  1. Page 28 of 105

    1 redesign the process. It directed, however, that its NWS orders “remain in effect” 2 and that the Company continue its Grid Needs and quarterly filings.59 3 My concern is that the record doesn’t establish that the Company evaluated 4 reasonable alternatives before seeking funding for capital investments included in 5 the TSP. I am not suggesting that a non-wires solution will fit every need or that 6 every project requires a competitive solicitation. However, Eversource needs to 7 demonstrate that adequate consideration was given to cost-effective solutions. 8 9 Q26 Has the Company demonstrated that it followed that process for the substation projects in this plan? 10 A. No. The Company states that its substation capacity projects “are all at the 11 conceptual stage,” “do not currently have planned in-service dates,” “do not have 12 approved scopes of work,” and “do not currently have NWA solutions identified.” 13 Several measures needed to evaluate alternatives – energy above rating, the 14 duration or event frequency remain undeveloped. The Company also states that it 15 “does not currently generate an hourly load forecast.”60 The Company states that 16 it creates 24-hour load profiles for a station once a need is identified, but it did not 17 provide any for these projects.61 18 The Company’s own sequence runs backward. It states that “following initial 19 funding of these projects, all available solutions including permanent load 20 transfers, non-wires solutions, and traditional solutions are identified and 21 evaluated.” Several projects have already passed that point. Triangle 11A, 22 Rockville 14W, Tracy 14M and Frybrook 13B have initial funding approved, 23 Baldwin 13F has initial funding submitted, and Campville 14R has partial 24 funding.62 The Company should reconcile that description with the DSPG’s 59 Notice of Docket Closing, Docket No. 26-08-08 (Apr. 17, 2026) at 1. OCC-594 at 1–3; OCC-812 at 1. 61 Responses to OCC-574(b) (f), and OCC-587(b) 62 Response to OCC-599. 60 Direct Testimony of Nikhil Balakumar Page 25
  2. Page 29 of 105

    1 expectation that alternatives inform the IFR and provide the screening records 2 associated with each project’s actual approval stage.63 3 The Company’s own record also indicates that these needs are not urgent. It states 4 that “[a]ll substation forecasted violations are mitigated by using pre-contingent 5 load transfers to adjacent substations with remaining capacity.” For two listed 6 substations, Rocky Hill 12Y and Brooklyn 30Y, it anticipates a permanent load 7 transfer “with settings changes only.” It describes permanent load transfers as “in 8 many cases, a preferred solution” that is “typically substantially lower cost than 9 substation investments,” yet it did not track those transfers before 2024.64 10 Because PURA treats NWS compliance as evidence of prudence, the burden is on 11 the Company to show that screening informed the funding it seeks. A 12 commitment to screen these projects after rates are set does not meet that burden. 13 14 Q27 Does the record for the Company’s own non-wires candidates support the amounts it requests? 15 A. No. The Company presents battery proposals for Campville 14R and Frybrook 16 13B. For Campville, it identifies a 6.5 MW/11 MWh system estimated at $24.06 17 million against a $77 million traditional solution. For Frybrook, it identifies a 2.5 18 MW/10 MWh system estimated at $20.1 million against $25 million.65 In 19 discovery, the Company states that both proposals remain conceptual, have initial 20 funding approved, and must be reevaluated against other solutions before a final 21 proposal is selected, and that the underlying needs are funded in the Sustained 22 tier.66 Its cost tables now carry $52.3 million for Campville and $20 million for 23 Frybrook without reconciling those figures to either the battery or the traditional 63 OCC-599 at 2–3; CLF-SC-023, Attachment 1 at 41. 64 Response to OCC-599 at 2–3. 65 Exh. CLP-TSP-3 at 103, 105–106. The Company notes that these figures were filed in Docket No. 22-0605 and would change if updated. 66 Response to OCC-579(a)(i)–(ii). Direct Testimony of Nikhil Balakumar Page 26
  3. Page 30 of 105

    1 alternative.67 My concern is not that no NWA work exists, but that the Company 2 has not shown which current scopes, costs and alternatives support the amounts it 3 asks customers to fund. 4 PURA’s review of West Brookfield 14H does not close that gap. PURA reviewed 5 the Company’s battery comparison for the $16.9 million transformer project, 6 identified a potential NWS opportunity, and accepted the Company’s decision not 7 to issue a solicitation, stating that the decision would not be construed as 8 noncompliance.68 I do not suggest otherwise. PURA did, however, find that 9 “comparing the cost to a BESS with an assumed $2 million per MWh cost is an 10 inadequate methodology to screen grid needs,” and that the Company did not 11 explain how alternatives other than batteries were considered, while recognizing a 12 good-faith screening effort. The relevant question is whether the analysis 13 supporting the investments in this case addresses those deficiencies. As I explain 14 below, it does not: the Company’s January 2026 Grid Needs narratives still price 15 battery alternatives at “$2M per MWh.”69 West Brookfield also demonstrates why 16 screening and funding status must be reported by project rather than described 17 through a single characterization of all substations. 18 19 Q28 Are the line capacity and New Customer budgets supported by identified, screened projects? 20 A. Only in part. The Company budgets about $19 million a year for line capacity, or 21 roughly $95 million over five years.70 Its list of feeder capacity projects contains 22 21 projects totaling $19.46 million, with in-service dates in 2027 and 2028. 23 Because that list reports project costs rather than a five-year spending schedule, 67 Response to OCC-599(a) at 2. Response to OCC-590, Attachment 1; Decision, Docket No. 25-08-08 at 1, 7–8. 69 Response to OCC-590, Attachment 3 at 5. 70 Exh. CLP-TSP-1 at 49–50. 68 Direct Testimony of Nikhil Balakumar Page 27
  4. Page 31 of 105

    1 the difference does not by itself establish excess funding. It does show that the 2 Company has not identified what most of the allowance would fund.71 3 The screening record is also incomplete. Several of the identified projects do not 4 appear in the 2025 or 2026 Grid Needs Filings.72 While some may fall below the 5 filing thresholds, the record does not clearly show how the full set of projects was 6 screened through the NWS process. An absent listing does not by itself establish 7 noncompliance, but the Company should identify the screening result or 8 documented basis for exclusion for each project. 9 The New Customer budget of $400 million averages $80 million a year.73 Actual 10 New Customer spending was $41.0 million in 2022, $60.2 million in 2023 and 11 $63.2 million in 2024.74 The Company’s 2027 project list includes a $50.0 million 12 line item for “Requests for New Service work less than $250k,” with no location 13 or scope identified (“TBD”).75 I recognize that New Customer work is driven by 14 customer requests and is not subject to NWS screening. The Company should 15 nonetheless support a near doubling of the historical run rate with a forecast of 16 requests, not an unspecified allowance. 17 18 Q29 What does the Campville right-of-way rebuild show about the Company’s evaluation of alternatives? 19 A. It shows that the Company continues to rely on the screening method PURA 20 found inadequate. 21 The comparison prices a 22.5 MWh battery at “$2M per MWh,” the assumption 22 PURA found inadequate, and compares costs without the ten-year total-cost view 71 Response to OCC-594, Attachment 1. Response to OCC-590, Attachments 1–2; Response to OCC-594, Attachment 1. 73 Exh. CLP-TSP-1 at 49. 74 Exh. CLP-TSP-3 at 53. 75 Response to OCC-813, Attachment 1. 72 Direct Testimony of Nikhil Balakumar Page 28
  5. Page 32 of 105

    1 the Company’s own Planning Guide requires.76 At the approximately $420,000 to 2 $450,000 per MWh that PURA cited for UI, the same battery would cost about 3 $9.5 million to $10.1 million.77 That does not establish that a battery is the better 4 choice; the rebuild also replaces aging conductor, and the battery would support 5 the contingency for four hours. It does establish that the Company’s screening 6 cannot support its funding requests. The Company should separate capacity relief 7 from unavoidable asset-condition work and compare technically feasible options 8 on a consistent, lifecycle basis. 9 Q30 Are you recommending that all capacity work be stopped? 10 A. No. N-1 overloads can create legitimate investment needs even when equipment 11 operates within its ratings with all elements in service. My recommendation 12 concerns approval of the proposed budget on this record. The Company should 13 complete the substation due diligence before the substation capacity allowance is 14 approved; the line-project budget may be approved once the reconciliation and 15 NWA process requirements described above are satisfied.78 16 17 Q31 Is the Company’s transformer replacement volume based on the condition of its fleet? 18 A. No. The proposed replacement volume appears to be driven in by an age-based 19 goal. The Company’s “Asset Health philosophy for transformers” is to “maintain 20 a transformer fleet that does not exceed 70 years of age and an average age of 21 approximately 35 years.” At the same time, the Company confirms that no law, 22 regulation, manufacturer requirement, or mandatory engineering standard requires 23 retirement at any specific age.79 The units included in the plan are described as 76 Response to OCC-590, Attachment 3 at 5;. Decision, Docket No. 25-08-08 at 7, 10. 78 OCC-594(e) at 2; OCC-599(c) at 3; OCC-812(b) at 1–2. 79 Response to OCC-596. 77 Direct Testimony of Nikhil Balakumar Page 29
  6. Page 33 of 105

    1 “proactive replacements of units over 50 years old with asset health concerns.” 2 Only one project, Stevenson 14A, replaces a transformer that has already failed.80 3 The Company also has condition-based information available to support 4 replacement decisions. It evaluates transformers using EPRI’s Power Transformer 5 Expert System (“PTX”). The company reports 27 units, or about 8.6 percent of 6 its Connecticut fleet, in poor condition.81 Its engineers recommend replacement 7 when two of six parameters are high risk, and age being only one of those 8 parameters.82 For other distribution assets, the Company states that it uses a 9 “condition-based asset management approach”83 and “does not replace equipment 10 solely based on age or failure risk without first conducting an appropriate 11 assessment.”84 The transformer replacement plan does not appear fully consistent 12 with that stated approach. 13 14 Q32 Does the Company’s failure record and failure model support the proposed replacement volume? 15 A. No. The Company’s six most recent transformer failures were all internal failures, 16 at ages 32, 50, 52, 52, 56 and 83.85 Five of the six occurred before the Company’s 17 70-year age goal. The oldest unit on the system, Shepaug 13A-21X, is 85 years 18 old and has short-term and long-term health index values of 0.194 and 0.289, both 19 well within the healthy range. The Company nonetheless confirms that the unit is 20 in the replacement plan, and states that its exhibit indicating otherwise “was an 21 error.”86 80 Response to OCC-595. Response to OCC-596. 82 Response to OCC-597. 83 Response to OCC-800. 84 Response to OCC-801. 85 Response to OCC-596. 86 Response to OCC-598. 81 Direct Testimony of Nikhil Balakumar Page 30
  7. Page 34 of 105

    1 The proposed replacement volume is also several times the historical pace and 2 exceeds the number of units the Company rates in poor condition (Table 2). 3 Table 2: Substation Transformer Replacement Comparison Basis Historical pace 2026 budget Sustained tier TSP tier Units now in poor condition (PTX above 0.5) Replacements per year 1 to 2 3 6 6 in 2027–2029; 8 in 2030–2031 – Five-year total 5 to 10 15 30 34 27 4 The Sustained tier alone would replace more units than the Company rates in poor 5 condition. A condition-based approach would start with those units and evaluate, 6 as the Company’s own process contemplates, whether repair, refurbishment, load 7 transfer, or use of spares can address the risk before replacement is required. The 8 resulting replacement count could therefore be lower than 27. 9 The additional replacements also do not change the number of failures the 10 Company expects. Its plan summary shows one transformer failure per year 11 beginning in 2030 under both the Sustained and TSP tiers.87 When asked what the 12 two additional annual replacements under the TSP tier would change, the 13 Company stated that the reduced risk would allow failure funding “to be diverted 14 into other areas of need within the asset health portfolio.” It did not quantify the 15 reduction in risk or identify any corresponding savings to customers.88 The 16 Company also has not provided any deferral or life-extension analysis for the 17 units proposed for replacement, stating that “project sequencing and deferral 18 options will be evaluated” after initial funding.89 19 The Company’s own maintenance practices also support a condition-based 20 approach. It states that it “has effectively maximized the life of Transformers by 21 extensive maintenance and monitoring practices,” and that spares “are an 87 Exh. CLP-TSP-3 at 11. Response to OCC-810. 89 Response to OCC-597. 88 Direct Testimony of Nikhil Balakumar Page 31
  8. Page 35 of 105

    1 effective mitigation plan for emergent failures,” although not a “one-size fits all” 2 long-term solution.90 I agree that spares alone are not a long-term strategy. But 3 continuous monitoring and PTX trending may provide information on declining 4 condition and can support replacement when a unit’s condition warrants it, within 5 the two- to five-year lead time the Company describes. 6 7 Q33 Has the Company supported the cost of its transformer replacement program? 8 A. Not fully. The Company describes the program in several different ways and has 9 not provided a clear cost per transformer. Table 3 shows the average per-unit cost 10 implied by the Company’s own statements. 11 Table 3: Average Cost per Transformer Implied by Company Statements Company statement About $78 million a year for an average of eight transformers Sustained tier: $243.3 million for 30 units TSP tier: $273.3 million for 34 units Increment: $15 million a year for two added units in 2030–2031 2017–2025 in service: $77.0 million at one to two units a year (9 to 18 units) Implied average per unit ~$9.8M Source ~$8.1M ~$8.0M $7.5M OCC-811 OCC-811 OCC-810 ~$4.3M–$8.6M OCC-811 CLP-TSP-1 at 56 12 Planned spending also increases faster than the planned replacement volume. 13 Average annual spending under the Sustained tier is about 5.7 times the historical 14 in-service level, while the number of units replaced per year increases by roughly 15 three to six times. This suggests a higher average cost per transformer, but the 16 Company has not explained that increase. 17 The Company states that unit cost metrics are “not a reliable means of tracking” 18 its annual projects.91 But transformer replacements are discrete projects with 90 91 Id. Response to OCC-789. Direct Testimony of Nikhil Balakumar Page 32
  9. Page 36 of 105

    1 individual authorizations. The Company should therefore provide the expected 2 cost and scope for each transformer it proposes to replace. 3 Q34 What do you recommend PURA do with the Sustained tier? 4 A. PURA should neither accept the Sustained tier as the minimum investment level 5 nor approve it as a five-year budget. The Company has not demonstrated that its 6 proposed spending above historical levels is cost-effective or affordable, nor has it 7 adequately demonstrated the need for the proposed capacity investments and 8 transformer replacement volumes. 9 If PURA authorizes any forecast capital spending under the Sustained tier, it 10 should: 11 • Historical Baseline: Require the Company to establish the historical 12 spending baseline prescribed by the Reliability Framework, escalated as 13 directed by PURA, and justify any spending above that baseline through 14 documented project- or program-level need and quantified benefits. 15 • Substation Capacity: Exclude from forecast-based recovery projects 16 lacking an approved scope, cost estimate, in-service date, or documented 17 NWS screening. Such costs should be considered only after the required 18 information is provided. 19 • Line capacity: Require documented NWS screening results or justified 20 exclusions for each project, using updated battery cost assumptions rather 21 than the $2 million/MWh assumption previously rejected by PURA. 22 • Transformer replacements: Limit replacements to transformers with 23 documented poor condition, along with the failed Stevenson 14A unit, 24 supported by unit-level condition assessments, evaluated alternatives, and 25 cost estimates. Direct Testimony of Nikhil Balakumar Page 33
  10. Page 37 of 105

    • 1 New Customer investments: Require the Company to substantiate the 2 proposed budget with a documented forecast of customer service requests. 3 These recommendations are consistent with OCC Witnesses Wilson’s and Tully’s 4 recommendation that PURA reject the TSP and use the IDSP process to inform 5 any future multi-year capital investment plan. 6 C. The Targeted System Performance Tier 7 8 Q35 What does the $374 million TSP increment fund, and when would it be spent? 9 A. The increment has three components: $155.0 million for resilience, $143.3 10 million for asset health, and $75.8 million for enhanced reliability. Most of the 11 spending occurs late in the five-year period. Of the $374 million total, $228.1 12 million, or about 61 percent, would be spent in 2030 and 2031.92 13 Under the F-Factor, PURA would approve the full amount now for work that 14 would largely begin years later. Second, apart from the $155 million spacer cable 15 resiliency plan, the increment mostly accelerates programs the Company already 16 runs: smart switches, right-of-way lines, underground and overhead conductor 17 replacement, programs for worst-served customers and towns, and, in 2030 and 18 2031, substation aging infrastructure and two more transformer replacements a 19 year. The items the Company names account for about $119 million of the $143.3 20 million asset health amount. The Company has not identified the rest.93 21 22 Q36 Does the TSP increment meet PURA’s requirement to quantify incremental benefits? 23 A. No. The increment is the clearest test of that requirement, and the Company’s 24 own answer shows that it has not met it. The Company describes the Sustained 92 93 Response to OCC-809. Response to OCC-809. Direct Testimony of Nikhil Balakumar Page 34