  1. Page 267 of 276

    REGULATORY ASSISTANCE PROJECT (RAP)® ELECTRIC COST ALLOCATION FOR A NEW ERA | 265 or in a more specific sense to denote the customer demand at Loss-of-energy expectation a specific point in time. A mathematical study of a utility system, applying expected availability of multiple generating resources, that estimates Load factor the expected energy loss at each hour of the year when The ratio of average load of a customer, customer class power supply and demand response resources are insufficient or system to peak load during a specific period of time, to meet customer demand. Related terms: loss-of-load expressed as a percentage. probability, loss-of-load hours, loss-of-load expectation, probability of peak and expected unserved energy. Load following The process of matching variations in load over time by Loss-of-energy expectation method increasing or decreasing generation supply or, conversely, A method for allocating demand-related costs in a manner decreasing or increasing loads. One or more generating that is weighted over all of the hours with reliability risks. units or demand response resources will be designated as the load following resources at any given time. Baseload Marginal cost of service study and intermediate generation is generally excluded from this A cost allocation study that apportions costs among customer category except in extraordinary circumstances. classes using estimates of how costs change over time in response to changes in customer usage. See also embedded Load shape cost of service study and total service long-run incremental The distribution of usage across the day and year, reflecting cost. the amount of power used in low-cost periods versus highcost periods. Marginal costs The cost of augmenting output. Short-run marginal costs Long-run marginal costs/long-run incremental costs are the incremental expenses associated with increasing The costs of expanding or maintaining the level of utility output with existing facilities. Long-run marginal costs are service, including the cost of a new or replacement power the incremental capital and operating expenses associated plants, transmission and distribution, reserves, marginal with increasing output over time with an optimal mix of losses, and administrative and environmental costs, measured assets. Total system long-run incremental costs are the costs over a period of years in which new investment is expected to of building a new system in its entirety, a measure used to be needed. determine if an existing utility system is economical. Losses/energy losses/line losses Marginal cost revenue requirement Abbreviation: The energy (kilowatt-hours) and power (kilowatts) lost or MCRR unaccounted for in the operation of an electric system. Losses An output in a marginal cost of service study, where the are usually in the form of energy lost to heat, sometimes marginal unit costs for each element of the electric system referred to as technical losses; energy theft from illegal are multiplied by the billing determinants for each class connections or tampered meters is sometimes referred to as to produce a class marginal cost revenue requirement for nontechnical losses. each element. These can be aggregated to produce a system MCRR. It is only happenstance if the system MCRR equals the embedded cost revenue requirement, so the elements of the MCRR can be used in different ways to allocate embedded costs among the customer classes. See also reconciliation.
  2. Page 268 of 276

    266 | ELECTRIC COST ALLOCATION FOR A NEW ERA REGULATORY ASSISTANCE PROJECT (RAP)® Megawatt Abbreviation: MW includes the state, territorial and federal commissions that A megawatt is equal to 1 million watts or 1,000 kilowatts. regulate utilities and some transportation services. Megawatt-hour Abbreviation: MWh NERA method A megawatt-hour is equal to 1 million watt-hours or 1,000 An approach to measuring marginal costs for electric utilities kilowatt-hours. that considers a mix of time frames. It looks at customerrelated costs such as metering on a full replacement or new Megawatt-year install basis and at transmission or distribution capacity costs A megawatt-year is the amount of energy that would equal over a time frame of 10 years or more to include at least some 1 megawatt continuously for one year, or 8.76 million capacity upgrades. Generation costs consider the new install kilowatt-hours. Also known as an average megawatt. costs for peaking capacity and a dispatch model approach to variable energy costs. The NERA method has formed the Meter data management system foundation for the methods used in several states today, A computer and control system that gathers metering but each state has modified the approach. This approach is information from smart meters and makes it available to named after the firm that developed it in the 1970s, National the utility and, optionally, to the customer. A meter data Economic Research Associates (now NERA Economic management system is part of the suite of smart technologies Consulting). and is integral to the smart grid concept. New-customer-only method Abbreviation: NCO Midpeak A short-run method for estimation of marginal customer Hours that are between on-peak hours and off-peak hours. connection costs based on the cost of hookups for new These are typically the hours when intermediate power plants customers. This method may or may not include the are operating but peaking units are not. Used primarily in percentage of existing hookups that are replaced every year. the base-intermediate-peak cost allocation method and in See also rental method. time-of-use rate design. Noncoincident peak Abbreviation: NCP Minimum system method The maximum demand of a customer, group of customers, A method for classifying distribution system costs between customer class, distribution circuit or other portion of a customer-related and demand- or energy-related. It estimates utility system, independent of when the maximum demand the cost of building a hypothetical system using the minimum for the entire system occurs. size components available as the customer-related costs and the balance of costs as demand-related or energy-related. Off-peak The period of time that is not on-peak. During off-peak Municipal utility Abbreviation: muni periods, system costs are generally lower and system A utility owned by a unit of government and operated under reliability is not an issue, and only generating units with the control of a publicly elected body. lower short-run variable costs are operating. This may include high-load hours if nondispatchable generation, such as solar National Association of Regulatory Utility Commis- photovoltaic energy, is significant within the service area. sioners Acronym: NARUC Time-of-use rates typically have off-peak prices that are lower The association of state and federal regulatory agencies that than on-peak prices. determine electric utility tariffs and service standards. It
  3. Page 269 of 276

    REGULATORY ASSISTANCE PROJECT (RAP)® ELECTRIC COST ALLOCATION FOR A NEW ERA On-peak Peak demand The period of time when storage units and generating The maximum demand by a single customer, a group of units with higher short-run variable costs are operating to customers located on a particular portion of the electric supply energy or when transmission or distribution system system, all of the customers in a class or all of a utility’s congestion is present. During on-peak periods, system costs customers during a specific period of time — hour, day, are higher than average and reliability issues may be present. month, season or year. | 267 Many rate designs and utility programs are oriented to reducing on-peak usage. Planning and investment decisions Peaking resources/peaking generation/peakers are often driven by expectations about the timing and Generation that is used to serve load during periods of high magnitude of peak demand during the on-peak period. demand. Peaking generation typically has high fuel costs or Time-of-use rates typically have on-peak prices that are limited availability (e.g., storage of hydrogeneration) and often higher than off-peak prices. has low capital costs. Peaking generation is used for a limited number of hours, especially as compared with baseload Operational characteristics method generation. Peaking resources often include nongeneration The traditional version of this method uses the capacity resources, such as storage or demand response. factor of a resource to determine the energy-related percentage of the costs of a generation asset and designates Peak load the remainder as demand-related. Although this provides The maximum total demand on a utility system during a a reasonable result in some circumstances, it inaccurately period of time. increases the demand-related percentage for less-reliable resources. A variation on this approach is to use the operating Peak responsibility method factor — the ratio of output to the equivalent availability of A method of apportioning demand-related generation or the unit — as the energy-related percentage. transmission costs based on the customer class share of maximum demand on the system. The metric can be a single Operations and maintenance costs Abbreviation: O&M hour (1 CP), the highest hour in several months (such as 4 CP), All costs associated with operating, maintaining and the highest hour in every month (12 CP) or the entire group of supporting the utility plant, including labor, outside services, highest peak hours (such as 200 CP). See also coincident peak. administrative costs and supplies. For generation facilities, this includes O&M expenses that vary directly with the Performance-based regulation Abbreviation: PBR output of the facility (dispatch O&M), such as fuel and water An approach to determining the utility revenue requirement treatment, and expenses that do not vary with output but are that departs from the classical formula of rate base, rate incurred yearly or monthly (nondispatch O&M). of return, and operation and maintenance expense. It is designed to encourage improved performance by utilities on Peak capacity allocation factor Acronym: PCAF cost control or other regulatory goals. An allocation factor where a weighted portion of demandrelated costs is assigned to every hour in excess of 80% of Postage stamp pricing peak demand. This method, used in California, is weighted The practice of having separate sets of prices for a relatively such that the peak hour has an allocation that is 20 times the small and easily identifiable number of customer classes. Every allocation for the hours at 81% of peak demand and twice the customer in a given customer class generally pays the same allocation of an hour at 90% of peak demand. prices regardless of location in a utility’s service territory, although separate prices may exist for subclasses in some cases.
  4. Page 270 of 276

    268 | ELECTRIC COST ALLOCATION FOR A NEW ERA REGULATORY ASSISTANCE PROJECT (RAP)® Power factor Rate base The fraction of power actually used by a customer’s electrical The net investment of a utility in property that is used equipment compared with the total apparent power supplied, to serve the public. This includes the original cost net of usually expressed as a percentage. A power factor indicates depreciation, adjusted by working capital, deferred taxes the extent to which a customer’s electrical equipment causes and various regulatory assets. The term is often misused to the electric current delivered at the customer’s site to be out describe the utility revenue requirement. of phase with system voltage. Rate case Power quality A proceeding, usually before a regulatory commission, The power industry has established nominal target operating involving the rates, revenues and policies of a public utility. criteria for a variety of properties associated with the power flowing over the electric grid. These include frequency, Rate design voltage, power factor and harmonics. Power quality describes Specification of prices for each component of a rate schedule the degree to which the system, at any given point, is able to for each class of customers, which are calculated to produce exhibit the target operating criteria. the revenue requirement allocated to the class. In simple terms, prices are equal to revenues divided by billing units, Primary voltage/primary service based on historical or assumed usage levels. Total costs are Primary voltage normally includes voltages between 2 kV and allocated across the different price components such as 34 kV. Primary voltage facilities generally are considered part customer charges, energy charges and demand charges, and of the distribution system. each price component is then set at the level required to generate sufficient revenues to cover those costs. Probability-of-dispatch method Abbreviation: POD A cost allocation methodology that considers the likelihood Rate of return that specific generating units and transmission lines will be The weighted average cost of utility capital, including the cost needed to provide service at specific periods during the year of debt and equity, used as one of the three core elements and assigns costs to each period based on those probabilities. of determining the utility revenue requirement and cost of service, along with rate base and operating expense. Public utilities commission/public service commission Rate year The state regulatory body that determines rates for regulated The period for which rates are calculated in a utility rate utilities. Although they go by various titles, these two are the case, usually the 12-month period immediately following most common. the expected effective date of new rates at the end of the proceeding. Public Utilities Regulatory Policy Act Acronym: PURPA Real economic carrying charge Acronym: RECC This federal law, enacted in 1978 and amended several times, An annualized cost expressed in percentage terms that contains two essential elements. The first requires state reflects the annual “mortgage” payment that would be regulators to consider and determine whether specific required to pay off a capital investment at the utility’s real rate-making policies should be adopted, including whether (net of inflation) cost of capital over its expected lifetime. It rates should be based on the cost of service. The second is used in long-run marginal cost and total system long-run requires utilities to purchase power at avoided-cost prices incremental cost studies. from independent power producers.
  5. Page 271 of 276

    REGULATORY ASSISTANCE PROJECT (RAP)® ELECTRIC COST ALLOCATION FOR A NEW ERA | 269 Reconciliation/revenue reconciliation/ an estimate of a rental price. This is a long-run method for cost reconciliation customer connection costs that has been a part of the NERA In a marginal cost of service study, it is only happenstance method for marginal costs. See also new-customer-only if the system marginal cost revenue requirement is equal method. to the embedded cost revenue requirement that needs to be recovered by the utility to earn a fair return. As a result, Reserves/reserve capacity/reserve margin the marginal cost revenue requirement must be reconciled The amount of capacity that a system must be able to supply, to the embedded cost revenue requirement. There are two beyond what is required to meet demand, to assure reliability primary methods for this: equal percentage of marginal cost when one or more generating units or transmission lines are and the inverse elasticity rule. See also marginal cost revenue out of service. Traditionally a 15% to 20% reserve capacity requirement. was thought to be needed for good reliability. In recent years, due to improved system controls and data acquisition, the Regional Greenhouse Gas Initiative accepted value in some areas has declined to 10% or lower. An agreement among Northeast and mid-Atlantic states to limit the amount of greenhouse gases emitted in the electric Restructured state/restructured utility/ power sector and to price emissions by auctioning emissions restructured market allowances. Replacement of the traditional vertically integrated utility with some form of competitive market. In some cases, the Regional transmission organization Abbreviation: RTO generation and transmission components of service are An independent regional transmission operator and service purchased by the customer-serving distribution utility provider established by FERC or that meets FERC’s RTO in a wholesale competitive market. In other cases, retail criteria, including those related to independence and market customers are allowed to choose their generation suppliers size. RTOs control and manage the high-voltage flow of directly in a competitive market. electricity over an area generally larger than the typical power company’s service territory. Most also serve as independent Retail competition/retail choice system operators, operating day-ahead, real-time, ancillary A restructured market in which customers are allowed to or services and capacity markets, and conduct system planning. must choose their own competitive supplier of generation See also independent system operator. and transmission services. In most states with retail choice, the incumbent utility or some other identified entity is Renewable portfolio standard Abbreviation: RPS designated as a default service provider for customers who A requirement established by a state legislature or regulator do not choose another supplier. In Texas, there is no default that each electric utility subject to its jurisdiction obtain service provider and all customers must choose a retail a specified portion of its electricity from a specified set of supplier. resources, usually renewable energy resources but sometimes including energy efficiency, nuclear energy or other Revenue requirement categories. The annual revenues that the utility is entitled to collect (as modified by adjustment clauses). It is the sum of operations Rental method and maintenance expenses, depreciation, taxes and a return A method of estimating marginal customer connection costs on rate base. In most contexts, “revenue requirement” and where the cost of new customer connection equipment is “cost of service” are synonymous. multiplied by the real economic carrying charge to obtain
  6. Page 272 of 276

    270 | ELECTRIC COST ALLOCATION FOR A NEW ERA REGULATORY ASSISTANCE PROJECT (RAP)® Rider/tariff rider Smart meter A special tariff provision that collects a specified cost or An electric meter with electronics that enable recording refunds a specific consumer credit, usually over a limited of customer usage in short time intervals and two-way period. See also adjustment clause and tracker. communication of data between the utility, the meter and optionally the customer. Secondary voltage/secondary service Secondary voltage normally includes only voltages under Spinning reserve 600 volts. Secondary voltage facilities generally are Any energy resource or decremental load that can be called considered part of the distribution system. upon within a designated period of time and that system operators may use to balance loads and resources. Spinning Service line/service drop reserves may be in the form of generators, energy storage or The conductor directly connecting an electricity customer to demand response. Spinning reserves may be designated by the grid, typically between the meter and the line transformer. how quickly they can be made available, from instantaneously The term “service drop” derives from the fact that in many up to some short period of time. In the past, this meant actual cases this line literally drops down from shared transformers rotating (spinning) power plant shafts, but today “spinning” attached to overhead lines, but today many are underground. reserves can be provided by battery storage, flywheels or customer load curtailment. Short-run marginal costs/short-run incremental costs Straight fixed/variable The costs incurred immediately to expand production A rate design method that designate much or all of the and delivery of utility service, not including any capital distribution system as a fixed cost and places all of those investments. They are usually much lower than the average costs on customers through customer charges. There are of costs but may be higher than average costs during periods related cost allocation approaches, which designate the of system stress or deficiency of capacity. entire distribution system as a customer-related cost and transmission and generation capacity as entirely demand- Site infrastructure related. See also minimum system method and basic The utility investment that is located at the customer customer method. premises and serves no other customers than those located at a single point of delivery from the distribution system. Stranded costs Site infrastructure costs are either paid by the customer at Utility costs for plant that is no longer used or no longer the time of service connection or else classified as customer- economic. This may include fossil-fueled power plants made related costs in cost of service studies. uneconomic by new generating technologies; assets that fail to perform before they are fully depreciated; or distribution Smart grid facilities built to serve customers who are no longer taking An integrated network of sophisticated meters, computer utility service, such as failed industrial sites and customers controls, information exchange, automation, information choosing self-generation as a replacement for utility service. processing, data management and pricing options that can Some regulators allow recovery of stranded costs from create opportunities for improved reliability, increased continuing customers and the inclusion of these costs in the consumer control over energy costs and more efficient cost of service methodology. utilization of utility generation and transmission resources.
  7. Page 273 of 276

    REGULATORY ASSISTANCE PROJECT (RAP)® ELECTRIC COST ALLOCATION FOR A NEW ERA | 271 Substation current service needs. Used as a metric for the cost that a new A facility with a transformer that steps voltage down from competitive entrant would incur to provide utility services, transmission or subtransmission voltage to distribution as an indicator of the equitability of current class cost voltage, to which one or more circuits or customers may be allocations and rate designs. connected. Tracker System load factor A rate schedule provision giving the utility company the The ratio of the average load of the system to peak load ability to change its rates at different points in time to during a specific period of time, expressed as a percentage. recognize changes in specific costs of service items without the usual suspension period of a rate filing. Costs included in System peak demand a tracker are sometimes excluded from cost of service studies. The maximum demand placed on the electric system at a See also adjustment clause and rider/tariff rider. single point in time. System peak demand may be a measure for an entire interconnection, for subregions within an Transformer interconnection or for individual utilities or service areas. A device that raises (steps up) or lowers (steps down) the voltage in an electric system. Electricity coming out of a Tariff generator is often stepped up to very high voltages (230 kW or A listing of the rates, charges and other terms of service for a higher) for injection into the transmission system and then utility customer class, as approved by the regulator. repeatedly stepped down to lower voltages as the distribution system fans out to connect to end-use customers. Some Test year energy loss occurs with every voltage change. Generally, A specific period chosen to demonstrate a utility’s need for higher voltages can transport energy for longer distances with a rate increase or decrease. It may include adjustments to lower energy losses. reflect known and measurable changes in operating revenues, expenses and rate base. A test year can be either historical or Transmission/transmission system projected (often called “future” or “forecast” test year). That portion of the electric system designed to carry energy in bulk, typically at voltages above 100 kV. The transmission Time-of-use rates/time-varying rates Abbreviation: system is operated at the highest voltage of any portion of TOU the system. It is usually designed to either connect remote Rates that vary by time of day and day of the week. TOU generation to local distribution facilities or to interconnect rates are intended to reflect differences in underlying costs two or more utility systems to facilitate exchanges of energy incurred to provide service at different times of the day between systems. or week. They may include all costs or reflect only time differentiation in a component of costs such as energy Transmission and distribution Abbreviation: T&D charges or demand charges. The combination of transmission service and equipment and distribution service and equipment. Total service long-run incremental cost Abbreviation: TSLRIC Used and useful The cost of replicating the current utility system with new A determination on whether investment in utility power supply, transmission and distribution resources, infrastructure may be recovered in rate base, such that new using current technology, and optimizing the system for rates will enable the utility to recover those costs in the future
  8. Page 274 of 276

    272 | ELECTRIC COST ALLOCATION FOR A NEW ERA REGULATORY ASSISTANCE PROJECT (RAP)® when that plant will be providing service (i.e., when it will be Volt-ampere reactive Acronym: VAR used and useful). In general, “used” means that the facility is A unit by which reactive power is expressed in an alternating actually providing service, and “useful” means that, without current electric power system. Reactive power exists in an the facility, either costs would be higher or the quality of alternating current circuit when the current and voltage are service would be lower. not in phase. Variable resources/variable renewable resources/ Volumetric energy charges/volumetric rate intermittent resources A rate or charge for a commodity or service calculated on the Technologies that generate electricity under the right basis of the amount or volume the purchaser receives. conditions, such as when the sun is shining for solar. Watt Vertically integrated utility The electric unit used to measure power, capacity or demand. A utility that owns its own generating plants (or procures A kilowatt equals 1,000 watts; a megawatt equals 1 million power to serve all customers), transmission system and watts or 1,000 kilowatts. distribution lines, providing all aspects of electric service. Watt-hour Volt Abbreviation: V The amount of energy generated or consumed with 1 watt The standard unit of potential difference and electromotive of power over the course of an hour. One kilowatt-hour force, formally defined to be the difference of electric equals 1,000 watts consumed or delivered for one hour. One potential between two points of a conductor carrying a megawatt-hour equals 1,000 kilowatt-hours. One terawatt- constant current of 1 ampere, when the power dissipated hour equals 1,000 megawatt-hours. In abbreviations, the W is between these points is equal to 1 watt. A kilovolt is equal capitalized in recognition of electrical pioneer James Watt. to 1,000 volts. In abbreviations, the V is capitalized in recognition of electrical pioneer Alessandro Volta. Zero-intercept approach/zero-intercept method A method for classifying distribution system costs between Volt-ampere customer-related and demand- or energy-related that uses A unit used for apparent power in an alternating current a cost regression calculation to compare components of electrical circuit, which includes both real power and reactive different size actually used in a system to estimate the costs of power. This unit is equivalent to a watt but is particularly a hypothetical zero-capacity distribution system. relevant in circumstances where voltage and current are out of phase, meaning there is a non-zero amount of reactive power. This unit and its derivatives (e.g., kilovolt-ampere) are typically used for line transformers.
  9. Page 275 of 276

    No text on this page. It may be a picture of a page, such as a scan or a chart.
  10. Page 276 of 276

    Regulatory Assistance Project (RAP)® 50 State Street, Suite 3 [phone removed] Belgium · China · Germany · India · United States Montpelier, VT 05602 raponline.org USA
1 page match

As listed on the current system

Prefiled testimony: 10/21/2026 - Sponsor: TBD / Witness: Melissa Whited [26-05-10]

This filing on the current system (opens in a new tab)