    54 | ELECTRIC COST ALLOCATION FOR A NEW ERA REGULATORY ASSISTANCE PROJECT (RAP)® decisions for storage and dispatchable hydro resources are adding capacity at any hour to a system, even off-peak hours, typically made to maximize the benefits from the limited has a small but discernible beneficial impact on reliability. supply of other time-shiftable generation resources. Many resources can be justified only if all of the attributes are Prior to PURPA, most long-term purchased power considered, including contribution to meeting peak demand contracts had separate capacity and energy elements. These and contribution to meeting other needs such as fuel cost were mostly for fuel-dependent power plants. This rate form reduction. allowed the owner to obtain capital cost recovery in a predict- The typical vertically integrated utility calculates the in- able payment and the receiving utility to control the output stalled capacity requirement by determining what amount of as needed to fit varying loads, paying for short-run variable existing and new capacity will provide acceptable reliability, costs as incurred. Today many power purchase contracts measured by such statistical parameters as the mathematical are expressed entirely on a volumetric basis, based on an expected value of the number of hours in which it cannot expected pattern of output. This change in how contracts are serve load or of the amount of customer energy it will not be priced in the wholesale market does not dictate any particular able to serve in a year, due to insufficient available genera- approach to how costs are allocated in the retail rate-setting tion. Those expected values are computed from models that process. simulate the scheduling of generation maintenance and the random timing of forced outages for many potential combi- Generation Capacity Costs Beyond these energy needs, most regions of the United nations of outages and load levels. In large portions of North America, the capacity requirement is determined regionally States also plan around the amount of shared generation by an ISO/RTO and then allocated to the load-serving capacity needed, and these processes can drive a significant entities, transmission control areas or utilities.28 amount of generation costs. The amount of capacity required by a utility system, typically denominated in megawatts (MWs) or gigawatts at the time of the system coincident peak, determines whether the utility should retire existing plants, add new resources or delay planned retirements, or keep the system as it is. All those decisions have costs and benefits. Required reserves are usually expressed as the percentage reserve margin, which is: (capacity – peak load) ÷ peak load; or (capacity ÷ peak load) – 1 Capacity may be defined as installed capacity, demon- This determination may be made by an ISO/RTO, a holding strated capacity or unforced capacity (installed capacity company or other aggregation of interconnected load. reduced by the resource’s forced outage rate). There may Although the typical planning procedures used to date by be special provisions to recognize that an installed MW of utilities and ISOs have often served their original purposes to solar, wind or seasonal hydro capacity is not equivalent to an measure the least-cost resources available at the utility system installed MW of combustion turbine capacity with guar- level, these procedures often oversimplify important aspects anteed fuel availability or a MW of battery storage capacity of overall capacity and reliability issues. The key principle is located at a distribution substation. Capacity requirements that reliability-related costs are not all “caused” by one hour may also be satisfied with curtailable load, energy storage or or a few hours of demand during the year. A system must expected price response to peak pricing. The cost of capacity have some form and level of capacity available at all hours. to meet a very short-term need is very different from the cost Loss-of-energy expectation27 studies generally show that of baseload capacity that serves customers around the clock 27 Different analysts refer to related measures as loss-of-load hours, loss-ofload expectation, expected unserved energy and loss-of-load probability. 28 Some of the utilities in the ISOs/RTOs are restructured and do not provide generation services, so the cost of service study need not deal with generation costs. However, all the utilities in the SPP and most of those in MISO are vertically integrated, as are some jurisdictions in PJM (West Virginia, Virginia, Kentucky and the PJM pieces of North Carolina, Indiana and Michigan) and ISO-NE (Vermont) and municipal and cooperative utilities in most restructured jurisdictions.
  2. Page 57 of 276

    REGULATORY ASSISTANCE PROJECT (RAP)® ELECTRIC COST ALLOCATION FOR A NEW ERA and throughout the year, and the cost analyst must be aware of these differences. | week) contribute to the need for installed capacity. • Forced outage rates. All generation units experience Peak load is generally the utility’s maximum hourly some mechanical failures. The higher the frequency output requirement under the worst weather conditions of forced outages, the more likely it is that a relatively expected in the average year (e.g., the coldest winter day high-load hour will coincide with outages, eliminating for winter-peaking utilities or the hottest summer day for available reserve and resulting in the loss of load. summer-peaking utilities). In the ISOs/RTOs, the peak load 55 • Unit sizes. If all of a system’s units were very small (say, is usually the utility’s contribution to the actual or expected under 1% of system peak), the random outages could ISO/RTO peak load. Although the reserve margin is often be expected to spread quite evenly through the year. stated on the basis of a single peak hour as a matter of mea- With larger units, outages are much lumpier, and loss surement convention, the derivation of the reserve margin of a small number of large units can create operating takes into account far more information than the load in that problems. Hence, systems with larger units tend to need one hour. The most important parameters in determining the higher reserve margins, all else being equal. required reserve margin are the following: • • • Other operating constraints. Although hydro resources Load shape, especially the relationships among the have the highest overall reliability, they produce power annual and weekly peaks and the number of other hours only when water is available to run them. Some hydro with loads close to the peaks. The system must have resources are required to be operated for flood control, enough reserve capacity to endure generation outages at navigation, irrigation, recreation, wildlife or other pur- the high-load hours. The near-peak hours matter because poses, and these other constraints may affect the ability the probability of any given combination of outages of the resource to provide power at full capacity when coinciding with the peak hour is very low, but if there are system peak loads occur. hundreds of hours in which that combination of outages Some of the factors in this list affect the reliability value would result in a supply shortage, the probability of loss of various types of generation, while others highlight the of load would be much larger. types of load that increase required capacity reserve levels. A Maintenance requirements. Utilities attempt to schedule large unit with frequent forced outages may contribute little generator maintenance in periods with loads lower to ongoing system reliability even though it has a significant than the peak, typically in the autumn and spring, and nameplate capacity. If such a unit has high ongoing costs occasionally in the winter for strongly summer-peaking that could be reduced or eliminated through retirement, utilities and in the summer for strongly winter-peaking continued operation must primarily be justified by its energy utilities. Utilities with both modest maintenance benefits. On the demand side, long daily periods of high loads requirements and several months with loads reliably well can mean that many weekday hours (and even some weekend below those in the peak months can schedule all routine hours) in each month will contribute to capacity require- maintenance in the off-peak months while leaving ments, proportionately shifting capacity responsibility toward enough active capacity to avoid any significant risk of customers with high load factors. Table 2 on the next page a capacity shortage in those months. But many utilities summarizes cost drivers for power supply capacity. have large maintenance requirements (especially for The value of capacity is partly a function of the type of coal-fired and nuclear units) and only modest reductions capacity and the location of that capacity. Although required in peak exposure in the shoulder months. After subtract- capacity (measured in MWs) is determined by demand in a ing required maintenance, the effective reserve margin subset of hours, along with the characteristics of the power may be very similar throughout the year, increasing the plants, the cost of capacity (measured in dollars per MW-year) chance that a combination of outages will result in loss of is in large part determined by energy requirements. load. As a result, high loads in any month (or perhaps any In the previous millennium, the cheapest form of
  3. Page 58 of 276

    56 | ELECTRIC COST ALLOCATION FOR A NEW ERA REGULATORY ASSISTANCE PROJECT (RAP)® Table 2. Cost drivers for power supply Resource type Purpose Investmentrelated costs Maintenance costs Fuel costs High High Low Medium Medium Medium Low Low High Very high Low Low or none Baseload nuclear, geothermal Power at all hours Coal, intermediate combined cycle Power at many hours Peaking Power in peak hours, plus reserves at all hours Hydro Power at some or all hours Wind Power at some hours High Low None Solar Power at some hours High Low None Storage Power at peak hours, plus reserves at all hours High Low Low — for purchased kWhs capacity to serve peak needs was typically considered to be a of certain lines can change significantly over time. Carrying combustion turbine. These units had low investment costs more power requires larger conductors, multiple conductors and low ongoing O&M expenses but were inefficient and and/or higher voltages, all of which increase costs. typically used more expensive fuels. These characteristics If each load center in a utility’s territory had about the made them perfect to run infrequently during peak times and amount of generation required to meet its peak load, and the for other short-term reliability needs. Conversely, it made power plants were similar so the utility had no interest in sense to make major investments in units with high upfront exporting power from one area to another, the transmission costs but high efficiency and cheap fuel prices and to run system would exist primarily to allow each load center to these units nearly year-round. These major investments were draw on the others for backup supply when local generation driven by year-round energy requirements, not peak loads. was unavailable. In real utility systems, power plants are often Today, in contrast, the least expensive form of capacity distributed very differently from load, with large centralized to serve extreme peak loads may not be a generating unit at plants built to capture economies of scale, often in areas far all. For very low-duration loads, demand response, customer from major load centers. Generation may be sited remotely response to critical peak pricing or battery storage may be away from load for environmental reasons, to facilitate access the least-cost resource to serve a very short-duration peak, to fuel and to minimize land costs and land use conflict. sometimes described as a needle peak. The ability to curtail Generation plants also tend to vary considerably in fuel an end-use load saves not only the amount of capacity repre- cost, efficiency and flexibility; allowing the utility to use the sented by the reduced load but also the marginal line losses least-cost mix of generation at all load levels may require and reserves that would be required to reliably sustain that additional transmission. load. Similarly, the ability to dispatch DERs also avoids line By contrast, demand response, energy efficiency and losses that would be required to deliver generated capacity to energy storage can be very carefully targeted geographically that location.29 to provide needed capacity in a specific area without the need for any additional transmission. 5.1.2 Transmission The costs of transmission lines depend on the length Although separating all the causes of the structure of an existing transmission system can be difficult, especially for a of the lines, the terrain they must cover and the amount of power they need to carry at different times, sometimes in either direction. The maximum usage of many transmission lines is not necessarily at system peak hours, and the usage 29 The capacity saved can be as high as 1.4 times the load reduced, when marginal line losses and reserves are taken into account. For a detailed discussion of this, see Lazar and Baldwin (2011).
  4. Page 59 of 276

    REGULATORY ASSISTANCE PROJECT (RAP)® utility whose distribution of load and generation has changed over the decades, decisions about the nature and location of ELECTRIC COST ALLOCATION FOR A NEW ERA 200% sizing and cost of transmission. Underground transmission is particularly sensitive to the buildup of heat around the lines, so the duration of peak loads and the extent to which loads decline from the peak period to the off-peak period affects the sizing of underground lines. An underground line may be able to carry twice as much load for a 15-minute peak after a day of low loads as for an eight-hour peak with a high daily load factor. To reduce losses and the buildup of heat from frequent high loads, utilities must install larger cables, or more cables, than they would to meet shorter duration loads. The capacity of overhead lines is often limited by the Permissible load in percentage of rated kVA Energy load over the course of many hours also affects the Overload following initial load of: 50% rated kVA 70% rated kVA 90% rated kVA 180% kVA= kilovolt-amperes 160% 140% 120% 100% 0 2 sagging caused by thermal expansion of the conductors, which also occurs more readily with summer peak conditions of high air temperatures, light winds and strong sunlight. 6 4 Duration of overload in hours 8 Source: Bureau of Reclamation. (1991). Permissible Loading of Oil-Immersed Transformers and Regulators Overheating and sagging also reduce the operating life of two hours or 24 hours.30 A transformer that was loaded to the conductors. A transmission facility normally will have a 50% of its rating in the afternoon can endure an overload of higher capacity rating for winter than for summer because 190% for 30 minutes or 160% for an hour. If the afternoon the heat buildup is ameliorated in cooler weather. load was 90% of the transformer rating, it could carry only The costs of substations, including the power transform- 57 Figure 16. Permissible overload for varying periods generation facilities can have important effects on the costs of the transmission system. | 160% of its rated load for 30 minutes or 140% for an hour.31 ers on which they are centered, are determined by both peak Similarly, if the transformer’s high-load period is current- loads and energy use. The capacity of a station transformer ly eight hours in the afternoon and evening, and the preced- is limited by the buildup of heat created by electric energy ing load is 50% of rated capacity, afternoon load reductions losses in the equipment. Every time a transformer approaches that cut the high-load period to three hours would increase or exceeds its rated capacity (a common occurrence, since the permissible load from about 108% of rated capacity to transformers can typically operate well above their rated about 127%. Under these circumstances, the transformer can capacity for short periods), its internal insulation deteriorates meet higher load without replacement or addition of new and it loses a portion of its useful life. transformers. Figure 16 illustrates the effect of the length of the peak Short peaks and low off-peak loads allow the transformer load, and the load in preceding hours, on the load that a to cool between peaks, so it can tolerate a higher peak cur- transformer can carry without losing operating life (Bureau rent. Long overloads and higher load levels increase the rate of Reclamation, 1991, p. 14). The initial load in Figure 16 is of aging per overload, and frequent overloads lead to rapid defined as the maximum of the average load in the preceding failure of the transformer. 30 This specific example is for self-cooled and water-cooled transformers designed for a 55 degrees Celsius temperature rise; other designs show similar patterns. 31 Utilities recognize that the length of overloads is critical to determining whether a transformer needs to be replaced. For example, Potomac Electric Power Co. (Pepco) in Maryland has established standards for replacing line transformers when the estimated average load over a fivehour period exceeds 160% of the rating of overhead transformers or 100% for pad-mounted transformers (Lefkowitz, 2016, p. 41). The company has not found it necessary to establish comparable policies for shorter periods.
  5. Page 60 of 276

    58 | ELECTRIC COST ALLOCATION FOR A NEW ERA REGULATORY ASSISTANCE PROJECT (RAP)® Table 3. Cost drivers for transmission Connection to (or between) Purpose Typical length of line Investmentrelated costs Maintenance costs Remote baseload generation Power at all hours Long High Low Remote wind or solar Power at some hours Long High Low Peaking resources Power in peak hours, plus reserves at all hours Short Low Low Hydro Power at some or all hours Long High Low Neighbor utilities Reserve sharing; energy trading Short to long Vary Low Substations networked for reliability Power at some hours Short Medium Low Storage and substations Power at peak hours, plus reserves at all hours Very short Very low Low In a low load factor system, these high loads will occur other components are designed to serve a single customer. less frequently, and the heavy loading will not last as long. If Substations and line transformers must be larger — or will the only high-demand hours were the 12 monthly peak hours, wear out more rapidly — if they experience many high- for example, most transformers would be retired for other load hours in the year and if daily load factors are high. reasons before they experienced significant damage from Underground and overhead feeders are also subject to the overloads. In this situation, larger losses of service life per effects of heat buildup from long hours of relatively high use. overload would be acceptable, and the short peak would allow greater overloads for the same loss of service life. The allowable load on distribution lines is determined by both thermal limits and allowable voltage drop. Higher loads With high load factors, there are many hours of the year on a primary feeder may require upgrades (raising the feeder when the transformers are at or near full loads. In this case, voltage, adding a new feeder, reconductoring to a larger wire the transformer must be sized to limit overloads to acceptable size, increasing supply from single-phase to three-phase) levels and frequency of occurrence commensurate with a to maintain acceptable voltage at the end of the feeder. reasonable projected lifespan for the asset. If the transformer Small secondary customers can be farther from the line is often near full capacity with frequent overloads, it will fail transformers than large customers (allowing the utility to use more rapidly. fewer transformers to serve the same load) and can be served Transmission lines serve many purposes, including connecting remote generating plant to urban centers and with smaller conductors. As with station transformers, line transformers can enabling the optimal economic interchange of power handle moderate overloads for relatively short periods of a between regions with different load patterns and generation few hours but will deteriorate quickly if subjected to extended options. Each transmission segment can be separately overload conditions. Therefore, the sizing of transformers examined and allocated on a cost-reflective basis. Table 3 takes into consideration not only the maximum capacity provides examples of this. required but also the underlying load shape. Figure 17 on the 5.1.3 Distribution The factors driving load-related distribution costs are next page shows actual data from a confidential load research sample on a summer peak day for 10 residential customers who share a line transformer. Although no group of 10 similar to those for transmission. Different components customers is identical to any other group of 10 customers, this are built and sized for different reasons; some serve the demonstrates how diversity determines the need for the sizing shared needs of hundreds or thousands of customers, while of system elements. Only three of the 10 customers peak at the
  6. Page 61 of 276

    REGULATORY ASSISTANCE PROJECT (RAP)® ELECTRIC COST ALLOCATION FOR A NEW ERA | 59 Figure 17. Summer peak day load from 10 residential customers on one line transformer Customer coincident peak Total load shape Customer noncoincident peak 12 10 8 6 4 2 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 Hour of day Source: Confidential load research sample same time as the 4 p.m. coincident peak for the group, and the connecting additional customers consists mostly of addi- coincident peak is only 86% of the sum of the individual peaks tional line transformers (if the new customer is isolated from on this day. Furthermore, although not shown in this figure, others) and secondary distribution lines. This is true even if this coincident peak is only 64% of the sum of the annual non- those investments may serve multiple customers, particularly coincident peaks for the individual customers. It is important in urban and suburban areas. These shared facilities are to note that a group of 10 residential customers is often less largely justified by the total revenues of the customers served, diverse than the combined loads from multiple customer not the peak load or number of customers. A particular classes, which determine the need for substation and genera- transmission line, substation or feeder to serve an area could tion capacity upstream of the final line transformer. be justified by a single very large load, a small number of large It is important to note that the load exceeds 50 kVA for customers or a large number of very small customers. only three hours and is below 40 kVA for 18 hours of this Nearly every electric utility has a line extension policy summer peak day. Referring back to Figure 16, under these that sets forth the division of costs incurred to extend service circumstances, a 50-kVA transformer would likely be adequate to new customers. Typically, this policy provides for a certain to serve this load, because the overload is for only a short amount of investment by the utility, with any additional in- period. By contrast, the sum of the maximum noncoincident vestment paid for by the new customers. These provisions are peak loads of the 10 customers is more than 90 kVA. intended to ensure that new customers pay the incremental A large portion of the distribution investment is driven cost of connecting them to the system without raising rates primarily by the need to serve a geographical region. Once a to other customers. For most utilities, there is no correspond- decision is made to build a circuit, the incremental cost of ing credit where new service has a cost that is lower than the
  7. Page 62 of 276

    60 | ELECTRIC COST ALLOCATION FOR A NEW ERA REGULATORY ASSISTANCE PROJECT (RAP)® Table 4. Cost drivers for distribution Type Purpose Investmentrelated costs Maintenance costs Substations Power at all hours; capacity for high-load hours High Low Primary circuits Power at all hours; capacity for high-load hours High Low Line transformers Power at all hours; capacity for localized high-load hours Medium Low Secondary service lines Power at all hours; capacity for localized high-load hours Medium Low Meters: Traditional Measuring usage Low Low Meters: Advanced Multiple functions Medium Low average embedded cost of service, a circumstance that results different types of equipment. Most of the distinctions among in benefits to the utility and other ratepayers. types of equipment represent alternative or complementary The final components in the distribution system are methods for providing the same service. For example, meters, typically installed for all residential and general various primary distribution feeders operate at 4 kV, 13 kV service customers but not for very predictable loads like or 25 kV and may be overhead or underground construction, traffic signals or streetlights. How to classify the cost is a depending on load density, age of the equipment, local matter of debate. On one hand, a meter is needed because governmental requirements and other considerations. usage levels vary from customer to customer and month to Although the power flowing from generation to a customer month, a theoretically usage-related cost. But on the other served at 25 kV may not flow over any 4-kV feeder, the 4-kV hand, one meter is needed for every metered customer, and feeders serve the same function as the 25-kV feeders and (in meter costs do not typically vary from customer to customer places in which they are adequate) at lower cost.33 Serving within a class. In addition, smart meters entail both higher some customers at 4 kV and spreading the feeder costs among direct investment costs and back office investments but all distribution customers does not increase costs allocated provide generation, transmission and distribution system to the customers served directly from the 25-kV feeders; benefits by allowing more precise measurement and converting the 4-kV feeders to a higher voltage would likely control of local loads and more accurate assignment of increase costs to all distribution customers, including those peaking capacity requirements. Lastly, the cost of current now served at 25 kV. In this situation, all the feeders should be transformers and potential transformers necessary to meter treated as serving a single function, and all their costs should large customers should be included as part of their metering be allocated in the same manner. costs — an issue common between embedded and marginal Similarly, most customers served by single-phase primary cost methods.32 Table 4 summarizes cost drivers in the distribution are served with that configuration because it is distribution system. cheaper than extending three-phase primary distribution, 5.1.4 Incremental and Complementary Investments which they do not require because of the nature of their loads. Good economic analysis should distinguish properly between complementary or alternative investments, which substitute for one another, and incremental investments, which add costs to the system. Customers receive service at different voltages and with 32 Current transformers reduce the amperage so a meter can read it. Potential transformers reduce the voltage for meter reading (Flex-Core, n.d.). 33 Conversely, the 4-kV supply to some customers is from transformers fed directly from transmission without using the 25-kV system.
  8. Page 63 of 276

    REGULATORY ASSISTANCE PROJECT (RAP)® On the other hand, some distinctions in voltage level ELECTRIC COST ALLOCATION FOR A NEW ERA | 61 to the total load that needs to be served by the line or the represent incremental investment: happenstance that the subtransmission line is already in • Most customers served at distribution voltages cannot take place. If it is less expensive to serve customers with the lower service directly from the transmission system. Even if a voltage, it would be inequitable to charge them more for transmission line runs right past a supermarket or housing being served at that voltage. • development, the utility must run a feeder from a distri- Similarly, distribution poles carrying only secondary bution substation to serve those customers. Distribution lines are less expensive than poles carrying primary lines. If in its broadest sense is thus principally an incremental a customer served by a secondary-only pole had to be served service, rather than an alternative to transmission, needed at primary voltage instead, the primary pole would be more by and provided to some customers but not all.34 expensive, and that higher cost would almost certainly be al- Similarly, most customers who take service at secondary located to all distribution customers. Secondary poles (unlike voltage have a primary line running by or to their prem- line transformers and most secondary lines) are lower-cost ises yet cannot take service directly at primary voltage.35 alternatives to some primary poles.37 The line transformers are incremental equipment that would not be necessary if the customers could take service at primary voltage.36 These incremental costs should be functionalized so that 5.2 Determining Customer Classes In addition to administrative simplicity, the purpose of they are allocated to the loads that cause them to be incurred, separating customers into broad classes flows from the idea while each group of complementary costs (such as various that different types of customers are responsible for different distribution voltages) generally should be treated as a single types of costs, and thus it is fairer and more efficient to charge function and recovered from all customers who use any of the them separate rates. One set of rates for each customer class, alternative facilities. based on separate cost characteristics, is the key feature of In other situations, distinguishing between incremental postage stamp pricing for electric utilities. As a result, it is and complementary costs can be more complicated. Exam- very important to determine appropriate customer classes ples include the treatment of transmission equipment at with different cost characteristics at the outset of a cost of different voltages and the treatment of secondary poles. Many service study. The number of classes will vary from utility to embedded cost of service studies treat subtransmission as utility and may vary depending on the costing methodology an incremental cost separate from transmission and charge being used. In addition to equitable cost allocation, different more for delivery to customer classes served directly from rate structures are often used for different rate classes. For the subtransmission system or from substations fed by the example, residential customer classes generally do not have subtransmission system. For the most part, utilities use lower demand charges today, but most large industrial classes do. transmission voltage where it is less expensive than higher This means that decisions regarding the number and type voltages, either due to the lower cost of construction relative of customer classes can also have rate design implications, 34 In some cases, a distribution substation and feeder can bring service to customers that would otherwise be served by an extension of the transmission system at higher cost. Identifying and accounting for that limited complementary service is probably not warranted in most embedded cost of service study applications. 36 Although most networked secondary conductors parallel primary lines and are incremental to the primary system, a limited number of secondary conductors extending beyond the primary lines are complementary, because they avoid the need to extend primary lines. 35 Another way of looking at this relationship is that secondary customers are those for whom providing service at secondary has a lower total cost than providing service at primary. Sharing utility-owned transformer capacity is less expensive than having each customer build its own transformer. See Chapter 11 for a discussion of primary and secondary distribution and their allocation. 37 Similarly, a portion of the secondary lines replaces primary lines. If the customers that can be served with secondary poles required primary service, the utility would need to extend the primary lines rather than secondary lines. Hence, a portion of the secondary lines is also complementary to the primary system, rather than additive.
  9. Page 64 of 276

    62 | ELECTRIC COST ALLOCATION FOR A NEW ERA although this is not necessarily permanent. REGULATORY ASSISTANCE PROJECT (RAP)® A word of caution is appropriate here. With respect to Most utilities distinguish among residential customers, technology-driven class characteristics such as electric space small commercial customers, large commercial customers, heat, water heat, vehicles or solar installations, singling out industrial customers and street lighting customers. The customers based on technology adoption has serious practical commercial and industrial classes often are collectively termed and theoretical downsides. Furthermore, addressing one general service rate classes. In many cases, general service cus- minor cost distinction is likely not fair or efficient if several tomers are categorized by voltage levels. Customers served at other major cost distinctions, such as those listed above, are primary distribution voltage generally do not use, and should not addressed. It is wiser to consider multiple customer and not be allocated, costs of secondary distribution facilities, and service characteristics simultaneously to create technology- customers served at transmission voltage generally do not use, neutral subclasses for both cost allocation and rate design and should not be allocated, costs of distribution facilities. purposes. Many utilities also separate general service classes with even greater granularity than using simple voltage criteria. One area where utility practices can vary significantly is To begin, electric space heating customers are likely to have different load characteristics from the nonheating customers, with significantly more usage and a different whether there is more than one residential class or, alterna- daily load shape in the winter. For a winter-peaking system, tively, multiple residential subclasses. Some utilities separate this could mean that electric heating customers should out residential customers based on a measure of size, such be allocated proportionately more costs. Conversely, in a as peak demand or energy use. This can be significant in summer-peaking system, electric heating customers should be jurisdictions that categorize farms or large master-metered allocated proportionately fewer overall costs. However, this multifamily buildings as residential in a formal sense. Some issue, which is essentially a question of a potential intraclass jurisdictions also create separate classes based on the usage of cross-subsidy between types of residential customers, can specific technologies like electric resistance heating. In some also be addressed through changes to rate design. Seasonally jurisdictions, low-income discount customers are treated as a differentiated rates, if based appropriately on cost causation, separate rate class. can achieve the same distributional impact as separate rate The creation of multiple residential classes or subclasses classes for heating and nonheating customers while bringing is typically justified on cost grounds. There are inarguably additional benefits from the improved efficiency of pricing. many cost distinctions among different types of residential The creation of an electric heating rate class can have customers, and simple postage stamp cost allocation and other implications. In regions where electric heating custom- rate structures may not capture many of those distinctions. ers are disproportionately low-income, this decision also has Regulators and utilities have long analyzed the causes of such significant equity implications. There can also be environ- differences, which vary widely across the country. Some of mental repercussions to this choice. Concerns would arise, the distinctions are based on technology (or, more accurately, for example, if electric heating rates promote use of gas and as a proxy for the load impacts of certain technologies), such coal in power plants to replace direct burning of gas on-site as electric space heating, electric water heating, solar or other for heating, which historically was often more efficient on a distributed generation and even electric vehicles. Other total energy basis. Recent developments in efficient electric distinctions are based on the characteristics of service. Those heating, particularly air and ground source heat pumps, may with relatively large impacts on cost allocation include: have switched the valence of these questions. In certain areas, • Single family versus multifamily. higher-income customers may be disproportionately adopt- • Urban (multiple customers per transformer) versus rural ing efficient electric heating. And the new electric technolo- (one customer per transformer). gies may now be significantly cleaner and more efficient than Overhead service versus underground service. on-site combustion of natural gas, particularly if powered by •
  10. Page 65 of 276

    REGULATORY ASSISTANCE PROJECT (RAP)® ELECTRIC COST ALLOCATION FOR A NEW ERA | zero emissions electric resources. A seasonal and time-varying for single-family and multifamily residential customers. cost study and time-varying rates may enable appropriate cost There are many reasons to believe that the cost of serving recovery without need for a separate class. multifamily buildings is substantially lower than serving Several states have considered creating a separate rate 63 single-family homes on average: class for customers with solar PV systems. Because solar • Shared service drops. customers may have different usage patterns than other • Increased diversity of load for line transformers and sec- customers, this is reasonable to investigate. However, it is not clear that there is a significant cross-subsidy to address, ondary distribution lines, enabling more efficient sizing. • Reduced cost of distribution per customer, since no particularly at low levels of PV adoption. Current rate design distribution lines are required between customers in the practices for solar customers in many jurisdictions — such building.38 as net metering using flat volumetric rates, monthly netting • Reduced coincidence with both summer and winter peak and crediting at the retail rate — are fairly simple. These loads because common walls reduce space conditioning rate design practices could be improved significantly over use relative to single-family units of the same square time and integrated with broader rate design reforms. For footage, and because lighting and baseload appliances such example, a time-varying cost study would allow the creation as refrigerators and water heaters (if electric) are a larger of more granular time-varying rates so that solar customers percentage of loads for units with fewer square feet. pay an appropriate price for power received during nonsolar • Reduced need for secondary distribution lines in cases hours and are credited with an appropriate price for power where the multifamily building can be served directly delivered to the distribution system during solar hours. This from the transformer. would include changes to netting periods, which would reveal • Reduced summer peak coincidence if space cooling is more information about how a solar customer actually uses provided through a separate commercial account for the the electric system. building, rather than as part of the individual residential accounts. In terms of rate classes for specific technologies, some utilities separate out customers with electric water heating as • Reduced costs of manual meter reading, where still a proxy for a flat load shape and the potential for load control. applicable. In the future, some utilities may seek to make electric vehicle There may be countervailing considerations in some adoption a separate rate class as a substantially controllable service territories, such as if multifamily buildings are served load with distinct usage characteristics. However, these by more expensive underground service and single-family technologies may not need consideration as a separate rate buildings are served with cheaper overhead lines. A similar class, particularly given efforts to improve the cost causation set of considerations may cause some utilities to disaggregate basis of rate design more generally. Again, time-varying rates customers by geography, such as those residing inside and will appropriately charge customers with peak-oriented loads outside city limits.39 Customers in deeply rural areas tend and appropriately benefit customers with loads concentrated to be more expensive to serve, since they typically are too in low-cost hours or controlled into those hours. far from their neighbors to share transformers, require a Some utilities have implemented separate rate classes 38 This distinction is important where some distribution costs are classified as customer-related. In those situations, each multifamily building (rather than each meter) should be treated as one customer, as would a single commercial customer of the same size and load. 39 For example, Seattle City Light, a municipal utility, has two rate schedules for most commercial and industrial classes within the city: one for the highly networked higher-cost underground system in the urban core, long run of primary line along the public way, and generally and another for the balance of the city, plus separate higher rates for the adjacent cities and towns where it provides service. Compare Schedules MDC, MDD, MDS and MDT at Seattle City Light (n.d.). The city of Austin, Texas, also applies different rates to customers outside the city limits (Austin Energy, 2017). In many places, cities impose franchise fees or municipal taxes that make customer bills inside cities higher than those outside cities, even though the cost data may suggest the opposite is more equitable.