Prefiled testimony
Witness: Nikhil Balakumar
Files2
26-05-10_Direct Testimony Eclipse FINAL.pdf
PDF · 1.4 MB · 105 pagesText searchable
Download 26-05-10_Direct Testimony Eclipse FINAL.pdfRead the text of 26-05-10_Direct Testimony Eclipse FINAL.pdf
Attachment 1 - Nikhil Balakumar_Resume.pdf
PDF · 126 KB · 2 pagesText searchable
Download Attachment 1 - Nikhil Balakumar_Resume.pdfRead the text of Attachment 1 - Nikhil Balakumar_Resume.pdf
Words on different pages
Every word of Eversource rate increase is in the text below, but not all on one page. Pages with any of them are listed and highlighted. Clear highlighting
Page 19 of 105
1 outlined regarding the lack of in-depth capital planning that would protect 2 Eversource customers from unnecessary costs in a multi-year rate plan tied to a 3 forward-looking capital plan. 4 Q18 If PURA intends to approve a version of the TSP, what is your position? 5 A. The Company’s proposal represents a “business-as-usual” approach focused on 6 traditional capital expenditures and lacks a sense of urgency to scale up grid 7 modernization investments that will accelerate the transition towards a more 8 dynamic and cost-effective system. The Company itself states that the third tier of 9 investment (i.e. Advancing the Grid) is a “longer-term proposition for 10 Connecticut.” This contradicts its stated goals on DER enablement and a dynamic 11 modern grid and the priorities of utilities across the country. 12 Modernizing the grid should not be a longer-term proposition, but should be 13 strategically designed now to ensure the Company can rapidly scale up the tools 14 and programs that would defer traditional buildout and run its system as 15 efficiently as possible. If PURA decides to approve a version of the TSP, the 16 Company should not accept Eversource’s artificial tiering but instead prioritize 17 investments within the proposed TSP that enable it to rapidly scale up to a 18 “flexibility first” approach that ensures future capital plans consider the full range 19 of modern, cost-effective solutions. Specifically, Eversource should be using the 20 upcoming term of the proposed TSP to rapidly gain operational experience with 21 key DER flexibility approaches such that these programs can be scaled by the end 22 of the TSP term and leading into the next cycle of investments. 23 As described in my testimony below, my recommendations outline a streamlined 24 and strategic alternative proposal to support these objectives that a) reduces 25 investment levels across the Sustained and Targeted System Performance tiers 26 while b) bringing forward key Advancing the Grid Investments. Direct Testimony of Nikhil Balakumar Page 16Page 20 of 105
1 B. Sustained Tier 2 Q19 How does the Company define and justify the Sustained tier? 3 A. The Sustained tier totals $3.611 billion from 2027 through 2031.21 The Company 4 describes it as necessary to maintain reliability “at levels that the Company has 5 generally maintained since the last rate case in Docket No. 17-10-46 (2018),” and 6 as “the minimum level of investment needed” to do so.22 The Company projects 7 that the tier would improve five-year SAIDI by 0.7 minutes, which it describes as 8 maintains current performance.23 9 The Sustained tier, however, is not simply a continuation of current spending. It 10 includes several significant increases. The Company proposes to increase 11 substation transformer replacements from an average of three per year in the 2026 12 budget to six per year, compared with a historical pace of one to two per year.24 It 13 also increases Grid Modernization spending from $10 million in 2026 to a $14 14 million per year, and vegetation management from $59 million to $91 million per 15 year.25 In addition, the tier includes $400 million for New Customer and $393 16 million for Peak Load/Capacity. 26 17 Because the Company describes this tier as the minimum needed, it should show 18 why each of these increases is necessary to achieve that result. The record does 19 not yet demonstrate that connection. 21 Exh. CLP-TSP-3 at 8. Exh. CLP-TSP-1 at 17. 23 Exh. CLP-TSP-3 at 8, 11. 24 Exh. CLP-TSP-3 at 11, Response to OCC-597. 25 Exh. CLP-TSP-3 at 11. 26 Response to OCC-811. 22 Direct Testimony of Nikhil Balakumar Page 17Page 21 of 105
1 2 Q20 How does the Sustained tier compare with Company’s capital spending since 2017? 3 A. The Sustained tier exceeds the Company’s actual capital expenditures in every 4 year from 2017 through 2024. The Company’s annual Capital Books report those 5 expenditures and provide the closest comparison in the record to the proposed 6 five-year plan.27 From 2017 through 2024, Connecticut Distribution capital 7 expenditures averaged $434 million per year and peaked at $558 million in 8 2023.28 By comparison, the Sustained tier would spend $667 million in 2027 and 9 average about $722 million per year over five years.29 10 Figure 1: Connecticut Distribution Capital, Actual and Planned, Compared with the Sustained Tier ($ million) 11 12 The largest growth categories show a similar pattern on an in-service basis 13 (Figure 1). Under the Sustained tier, annual New Customer investment would be 14 nearly twice the historical average, Peak Load/Capacity would be about two and a 15 half times higher, and substation transformer replacement would be nearly six 16 times higher. The historical amounts are plant placed in service, while the tier 17 amounts are planned investment, so the comparison is indicative rather than exact. 27 Exh. CLP-ADDITIONS-12. Exh. CLP-ADDITIONS-12 at 28, 45, 65, 83, 102, 121, 145, 167. 29 Exh. CLP-TSP-3 at 10. 28 Direct Testimony of Nikhil Balakumar Page 18Page 22 of 105
1 Table 1: Sustained Tier Compared With 2017–2025 In-Service Additions30 Category Peak Load / Capacity New Customer Substation transformer replacement 2017–2025 in service (avg. per year) $31.0M $42.6M Sustained tier 2027–2031 (avg. per year) $78.6M $80.0M $8.6M $48.7M Increase 2.5× 1.9× 5.7× 2 3 4 Q21 Is the Company’s description of the Sustained tier as a minimum consistent with its 2025 capital plan? 5 A. No. The Company’s own statements do not support treating the Sustained tier as a 6 clear minimum. 7 First, the Company states that past investments have consistently proven to be 8 “right sized” to maintain reliability and that the system “has continued to perform 9 well for customers, so long as there is adequate and consistent investment made to 10 maintain the system in its current state, which the Company has achieved.” The 11 Company now states that “the system is at a crossroads where a step-up in 12 investment is needed.”31 If past spending was sufficient to maintain reliability, the 13 Company should explain why a much higher level is now the minimum needed to 14 do the same. 15 Second, the Company cut its 2025 Connecticut capital plan for reasons unrelated to 16 system need to $375.3 million, from $450.6 million actual in 2024.32 The 2025 17 capital book states that the Plan reflects a reduction in spending for Connecticut to 18 lower the cost recovery risk, and identifies a “decrease in overall CT capital plan 19 due to regulatory recovery risk” 33 as the first variance driver. When asked 20 whether that level fell below what was needed to maintain reliability, the Company 30 Response to OCC-811. Exh. CLP-TSP-1 at 22–23. 32 Id. at 167. 33 Exh. CLP-ADDITIONS-12 at 167. 31 Direct Testimony of Nikhil Balakumar Page 19Page 23 of 105
1 responded that the 2025 investment amount was not below the level the Company 2 considered necessary to maintain reliability in the short term.34 It added that “there 3 is no ‘reliability or safety consequence’ associated with such a short-term deviation 4 in budget expenditures”, and that it took “significant care to identify capital work 5 that could be toggled back without an immediate impact to safety and reliability.”35 6 The Company’s dedicated reliability investment was $123.4 million in the 2025 7 plan. Under the Sustained tier it would be $236.6 million in 2027.36 8 The Company also states that a sustained reduction in spending could affect 9 reliability by 12 to 15 percent over five years, “assuming no improvement in the 10 reduced expenditure level.” 37 I do not dispute that consistent investment is 11 necessary. The issue is that the Company has not shown where the actual 12 minimum lies between the lower 2025 spending level and the Sustained tier’s 13 average of about $722 million per year. 14 Finally, the Company acknowledges that its reliability “remains in the top quartile 15 based on the IEEE benchmarking study.” 38 PURA has identified top-quartile 16 performance in the four years before a rate case as a consideration in deciding 17 whether to approve a plan designed to improve reliability further.39 The Sustained 18 tier, by the Company’s own description, is designed to maintain performance, not 19 improve it. Holding a top-quartile position should not require spending well above 20 the levels that produced that position. 21 Q22 How does the Company calculate the reliability benefit of each tier? 22 A. The Company assigns SAIDI improvement to only two capital programs – 23 Reliability Improvement Specific Projects and the Smart Switches Program, along 34 Response to OCC-795. Response to OCC-781. 36 Response to OCC-795. 37 Response to OCC-781. 38 Exh. CLP-TSP-3 at 32; 39 Docket No. 17-12-03RE08, Decision at 44. 35 Direct Testimony of Nikhil Balakumar Page 20Page 24 of 105
1 with vegetation management. It then applies a “System Degradation” factor that 2 worsens SAIDI by the same 15.6 minutes under both tiers.40 3 I have several concerns with this approach. First, the degradation factor has a 4 significant effect on the result, but the Company has not provided the basis for 5 that assumption. Second, the Sustained tier produces a net SAIDI improvement of 6 only 0.7 minutes, or about one percent of 2025 Blue-Sky SAIDI, even though the 7 Company describes the tier as the minimum needed to maintain reliability.41 8 Third, the additional SAIDI benefit of the TSP tier comes entirely from the same 9 two reliability programs. The Company assigns no SAIDI benefit to the resilience 10 or asset health portions of the second tier of proposed TSP investment, which 11 accounts for about $298 million of the $374 million.42 12 13 Q23 Has the Company’s past capital spending delivered the reliability results it now projects? 14 A. The Company’s own data does not show that it has. From 2021 through 2025, the 15 Company placed about $985 million of reliability capital in service.43 Over the 16 same period, Blue-Sky SAIDI increased from 70.7 minutes in 2021 to 77.5 17 minutes in 2025, after improving slightly through 2023.44 I am not suggesting that 18 reliability capital produced no benefit, or that a single year’s result proves 19 anything. Weather and other factors affect annual reliability results. But the 20 Company asks PURA to accept a projected 6.1-minute improvement under the 21 TSP tier, while also explaining that its past spending “cannot necessarily be 22 directly and instantaneous[ly] translated to SAIDI and SAIFI performance.” 23 When asked to identify the expected reliability performance associated with the 24 2021–2025 spending when it was authorized, the Company did not identify one.45 40 Response to OCC-807. Exh. CLP-TSP-1 at 17, 76; Response to OCC-807. 42 Response to OCC-809. 43 Response to OCC-804 Attachment 1. 44 Exh. CLP-TSP-1 at 76, Table 1. 45 Response to OCC-804. 41 Direct Testimony of Nikhil Balakumar Page 21Page 25 of 105
1 The selection process behind that spending also matters. The Company’s cost- 2 effectiveness ranking tool, ReBOT, was first used “to drive reliability work in 3 2024 to support the selection of the 2025 TripSaver program.”46 None of the 4 2017–2024 reliability capital was selected using that tool. In 2023, when actual 5 spending exceeded plan by $91.5 million, the Company identified the two largest 6 additions to the capital plan as an approximately $22.0 million trip-saver program 7 and approximately $20.0 million of circuit patrol fixes addressing deficiencies 8 identified by a third party.47 9 The 2017–2025 record is therefore important context for evaluating the 10 Company’s new five-year projections. That record does not, by itself, support pre- 11 approving five more years of substantially higher spending on the strength of 12 projected reliability benefits. I address the prudence of the 2017–2025 additions 13 separately in the Capital Additions section of my testimony. 14 Figure 2: Reliability Capital Placed in Service and Blue-Sky SAIDI, 2021–2025 15 16 46 47 Response to OCC-792. Responses to OCC-780 and OCC-792. Direct Testimony of Nikhil Balakumar Page 22Page 26 of 105
1 The Sustained Tier’s Growth Drivers 2 Q24 What spending is at issue? 3 A. The Company’s direct testimony states that average baseline funding for Peak 4 Load/Capacity is approximately $50 million per year for substations and $19 5 million per year for lines, or about $345 million over five years.48 The Company’s 6 capital-plan presentation, however, shows $393 million of Capacity spending over 7 the same five-year period under the Targeted System Performance tier.49 In 8 discovery, the Company also reports $393 million for both the Sustained and 9 Targeted System Performance tiers. 10 The capital-plan presentation and discovery responses are consistent with each 11 other, but they leave an approximately $48 million difference from the amount 12 described in direct testimony. The Company should explain whether that 13 difference reflects updated estimates, different project scope, or another 14 adjustment, and identify the amount actually included in its request. It should also 15 reconcile that amount to the underlying substation and line projects, annual 16 spending, and any program-level allowances. Without that reconciliation, it is 17 difficult to determine what work the proposed funding would support. 18 19 Q25 Was the Company required to evaluate non-wires solutions before seeking funding for its capacity projects? 20 A. Yes. The Company’s own planning documents and PURA’s NWS process both 21 call for alternatives to be identified and compared before a wires solution is 22 funded.50 The Company’s 2021 NWA Framework screens station capacity needs 23 first, using standard technical and cost assumptions, so that only viable candidates 24 proceed to detailed engineering; its economic test compares the present value of 48 Exhibit CLP-TSP-1 at 50 Exhitbit CLP-TSP-3 at 42 50 I use “non-wires solutions” (“NWS”) in this section and retain “NWA” when referring to the Company’s 2021 NWA Framework. 49 Direct Testimony of Nikhil Balakumar Page 23Page 27 of 105
1 the non-wires alternative plus the deferred conventional project with the 2 conventional project built when first needed.51 The Framework also disqualifies 3 any need that arises within two years of the base year, and any station with a 4 transformer health index above 0.5.52 The Company states that it now follows the 5 process PURA approved in Docket No. 24-08-08,53 but it has not stated whether it 6 still applies the Framework’s two-year exclusion. 7 The Company’s Distribution System Planning Guide (“DSPG”) follows the same 8 approach. It states that “the most cost-effective solution should be proposed as the 9 preferred solution,” with additional alternatives included in the initial funding 10 request (“IFR”) and Solution Design Committee (“SDC”) process, using a ten- 11 year view of capital, maintenance, energy and replacement costs.54 The Guide 12 also directs that NWS screening to consider these same cost elements over the 13 standard ten-year planning horizon.55 14 PURA’s NWS process is consistent with this principle. PURA has stated that “all 15 planned capital investments with an estimated cost greater than $250,000 should 16 be accounted for in either the Grid Needs Filing or in the quarterly filings.”56 It 17 “will consider the EDC’s compliance or non-compliance with the NWS process 18 as evidence in determining whether the Company acted in a prudent manner.”57 19 PURA has also confirmed that the Company keeps its burden of proof under the 20 prudence standard when it seeks cost recovery.58 In April 2026, PURA closed the 21 second NWS cycle without a screening decision and paused further cycles to 51 Response to OCC-578, Attachment 1 at 9–12. Id. at 9. 53 Response to OCC-578. 54 Response to CLF-SC-023, Attachment 1, at 41. 55 Id. at 40. 56 Docket No. 25-08-08, Decision (Dec. 10, 2025) at 12. 57 Docket No. 24-08-08, Decision at 9 n.4. 58 Docket No. 25-08-08, Decision at 1 n.1. 52 Direct Testimony of Nikhil Balakumar Page 24Page 28 of 105
1 redesign the process. It directed, however, that its NWS orders “remain in effect” 2 and that the Company continue its Grid Needs and quarterly filings.59 3 My concern is that the record doesn’t establish that the Company evaluated 4 reasonable alternatives before seeking funding for capital investments included in 5 the TSP. I am not suggesting that a non-wires solution will fit every need or that 6 every project requires a competitive solicitation. However, Eversource needs to 7 demonstrate that adequate consideration was given to cost-effective solutions. 8 9 Q26 Has the Company demonstrated that it followed that process for the substation projects in this plan? 10 A. No. The Company states that its substation capacity projects “are all at the 11 conceptual stage,” “do not currently have planned in-service dates,” “do not have 12 approved scopes of work,” and “do not currently have NWA solutions identified.” 13 Several measures needed to evaluate alternatives – energy above rating, the 14 duration or event frequency remain undeveloped. The Company also states that it 15 “does not currently generate an hourly load forecast.”60 The Company states that 16 it creates 24-hour load profiles for a station once a need is identified, but it did not 17 provide any for these projects.61 18 The Company’s own sequence runs backward. It states that “following initial 19 funding of these projects, all available solutions including permanent load 20 transfers, non-wires solutions, and traditional solutions are identified and 21 evaluated.” Several projects have already passed that point. Triangle 11A, 22 Rockville 14W, Tracy 14M and Frybrook 13B have initial funding approved, 23 Baldwin 13F has initial funding submitted, and Campville 14R has partial 24 funding.62 The Company should reconcile that description with the DSPG’s 59 Notice of Docket Closing, Docket No. 26-08-08 (Apr. 17, 2026) at 1. OCC-594 at 1–3; OCC-812 at 1. 61 Responses to OCC-574(b) (f), and OCC-587(b) 62 Response to OCC-599. 60 Direct Testimony of Nikhil Balakumar Page 25
As listed on the current system
Prefiled testimony: 10/21/2026 - Sponsor: TBD / Witness: Nikhil Balakumar [26-05-10]