Prefiled testimony
Witness: Nikhil Balakumar
Files2
26-05-10_Direct Testimony Eclipse FINAL.pdf
PDF · 1.4 MB · 105 pagesText searchable
Download 26-05-10_Direct Testimony Eclipse FINAL.pdfRead the text of 26-05-10_Direct Testimony Eclipse FINAL.pdf
Attachment 1 - Nikhil Balakumar_Resume.pdf
PDF · 126 KB · 2 pagesText searchable
Download Attachment 1 - Nikhil Balakumar_Resume.pdfRead the text of Attachment 1 - Nikhil Balakumar_Resume.pdf
Words on different pages
Every word of Eversource rate increase is in the text below, but not all on one page. Pages with any of them are listed and highlighted. Clear highlighting
Page 35 of 105
1 effective mitigation plan for emergent failures,” although not a “one-size fits all” 2 long-term solution.90 I agree that spares alone are not a long-term strategy. But 3 continuous monitoring and PTX trending may provide information on declining 4 condition and can support replacement when a unit’s condition warrants it, within 5 the two- to five-year lead time the Company describes. 6 7 Q33 Has the Company supported the cost of its transformer replacement program? 8 A. Not fully. The Company describes the program in several different ways and has 9 not provided a clear cost per transformer. Table 3 shows the average per-unit cost 10 implied by the Company’s own statements. 11 Table 3: Average Cost per Transformer Implied by Company Statements Company statement About $78 million a year for an average of eight transformers Sustained tier: $243.3 million for 30 units TSP tier: $273.3 million for 34 units Increment: $15 million a year for two added units in 2030–2031 2017–2025 in service: $77.0 million at one to two units a year (9 to 18 units) Implied average per unit ~$9.8M Source ~$8.1M ~$8.0M $7.5M OCC-811 OCC-811 OCC-810 ~$4.3M–$8.6M OCC-811 CLP-TSP-1 at 56 12 Planned spending also increases faster than the planned replacement volume. 13 Average annual spending under the Sustained tier is about 5.7 times the historical 14 in-service level, while the number of units replaced per year increases by roughly 15 three to six times. This suggests a higher average cost per transformer, but the 16 Company has not explained that increase. 17 The Company states that unit cost metrics are “not a reliable means of tracking” 18 its annual projects.91 But transformer replacements are discrete projects with 90 91 Id. Response to OCC-789. Direct Testimony of Nikhil Balakumar Page 32Page 36 of 105
1 individual authorizations. The Company should therefore provide the expected 2 cost and scope for each transformer it proposes to replace. 3 Q34 What do you recommend PURA do with the Sustained tier? 4 A. PURA should neither accept the Sustained tier as the minimum investment level 5 nor approve it as a five-year budget. The Company has not demonstrated that its 6 proposed spending above historical levels is cost-effective or affordable, nor has it 7 adequately demonstrated the need for the proposed capacity investments and 8 transformer replacement volumes. 9 If PURA authorizes any forecast capital spending under the Sustained tier, it 10 should: 11 • Historical Baseline: Require the Company to establish the historical 12 spending baseline prescribed by the Reliability Framework, escalated as 13 directed by PURA, and justify any spending above that baseline through 14 documented project- or program-level need and quantified benefits. 15 • Substation Capacity: Exclude from forecast-based recovery projects 16 lacking an approved scope, cost estimate, in-service date, or documented 17 NWS screening. Such costs should be considered only after the required 18 information is provided. 19 • Line capacity: Require documented NWS screening results or justified 20 exclusions for each project, using updated battery cost assumptions rather 21 than the $2 million/MWh assumption previously rejected by PURA. 22 • Transformer replacements: Limit replacements to transformers with 23 documented poor condition, along with the failed Stevenson 14A unit, 24 supported by unit-level condition assessments, evaluated alternatives, and 25 cost estimates. Direct Testimony of Nikhil Balakumar Page 33Page 37 of 105
• 1 New Customer investments: Require the Company to substantiate the 2 proposed budget with a documented forecast of customer service requests. 3 These recommendations are consistent with OCC Witnesses Wilson’s and Tully’s 4 recommendation that PURA reject the TSP and use the IDSP process to inform 5 any future multi-year capital investment plan. 6 C. The Targeted System Performance Tier 7 8 Q35 What does the $374 million TSP increment fund, and when would it be spent? 9 A. The increment has three components: $155.0 million for resilience, $143.3 10 million for asset health, and $75.8 million for enhanced reliability. Most of the 11 spending occurs late in the five-year period. Of the $374 million total, $228.1 12 million, or about 61 percent, would be spent in 2030 and 2031.92 13 Under the F-Factor, PURA would approve the full amount now for work that 14 would largely begin years later. Second, apart from the $155 million spacer cable 15 resiliency plan, the increment mostly accelerates programs the Company already 16 runs: smart switches, right-of-way lines, underground and overhead conductor 17 replacement, programs for worst-served customers and towns, and, in 2030 and 18 2031, substation aging infrastructure and two more transformer replacements a 19 year. The items the Company names account for about $119 million of the $143.3 20 million asset health amount. The Company has not identified the rest.93 21 22 Q36 Does the TSP increment meet PURA’s requirement to quantify incremental benefits? 23 A. No. The increment is the clearest test of that requirement, and the Company’s 24 own answer shows that it has not met it. The Company describes the Sustained 92 93 Response to OCC-809. Response to OCC-809. Direct Testimony of Nikhil Balakumar Page 34Page 38 of 105
1 tier as the minimum needed to maintain reliability.94 By that definition, every 2 dollar of the increment is discretionary. That is exactly the spending to which 3 PURA’s requirement applies: a budget above the historic baseline must quantify 4 its incremental benefits, costs and reliability improvements.95 5 The Company was asked to explain what each TSP program adds beyond the 6 Sustained tier. Its response points to a summary chart where the distinction is 7 shown only through changed symbols.96 Those symbols do not quantify 8 incremental benefits. 9 The Company’s own figures provide more detail, but they still do not support the 10 $374 million increment: 11 • Enhanced reliability ($75.8 million). This is the only portion with a 12 quantified reliability benefit. The Company projects about 5.4 additional 13 minutes of SAIDI improvement over the Sustained tier, all from two 14 reliability programs. 97 Measured against the full increment, that is roughly 15 $70 million per minute, with no comparison to the value of that benefit. • 16 Resilience ($155.0 million). The Company states that it selected zones with 17 “the highest potential for cost-effective resiliency improvement,” 98 but 18 provides no cost-effectiveness result for any zone. The only quantified 19 benefit is a value-of-lost-load estimate, not avoided storm restoration cost, as 20 discussed below. 21 • Asset health ($143.3 million). The stated benefit is fewer emergent failures.99 Yet, as discussed above, the Company projects the same 22 94 Exh. CLP-TSP-1 at 17. Docket No. 17-12-03RE08, Decision at 47. 96 Response to OCC-809, Exh. CLP-TSP-3 at 11. 97 Response to OCC-807. 98 Response to OCC-808. 99 Exh. CLP-TSP-3 at 8. 95 Direct Testimony of Nikhil Balakumar Page 35Page 39 of 105
1 transformer failure rate under both tiers. Equipment failure also accounts for 2 19.7 percent of blue-sky outage events and 1.9 percent of major storm-day 3 events. 100 4 The Company has the tools to perform this analysis. It describes its planning 5 approach as “metrics-based,” using benefit-cost analysis and measures such as 6 “$/CMI saved” to prioritize reliability investments.101 It also calculated a benefit- 7 cost ratio for a $1.5 million-per-year storm analytics platform.102 No comparable 8 analysis was provided for the $374 million TSP increment. 9 The burden is on the Company to support the proposed spending. PURA should 10 not approve $374 million based on qualitative indicators alone. If this analysis is 11 provided for the first time in rebuttal, parties will have limited opportunity to test 12 it, which PURA should consider in weighing that evidence. 13 14 Q37 Has the Company demonstrated that the resiliency plan will reduce storm impacts and storm costs for customers? 15 A. No. The Company states that the main goal of the TSP tier is “system hardening 16 and reduced storm cost.”103 The record does not show either result. I have two 17 concerns. 18 First, the Company's benefit analysis focuses on the value of lost load (Table T- 19 8), which represents the economic costs customers experience during an outage. 20 Storm restoration costs, by contrast, are costs recovered from customers through 21 rates. PURA’s resilience framework recognizes these as separate benefits and 22 states that avoided storm restoration costs can be estimated based on shorter 23 outages and “the cost of restoration crews that would have been needed if those 100 Exh. CLP-TSP-2 at 12. Exh. CLP-TSP-3 at 34. 102 Id. at 129. 103 Exh. CLP-TSP-3 at 12. 101 Direct Testimony of Nikhil Balakumar Page 36Page 40 of 105
1 interruptions had occurred.”104 A separate assessment of avoided restoration 2 costs would help establish the extent to which the proposed investments could 3 reduce storm-related costs ultimately borne by ratepayers. 4 Second, PURA’s resilience framework calls for a benefit-cost analysis over 5 several time windows, including avoided customer interruption costs, storm 6 restoration costs, and vegetation and pole costs, using recent storm history to 7 estimate storm frequency.105 One of the Company’s witnesses led the work to 8 build the benefit-cost analysis “required by PURA as part of its Reliability and 9 Resiliency Framework.”106 While the Company reports a benefit-cost ratio for its 10 storm analytics platform. It does not present a comparable ratio for the broader 11 resiliency plan. Without a consolidated assessment of costs and benefits, it is 12 difficult to evaluate the cost-effectiveness of the proposed investments. 13 14 Q38 Has the Company supported the $71.0 million of O&M it proposes for the TSP tier? 15 A. The Fund would compensate customers for local grid services, including “deferral 16 of infrastructure investments.”107 The Company has not provided a detailed 17 breakdown of the $38 million, other than stating that “most of the budget” would 18 go to customer compensation.108The grid DERMS needed to support the Fund 19 would not be fully functioning until “the beginning of 2029.”109 I support paying 20 customers for grid services, but the Fund should be tied to specific capacity needs 21 and the investments it is intended to defer. Otherwise, customers could end up 22 paying for both the alternative and the underlying capital investment. 104 Docket No. 17-12-03RE08, Decision at 64–65. Docket No. 17-12-03RE08, Decision at 65–66 and Table 21. 106 Exh. CLP-TSP-1 at 13. 107 Response to OCC-581 at 1. 108 Id. at 2. 109 Response to OCC-582 at 3. 105 Direct Testimony of Nikhil Balakumar Page 37Page 41 of 105
1 The vegetation management increase, from $59 million to $91 million per year, 2 applies under all three tiers.110 The Company also proposes 21 new vegetation 3 management employees “to bring work in house,” while stating that its vegetation 4 proposal “will be based on results of [a] competitive RFP, currently underway.” 5 111 112 6 the $91 million spending level, the basis for that amount remains unclear. Until the RFP results and the proposed in-house staffing are reconciled with 7 8 Q39 Would customers be protected if the promised spending or benefits are not delivered? 9 A. Not adequately. As I explained above, the F-Factor reconciles only total plant in 10 service. The Company’s proposed reliability penalty would begin only when 11 Blue-Sky SAIDI exceeds its five-year average plus one standard deviation, or 12 74.8 minutes on 2021–2025 data.113 The Company’s 2025 Blue-Sky SAIDI of 13 77.5 minutes was already worse than that threshold.114 The penalties exclude 14 major event days, so they do not measure the storm performance the resiliency 15 plan is meant to improve.115 The maximum penalty is $3.5 million per metric.116 16 Under the TSP tier, customers would pay for a promised 6.1-minute improvement 17 whether or not it is achieved, and penalties would apply only if performance 18 deteriorated beyond today’s level. That allocation of risk is the reverse of what a 19 customer-funded, forward-looking plan should provide. 110 Exh. CLP-TSP-3 at 11. Exh. CLP-TSP-3 at 43. 112 Id. at 112. 113 Exh. CLP-TSP-1 at 75. 114 Id. at 76, Table 1. 115 Id. at 74. 116 Id. at 79. 111 Direct Testimony of Nikhil Balakumar Page 38Page 42 of 105
1 D. Relationship to the 2017–2025 Capital Additions 2 3 Q40 How does your review of the Company’s 2017–2025 capital additions bear on the TSP request? 4 A. The Company asks PURA to find that approximately $4.3 billion of capital 5 additions placed in service from 2017 through 2025 was prudently incurred.117 In 6 the same case, it asks PURA to place five years of forecast capital into rates 7 through the F-Factor.118 The historical record is therefore relevant to how the 8 Company plans, authorizes, controls, and measures capital spending. It also 9 provides an important benchmark for the TSP request. 10 First, history sets the baseline. PURA’s Reliability Framework requires a budget 11 above the historical baseline to quantify the associated incremental benefits, costs, 12 and reliability improvements.119 As discussed above, the Sustained tier alone, 13 excluding Information Technology and Facilities, would average about 1.6 times 14 the Company’s 2017–2024 Connecticut Distribution capital spending. The 2017– 15 2025 record is therefore the appropriate starting point for evaluating the TSP. 16 Second, the Company’s approved plans have not consistently limited actual 17 spending. Connecticut Distribution capital spending exceeded the annual Capital 18 Book plan in seven of the eight years from 2017 through 2024, by a cumulative 19 $350.7 million, or 11 percent. The largest variances were $84.0 million in 2018 20 and $91.5 million in 2023, about 26 and 20 percent above plan.120 Spending was 21 below plan only in 2024. When asked for documentation authorizing spending 22 above plan, the Company referred to its capital books and total-company variance 23 analyses but did not identify a separate authorization.121 117 Exh. CLP-ADDITIONS-1 at 9, 45. Id. at 54. 119 Docket No. 17-12-03RE08, Decision at 47. 120 Exh. CLP-ADDITIONS-12 at 8, 28, 45, 65, 83, 102, 121, 145, 167. 121 Response to OCC-779. 118 Direct Testimony of Nikhil Balakumar Page 39Page 43 of 105
1 The supporting documentation was also limited. Before 2024, annual programs 2 “were documented and supported by the Company’s capital book,” which the 3 Company states “serves as documentation and approval of the capital plan.”122 In 4 discovery, however, the Company described those books as giving departmental 5 leaders an overview of the annual budget ultimately proposed to the Board of 6 Trustees.123 Annual programs and annual work orders account for approximately 7 $2.29 billion of the additions; the Company did not dispute that amount when 8 asked for the related authorizations.124 The Company also acknowledges that 9 some authorizations were prepared after the in-service date after an automated 10 tool identified pending items.125 Its testimony states that program-level 11 authorizations require “a financial evaluation on a unit cost basis.”126 In 12 discovery, it states that unit cost metrics “are not a reliable means of tracking” its 13 annual programs.127 At the same time, the Company justifies authorizing these 14 programs in the aggregate because their costs are “highly consistent with the same 15 cost drivers occurring over and over.”128 Costs that are highly consistent can be 16 tracked per unit. A five-year capital plan approved in advance would rest on the 17 same authorization practices. 18 Third, the TSP continues or accelerates many existing programs, sometimes under 19 different labels. As discussed above, the increment includes programs customers 20 have funded for years without clearly measured outcomes. The Company also 21 states that work deferred from the 2025 plan “is planned for completion either as 22 part of the 2026 capital plan, or as part of the Company’s work plan over the next 23 few years,” without identifying whether that work is included in the TSP.129 122 Exh. CLP-ADDITIONS-1 at 26. Response to OCC-779. 124 Response to OCC-790. 125 Exh. CLP-ADDITIONS-1 at 22. 126 Id. at 37 n.4. 127 Response to OCC-789. 128 Exh. CLP-ADDITIONS-1 at 26. 129 Response to OCC-781. 123 Direct Testimony of Nikhil Balakumar Page 40Page 44 of 105
1 PURA should understand how prior work, deferred work, and proposed TSP 2 spending fit together before approving forward funding. 3 Fourth, outcomes and overlap have not always been clearly measured. As 4 discussed above, the Company could not identify the reliability performance 5 expected when it authorized its 2021–2025 reliability capital, has not quantified 6 the benefits of certain resiliency programs, and has not shown whether proposed 7 TSP resiliency work overlaps with plant placed in service since 2017. 8 My conclusions on whether the 2017–2025 additions were prudently incurred are 9 set out in the Capital Additions section of my testimony. For purposes of the TSP, 10 the point is narrower: if the documentation supporting in-service plant is limited, 11 PURA should not approve forward spending for projects that are still conceptual, 12 lack completed alternatives analyses, or do not yet have quantified benefits. 13 E. Advancing the Grid Tier 14 15 Q41 What proposed investments do you address that were included in the “Advancing the Grid” Tier? 16 A. My testimony addresses the following investments: 17 • Distributed Energy Resource Management System ($24.1 million)130 18 • Grid Compensation Fund ($38 million) 19 • Planning Analytics – Advanced Forecasting and Planning Tools ($15 20 million) 130 DERMS investment were included in both the “Sustained” and “Advancing the Grid” tier. Both set of investments are addressed here. Direct Testimony of Nikhil Balakumar Page 41