary commercial Primary industrial Street lighting Resource type Base 39.6% 39.2% 19.4% 1.8% Peaker 44.3% 35.8% 17.7% 2.2% Solar 37.5% 43.1% 18.7% 0.6% Storage 43.8% 37.4% 17.2% 1.7% Class share of total load 39.7% 39.6% 19.1% 1.6% Base Peaking Solar Storage | 181Page 184 of 276
182 | ELECTRIC COST ALLOCATION FOR A NEW ERA REGULATORY ASSISTANCE PROJECT (RAP)® Works Cited in Part III Arkansas Public Service Commission. (2013, December 30). Docket No. 13-028-U, Order No. 21 in general rate case for Entergy Arkansas. Retrieved from http://www.apscservices.info/pdf/13/13-028-U_431_1.pdf Barrett, L. (2012, March 29). Nova Scotia-located coal plants next to go. Australia’s Mining Monthly. Retrieved from https://www.miningmonthly.com/archive/news/1300953/nova-scotia-located-coal-plants BC Hydro. (2014, June 19). 2015 rate design application (RDA): Cost of service (COS) methodology review [Presentation]. Retrieved from http://www.bchydro.com/content/dam/BCHydro/customer-portal/documents/corporate/regulatoryplanning-documents/regulatory-matters/cos-methodology-review-workshop-presentation.PDF Behnke, M., Erdman, W., Horgan, S., Dawson, D., Feero, W., Soudi, F., et al. (2005). Secondary network distribution systems background and issues related to the interconnection of distributed resources (NREL/TP-560-38079). Golden, CO: National Renewable Energy Laboratory. Retrieved from https://www.nrel.gov/docs/fy05osti/38079.pdf Bonbright, J. (1961). Principles of public utility rates. New York, NY: Columbia University Press. Bonneville Power Administration. (n.d.). Current power rates [Webpage]. Retrieved from https://www.bpa.gov/ Finance/RateInformation/Pages/Current-Power-Rates.aspx Burbank Water and Power. (n.d.). BWP free WiFi [Webpage]. Retrieved from https://www.burbankwaterandpower.com/bwp-free-wifi Burlington Electric Department. (2019, February 1). Rates & fees [Webpage]. Retrieved from https://www.burlingtonelectric.com/rates-fees California Energy Commission. (2014, May 21). California transmission lines – substations enlargement maps. Retrieved from https://ww2.energy.ca.gov/maps/infrastructure/3part_enlargements.html California Public Utilities Commission. (2007, July 12). Opinion addressing electric and gas residential line extension allowance calculation methodology. Application No. 05-09-019 et al., Decision No. 07-07-019. Retrieved from http://docs.cpuc.ca.gov/PublishedDocs/WORD_PDF/FINAL_DECISION/70109.PDF California Public Utilities Commission. (2014, December 18). Decision regarding smartmeter opt-out provisions. Application No. 11-03-014 et al., Decision No. 14-12-078. Retrieved from http://docs.cpuc.ca.gov/PublishedDocs/ Published/G000/M143/K904/143904205.PDF Chelan County Public Utility District. (n.d.). Rates and policies [Webpage]. Retrieved from https://www.chelanpud.org/my-pud-services/rates-and-policies Chelan County Public Utility District. (2018, November 5). Cryptocurrency rate: Board preview of Nov. 7 public information meeting [Presentation]. Retrieved from https://www.chelanpud.org/docs/default-source/defaultdocument-library/nov-5-board-preview-of-nov-7-info-meeting.pdf Chernick, P. (2010, August 20). Rebuttal testimony on behalf of the Office of the People’s Counsel. Maryland Public Service Commission Case No. 9230. Chernick, P., and Meyer, M. (1982). Capacity/energy classifications and allocations for generation and transmission plant. Award Papers in Public Utility Economics and Regulation. East Lansing, MI: Michigan State University, Institute for Public Utilities.Page 185 of 276
REGULATORY ASSISTANCE PROJECT (RAP)® ELECTRIC COST ALLOCATION FOR A NEW ERA Colorado Public Utilities Commission. (2018, June 15). Proceeding No. 17AL-0477E, Decision No. C18-0445 in rate case for Black Hills/Colorado Electric Utility Co. Retrieved from https://www.dora.state.co.us/pls/efi/EFI_Search_UI.Show_ Decision?p_session_id=&p_dec=25270 Coyle, E. (1982, June 24). Average and excess demand once again. Public Utilities Fortnightly. Delmarva Power & Light. (2016, August 15). Response to the Office of the People’s Counsel data request 5-11, Attachment D. Maryland Public Service Commission Case No. 9424. Drazen, M. and Mikkelsen, R. (2013, December 2). Rebuttal evidence on behalf of the Industrial Group. Nova Scotia Utility and Review Board NSPI-P-892/Matter No. M05473, Exhibit N-28. Retrieved from https://uarb.novascotia.ca/fmi/webd/UARB15 Electric Reliability Council of Texas. (2018). 2017 ERCOT hourly load data [Data set]. Retrieved from http://www.ercot.com/gridinfo/load/load_hist/ El Paso Electric Co. (2015, October 29). El Paso Electric Company’s response to Office of Public Utility Counsel’s fifth request for information. Public Utility Commission of Texas Docket No. 44941. Retrieved from http://interchange.puc. texas.gov/Search/Documents?controlNumber=44941&itemNumber=215 Energy and Environmental Economics. (2014). California transportation electrification assessment — Phase 2: Grid impacts. San Francisco, CA: Author. Retrieved from http://www.caletc.com/wp-content/uploads/2016/08/CalETC_ TEA_Phase_2_Final_10-23-14.pdf ENGIE Resources (n.d.). Historical data reports [Webpage]. Retrieved from https://www.engieresources.com/historical-data Entergy Corp. (n.d.). How we trim trees [Webpage]. Retrieved from https://www.entergy.com/tree_trimming_how/ Fang, C. (2017, January 20). Direct testimony on behalf of San Diego Gas & Electric. California Public Utilities Commission Application No. 17-01-020. Retrieved from https://www.sdge.com/regulatory-filing/20491/applicationsdge-authority-implement-priority-review-and-standard-review Federal Energy Regulatory Commission. (n.d.). Form 1 — electric utility annual report [Database]. Retrieved from https://www.ferc.gov/docs-filing/forms/form-1/data.asp Federal Energy Regulatory Commission. (2008, April 21). Opinion and order on initial decision. 123 FERC ¶ 61,047. Docket No. EL05-19-002, Opinion No. 501. Retrieved from https://www.ferc.gov/whats-new/commmeet/2008/041708/E-7.pdf Federal Energy Regulatory Commission. (2011, July 21). Transmission planning and cost allocation by transmission owning and operating public utilities. 136 FERC ¶ 61,051. Docket No. RM10-23-000, Order No. 1000. Retrieved from https://www.ferc.gov/whats-new/comm-meet/2011/072111/E-6.pdf Gorman, H. (2018, November 15). Testimony on behalf of National Grid. Massachusetts Department of Public Utilities Docket No. 18-150. Retrieved from https://fileservice.eea.comacloud.net/FileService.Api/file/FileRoom/10043215 Green Mountain Power. (2016, April 1). Electric service extensions and relocations. Retrieved from http://greenmountainpower.com/wp-content/uploads/2017/01/Line-Extension-Rules-Regulations-4.1.16.pdf Hammer, N. (2018, May 30). Direct testimony on behalf of MidAmerican Energy Co. Iowa Utilities Board Docket No. RPU2018-0003. Retrieved from https://efs.iowa.gov/efs/ShowDocketSummary.do?docketNumber=RPU-2018-0003 | 183Page 186 of 276
184 | ELECTRIC COST ALLOCATION FOR A NEW ERA REGULATORY ASSISTANCE PROJECT (RAP)® Henry, T. (2012, October 31). Luminant coal units get permission to mothball this winter. National Public Radio. Retrieved from https://stateimpact.npr.org/texas/2012/10/31/luminant-coal-units-get-go-ahead-to-mothball-thiswinter/ Illinois Commerce Commission. (2008, September 10). Docket No. 07-0566, order in rate case for Commonwealth Edison Co. Retrieved from https://www.icc.illinois.gov/docket/files.aspx?no=07-0566&docId=128596 Institute for Energy Economics and Financial Analysis. (2019, March 4). Owners say Gibbons Creek coal plant in Texas will remain in mothball status. Retrieved from http://ieefa.org/owners-say-gibbons-creek-coal-plant-in-texas-willremain-in-mothball-status/ Johnson, B. (1980, December 4). Cost allocations: Limits, problems and alternatives. Public Utilities Fortnightly. Kahn, E. (1988). Electric utility planning and regulation. Washington, DC: American Council for an Energy-Efficient Economy. La Capra, R. (1992). Direct testimony on behalf of Boston Edison. Massachusetts Department of Public Utilities Docket No. 92-92. Lazar, J., and Baldwin, X. (2011). Valuing the contribution of energy efficiency to avoided marginal line losses and reserve requirements. Montpelier, VT: Regulatory Assistance Project. Retrieved from https://www.raponline.org/knowledgecenter/valuing-the-contribution-of-energy-efficiency-to-avoided-marginal-line-losses-and-reserve-requirements/ Lazard. (2018). Lazard’s levelized cost of energy analysis — Version 12.0. Retrieved from https://www.lazard.com/ media/450784/lazards-levelized-cost-of-energy-version-120-vfinal.pdf Levin, A. (2017, June 30). Prefiled response testimony on behalf of NW Energy Coalition, Renewable Northwest and Natural Resources Defense Council in rate case for Puget Sound Energy. Washington Utilities and Transportation Commission Docket No. UE-170033. Retrieved from https://www.utc.wa.gov/_layouts/15/CasesPublicWebsite/ GetDocument.ashx?docID=2309&year=2017&docketNumber=170033 Manitoba Hydro. (2015). Cost of service methodology review. Retrieved from https://www.hydro.mb.ca/regulatory_ affairs/pdf/electric/cost_of_service_study_submission/appendix_3_1_pcoss14.pdf Manitoba Public Utility Board (2016, December 20). Order in respect of a review of Manitoba Hydro’s cost of service study methodology. Order No. 164/16. Retrieved from http://www.pubmanitoba.ca/v1/pdf/16hydro/164-16.pdf Marcus, W. (1987). Testimony on behalf of Alberta Federation of Rural Electrification Associations and Alberta Association of Municipal Districts and Counties. Alberta Public Utilities Board 1987 Electric Energy Marketing Agency adjustment. Massachusetts Department of Public Utilities. (1989). Docket No. 88-250, order in rate case for Western Massachusetts Electric Co. Meyer, M. (1981, December 17). Clarifying NARUC demand allocation methods. Public Utilities Fortnightly. Michigan Public Service Commission. (2017, July 31). Case No. U-18124, order in natural gas rate case for Consumers Energy Co. Retrieved from https://mi-psc.force.com/sfc/servlet.shepherd/version/ download/068t0000001UUAgAAO Midcontinent Independent System Operator. (2018). Planning year 2019-2020 loss of load expectation study report. Carmel, IN: Author. Retrieved from https://cdn.misoenergy.org/2019%20LOLE%20Study%20Report285051.pdfPage 187 of 276
REGULATORY ASSISTANCE PROJECT (RAP)® ELECTRIC COST ALLOCATION FOR A NEW ERA Minnesota Power. (2013, May 28). Minnesota Power construction guide: Home edition. Retrieved from https://mnpower. com/Content/Documents/CustomerService/ConstructionCenter/residential-construction-guide-with-toc.pdf Minnesota Public Utilities Commission. (2016, June 3). Docket No. G-008/GR-15-424, order in natural gas rate case for CenterPoint Energy. Retrieved from https://www.edockets.state.mn.us/EFiling/edockets/searchDocuments.do?metho d=showPoup&documentId={92AB0946-4F77-4A70-BF38-7D36F88AC979}&documentTitle=20166-121975-01 Monitoring Analytics. (2014). 2013 state of the market report for PJM. Eagleville, PA: Author. Retrieved from http://www.monitoringanalytics.com/reports/PJM_State_of_the_Market/2013.shtml Monitoring Analytics. (2019). 2018 state of the market report for PJM. Eagleville, PA: Author. Retrieved from http://www.monitoringanalytics.com/reports/PJM_State_of_the_Market/2018.shtml National Association of Regulatory Utility Commissioners. (1989). Gas distribution rate design manual. Washington, DC: Author. Retrieved from http://documents.dps.ny.gov/public/Common/ViewDoc.aspx?DocRefId=%7B04381803-1D3A4CD7-BBE3-64EDB16835C0%7D National Association of Regulatory Utility Commissioners. (1992). Electric utility cost allocation manual. Washington, DC: Author. Retrieved from https://pubs.naruc.org/pub/53A3986F-2354-D714-51BD-23412BCFEDFD Newfoundland and Labrador Hydro (2018). 2018 cost of service methodology review report. Retrieved from http:// www.pub.nf.ca/applications/NLH2018CostofService/application/Application%20-%20Cost%20of%20Service%20 Methodology%20-%202018-11-15.PDF Northern Indiana Public Service Co. (2018). 2018 integrated resource plan executive summary. Retrieved from https://www.nipsco.com/docs/librariesprovider11/rates-and-tariffs/irp/irp-executive-summary.pdf Northern States Power Co.-Minnesota. (2010, November 3). General rules and regulations. Retrieved from https://www.xcelenergy.com/staticfiles/xe/PDF/Regulatory/Me_Section_6.pdf Nova Scotia Power. (2013a, June 28). 2013 Nova Scotia Power cost of service study. Nova Scotia Utility and Review Board Matter No. M05473, Exhibit N-1. Retrieved from https://uarb.novascotia.ca/fmi/webd/UARB15 Nova Scotia Power. (2013b, September 12). 2013 Nova Scotia Power cost of service study: Attachment 1 in response to IR-15. Nova Scotia Utility and Review Board Matter No. M05473, Exhibit N-3(i). Retrieved from https://uarb.novascotia. ca/fmi/webd/UARB15 Nova Scotia Utility and Review Board. (1995, September 22). Docket No. NSPI864, order in generic hearing respecting cost of service and rate design for Nova Scotia Power. Nova Scotia Utility and Review Board. (2012, August 20). Matter No. M04862, decision approving with conditions a load retention rate mechanism. Retrieved from https://uarb.novascotia.ca/fmi/webd/UARB15 Nova Scotia Utility and Review Board. (2014, March 11). Matter No. M05473, decision approving amended 2013 Nova Scotia Power cost of service study. Retrieved from https://uarb.novascotia.ca/fmi/webd/UARB15 NV Energy. (n.d.). IS-2 interruptible irrigation service [Webpage]. Retrieved from https://www.nvenergy.com/account-services/energy-pricing-plans/is-2 Otter Tail Power Co. (2017, July 21). Tariff schedules applicable to electric service of Otter Tail Power Company. Retrieved from https://www.otpco.com/media/1300/mn_indexandgeneralrulesandregulations.pdf | 185Page 188 of 276
186 | ELECTRIC COST ALLOCATION FOR A NEW ERA REGULATORY ASSISTANCE PROJECT (RAP)® Parmesano, H., Rankin, W., Nieto, A., and Irastorza, V. (2004). Classification and allocation methods for generation and transmission in cost-of-service studies. Los Angeles, CA: National Economic Research Associates. Retrieved from https://www.nera.com/content/dam/nera/publications/archive1/final%20report%20to%20PUBMH-NERA-20040401-1.pdf Patton, D., LeeVanSchaick, P., and Chen, J. (2017). 2016 assessment of the ISO New England electricity markets. Fairfax, VA: Potomac Economics. Retrieved from https://www.iso-ne.com/static-assets/documents/2017/08/isone-2016-som-report-full-report-final.pdf Patton, D., LeeVanSchaick, P., Chen, J., and Palavadi Naga, R. (2018). 2017 state of the market report for the New York ISO markets. Fairfax, VA: Potomac Economics. Retrieved from https://www.potomaceconomics.com/wp-content/ uploads/2018/06/NYISO-2017-SOM-Report-5-07-2018_final.pdf Peppin, M. (2013, November 4). Direct testimony on behalf of Northern States Power Co.-Minnesota. Minnesota Public Utilities Commission Docket No. E002/GR-13-868, Document No. 20311-93284-02. Retrieved from https:// www.edockets.state.mn.us/EFiling/edockets/searchDocuments.do?method=showPoup&documentId={21D30B7CA614-4649-AEE7-CDA29BD1192B}&documentTitle=201311-93284-02 Public Service Company of Colorado. (2018, December 3). Rules and regulations: Electric service distribution extension policy. Retrieved from https://www.xcelenergy.com/staticfiles/xe-responsive/Company/Rates%20&%20 Regulations/18AL-0852E-AL-1785-E-Distribution-Extension-Policy-Tariffs-FINAL.pdf Public Utility Commission of Texas. (2000, November 22). Interim order establishing generic customer classification and rate design. Docket No. 22344, Order No. 40. Retrieved from http://interchange.puc.texas.gov/Search/ Documents?controlNumber=22344&itemNumber=655 Public Utility Commission of Texas. (2015, December 18). Docket No. 43695, order in rate case for Southwestern Public Service Co. Retrieved from http://interchange.puc.texas.gov/Documents/43695_1018_876737.PDF Public Utility Commission of Texas. (2018, March 19). Docket No. 46449, order on rehearing in rate case for Southwestern Electric Power Co. Retrieved from http://interchange.puc.texas.gov/ Documents/46449_825_973078.PDF Rea, C. (2013, May 17). Testimony on behalf of MidAmerican Energy Co. Iowa Utilities Board Docket No. RPU-20130004. Retrieved from https://efs.iowa.gov/cs/groups/external/documents/docket/mdaw/mtgy/~edisp/182629.pdf Rudkevich, A., Hornby, R., and Luckow, P. (2014, February 28). Audit of Port Hawkesbury paper load retention tariff. Synapse Energy Economics and Newton Energy Group. Nova Scotia Utility and Review Board Matter No. M05803, Exhibit N-4. Retrieved from https://uarb.novascotia.ca/fmi/webd/UARB15 Seattle Municipal Archives. (1977, September 27). Utilities Committee meeting (Record Series 4601-03, Event ID 6544) [Audio recording]. Retrieved from https://www.seattle.gov/cityarchives/exhibits-and-education/seattlevoices/energy-conservation Seelye, W. (2016, November 23). Direct testimony on behalf of Kentucky Utilities Co. Kentucky Public Service Commission Case No. 2016-00370. Retrieved from https://psc.ky.gov/pscecf/2016-00370/derek.rahn%40lge-ku. com/11232016073202/10_-_KU_Testimony_and_Exhibits_-_Malloy_to_Spanos_-_FINAL.pdf Sterzinger, G. (1981, July 2). The customer charge and problems of double allocation of costs. Public Utilities Fortnightly.Page 189 of 276
REGULATORY ASSISTANCE PROJECT (RAP)® ELECTRIC COST ALLOCATION FOR A NEW ERA Steward, J. (2014). Direct testimony on behalf of Rocky Mountain Power. Utah Public Service Commission Docket No. 13-035-184. Retrieved from https://pscdocs.utah.gov/electric/13docs/13035184/249702 ExJJJDirTestSteward1-3-2014.pdf U.S. Energy Information Administration. (n.d.-a). Annual electric power industry report, Form EIA-861: 2001 [Data file]. Retrieved from https://www.eia.gov/electricity/data/eia861 U.S. Energy Information Administration. (n.d.-b). Form EIA-861M sales and revenue: 1990-current [Data file]. Retrieved from https://www.eia.gov/electricity/data/eia861m/ U.S. Energy Information Administration. (1992). Form EIA-860A: 1990 [Data file]. Retrieved from https://www.eia.gov/electricity/data/eia860/ U.S. Energy Information Administration. (2018, October 12). Electric sales, revenue, and average price. Retrieved from https://www.eia.gov/electricity/sales_revenue_price/ Utah Public Service Commission. (1999, March 4). Docket No. 97-035-01, report and order in investigation into the reasonableness of rates and charges of PacifiCorp. Retrieved from www.utilityregulation.com/content/ orders/99UT9703501r.pdf Washington Utilities and Transportation Commission. (1981). Cause U-81-41, sixth supplemental order in rate case for Puget Sound Power and Light Co. Washington Utilities and Transportation Commission. (1993, August 16). Docket No. UE-920499, ninth supplemental order on rate design issues. Xcel Energy. (2018, October 2-4). Leading the energy future [Presentation at the Wolfe Research Conference]. Retrieved from investors.xcelenergy.com/file/4025308/Index?KeyFile=1500113448 | 187Page 190 of 276
188 | ELECTRIC COST ALLOCATION FOR A NEW ERA Part IV: Marginal Cost of Service Studies REGULATORY ASSISTANCE PROJECT (RAP)®Page 191 of 276
REGULATORY ASSISTANCE PROJECT (RAP)® ELECTRIC COST ALLOCATION FOR A NEW ERA | 189 18. Theory of Marginal Cost Allocation and Pricing T he fundamental principle of marginal cost pricing is that economic efficiency is served when prices reflect current or future costs — that is, the true value of the resources being used to serve customers’ loads — rather than historical embedded costs. This is a strong underpinning Economic efficiency is served when prices reflect the true value of the resources being used to serve customers’ loads. that most analysts agree on, but there are serious theoretical and computational complications associated with the development of marginal costs. Marginal cost studies start from a similar At one extreme, a true short-run marginal cost study will measure only a tiny fraction of the cost of service that varies from hour to hour with usage and holds all other aspects of functionalization as embedded cost studies: generation, the system constant. At the other extreme, a TSLRIC study transmission, distribution. However, the data used are not measures the cost of replacing today’s power system with at all the same as those used in an embedded cost of service a new optimally designed and sized system that uses the study. The typical marginal cost of service study requires newest technology. In between is a range of alternatives, detailed hourly data on loads by customer class, marginal many of which have been used in states like Maine, New energy costs and measures of system reliability (loss-of-energy York, Montana, Oregon and California to determine revenue expectation, peak capacity allocation factor, probability of allocation among classes. The major conceptual issue in peak, etc.), as well as multiyear data on loads and investments these studies is using very short-run metrics for energy for the transmission and distribution system. cost and longer-term metrics for capital costs (generation, As will be discussed below with specific examples and ap- transmission and distribution capacity and customer plications, the time horizon of marginal cost studies and even connection costs). Many studies use these mixed time of individual components within studies can vary. Marginal horizons, but this is an error that should be avoided. costs can be measured in: • • • Marginal cost pricing generally is not connected to The short run, as with energy costs measured for one to the utility’s revenue requirement, except to some extent in three years, and all capital assets kept constant. restructured generation markets (where the costs are not sub- Intermediate periods ranging from six years (the length of ject to traditional cost of service regulation). The calculated two typical general rate cases for many utilities) to 15 years marginal costs may be greater or less than the allowed revenue (often used for analysis of T&D capital investments). requirement, which is normally computed on an accounting The long term, such as with long-run incremental costs or embedded cost basis. It is only happenstance if marginal for the entire generation function; long-run generation costs and embedded costs produce the same revenue. capacity costs based on equilibrium conditions; and the There is also no necessary connection between marginal rental of customer equipment in some marginal custom- cost pricing and cost allocation. To summarize the material er cost studies. The longest possible analysis would be a discussed in more depth below, in its simplest hypothetical total service long-run incremental cost study where an form, a marginal cost study computes marginal costs for optimal system is costed out. different elements of service, and these are multiplied by the
As listed on the current system
Prefiled testimony: 10/21/2026 - Sponsor: TBD / Witness: Melissa Whited [26-05-10]