Prefiled testimony
Witness: Nikhil Balakumar
Files2
26-05-10_Direct Testimony Eclipse FINAL.pdf
PDF · 1.4 MB · 105 pagesText searchable
Download 26-05-10_Direct Testimony Eclipse FINAL.pdfRead the text of 26-05-10_Direct Testimony Eclipse FINAL.pdf
Attachment 1 - Nikhil Balakumar_Resume.pdf
PDF · 126 KB · 2 pagesText searchable
Download Attachment 1 - Nikhil Balakumar_Resume.pdfRead the text of Attachment 1 - Nikhil Balakumar_Resume.pdf
Words on different pages
Every word of Eversource rate increase is in the text below, but not all on one page. Pages with any of them are listed and highlighted. Clear highlighting
Page 12 of 105
• 1 2 The Company must propose a concrete distributed intelligence pilot with specific use cases within one year of approval of the AMI deployment. • 3 The Company must include an evaluation of the potential of AMI to defer or 4 replace sensor investments and report as part of investigating how AMI can 5 support real-time operations and report on the progress of this investigation as 6 part of ongoing AMI updates. 7 8 Q10 Please summarize your conclusions and recommendations regarding the Company’s in-service investments. 9 A. I recommend that PURA: 10 • Direct-buried cable: Disallow about $26.5 million of 2022–2023 replacement 11 costs above the 2019–2021 unit cost, net of demonstrated inflation, absent a 12 contemporaneous analysis supporting full replacement. 13 • Capacity additions: Disallow capacity additions where the Company fails, by 14 the close of the record, to prove prudence of these investments by providing 15 the contemporaneous evaluation of non-wires alternatives, the load forecast 16 and the authorization documents for each Peak Load/Capacity project placed 17 in service from 2023 through 2025 ($145.4 million), do not find a project 18 prudent where the Company cannot make that showing, and disallow the cost 19 above the least-cost alternative where one was available. 20 • Resiliency additions: Require before-and-after storm performance data for the 21 resiliency programs and weigh the absence of measured benefits in deciding 22 whether resiliency additions placed in service after 2020 were prudently 23 incurred. 24 25 • Areas pending Company data: OCC is requesting additional data on capitalized vegetation work, the proactive direct-buried cable replacement Direct Testimony of Nikhil Balakumar Page 9Page 13 of 105
1 program, capitalized storm restoration costs from the 2018–2023 storms, 2 AMR meter additions, and the measured benefits of the resiliency programs. I 3 will provide my recommendations on these additions and whether they should 4 be included in rate base in full or in part in surrebuttal testimony. • 5 Planned plant additions: Include in rate base only plant additions that are 6 completed, in service and documented before the close of the record and 7 exclude all forecasted plant additions that are not in service and used and 8 useful. Our current estimate is that of the $847.8 million of interim period 9 plant the Company requested from January 2026 through June 2028 10 approximately $202.5 million will still be forecasted plant at the close of the 11 record and therefore should not be included in rate base, as well as the full 12 $664.9 million requested for the Rate Year. 13 These recommendations do not deny the Company recovery of prudent 14 investment. They remove an amount the record shows was not justified, defer a 15 finding where the record does not yet contain the information needed to 16 adequately assess prudency, and sets forth what OCC needs to evaluate the 17 Company’s forward-looking capital requests, including the TSP. 18 19 Q11 Please summarize your conclusions and recommendations regarding the Company’s storm recovery investments. 20 A. Storm recovery should be impact-based, not exclusively spend-based. Meeting the 21 monetary threshold alone should not make a storm “catastrophic.” I recommend 22 that PURA: 23 • Add to the monetary threshold an impact-based test, using the Connecticut Major 24 Storm criterion and IEEE 1366 Major Event Days or other impact-based criteria, 25 to decide which events qualify for extraordinary storm recovery. 26 • When seeking recovery for crew levels that exceed benchmarks for each ELM 27 event level in the ERP, require the Company to demonstrate the reasons at the 28 time and justify the excess, beyond the forecast alone, tied to individual Direct Testimony of Nikhil Balakumar Page 10Page 14 of 105
1 forecasted trouble spots. The Company may exceed a benchmark when conditions 2 require but should demonstrate the reasons at the time and justify the excess, 3 beyond the forecast alone, when seeking recovery. 4 • Disallow recovery of, at minimum, the portion of the $62.0 million requested for 5 storms MS24A, MS24B, MS24C, MS24D, MS24H, and MS24K that exceeds 6 established spending benchmarks. Consistent with OCC’s prior recommendation, 7 PURA should disallow costs above these benchmarks, particularly where the 8 Company has not demonstrated that its storm staging and resource decisions were 9 prudent. This proceeding should establish clear guardrails to prevent excessive 10 storm spending in the future. Customers should pay for prudent storm preparation 11 and restoration, not excessive pre-staging or costs driven by overstated forecasts 12 without demonstrated benefits. For these six events, the Company acknowledged 13 that forecasts overstated storm severity, contributing to higher costs. Our final 14 disallowance on these storms will depend on the subsequent information provided 15 by the Company in the record. 16 • Reject the Company’s storm-related programs and system hardening investments 17 until the Company demonstrates how it will improve its storm response and 18 reduce storm costs for customers. At a minimum, the Company should reconcile 19 its storm forecasts with actual outcomes and establish measurable performance 20 metrics for storm response costs, forecast accuracy, crew staging, restoration time 21 and lessons learned from each event, using the storm costs in this filing as a 22 baseline for future accountability. 23 Direct Testimony of Nikhil Balakumar Page 11Page 15 of 105
1 III. 2 TARGETED SYSTEM PERFORMANCE PLAN A. Purpose and Overview 3 Q12 What is the purpose of this portion of your testimony? 4 A. This portion of my testimony addresses the Company’s proposed five-year TSP 5 Plan for 2027 through 2031. I rely on the testimony and exhibits of the 6 Company’s TSP panel and the Company’s responses to OCC’s interrogatories. 7 My testimony examines whether the Company has shown that the plan is needed, 8 sufficiently developed to fund, and the lowest reasonable cost way to meet system 9 needs, including whether the Company evaluated non-wires solutions before 10 seeking funding for capacity projects. It supports the recommendation of OCC 11 Witnesses Wilson and Tully that PURA reject the TSP as a basis to establish a 12 multi-year capital plan and use the Integrated Distribution System Planning 13 (“IDSP”) process to inform any future multi-year capital plan.6 14 Q13 Please summarize the purpose of the proposed TSP. 15 A. The TSP should serve as a thoughtful and data-driven strategic plan for the 16 distribution system that deliberately and steadily progresses toward a vision for 17 the future state, while balancing performance and affordability for customers and 18 covers the planning horizon for operations and investment in the Company’s 19 distribution system over the timeframe of January 1, 2027 through December 31, 20 2031.7 Specifically, the TSP describes a broader approach to maintain or improve 21 performance with the focus on six goals including (1) safety, (2) high levels of 22 reliability, (3) sufficient capacity, (4) resiliency, (5) accommodating DERs, (5) a 23 transformation unto a dynamic modern grid and (6) affordability.8 6 Direct Testimony of OCC Witnesses Wilson and Tully. Exhibit CLP-TSP-1, at 16. 8 Exhibit CLP-TSP-1, at 15. 7 Direct Testimony of Nikhil Balakumar Page 12Page 16 of 105
1 The Company further elaborates on its goals of DERs and a dynamic modern grid 2 stating: (a) the system must be positioned to accommodate interconnected DER to 3 allow for renewable generation of electric power, as well as support of the 4 distribution system where those facilities can be leveraged as distribution assets 5 to defer traditional electric delivery infrastructure buildout; and (b) over the next 6 ten years and beyond, the system must be transformed into a dynamic modern 7 grid, leveraging cutting-edge technologies, equipment and controls, combined 8 with innovative engineering strategies and tools to increase functionality, capture 9 efficiencies and meet the challenges of a modern society with virtually zero 10 tolerance for electric interruptions.9 11 Q14 Please elaborate on how the proposed TSP is structured. 12 A. The Company has structured three levels of potential investment for the CL&P distribution system over the next five years:10 13 • 14 Sustained: The Company states the baseline investment plan is the 15 minimum level of investment needed to maintain reliability performance; 16 meet regulatory obligations; and maintain asset health and foundational 17 system planning capacity for safety and reliable operations. • 18 Targeted System Performance: The Company states this is a 19 supplementary tier of investment directed at achieving an escalating level 20 of asset-health replacements and enhanced reliability performance, while 21 also commencing a system resiliency initiative. • 22 Advancing the Grid: The Company is presenting an investment plan that 23 would build on the 5-Year TSP Plan over the longer term, accounting for 24 investments related to state policy initiatives and higher standards of 9 Exhibit CLP-TSP-1, at 15-16. Exhibit CLP-TSP-1, at 17-18. 10 Direct Testimony of Nikhil Balakumar Page 13Page 17 of 105
1 innovation and software tools including those to support DER integration, 2 clean-energy advancement and advancing the grid toward modernization. 3 Q15 What is your understanding of the Company’s request? 4 A. In the Targeted System Performance tier, the Company asks PURA to approve 5 $3.985 billion of capital spending over five years, from 2027 through 2031. This 6 includes $3.611 billion in the Sustained tier, which increases from $667 million in 7 2027 to $757 million in 2031.11 The Company describes the sustained tier as “the 8 minimum level of investment needed to maintain reliability performance; meet 9 regulatory obligations; and maintain asset health and foundational system 10 planning capacity for safety and reliable operations.”12 The second tier, Targeted 11 System Performance, adds $374 million, including $155.0 million for resilience, 12 $143.3 million for asset health, and $75.8 million for enhanced reliability.13 In 13 this second tier, the Company also proposes approximately $71 million of 14 incremental O&M, including a $38 million Grid Services Compensation Fund.14 15 The third tier, Advancing the Grid, builds off of the first two tiers then adds an 16 additional $396 million for a total of $4.381 billion. Under all three tiers, 17 vegetation management spending would increase from $59 million to $91 million 18 a year beginning in 2028.15 19 The Company presents the three tiers as “budget options” to allow PURA to 20 consider the appropriate balance between system needs and customer costs16, 21 while recommending the second tier, a.k.a. the Targeted System Performance 22 tier.17 However, if PURA considers the proposed TSP, it should evaluate the 11 Exh. CLP-TSP-3 at 10. Exh. CLP-TSP-1 at 17. 13 Response to OCC-809. 14 Exh. CLP-TSP-3 at 43. 15 Id. at 11. 16 Exh. CLP-TSP-1 at 47. 17 Exh. CLP-TSP-3 at 7, 11. 12 Direct Testimony of Nikhil Balakumar Page 14Page 18 of 105
1 proposal in the context of what the most strategic and cost-effective investments 2 should be approved - not artificially created tiers. 3 Q16 What would PURA be approving if it adopted one of the tiers? 4 A. PURA should be approving more than a planning concept as Eversource has 5 proposed. The Company proposes to recover TSP capital through the F-Factor 6 under its proposed Performance-Based Multi-Year Rate Plan (“PBMRP”), which 7 the Company describes as “tethered to the planned capital investment plan 8 described in the TSP Plan.”18 The Company states that the F-Factor would 9 provide “revenue support for ongoing capital expenditures,” subject to “periodic 10 and ongoing prudence reviews,” a cap, and “downward-only reconciliation in the 11 event actual overall plant-in-service is less than the capital expenditure 12 forecast.”19 The reconciliation compares total plant in service to the total forecast. 13 It does not compare individual projects or programs. Funds forecasted for a 14 project that is deferred or cancelled can be spent on other work without a refund. 15 The Company also states that PURA would make its prudence determination on 16 planned plant additions “in the next rate case at such time that those projects are 17 placed in-service.”20 18 Approval of a tier would therefore place five years of forecast capital into rates 19 before many of the projects have a defined scope, cost estimate, in-service date or 20 alternatives analysis. 21 Q17 What is your primary position on the TSP? 22 A. In conjunction with OCC Witnesses Wilson and Tully, we recommend that the 23 Authority deny the Company’s PBMRP proposal and only approve a one-year 24 rate plan in this docket. I agree with the concerns Ms. Wilson and Mr. Tully have 18 Exh. CLP-ADDITIONS-1 at 54. Response to OCC-579(a)(ii). 20 Exh. CLP-ADDITIONS-1 at 54. 19 Direct Testimony of Nikhil Balakumar Page 15Page 19 of 105
1 outlined regarding the lack of in-depth capital planning that would protect 2 Eversource customers from unnecessary costs in a multi-year rate plan tied to a 3 forward-looking capital plan. 4 Q18 If PURA intends to approve a version of the TSP, what is your position? 5 A. The Company’s proposal represents a “business-as-usual” approach focused on 6 traditional capital expenditures and lacks a sense of urgency to scale up grid 7 modernization investments that will accelerate the transition towards a more 8 dynamic and cost-effective system. The Company itself states that the third tier of 9 investment (i.e. Advancing the Grid) is a “longer-term proposition for 10 Connecticut.” This contradicts its stated goals on DER enablement and a dynamic 11 modern grid and the priorities of utilities across the country. 12 Modernizing the grid should not be a longer-term proposition, but should be 13 strategically designed now to ensure the Company can rapidly scale up the tools 14 and programs that would defer traditional buildout and run its system as 15 efficiently as possible. If PURA decides to approve a version of the TSP, the 16 Company should not accept Eversource’s artificial tiering but instead prioritize 17 investments within the proposed TSP that enable it to rapidly scale up to a 18 “flexibility first” approach that ensures future capital plans consider the full range 19 of modern, cost-effective solutions. Specifically, Eversource should be using the 20 upcoming term of the proposed TSP to rapidly gain operational experience with 21 key DER flexibility approaches such that these programs can be scaled by the end 22 of the TSP term and leading into the next cycle of investments. 23 As described in my testimony below, my recommendations outline a streamlined 24 and strategic alternative proposal to support these objectives that a) reduces 25 investment levels across the Sustained and Targeted System Performance tiers 26 while b) bringing forward key Advancing the Grid Investments. Direct Testimony of Nikhil Balakumar Page 16Page 20 of 105
1 B. Sustained Tier 2 Q19 How does the Company define and justify the Sustained tier? 3 A. The Sustained tier totals $3.611 billion from 2027 through 2031.21 The Company 4 describes it as necessary to maintain reliability “at levels that the Company has 5 generally maintained since the last rate case in Docket No. 17-10-46 (2018),” and 6 as “the minimum level of investment needed” to do so.22 The Company projects 7 that the tier would improve five-year SAIDI by 0.7 minutes, which it describes as 8 maintains current performance.23 9 The Sustained tier, however, is not simply a continuation of current spending. It 10 includes several significant increases. The Company proposes to increase 11 substation transformer replacements from an average of three per year in the 2026 12 budget to six per year, compared with a historical pace of one to two per year.24 It 13 also increases Grid Modernization spending from $10 million in 2026 to a $14 14 million per year, and vegetation management from $59 million to $91 million per 15 year.25 In addition, the tier includes $400 million for New Customer and $393 16 million for Peak Load/Capacity. 26 17 Because the Company describes this tier as the minimum needed, it should show 18 why each of these increases is necessary to achieve that result. The record does 19 not yet demonstrate that connection. 21 Exh. CLP-TSP-3 at 8. Exh. CLP-TSP-1 at 17. 23 Exh. CLP-TSP-3 at 8, 11. 24 Exh. CLP-TSP-3 at 11, Response to OCC-597. 25 Exh. CLP-TSP-3 at 11. 26 Response to OCC-811. 22 Direct Testimony of Nikhil Balakumar Page 17Page 21 of 105
1 2 Q20 How does the Sustained tier compare with Company’s capital spending since 2017? 3 A. The Sustained tier exceeds the Company’s actual capital expenditures in every 4 year from 2017 through 2024. The Company’s annual Capital Books report those 5 expenditures and provide the closest comparison in the record to the proposed 6 five-year plan.27 From 2017 through 2024, Connecticut Distribution capital 7 expenditures averaged $434 million per year and peaked at $558 million in 8 2023.28 By comparison, the Sustained tier would spend $667 million in 2027 and 9 average about $722 million per year over five years.29 10 Figure 1: Connecticut Distribution Capital, Actual and Planned, Compared with the Sustained Tier ($ million) 11 12 The largest growth categories show a similar pattern on an in-service basis 13 (Figure 1). Under the Sustained tier, annual New Customer investment would be 14 nearly twice the historical average, Peak Load/Capacity would be about two and a 15 half times higher, and substation transformer replacement would be nearly six 16 times higher. The historical amounts are plant placed in service, while the tier 17 amounts are planned investment, so the comparison is indicative rather than exact. 27 Exh. CLP-ADDITIONS-12. Exh. CLP-ADDITIONS-12 at 28, 45, 65, 83, 102, 121, 145, 167. 29 Exh. CLP-TSP-3 at 10. 28 Direct Testimony of Nikhil Balakumar Page 18
As listed on the current system