  1. Page 22 of 105

    1 Table 1: Sustained Tier Compared With 2017–2025 In-Service Additions30 Category Peak Load / Capacity New Customer Substation transformer replacement 2017–2025 in service (avg. per year) $31.0M $42.6M Sustained tier 2027–2031 (avg. per year) $78.6M $80.0M $8.6M $48.7M Increase 2.5× 1.9× 5.7× 2 3 4 Q21 Is the Company’s description of the Sustained tier as a minimum consistent with its 2025 capital plan? 5 A. No. The Company’s own statements do not support treating the Sustained tier as a 6 clear minimum. 7 First, the Company states that past investments have consistently proven to be 8 “right sized” to maintain reliability and that the system “has continued to perform 9 well for customers, so long as there is adequate and consistent investment made to 10 maintain the system in its current state, which the Company has achieved.” The 11 Company now states that “the system is at a crossroads where a step-up in 12 investment is needed.”31 If past spending was sufficient to maintain reliability, the 13 Company should explain why a much higher level is now the minimum needed to 14 do the same. 15 Second, the Company cut its 2025 Connecticut capital plan for reasons unrelated to 16 system need to $375.3 million, from $450.6 million actual in 2024.32 The 2025 17 capital book states that the Plan reflects a reduction in spending for Connecticut to 18 lower the cost recovery risk, and identifies a “decrease in overall CT capital plan 19 due to regulatory recovery risk” 33 as the first variance driver. When asked 20 whether that level fell below what was needed to maintain reliability, the Company 30 Response to OCC-811. Exh. CLP-TSP-1 at 22–23. 32 Id. at 167. 33 Exh. CLP-ADDITIONS-12 at 167. 31 Direct Testimony of Nikhil Balakumar Page 19
  2. Page 23 of 105

    1 responded that the 2025 investment amount was not below the level the Company 2 considered necessary to maintain reliability in the short term.34 It added that “there 3 is no ‘reliability or safety consequence’ associated with such a short-term deviation 4 in budget expenditures”, and that it took “significant care to identify capital work 5 that could be toggled back without an immediate impact to safety and reliability.”35 6 The Company’s dedicated reliability investment was $123.4 million in the 2025 7 plan. Under the Sustained tier it would be $236.6 million in 2027.36 8 The Company also states that a sustained reduction in spending could affect 9 reliability by 12 to 15 percent over five years, “assuming no improvement in the 10 reduced expenditure level.” 37 I do not dispute that consistent investment is 11 necessary. The issue is that the Company has not shown where the actual 12 minimum lies between the lower 2025 spending level and the Sustained tier’s 13 average of about $722 million per year. 14 Finally, the Company acknowledges that its reliability “remains in the top quartile 15 based on the IEEE benchmarking study.” 38 PURA has identified top-quartile 16 performance in the four years before a rate case as a consideration in deciding 17 whether to approve a plan designed to improve reliability further.39 The Sustained 18 tier, by the Company’s own description, is designed to maintain performance, not 19 improve it. Holding a top-quartile position should not require spending well above 20 the levels that produced that position. 21 Q22 How does the Company calculate the reliability benefit of each tier? 22 A. The Company assigns SAIDI improvement to only two capital programs – 23 Reliability Improvement Specific Projects and the Smart Switches Program, along 34 Response to OCC-795. Response to OCC-781. 36 Response to OCC-795. 37 Response to OCC-781. 38 Exh. CLP-TSP-3 at 32; 39 Docket No. 17-12-03RE08, Decision at 44. 35 Direct Testimony of Nikhil Balakumar Page 20
  3. Page 24 of 105

    1 with vegetation management. It then applies a “System Degradation” factor that 2 worsens SAIDI by the same 15.6 minutes under both tiers.40 3 I have several concerns with this approach. First, the degradation factor has a 4 significant effect on the result, but the Company has not provided the basis for 5 that assumption. Second, the Sustained tier produces a net SAIDI improvement of 6 only 0.7 minutes, or about one percent of 2025 Blue-Sky SAIDI, even though the 7 Company describes the tier as the minimum needed to maintain reliability.41 8 Third, the additional SAIDI benefit of the TSP tier comes entirely from the same 9 two reliability programs. The Company assigns no SAIDI benefit to the resilience 10 or asset health portions of the second tier of proposed TSP investment, which 11 accounts for about $298 million of the $374 million.42 12 13 Q23 Has the Company’s past capital spending delivered the reliability results it now projects? 14 A. The Company’s own data does not show that it has. From 2021 through 2025, the 15 Company placed about $985 million of reliability capital in service.43 Over the 16 same period, Blue-Sky SAIDI increased from 70.7 minutes in 2021 to 77.5 17 minutes in 2025, after improving slightly through 2023.44 I am not suggesting that 18 reliability capital produced no benefit, or that a single year’s result proves 19 anything. Weather and other factors affect annual reliability results. But the 20 Company asks PURA to accept a projected 6.1-minute improvement under the 21 TSP tier, while also explaining that its past spending “cannot necessarily be 22 directly and instantaneous[ly] translated to SAIDI and SAIFI performance.” 23 When asked to identify the expected reliability performance associated with the 24 2021–2025 spending when it was authorized, the Company did not identify one.45 40 Response to OCC-807. Exh. CLP-TSP-1 at 17, 76; Response to OCC-807. 42 Response to OCC-809. 43 Response to OCC-804 Attachment 1. 44 Exh. CLP-TSP-1 at 76, Table 1. 45 Response to OCC-804. 41 Direct Testimony of Nikhil Balakumar Page 21
  4. Page 25 of 105

    1 The selection process behind that spending also matters. The Company’s cost- 2 effectiveness ranking tool, ReBOT, was first used “to drive reliability work in 3 2024 to support the selection of the 2025 TripSaver program.”46 None of the 4 2017–2024 reliability capital was selected using that tool. In 2023, when actual 5 spending exceeded plan by $91.5 million, the Company identified the two largest 6 additions to the capital plan as an approximately $22.0 million trip-saver program 7 and approximately $20.0 million of circuit patrol fixes addressing deficiencies 8 identified by a third party.47 9 The 2017–2025 record is therefore important context for evaluating the 10 Company’s new five-year projections. That record does not, by itself, support pre- 11 approving five more years of substantially higher spending on the strength of 12 projected reliability benefits. I address the prudence of the 2017–2025 additions 13 separately in the Capital Additions section of my testimony. 14 Figure 2: Reliability Capital Placed in Service and Blue-Sky SAIDI, 2021–2025 15 16 46 47 Response to OCC-792. Responses to OCC-780 and OCC-792. Direct Testimony of Nikhil Balakumar Page 22
  5. Page 26 of 105

    1 The Sustained Tier’s Growth Drivers 2 Q24 What spending is at issue? 3 A. The Company’s direct testimony states that average baseline funding for Peak 4 Load/Capacity is approximately $50 million per year for substations and $19 5 million per year for lines, or about $345 million over five years.48 The Company’s 6 capital-plan presentation, however, shows $393 million of Capacity spending over 7 the same five-year period under the Targeted System Performance tier.49 In 8 discovery, the Company also reports $393 million for both the Sustained and 9 Targeted System Performance tiers. 10 The capital-plan presentation and discovery responses are consistent with each 11 other, but they leave an approximately $48 million difference from the amount 12 described in direct testimony. The Company should explain whether that 13 difference reflects updated estimates, different project scope, or another 14 adjustment, and identify the amount actually included in its request. It should also 15 reconcile that amount to the underlying substation and line projects, annual 16 spending, and any program-level allowances. Without that reconciliation, it is 17 difficult to determine what work the proposed funding would support. 18 19 Q25 Was the Company required to evaluate non-wires solutions before seeking funding for its capacity projects? 20 A. Yes. The Company’s own planning documents and PURA’s NWS process both 21 call for alternatives to be identified and compared before a wires solution is 22 funded.50 The Company’s 2021 NWA Framework screens station capacity needs 23 first, using standard technical and cost assumptions, so that only viable candidates 24 proceed to detailed engineering; its economic test compares the present value of 48 Exhibit CLP-TSP-1 at 50 Exhitbit CLP-TSP-3 at 42 50 I use “non-wires solutions” (“NWS”) in this section and retain “NWA” when referring to the Company’s 2021 NWA Framework. 49 Direct Testimony of Nikhil Balakumar Page 23
  6. Page 27 of 105

    1 the non-wires alternative plus the deferred conventional project with the 2 conventional project built when first needed.51 The Framework also disqualifies 3 any need that arises within two years of the base year, and any station with a 4 transformer health index above 0.5.52 The Company states that it now follows the 5 process PURA approved in Docket No. 24-08-08,53 but it has not stated whether it 6 still applies the Framework’s two-year exclusion. 7 The Company’s Distribution System Planning Guide (“DSPG”) follows the same 8 approach. It states that “the most cost-effective solution should be proposed as the 9 preferred solution,” with additional alternatives included in the initial funding 10 request (“IFR”) and Solution Design Committee (“SDC”) process, using a ten- 11 year view of capital, maintenance, energy and replacement costs.54 The Guide 12 also directs that NWS screening to consider these same cost elements over the 13 standard ten-year planning horizon.55 14 PURA’s NWS process is consistent with this principle. PURA has stated that “all 15 planned capital investments with an estimated cost greater than $250,000 should 16 be accounted for in either the Grid Needs Filing or in the quarterly filings.”56 It 17 “will consider the EDC’s compliance or non-compliance with the NWS process 18 as evidence in determining whether the Company acted in a prudent manner.”57 19 PURA has also confirmed that the Company keeps its burden of proof under the 20 prudence standard when it seeks cost recovery.58 In April 2026, PURA closed the 21 second NWS cycle without a screening decision and paused further cycles to 51 Response to OCC-578, Attachment 1 at 9–12. Id. at 9. 53 Response to OCC-578. 54 Response to CLF-SC-023, Attachment 1, at 41. 55 Id. at 40. 56 Docket No. 25-08-08, Decision (Dec. 10, 2025) at 12. 57 Docket No. 24-08-08, Decision at 9 n.4. 58 Docket No. 25-08-08, Decision at 1 n.1. 52 Direct Testimony of Nikhil Balakumar Page 24
  7. Page 28 of 105

    1 redesign the process. It directed, however, that its NWS orders “remain in effect” 2 and that the Company continue its Grid Needs and quarterly filings.59 3 My concern is that the record doesn’t establish that the Company evaluated 4 reasonable alternatives before seeking funding for capital investments included in 5 the TSP. I am not suggesting that a non-wires solution will fit every need or that 6 every project requires a competitive solicitation. However, Eversource needs to 7 demonstrate that adequate consideration was given to cost-effective solutions. 8 9 Q26 Has the Company demonstrated that it followed that process for the substation projects in this plan? 10 A. No. The Company states that its substation capacity projects “are all at the 11 conceptual stage,” “do not currently have planned in-service dates,” “do not have 12 approved scopes of work,” and “do not currently have NWA solutions identified.” 13 Several measures needed to evaluate alternatives – energy above rating, the 14 duration or event frequency remain undeveloped. The Company also states that it 15 “does not currently generate an hourly load forecast.”60 The Company states that 16 it creates 24-hour load profiles for a station once a need is identified, but it did not 17 provide any for these projects.61 18 The Company’s own sequence runs backward. It states that “following initial 19 funding of these projects, all available solutions including permanent load 20 transfers, non-wires solutions, and traditional solutions are identified and 21 evaluated.” Several projects have already passed that point. Triangle 11A, 22 Rockville 14W, Tracy 14M and Frybrook 13B have initial funding approved, 23 Baldwin 13F has initial funding submitted, and Campville 14R has partial 24 funding.62 The Company should reconcile that description with the DSPG’s 59 Notice of Docket Closing, Docket No. 26-08-08 (Apr. 17, 2026) at 1. OCC-594 at 1–3; OCC-812 at 1. 61 Responses to OCC-574(b) (f), and OCC-587(b) 62 Response to OCC-599. 60 Direct Testimony of Nikhil Balakumar Page 25
  8. Page 29 of 105

    1 expectation that alternatives inform the IFR and provide the screening records 2 associated with each project’s actual approval stage.63 3 The Company’s own record also indicates that these needs are not urgent. It states 4 that “[a]ll substation forecasted violations are mitigated by using pre-contingent 5 load transfers to adjacent substations with remaining capacity.” For two listed 6 substations, Rocky Hill 12Y and Brooklyn 30Y, it anticipates a permanent load 7 transfer “with settings changes only.” It describes permanent load transfers as “in 8 many cases, a preferred solution” that is “typically substantially lower cost than 9 substation investments,” yet it did not track those transfers before 2024.64 10 Because PURA treats NWS compliance as evidence of prudence, the burden is on 11 the Company to show that screening informed the funding it seeks. A 12 commitment to screen these projects after rates are set does not meet that burden. 13 14 Q27 Does the record for the Company’s own non-wires candidates support the amounts it requests? 15 A. No. The Company presents battery proposals for Campville 14R and Frybrook 16 13B. For Campville, it identifies a 6.5 MW/11 MWh system estimated at $24.06 17 million against a $77 million traditional solution. For Frybrook, it identifies a 2.5 18 MW/10 MWh system estimated at $20.1 million against $25 million.65 In 19 discovery, the Company states that both proposals remain conceptual, have initial 20 funding approved, and must be reevaluated against other solutions before a final 21 proposal is selected, and that the underlying needs are funded in the Sustained 22 tier.66 Its cost tables now carry $52.3 million for Campville and $20 million for 23 Frybrook without reconciling those figures to either the battery or the traditional 63 OCC-599 at 2–3; CLF-SC-023, Attachment 1 at 41. 64 Response to OCC-599 at 2–3. 65 Exh. CLP-TSP-3 at 103, 105–106. The Company notes that these figures were filed in Docket No. 22-0605 and would change if updated. 66 Response to OCC-579(a)(i)–(ii). Direct Testimony of Nikhil Balakumar Page 26
  9. Page 30 of 105

    1 alternative.67 My concern is not that no NWA work exists, but that the Company 2 has not shown which current scopes, costs and alternatives support the amounts it 3 asks customers to fund. 4 PURA’s review of West Brookfield 14H does not close that gap. PURA reviewed 5 the Company’s battery comparison for the $16.9 million transformer project, 6 identified a potential NWS opportunity, and accepted the Company’s decision not 7 to issue a solicitation, stating that the decision would not be construed as 8 noncompliance.68 I do not suggest otherwise. PURA did, however, find that 9 “comparing the cost to a BESS with an assumed $2 million per MWh cost is an 10 inadequate methodology to screen grid needs,” and that the Company did not 11 explain how alternatives other than batteries were considered, while recognizing a 12 good-faith screening effort. The relevant question is whether the analysis 13 supporting the investments in this case addresses those deficiencies. As I explain 14 below, it does not: the Company’s January 2026 Grid Needs narratives still price 15 battery alternatives at “$2M per MWh.”69 West Brookfield also demonstrates why 16 screening and funding status must be reported by project rather than described 17 through a single characterization of all substations. 18 19 Q28 Are the line capacity and New Customer budgets supported by identified, screened projects? 20 A. Only in part. The Company budgets about $19 million a year for line capacity, or 21 roughly $95 million over five years.70 Its list of feeder capacity projects contains 22 21 projects totaling $19.46 million, with in-service dates in 2027 and 2028. 23 Because that list reports project costs rather than a five-year spending schedule, 67 Response to OCC-599(a) at 2. Response to OCC-590, Attachment 1; Decision, Docket No. 25-08-08 at 1, 7–8. 69 Response to OCC-590, Attachment 3 at 5. 70 Exh. CLP-TSP-1 at 49–50. 68 Direct Testimony of Nikhil Balakumar Page 27
  10. Page 31 of 105

    1 the difference does not by itself establish excess funding. It does show that the 2 Company has not identified what most of the allowance would fund.71 3 The screening record is also incomplete. Several of the identified projects do not 4 appear in the 2025 or 2026 Grid Needs Filings.72 While some may fall below the 5 filing thresholds, the record does not clearly show how the full set of projects was 6 screened through the NWS process. An absent listing does not by itself establish 7 noncompliance, but the Company should identify the screening result or 8 documented basis for exclusion for each project. 9 The New Customer budget of $400 million averages $80 million a year.73 Actual 10 New Customer spending was $41.0 million in 2022, $60.2 million in 2023 and 11 $63.2 million in 2024.74 The Company’s 2027 project list includes a $50.0 million 12 line item for “Requests for New Service work less than $250k,” with no location 13 or scope identified (“TBD”).75 I recognize that New Customer work is driven by 14 customer requests and is not subject to NWS screening. The Company should 15 nonetheless support a near doubling of the historical run rate with a forecast of 16 requests, not an unspecified allowance. 17 18 Q29 What does the Campville right-of-way rebuild show about the Company’s evaluation of alternatives? 19 A. It shows that the Company continues to rely on the screening method PURA 20 found inadequate. 21 The comparison prices a 22.5 MWh battery at “$2M per MWh,” the assumption 22 PURA found inadequate, and compares costs without the ten-year total-cost view 71 Response to OCC-594, Attachment 1. Response to OCC-590, Attachments 1–2; Response to OCC-594, Attachment 1. 73 Exh. CLP-TSP-1 at 49. 74 Exh. CLP-TSP-3 at 53. 75 Response to OCC-813, Attachment 1. 72 Direct Testimony of Nikhil Balakumar Page 28