Prefiled testimony
Witness: Nikhil Balakumar
Files2
26-05-10_Direct Testimony Eclipse FINAL.pdf
PDF · 1.4 MB · 105 pagesText searchable
Download 26-05-10_Direct Testimony Eclipse FINAL.pdfRead the text of 26-05-10_Direct Testimony Eclipse FINAL.pdf
Attachment 1 - Nikhil Balakumar_Resume.pdf
PDF · 126 KB · 2 pagesText searchable
Download Attachment 1 - Nikhil Balakumar_Resume.pdfRead the text of Attachment 1 - Nikhil Balakumar_Resume.pdf
Words on different pages
Every word of Eversource rate increase is in the text below, but not all on one page. Pages with any of them are listed and highlighted. Clear highlighting
Page 32 of 105
1 the Company’s own Planning Guide requires.76 At the approximately $420,000 to 2 $450,000 per MWh that PURA cited for UI, the same battery would cost about 3 $9.5 million to $10.1 million.77 That does not establish that a battery is the better 4 choice; the rebuild also replaces aging conductor, and the battery would support 5 the contingency for four hours. It does establish that the Company’s screening 6 cannot support its funding requests. The Company should separate capacity relief 7 from unavoidable asset-condition work and compare technically feasible options 8 on a consistent, lifecycle basis. 9 Q30 Are you recommending that all capacity work be stopped? 10 A. No. N-1 overloads can create legitimate investment needs even when equipment 11 operates within its ratings with all elements in service. My recommendation 12 concerns approval of the proposed budget on this record. The Company should 13 complete the substation due diligence before the substation capacity allowance is 14 approved; the line-project budget may be approved once the reconciliation and 15 NWA process requirements described above are satisfied.78 16 17 Q31 Is the Company’s transformer replacement volume based on the condition of its fleet? 18 A. No. The proposed replacement volume appears to be driven in by an age-based 19 goal. The Company’s “Asset Health philosophy for transformers” is to “maintain 20 a transformer fleet that does not exceed 70 years of age and an average age of 21 approximately 35 years.” At the same time, the Company confirms that no law, 22 regulation, manufacturer requirement, or mandatory engineering standard requires 23 retirement at any specific age.79 The units included in the plan are described as 76 Response to OCC-590, Attachment 3 at 5;. Decision, Docket No. 25-08-08 at 7, 10. 78 OCC-594(e) at 2; OCC-599(c) at 3; OCC-812(b) at 1–2. 79 Response to OCC-596. 77 Direct Testimony of Nikhil Balakumar Page 29Page 33 of 105
1 “proactive replacements of units over 50 years old with asset health concerns.” 2 Only one project, Stevenson 14A, replaces a transformer that has already failed.80 3 The Company also has condition-based information available to support 4 replacement decisions. It evaluates transformers using EPRI’s Power Transformer 5 Expert System (“PTX”). The company reports 27 units, or about 8.6 percent of 6 its Connecticut fleet, in poor condition.81 Its engineers recommend replacement 7 when two of six parameters are high risk, and age being only one of those 8 parameters.82 For other distribution assets, the Company states that it uses a 9 “condition-based asset management approach”83 and “does not replace equipment 10 solely based on age or failure risk without first conducting an appropriate 11 assessment.”84 The transformer replacement plan does not appear fully consistent 12 with that stated approach. 13 14 Q32 Does the Company’s failure record and failure model support the proposed replacement volume? 15 A. No. The Company’s six most recent transformer failures were all internal failures, 16 at ages 32, 50, 52, 52, 56 and 83.85 Five of the six occurred before the Company’s 17 70-year age goal. The oldest unit on the system, Shepaug 13A-21X, is 85 years 18 old and has short-term and long-term health index values of 0.194 and 0.289, both 19 well within the healthy range. The Company nonetheless confirms that the unit is 20 in the replacement plan, and states that its exhibit indicating otherwise “was an 21 error.”86 80 Response to OCC-595. Response to OCC-596. 82 Response to OCC-597. 83 Response to OCC-800. 84 Response to OCC-801. 85 Response to OCC-596. 86 Response to OCC-598. 81 Direct Testimony of Nikhil Balakumar Page 30Page 34 of 105
1 The proposed replacement volume is also several times the historical pace and 2 exceeds the number of units the Company rates in poor condition (Table 2). 3 Table 2: Substation Transformer Replacement Comparison Basis Historical pace 2026 budget Sustained tier TSP tier Units now in poor condition (PTX above 0.5) Replacements per year 1 to 2 3 6 6 in 2027–2029; 8 in 2030–2031 – Five-year total 5 to 10 15 30 34 27 4 The Sustained tier alone would replace more units than the Company rates in poor 5 condition. A condition-based approach would start with those units and evaluate, 6 as the Company’s own process contemplates, whether repair, refurbishment, load 7 transfer, or use of spares can address the risk before replacement is required. The 8 resulting replacement count could therefore be lower than 27. 9 The additional replacements also do not change the number of failures the 10 Company expects. Its plan summary shows one transformer failure per year 11 beginning in 2030 under both the Sustained and TSP tiers.87 When asked what the 12 two additional annual replacements under the TSP tier would change, the 13 Company stated that the reduced risk would allow failure funding “to be diverted 14 into other areas of need within the asset health portfolio.” It did not quantify the 15 reduction in risk or identify any corresponding savings to customers.88 The 16 Company also has not provided any deferral or life-extension analysis for the 17 units proposed for replacement, stating that “project sequencing and deferral 18 options will be evaluated” after initial funding.89 19 The Company’s own maintenance practices also support a condition-based 20 approach. It states that it “has effectively maximized the life of Transformers by 21 extensive maintenance and monitoring practices,” and that spares “are an 87 Exh. CLP-TSP-3 at 11. Response to OCC-810. 89 Response to OCC-597. 88 Direct Testimony of Nikhil Balakumar Page 31Page 35 of 105
1 effective mitigation plan for emergent failures,” although not a “one-size fits all” 2 long-term solution.90 I agree that spares alone are not a long-term strategy. But 3 continuous monitoring and PTX trending may provide information on declining 4 condition and can support replacement when a unit’s condition warrants it, within 5 the two- to five-year lead time the Company describes. 6 7 Q33 Has the Company supported the cost of its transformer replacement program? 8 A. Not fully. The Company describes the program in several different ways and has 9 not provided a clear cost per transformer. Table 3 shows the average per-unit cost 10 implied by the Company’s own statements. 11 Table 3: Average Cost per Transformer Implied by Company Statements Company statement About $78 million a year for an average of eight transformers Sustained tier: $243.3 million for 30 units TSP tier: $273.3 million for 34 units Increment: $15 million a year for two added units in 2030–2031 2017–2025 in service: $77.0 million at one to two units a year (9 to 18 units) Implied average per unit ~$9.8M Source ~$8.1M ~$8.0M $7.5M OCC-811 OCC-811 OCC-810 ~$4.3M–$8.6M OCC-811 CLP-TSP-1 at 56 12 Planned spending also increases faster than the planned replacement volume. 13 Average annual spending under the Sustained tier is about 5.7 times the historical 14 in-service level, while the number of units replaced per year increases by roughly 15 three to six times. This suggests a higher average cost per transformer, but the 16 Company has not explained that increase. 17 The Company states that unit cost metrics are “not a reliable means of tracking” 18 its annual projects.91 But transformer replacements are discrete projects with 90 91 Id. Response to OCC-789. Direct Testimony of Nikhil Balakumar Page 32Page 36 of 105
1 individual authorizations. The Company should therefore provide the expected 2 cost and scope for each transformer it proposes to replace. 3 Q34 What do you recommend PURA do with the Sustained tier? 4 A. PURA should neither accept the Sustained tier as the minimum investment level 5 nor approve it as a five-year budget. The Company has not demonstrated that its 6 proposed spending above historical levels is cost-effective or affordable, nor has it 7 adequately demonstrated the need for the proposed capacity investments and 8 transformer replacement volumes. 9 If PURA authorizes any forecast capital spending under the Sustained tier, it 10 should: 11 • Historical Baseline: Require the Company to establish the historical 12 spending baseline prescribed by the Reliability Framework, escalated as 13 directed by PURA, and justify any spending above that baseline through 14 documented project- or program-level need and quantified benefits. 15 • Substation Capacity: Exclude from forecast-based recovery projects 16 lacking an approved scope, cost estimate, in-service date, or documented 17 NWS screening. Such costs should be considered only after the required 18 information is provided. 19 • Line capacity: Require documented NWS screening results or justified 20 exclusions for each project, using updated battery cost assumptions rather 21 than the $2 million/MWh assumption previously rejected by PURA. 22 • Transformer replacements: Limit replacements to transformers with 23 documented poor condition, along with the failed Stevenson 14A unit, 24 supported by unit-level condition assessments, evaluated alternatives, and 25 cost estimates. Direct Testimony of Nikhil Balakumar Page 33Page 37 of 105
• 1 New Customer investments: Require the Company to substantiate the 2 proposed budget with a documented forecast of customer service requests. 3 These recommendations are consistent with OCC Witnesses Wilson’s and Tully’s 4 recommendation that PURA reject the TSP and use the IDSP process to inform 5 any future multi-year capital investment plan. 6 C. The Targeted System Performance Tier 7 8 Q35 What does the $374 million TSP increment fund, and when would it be spent? 9 A. The increment has three components: $155.0 million for resilience, $143.3 10 million for asset health, and $75.8 million for enhanced reliability. Most of the 11 spending occurs late in the five-year period. Of the $374 million total, $228.1 12 million, or about 61 percent, would be spent in 2030 and 2031.92 13 Under the F-Factor, PURA would approve the full amount now for work that 14 would largely begin years later. Second, apart from the $155 million spacer cable 15 resiliency plan, the increment mostly accelerates programs the Company already 16 runs: smart switches, right-of-way lines, underground and overhead conductor 17 replacement, programs for worst-served customers and towns, and, in 2030 and 18 2031, substation aging infrastructure and two more transformer replacements a 19 year. The items the Company names account for about $119 million of the $143.3 20 million asset health amount. The Company has not identified the rest.93 21 22 Q36 Does the TSP increment meet PURA’s requirement to quantify incremental benefits? 23 A. No. The increment is the clearest test of that requirement, and the Company’s 24 own answer shows that it has not met it. The Company describes the Sustained 92 93 Response to OCC-809. Response to OCC-809. Direct Testimony of Nikhil Balakumar Page 34Page 38 of 105
1 tier as the minimum needed to maintain reliability.94 By that definition, every 2 dollar of the increment is discretionary. That is exactly the spending to which 3 PURA’s requirement applies: a budget above the historic baseline must quantify 4 its incremental benefits, costs and reliability improvements.95 5 The Company was asked to explain what each TSP program adds beyond the 6 Sustained tier. Its response points to a summary chart where the distinction is 7 shown only through changed symbols.96 Those symbols do not quantify 8 incremental benefits. 9 The Company’s own figures provide more detail, but they still do not support the 10 $374 million increment: 11 • Enhanced reliability ($75.8 million). This is the only portion with a 12 quantified reliability benefit. The Company projects about 5.4 additional 13 minutes of SAIDI improvement over the Sustained tier, all from two 14 reliability programs. 97 Measured against the full increment, that is roughly 15 $70 million per minute, with no comparison to the value of that benefit. • 16 Resilience ($155.0 million). The Company states that it selected zones with 17 “the highest potential for cost-effective resiliency improvement,” 98 but 18 provides no cost-effectiveness result for any zone. The only quantified 19 benefit is a value-of-lost-load estimate, not avoided storm restoration cost, as 20 discussed below. 21 • Asset health ($143.3 million). The stated benefit is fewer emergent failures.99 Yet, as discussed above, the Company projects the same 22 94 Exh. CLP-TSP-1 at 17. Docket No. 17-12-03RE08, Decision at 47. 96 Response to OCC-809, Exh. CLP-TSP-3 at 11. 97 Response to OCC-807. 98 Response to OCC-808. 99 Exh. CLP-TSP-3 at 8. 95 Direct Testimony of Nikhil Balakumar Page 35Page 39 of 105
1 transformer failure rate under both tiers. Equipment failure also accounts for 2 19.7 percent of blue-sky outage events and 1.9 percent of major storm-day 3 events. 100 4 The Company has the tools to perform this analysis. It describes its planning 5 approach as “metrics-based,” using benefit-cost analysis and measures such as 6 “$/CMI saved” to prioritize reliability investments.101 It also calculated a benefit- 7 cost ratio for a $1.5 million-per-year storm analytics platform.102 No comparable 8 analysis was provided for the $374 million TSP increment. 9 The burden is on the Company to support the proposed spending. PURA should 10 not approve $374 million based on qualitative indicators alone. If this analysis is 11 provided for the first time in rebuttal, parties will have limited opportunity to test 12 it, which PURA should consider in weighing that evidence. 13 14 Q37 Has the Company demonstrated that the resiliency plan will reduce storm impacts and storm costs for customers? 15 A. No. The Company states that the main goal of the TSP tier is “system hardening 16 and reduced storm cost.”103 The record does not show either result. I have two 17 concerns. 18 First, the Company's benefit analysis focuses on the value of lost load (Table T- 19 8), which represents the economic costs customers experience during an outage. 20 Storm restoration costs, by contrast, are costs recovered from customers through 21 rates. PURA’s resilience framework recognizes these as separate benefits and 22 states that avoided storm restoration costs can be estimated based on shorter 23 outages and “the cost of restoration crews that would have been needed if those 100 Exh. CLP-TSP-2 at 12. Exh. CLP-TSP-3 at 34. 102 Id. at 129. 103 Exh. CLP-TSP-3 at 12. 101 Direct Testimony of Nikhil Balakumar Page 36Page 40 of 105
1 interruptions had occurred.”104 A separate assessment of avoided restoration 2 costs would help establish the extent to which the proposed investments could 3 reduce storm-related costs ultimately borne by ratepayers. 4 Second, PURA’s resilience framework calls for a benefit-cost analysis over 5 several time windows, including avoided customer interruption costs, storm 6 restoration costs, and vegetation and pole costs, using recent storm history to 7 estimate storm frequency.105 One of the Company’s witnesses led the work to 8 build the benefit-cost analysis “required by PURA as part of its Reliability and 9 Resiliency Framework.”106 While the Company reports a benefit-cost ratio for its 10 storm analytics platform. It does not present a comparable ratio for the broader 11 resiliency plan. Without a consolidated assessment of costs and benefits, it is 12 difficult to evaluate the cost-effectiveness of the proposed investments. 13 14 Q38 Has the Company supported the $71.0 million of O&M it proposes for the TSP tier? 15 A. The Fund would compensate customers for local grid services, including “deferral 16 of infrastructure investments.”107 The Company has not provided a detailed 17 breakdown of the $38 million, other than stating that “most of the budget” would 18 go to customer compensation.108The grid DERMS needed to support the Fund 19 would not be fully functioning until “the beginning of 2029.”109 I support paying 20 customers for grid services, but the Fund should be tied to specific capacity needs 21 and the investments it is intended to defer. Otherwise, customers could end up 22 paying for both the alternative and the underlying capital investment. 104 Docket No. 17-12-03RE08, Decision at 64–65. Docket No. 17-12-03RE08, Decision at 65–66 and Table 21. 106 Exh. CLP-TSP-1 at 13. 107 Response to OCC-581 at 1. 108 Id. at 2. 109 Response to OCC-582 at 3. 105 Direct Testimony of Nikhil Balakumar Page 37Page 41 of 105
1 The vegetation management increase, from $59 million to $91 million per year, 2 applies under all three tiers.110 The Company also proposes 21 new vegetation 3 management employees “to bring work in house,” while stating that its vegetation 4 proposal “will be based on results of [a] competitive RFP, currently underway.” 5 111 112 6 the $91 million spending level, the basis for that amount remains unclear. Until the RFP results and the proposed in-house staffing are reconciled with 7 8 Q39 Would customers be protected if the promised spending or benefits are not delivered? 9 A. Not adequately. As I explained above, the F-Factor reconciles only total plant in 10 service. The Company’s proposed reliability penalty would begin only when 11 Blue-Sky SAIDI exceeds its five-year average plus one standard deviation, or 12 74.8 minutes on 2021–2025 data.113 The Company’s 2025 Blue-Sky SAIDI of 13 77.5 minutes was already worse than that threshold.114 The penalties exclude 14 major event days, so they do not measure the storm performance the resiliency 15 plan is meant to improve.115 The maximum penalty is $3.5 million per metric.116 16 Under the TSP tier, customers would pay for a promised 6.1-minute improvement 17 whether or not it is achieved, and penalties would apply only if performance 18 deteriorated beyond today’s level. That allocation of risk is the reverse of what a 19 customer-funded, forward-looking plan should provide. 110 Exh. CLP-TSP-3 at 11. Exh. CLP-TSP-3 at 43. 112 Id. at 112. 113 Exh. CLP-TSP-1 at 75. 114 Id. at 76, Table 1. 115 Id. at 74. 116 Id. at 79. 111 Direct Testimony of Nikhil Balakumar Page 38