  1. Page 78 of 276

    76 | ELECTRIC COST ALLOCATION FOR A NEW ERA REGULATORY ASSISTANCE PROJECT (RAP)® Figure 20. Sankey diagram for legacy embedded cost of service study Revenue requirement: 370 Billing & collection: Transmission: Generation: 250 Energy-related: 100 20 Demand-related: 195 Residential: 234.5 Distribution: 80 Customerrelated: 75 Commercial and industrial: 135.5 20
  2. Page 79 of 276

    REGULATORY ASSISTANCE PROJECT (RAP)® ELECTRIC COST ALLOCATION FOR A NEW ERA | 77 Figure 21. Sankey diagram for modern embedded cost of service study Revenue requirement: 370 Billing & collection: Transmission: Generation: 250 20 Distribution: 80 20 Customerrelated: All hours: 270 Residential: 198.75 Peak hours: 75 Commercial and industrial: 171.25 20
  3. Page 80 of 276

    78 | ELECTRIC COST ALLOCATION FOR A NEW ERA REGULATORY ASSISTANCE PROJECT (RAP)® “Fixed” versus “variable” costs In the past, some cost allocation studies have relied on a simplified model of cost causation, in which certain costs are labeled as variable and then classified as energy-related and apportioned among classes based on class kWh usage. The remaining costs, labeled as fixed, are classified as demand-related or customer-related and allocated on some measure of peak demand or customer number, respectively.49 This antiquated approach is based on fundamental misconceptions regarding cost causation. But it still underlies many arguments about cost allocation, perhaps because it typically works to the benefit of customer classes with high load factors and small numbers of customers — which describes most util- • Purchased power charges that depend on the amount of energy taken by the utility.52 Over the decades, nearly every other utility cost has been described as fixed in one context or another: capital, labor, materials and contract services. Most of these costs are fixed for the coming year, in the sense that they are committed (investments made, contracts signed, employees hired) and will not be immediately changed by usage levels (energy, demand or number of customers). However, almost all of these cost accounts are variable over a period of several years, and energy consumption may affect: ities’ large industrial classes, data centers and even supermar- • Whether excess generation capacity or other redundant kets.50 This technique ignores the reality that modern electric facilities can be retired or mothballed in order to reduce systems trade off capital, labor, contractual obligations, fuel operating and capital expenditures or repurposed to increase and other expenditures to minimize costs. the net benefits of the facility. One of the problems with using the fixed/variable dichotomy to classify costs is the ambiguity of the concept of a cost being “fixed.” Nearly all observers agree that certain generation costs are variable because they are short-term marginal costs that vary directly with usage patterns. These costs include: • Whether additional facilities are needed (increasing capital and operating costs). • Whether contracts are extended. • The cost of capacity that is built (e.g., combined cycle versus combustion turbine plants, larger T&D equipment to reduce losses). • Fuel purchasing and disposal costs.51 As a result, these costs are not fixed over the planning horizon. • Variable operating costs related to consumables From an economic perspective more generally, all costs vary in (e.g., water, limestone, activated carbon, ammonia) the long run. injected to increase output, reduce emissions or provide cooling to the power plant as it produces energy. Relatedly, nearly all competitive businesses and fee-charging • Allowances or offsets that must be purchased to emit public services recover their fixed costs based on units sold. various pollutants. 49 In rate design, this approach has been extended to argue that all “fixed” costs must be recovered through fixed charges, often meaning customer and demand charges. These approaches promote neither equity nor efficiency. 50 Similarly, the fixed/variable approach is attractive to those who would justify rate designs with lower energy charges and higher customer and demand charges. Customers do not pay an access fee to enter a supermarket. 51 In previous decades, utilities would even argue that some fuel costs are fixed, on the grounds that having fuel on hand was necessary to allow the plant to function when required, or that a certain amount of fuel was required for startup, before any energy could be generated. These arguments appear to have largely disappeared, although similar issues are raised by the fuel security debate at FERC. 52 Many observers would add another category — expenses whose amount and timing vary with hours of operation, output or unit starts — even though not all cost of service studies separate those costs from other O&M expenses.
  4. Page 81 of 276

    REGULATORY ASSISTANCE PROJECT (RAP)® Restaurants, theaters and airlines have many costs that can be characterized as fixed (land, buildings, equipment, a large share of labor) and vary their unit prices by time of use but ultimately recover their capital investments and long-term costs from sales of output. RAP has done extensive analysis of utility distribution system investment and the relationship of that investment to the number of customers, peak demands and total kWhs. We found that these costs are roughly linear with respect to each of these metrics (Shirley, 2001). ELECTRIC COST ALLOCATION FOR A NEW ERA | 79 6.2 Marginal Cost of Service Studies The fundamental principle of marginal cost pricing is that economic efficiency is served when prices reflect current or future costs — that is, the true value today of the resources that are being used to serve demand — rather than historical embedded costs. Advocates for a marginal cost of service study approach work backward from this pricing concept to suggest that cost allocation should be based around marginal costs as well. Critics of marginal Some version of the fixed/variable distinction may have been cost methods often point out that this economic theory close to reality in the middle of the last century. Most utilities is appropriate only when other conditions are present, relied primarily on fossil steam plants, using newer, more including that all other goods are priced based on marginal efficient plants to serve baseloads and older plants to serve costs, that there are no barriers to entry or exit from the intermediate and peak loads. The capital costs of each were market and that capital is fungible. not very different. Fuel costs for oil, coal and natural gas were This is a very broad concept because it abstracts from not very different. And because little was required in terms of and does not consider both theoretical and computational emissions controls, coal plants were not much more expen- issues associated with the development of marginal costs. In sive than other fossil-fueled plants.53 By the 1970s, however, contrast to the static snapshot that is typical of embedded conditions had changed radically. Oil prices rose dramatically, cost approaches, marginal cost of service studies account new coal plants were required to reduce air emissions, and for how costs change over time and which rate class new generation technologies arose: nuclear, with high capital characteristics are responsible for driving changes in cost. and O&M cost but low fuel prices; and combustion turbines, Importantly, marginal costs can be measured in the short with low capital and O&M costs but high fuel costs. Utilities run or long run. At one extreme, a true short-run marginal suddenly had a menu of options among generation technol- cost study will measure only a fraction of the cost of service, ogies, including the potential for trading off short-term fuel the portion that varies from hour to hour with usage costs for long-term capital investments. Today that menu has assuming no changes in the capital stock. At the other, a expanded even more and includes storage, demand response, total service long-run incremental cost study measures the price-responsive customer load and distributed generation. cost of replacing today’s power system with a new, optimally designed and sized system that uses the newest technology. As a result, the fixed/variable distinction has lost relevance In between is a range of alternatives, many of which have and adherents over the last several decades. For example, been used in states like Maine, New York, Montana, many regulators classify capital investments using methods Oregon and California in determining revenue allocation that recognize the contribution of energy requirements to among classes. the need for a wide variety of “fixed” costs for generation, transmission and distribution.54 There is a strong theoretical link between optimal rate design and long-run marginal costs. Allocation based on marginal costs works backward from this premise; because pricing 53 In some areas, such as the U.S. Northwest, Manitoba and Québec, utilities had access to ample low-cost hydro facilities and mostly avoided construction of thermal generation. 54 These methods are discussed in chapters 9, 10 and 11. should be determined on this basis, cost allocation should as well. In its simplest form, a marginal cost study computes marginal costs for different elements of service, which can be estimated using a number of techniques, including proxies,
  5. Page 82 of 276

    80 | ELECTRIC COST ALLOCATION FOR A NEW ERA regressions and other cost data. Table 11 shows illustrative marginal costs for different elements of the electric system. Different marginal cost of service studies may base their costing on different elements of the system or different combinations. The categories of costs included in each element can also be more or less expansive. The estimated marginal costs are then multiplied by the billing determinants for each class. This produces a class marginal cost revenue requirement and, when combined with other classes, a system MCRR. However, revenue determination solely on this marginal cost basis will typically be greater or less than the allowed revenue requirement, which is normally computed on an embedded cost basis. It is only happenstance REGULATORY ASSISTANCE PROJECT (RAP)® Table 11. Illustrative marginal cost results by element Cost Units per unit Customer connection Dollars per year $80 Secondary distribution Dollars per kW $40 Primary distribution Dollars per kW $80 Transmission Dollars per kW $50 Generation capacity Dollars per kW $100 On-peak Dollars per kWh $0.10 Midpeak Dollars per kWh $0.07 Off-peak Dollars per kWh $0.05 Energy by time period if marginal costs and embedded costs produce the same revenue or even similar levels of revenue. As a result, a first developed in the late 1970s was that generation costs marginal cost of service study must be adjusted to recover the were made up of capacity and energy costs, but the embedded correct annual amount from the revenue requirement. plant was not classified to obtain these costs. Marginal Two notable long-run methods are discussed in this energy costs were based on the incremental operating costs section: the long-run marginal cost approaches advocated of the system (discussed in Chapter 18 in more detail), while by Lewis Perl and his colleagues at the consulting firm capacity costs were the least cost of new capacity (at the time, National Economic Research Associates (NERA) — now typically a combustion turbine). The annualization for the NERA Economic Consulting — and the total service long- capacity costs of all types is not based on the embedded rate run incremental cost approach.55 In the 1980s, during the of return but on a real economic carrying charge (RECC) rate PURPA hearing era, many states considered and a few adopted that yields the same present value of revenue requirements the NERA method to measuring long-run marginal costs. when adjusted for inflation. California, Oregon, Montana and New York are examples For transmission and distribution costs in the NERA of states that began relying on this approach to measuring method, the marginal costs have typically been estimated marginal costs. This methodology generally looked at a 10-year by determining marginal investment for new capacity over or longer time horizon to measure what costs would change in a number of historical and projected years and relating that response to changes in peak demand and energy requirements investment to changes in some type of load or capacity during different time periods and the number of customers measure in kWs. This relationship can be found either served (National Economic Research Associates, 1977). One using regression equations (cumulative investment versus essential element of this was to define the cost of generation cumulative increase in load over the time period) or by to meet peak period load growth (peaker units and associated simply dividing the number of dollars of investment by the T&D capacity) as much higher than the cost to meet off-peak total increase in load over the time period. O&M costs are load growth (increased utilization of existing assets). This generally based on some type of average over a number of approach was influenced by Alfred Kahn’s theoretical focus on historical and projected years, although obvious trends or peak load costs and management (Kahn, 1970), and he himself anomalies can be taken into account. was associated with NERA for many years. For generation, one of the theoretical advances that made marginal cost of service studies attractive when they were 55 Short-run marginal cost approaches are actually much simpler, primarily varying fuel consumption and purchased power costs, but are applicable only in a limited number of circumstances.
  6. Page 83 of 276

    REGULATORY ASSISTANCE PROJECT (RAP)® ELECTRIC COST ALLOCATION FOR A NEW ERA | 81 For customer costs, the same type of arguments over presence of either can shift costs sharply among consumer classification between distribution demand and customer classes. Because of this imbalanced result, regulators have costs occur as in embedded cost studies. The marginal cost adopted modifications to this methodology to equalize the study needs data on the current costs of hooking up new time horizon for different elements of the cost of service. For customers by class. The method for annualizing the costs is example, not all customers will require new service drops in dispute (RECC versus a new-customer-only method that and meters over a 10-year period — only new customers and assigns the costs by new and replacement customers). O&M those whose existing facilities fail. Some states apportion costs are again typically based on some type of average over costs within functional categories, avoiding this problem and historical and projected years. addressing markets with partial retail choice. The time horizon used for the NERA approach has In contrast to the NERA approach and other marginal proven controversial because it assumed the utility would cost approaches, which start from the parameters and install exactly the number of new customer connections and investments found in the existing system, the total service distribution lines required by new customers (i.e., all cus- long-run incremental cost approach looks at a period long tomer costs are “marginal”) but would consider the adequacy enough so that all costs truly are variable. This allows for of existing generation and transmission (which may be an estimate of what the system would look like if it were oversized to meet current needs) in determining the need for completely constructed using today’s technologies and today’s additional generation and transmission (meaning only some costs. Today, new generation is often cheaper than existing G&T costs are “marginal”). Many utilities have used a 10-year resources, while the cost of transmission and distribution time horizon in this analysis, a period in which many found continues to rise. substantial excess capacity and, therefore, relatively low costs The TSLRIC approach was developed in the context of to meet increasing power supply needs. In addition, this regulatory reform for telecommunications (International methodology, as most often used, treats the cost of increased Telecommunication Union, 2009). In the 1990s, as telecom- off-peak usage as only the fuel and variable power costs munication technology advanced rapidly, incumbent local and losses associated with operating existing resources for exchange companies (better known as phone companies) additional hours, with no associated investment-related or faced competition from new market entrants that did not have maintenance-related cost, despite the reliance on expensive legacy system costs. These new competitors were able to offer investments to produce that power. service at lower cost than the local phone companies. Regu- The combination of these assumptions meant that many lators did not want to discourage innovation but also did not marginal cost of service studies over the last several decades want existing customers served by the local phone companies would come to three basic conclusions: to suffer rate increases if select customers left the system. • Power supply and transmission costs to meet off-peak The TSLRIC approach constructs a hypothetical system loads were relatively low, due to available excess capacity. with optimal sizing of components, with neither excess Power supply and transmission costs to meet peak load capacity nor deficient capacity. It would use the most modern growth were higher. technology. In the context of an electric utility, it would likely Distribution costs always grew in lockstep with the rely on wind, solar and storage to a greater extent than most number of customers and distribution demands. systems today, which would likely lead to lower costs. But it The most serious shortcoming of the NERA methodology would also incur the cost of today’s environmental and land is that if power supply is surplus due to imperfect forecasting, use restrictions, such as the requirement for lower emissions it assigns a very low cost to power; if it is scarce, the method from generation and undergrounding of transmission and assigns a very high cost. Neither of those circumstances distribution lines. These requirements have substantial is caused by the action of consumers in any class, but the societal benefits but can also drive up electric system costs. • •
  7. Page 84 of 276

    82 | ELECTRIC COST ALLOCATION FOR A NEW ERA REGULATORY ASSISTANCE PROJECT (RAP)® One advantage of a TSLRIC study over a NERA-style method to set rates for new customers or incremental usage. study is that no class is advantaged or disadvantaged by a Some jurisdictions have applied this technique for rate design current surplus or deficiency of power supply or distribution within classes — as the foundation for most “economic network capacity, since costs for all classes would be based development” rate discounts where marginal costs are lower on an optimal mix of resources to serve today’s needs. This is than embedded costs, as well as for inclining block rates one of the most common critiques of the NERA methodology where marginal costs are higher than embedded costs. In — that it favors any class that is served dominantly by the addition, some jurisdictions have applied this technique elements of a system that are in surplus. across rate classes, allocating new incremental resources to 6.3 Combining Frameworks Several jurisdictions require both an embedded and specific rate classes. Depending on the trajectory of costs, this can have two different intended purposes: • To provide a foundation upon which to impose on a marginal cost of service study to support cost allocation fast-growing classes the high costs of growth and to and rate design. As a result, utilities and other parties shelter slower-growing classes from these new costs. may file several studies in the course of a rate proceeding. • To provide a foundation to give the benefit of low-cost A regulator may reasonably use multiple cost studies in new resources to the growing class. reaching decisions, using multiple results to define a range This approach to differential treatment of incremental of reasonableness. Within that range, the regulator can resources may be applicable to situations where costs are apply judgment and all of the relevant non-cost concerns to being driven by disparate growth among customer classes. determine the allocation of the revenue requirements among In the 1980s, for example, commercial loads in the U.S. grew classes. Furthermore, the different types of studies provide much faster than residential loads, and this technique could different information that can be used at other stages in the be used to assign the cost of expensive new resources to the rate-making process. classes causing those new costs to be incurred. One approach is to use embedded cost methods to determine the allocation of the revenue requirement among customer classes and then a forward-looking cost method of some kind to design rates within classes. This applies the 6.4 Using Cost of Service Study Results Quantitative cost of service study results should serve focus of embedded cost studies on equitably sharing the only as a guide to the allocation of revenue responsibility costs among classes while maximizing the efficiency of price among classes, not as the sole determinant. Even the best signals in the actual rates that individual customers face in cost of service study reflects many judgments, assumptions making consumption decisions that will affect future costs. and inputs. Other reasonable judgments, assumptions and The appropriate form of price signals can also be influenced inputs would result in different cost allocations. Additionally, by externalities that are not part of the embedded costs for a loads may be unstable, significantly changing class revenue regulated utility. For example, many regulatory agencies that responsibility between cost studies, particularly for traditional allocate costs among classes on embedded costs have reflect- studies that base costs on single peak hours in one or several ed higher long-run marginal costs in adopting inclining block months. More globally, concepts of equity extend beyond the or time-of-use rates for customers with high levels of usage cost of service study’s assignment of responsibility for causing (either because large customers are better able to respond costs or using the services provided by those costs to include to price signals or because the larger customers have more relative ability to pay, gradualism in rate changes, differential expensive load shapes, such as for space conditioning). risks by function and class and other policy considerations. In some situations, regulators will use one costing method to set rates for existing load while using a different Chapter 27 addresses the many ways in which the results of cost of service studies can be used to guide regulators.
  8. Page 85 of 276

    REGULATORY ASSISTANCE PROJECT (RAP)® ELECTRIC COST ALLOCATION FOR A NEW ERA | 83 7. Key Issues for 21st Century Cost Allocation M any important cost allocation issues for the These changes both enable and require new approaches current era are fundamentally different from in order to efficiently and equitably allocate costs across those that existed when NARUC published its customer classes. 1992 Electric Utility Cost Allocation Manual. This chapter sets forth the changes the industry has experienced and describes the approaches that may be needed to address those changes 7.1.1 Distribution System Monitoring and Advanced Metering Infrastructure in cost allocation studies. Inevitably, additional costing issues will emerge and In the past, customer meters were used solely to measure usage and render bills. Today, so-called smart meters are require recognition in future cost of service studies. The part of a complex web of assets that enable energy efficiency, fundamental considerations are why the costs were incurred peak load management and improved system reliability, in and who currently benefits from the costs. Costs are often addition to the traditional measuring of usage and rendering categorized using engineering and accounting perspectives of bills. that are useful for many applications but must not be More recently, a number of utilities have used advanced allowed to obscure the fundamental questions of causation meters to support demand response and other programs. and benefits. Sacramento Municipal Utility District, for example, ran a pilot 7.1 Changes to Technology and the Electric System Technological change has affected every element of the electric system since the studies and decisions that informed program to test the impacts of dynamic pricing and smart technology on peak load shaving and energy conservation. Figure 22 on the next page shows how customers in the program took steps to lower their electricity usage during highload, higher-cost hours (Potter, George and Jimenez, 2014). Smart meters (along with supporting data acquisition the 1992 NARUC cost allocation manual. These changes include: and data management hardware and software) can provide a • number of services that improve reliability and reduce costs • • Improved distribution system monitoring and advanced metering infrastructure, leading to new comprehensive of generation, transmission and distribution.56 Analysts have data on the system and customers. identified a wide range of expected and potential benefits. Evolution of resource options to include significant These include: amounts of variable renewables, new types of storage, • Reduced line losses. energy efficiency and demand response. • Voltage control. Significant commitments to DERs behind customer • Improved system planning and transformer sizing. meters, including rooftop solar and storage. • The ability to implement rate designs that encourage energy efficiency. • Beneficial electrification of transportation. • Changes in fuel prices and the resource supply mix that • Reduced peak loads. have dramatically changed the operating pattern of • Integration of EVs and renewables. various generation resources (addressed in more detail in Section 7.2). 56 The broader concept of “smart grid” includes distribution (and sometimes transmission) automation devices such as automatic reclosers, voltage controls, switchable capacitors and sensors.
  9. Page 86 of 276

    84 | ELECTRIC COST ALLOCATION FOR A NEW ERA REGULATORY ASSISTANCE PROJECT (RAP)® Figure 22. Customer behavior in Sacramento Municipal Utility District pricing pilot Default critical peak pricing Percentage of customers 100% Default time-of-use and critical peak pricing 90% Default time-of-use pricing 80% Opt-in critical peak pricing Opt-in time-of-use pricing 70% 60% 50% 40% 30% 20% 10% 0% Did laundry off-peak Turned off lights Did dishes off-peak Turned off air conditioner Increased temperature on thermostat Source: Potter, J., George, S., and Jimenez, L. (2014). SmartPricing Options Final Evaluation Operating savings from, among other things, reduced demand that had been roughly constant for decades. Due to labor needs and improved outage management. significant solar capacity in some regions, such as California Lastly, smart meters, distribution sensors and modern and Hawaii, costs (e.g., extra spinning reserves, out-of-merit computing power provide utilities with large amounts of data dispatch or quick-start generation) may also be incurred to that can be used to determine the usage patterns of distribu- rapidly ramp up other generation as solar output falls in the tion and transmission equipment in great detail and support late afternoon, particularly if customer load does not drop direct hourly allocation of costs. dramatically from afternoon to evening.58 Excess solar gener- • ation may create ramping costs, while storage resources may 7.1.2 Variable Renewables, Storage, Energy Efficiency and Demand Response New variable renewable resources, such as wind and reduce ramping costs by both raising load at the beginning of the ramp period and trimming the peak toward the end of the ramp period. solar, are highly capital-intensive, and their contribution In Hawaii, June load shapes changed as increased levels to system reliability varies greatly from region to region of distributed solar were added to the system. Figure 23 on the depending on when their generation occurs relative to peak next page illustrates this, using data from the Federal Energy demand.57 The emergence of demand response as a service Regulatory Commission (n.d.). In 2006, the system peak provides an opportunity to meet narrow periods of peak demand was approximately 1,200 MWs at 1 to 3 p.m. By 2017, demand with relatively little capital investment by rewarding with extensive deployment of customer-sited solar, the peak customers who curtail usage on request. demand was 1,068 MWs at 9 p.m. A cost allocation scheme Investments in renewable resources, driven by policy and economic trends, can greatly change patterns in supply and 57 Growth in solar resources, whether central or distributed, gradually reduces the reliability value of incremental solar capacity in many respects; the same is true for wind resources with respect to the reliability value of incremental wind and the equivalent for (if they become economically must be adaptable enough to be relevant as significant changes in the shape and character of utility-served load take place. competitive) tidal and wave energy. In contrast, these different resources may be complementary to one another in certain respects. 58 The resulting load shape, first identified by Denholm, Margolis and Milford in 2008, is commonly known as a duck curve. See also Lazar (2016).
  10. Page 87 of 276

    REGULATORY ASSISTANCE PROJECT (RAP)® ELECTRIC COST ALLOCATION FOR A NEW ERA Figure 23. Evolution of system load in Hawaii on typical June weekday | 85 well to the shape of the summer diurnal load (Slusarewicz and Cohan, 2018; Electric Reliability Council of Texas, 2019). The costs of these resources can be assigned to the 1,200 hours in which they generate energy, as discussed in Chapter 17. Determining the hours that variable resources June 13, 2006 provide energy (on either a historical or normalized forecast basis) is generally straightforward. System demand in megawatts June 5, 2012 Distributed storage presents other issues and 1,000 opportunities, as it is a capital-intensive peaking resource with no direct fuel costs, dependent on charging from other resources, and provides a variety of energy, capacity, transmission, distribution and ancillary services to the system and sometimes backup supply to host customers. Storage may June 20, 2017 800 displace T&D investments, reduce fuel consumption, enable renewable energy integration and provide emergency service at customer sites. Each of these functions has a different place in a modern cost allocation study. A portfolio of energy efficiency measures reduces energy 600 0 2 4 6 8 10 12 14 16 18 20 22 24 Hour of day Data source: Federal Energy Regulatory Commission. Form No. 714 — Annual Balancing Authority Area and Planning Area Report The capacity role and treatment of variable renewable requirements, generation capacity requirements and stress on T&D equipment, as well as reduces customer billing determinants. As discussed in Section 14.1, energy efficiency expenditures can be classified and allocated in proportion to the benefits they produce. The plans and evaluation resources, such as wind and solar, vary among jurisdictions reports of the program administrator (the utility or a third and RTOs. The cost of service study should reflect the role of party authorized to provide those services) generally provide these resources in supply planning, by classifying part of the sufficient data on the load shape and class distribution of load renewable costs as demand-related and allocating those costs reductions. Since energy efficiency costs are recovered through in proportion to class consumption in the hours contributing a variety of mechanisms (rate based or expensed, through base to capacity requirements. This should recognize that different rates or a discrete conservation surcharge or rider), the cost types of variable renewable resources can be complementary allocation should reflect the cost recovery method. in many respects as long as the temporal patterns, either The costs of demand response programs — direct load daily or seasonal, are different. Even solar in slightly different control, customer load automation (e.g., setback thermostats) regions can be complementary since they may not be affected and price-responsive load (e.g., critical peak pricing) — in an identical way by cloud cover. For example, as shown should similarly be apportioned to reflect their benefits, so in Figure 24 on the next page, a mix of wind resources from that cost-effective demand response is a net benefit to both West and South Texas plus solar production combine to pro- participants and nonparticipants.59 An hourly assignment duce an overall resource shape that corresponds moderately method, where the costs of demand response are apportioned 59 Under conventional rate designs, participants (and their classes) generally retain a smaller share of the benefits of demand response (other than incentives for program participation, which may include peak-time rebates) than of energy efficiency programs. Depending on the program design, the incentives for the participants may be reflected in cost allocation and rate design through (1) reduced allocation of costs to the participating customers and classes to reflect improved load shape, (2) payment of incentives (including peak-time rebates) and allocation of those and other utility expenditures as costs, or (3) a combination of the two, as long as the benefits are not double-counted. Dynamic peak pricing may encourage demand response without explicit incentives, with the cost allocation to the participants’ class reflecting the improved load shape.