  1. Page 53 of 105

    1 Specifically, the Company’s DERMS proposal has the following gaps: 2 • Targeted deployment is too limited: The Company states the DERMS 3 demonstration program is designed to implement multiple DERMS-dependent 4 use cases in a “targeted location”141 and identifies the Triangle substation was 5 identified as an opportunity for a DERMS demonstration.142 However, simply 6 focusing on one location could limit the ability to demonstrate and scale key 7 DER use cases including the ones the Company mentions. The Company itself 8 acknowledges DER potential is in rural areas in contrast to where load is 9 concentrated143 which means that focusing on one location will limit the 10 ability to demonstrate both flexible interconnection and local distribution grid 11 services. Moreover, the locations of aggregated DERs from the Company’s 12 connected solutions program may not overlap with load constraints but 13 nevertheless it will be critical to demonstrate utility DERMS to an 14 edge/aggregator DERMS dispatch to build the technical foundation to 15 leverage VPPs to address distribution constraints. 141 OCC-584, (b), at 3. OCC-585, (a), at 1. 143 Exhibit CLP-TSP-3, at 29. 142 Direct Testimony of Nikhil Balakumar Page 50
  2. Page 54 of 105

    • 1 Minimal commitments on use case implementation: The Company vaguely 2 discusses that dynamic flexible interconnection could be implemented via the 3 demonstration but provides no commitments or plans to do so. Moreover, the 4 Company states the Grid Services Compensation Fund is an important enabler 5 of the DERMS demonstration and provides examples of how the Grid 6 Compensation fund could be tied to DERMS.144 While I acknowledge the 7 Company is in the planning stages, any approval of this investment should 8 require a detailed plans on how and when use cases will be demonstrated and 9 scaled. This should include details of the offerings, targeted locations and 10 milestones for when demonstrations will occur. • 11 No plan to scale: The Company states that a fully functioning DERMS 12 solution could be available at the beginning of 2029 but primarily discusses 13 the demonstration program which will inform efforts to deploy at scale across 14 Connecticut.145 However, the Company offers no process or milestones for 15 how and when DERMS will be scaled and for what use cases. When detailing 16 the implementation of each use, the Company should also provide milestones 17 on any subsequent evaluation period post demonstrations and when a scalable 18 plan will be developed. 19 While I appreciate that DERMS is in its early planning stages and agree that it is 20 appropriate to initially deploy DERMS at targeted locations, an iterative roadmap 21 needs to be established for how, when and where DER use cases the Company 22 intends to demonstrate each use case and how that will be scaled up. Such a 23 roadmap is critical as DERMS is the connective tissue and unifying technology 24 across a broad set of DER use cases and transitioning to a flexible, cost-effective 25 grid. PURA acknowledges this in Docket No. 25-01-27 stating DERMS can 26 “provide value across utility operations broadly” and “enable numerous present 144 145 OCC-584, (b), at 3. OCC-584, (b), at 3. Direct Testimony of Nikhil Balakumar Page 51
  3. Page 55 of 105

    1 and future utility functions in addition to flexible interconnection”.146 Both 2 Illinois147 and Massachusetts148 have developed and/or required such roadmaps, 3 which can be used to accelerate progress in Connecticut. 4 Q51 What should be included in this roadmap regarding flexible interconnection? 5 A. I recommend two key components be included in this roadmap: (1) commitments 6 and timelines for estimated MWs enabled and (2) a broader voltage management 7 strategy to support DER integration. 8 PURA’s proposed decision on dynamic flexible interconnection requires a phased 9 approach starting with 10% of substations by May 1, 2028 to 100% of substations 10 by November 1, 2030, which aligns with my recommendation to scale up 11 flexibility first approaches in the TSP term. As part of this roadmap, the Company 12 should conduct a broader analysis of its substations to estimate how many MWs 13 of additional DERs can be integrated and layout a timeline for doing so in the 14 TSP term. Commonwealth Edison in Illinois recently committed to enabling 650+ 15 MW of DERs over the next 5 years of their Multi-Year Integrated Grid Plan as 16 described in the figure below. 146 Docket No. 25-01-27, Proposed Decision, September 15, 2026, at 19. ComEd Grid Plan: DERMS and Flexible Interconnection Roadmap, January, 16, 2026. https://icc.illinois.gov/docket/P2026-0047/documents/375128/files/657435.pdf 148 D.P.U. 23-115/D.P.U. 23-117/D.P.U. 23-126, Order, DPU directed the filing of a DERMS readiness plan, August 11, 2026, at 91. 147 Direct Testimony of Nikhil Balakumar Page 52
  4. Page 56 of 105

    1 2 Figure 7: Commonwealth Edison DERMS and Flex IX Roadmap149 3 It is also important to recognize that this use case primarily relies on DERMS 4 managing thermal constraints to accommodate more DERs. However, as more 5 DERs are integrated beyond the static limits of the system, voltage issues are 6 expected to rise which could limit the potential of dynamic flexible 7 interconnection even if dynamic hosting capacity is available. ComEd recently 8 proposed a Voltage Optimization Merger with plans to integrate Voltage 9 Optimization (“VO”) functionality into the DERMS platform to enable more 10 precise voltage management control in areas with high-DER penetration. This 11 would expand DERMS functionality to coordinate with voltage regulators and 12 capacitors, enabling closed-loop voltage control for both firm and flexible 13 DERs.150 Thus, this roadmap should also include a broader strategy to integrate 14 DERMS with the Company’s broader voltage management strategy to mitigate 15 the voltage impacts of DERs and thus maximize DER integration. 149 ComEd Grid Plan: DERMS and Flexible Interconnection Roadmap, January, 16, 2026, at 12. https://icc.illinois.gov/docket/P2026-0047/documents/375128/files/657435.pdf 150 ComEd Grid Plan: DERMS and Flexible Interconnection Roadmap, January, 16, 2026, at 16-17. Direct Testimony of Nikhil Balakumar Page 53
  5. Page 57 of 105

    1 2 Q52 What should be included in this roadmap regarding DER distribution grid services? 3 A. I recommend three key components be included in this roadmap: (1) a direct link 4 between DERMS and the programs implementing grid services such that DERMS 5 deployment is informed by such programs; (2) targets for DERMS coverage at 6 strategic locations that would benefit from various grid services; and (3) timelines 7 for detailing and deploying an architecture that allows DERMS to dispatch 8 aggregators and VPPs. 9 First, similar to flexible interconnection, DERMS deployment for grid services 10 should be guided by the programs implementing grid services (i.e NWSs and the 11 Grid Services Compensation Fund). As described below, the Grid Services 12 Compensation Fund should identify and prioritize a comprehensive set of DER 13 grid services the Company wishes to demonstrate. Accordingly, the Company 14 should prioritize the demonstration of dispatch capabilities based on the services 15 that will be provided. In eastern Massachusetts, the Company conducted its first 16 locational demand response program in Summer 2026, utilizing its aggregator 17 DERMS to reduce load during peak events at three substations in the Boston area 18 with identified risk of overload. The Boston substation peak load reduction 19 program was implemented in coordination with the Company’s Massachusetts 20 Grid. 151 21 Second, similar to PURA’s proposed order on flexible interconnection, I believe it 22 is appropriate to have similar targets for DERMS coverage and availability for 23 grid services across substations and feeders. However, it is important to recognize 24 that different locations are more appropriate for different use cases. As part of 25 developing these targets, the Company should identify and commit to timelines of 26 DERMS coverage for specific locations that are expected to benefit from 27 locational grid services such as load concentrated areas that need capacity and 151 OCC-584. (a), at 1. Direct Testimony of Nikhil Balakumar Page 54
  6. Page 58 of 105

    1 critical infrastructure that requires resiliency. This should be informed by the 2 Company’s NWA and Grid Compensation Fund priorities. 3 Finally, this roadmap should explicitly call out the Company’s strategy for using 4 its grid DERMS to dispatch aggregations of DERs (i.e the formal architecture 5 governing the interaction between the grid DERMS and an aggregator/edge 6 DERMS152) and should do so on a timeline in coordination with the Grid 7 Compensation Fund. 8 9 Q53 What should be included in this roadmap regarding DER bulk power grid services? 10 A. This roadmap should detail how and when the Company intends to do 11 Transmission & Distribution (“T&D”) coordination for DERs provided grid 12 services at different levels of the system. The Company currently dispatches 13 DERs as part of ConnectedSolutions for ISO-New England system peak load 14 reduction.153 Moreover, ISO-NE’s implementation of FERC Order 2222 for 15 energy and ancillary services markets is set for November 1, 2026.154 While I 16 acknowledge that distribution grid services are in early stages and T&D conflicts 17 are unlikely in the near-term, it is important to include this on the roadmap for 18 eventual investigation once dynamic flexible interconnection and DER 19 distribution grid services are scaled up. 20 21 Q54 What should be included in this roadmap on the broader locational deployment of DERMS? 22 A. As described above, DERMS serves multiple critical use cases often at entirely 23 different locations on the system. Thus, the Company will likely need to balance 24 competing priorities. The Company should detail more broadly how it intends to 152 OCC-582, (c)(iv), at 3. OCC-584, (a), at 1. 154 https://www.ferc.gov/ferc-order-no-2222-explainer-facilitating-participation-electricity-marketsdistributed-energy 153 Direct Testimony of Nikhil Balakumar Page 55
  7. Page 59 of 105

    1 deploy DERMS across its system and how it will prioritize specific locations and 2 use cases. 3 4 Q55 What should be included in this roadmap on the coordination of other grid modernization investments? 5 A. The Company should detail how the DERMS deployment will be coordinated and 6 sequenced with other investments including Advanced forecasting capabilities 7 and AMI. Specifically, advanced forecasting and AMI should ideally be deployed 8 iteratively at specific locations aligned with where DERMS can enable specific 9 flexibility approaches. 10 Q56 What is your recommendation? 11 A. If PURA approves a version of the TSP, I recommend the proposed DERMS 12 investment be approved only conditional on the development of an iterative 13 roadmap with annual updates that details following: 14 • How and when dynamic flexible interconnection, DER distribution grid 15 services and DER bulk power services will be demonstrated and scaled as 16 further described above. 17 • A broader strategy for how DERMS locational deployment will be 18 prioritized across the company’s service territory to balance the 19 implementation of various use cases as further described above. 20 21 22 • Details on how various grid modernization investments will be coordinated with DERMS including advanced planning & forecasting tools and AMI 23 Direct Testimony of Nikhil Balakumar Page 56
  8. Page 60 of 105

    1 Grid Services Compensation Fund 2 Q57 Please describe scope of the proposed investment. 3 A. The Company is proposing $38m for the Grid Service Compensation Fund 4 (“GSCF”) to compensate customer-owned front of the meter and behind the meter 5 dispatchable DER and flexible loads for providing local grid services dispatched 6 by real-time system operators using the Company’s grid and aggregator 7 Distributed Energy Resource Management System. These offerings intend to 8 leverage existing DER capacity to reduce distribution system infrastructure costs 9 relative to traditional solutions. Specifically, DERs can provide valuable grid 10 services for: 1) deferral of infrastructure investments when DER dispatch can 11 reliably reduce peak demand on local infrastructure that is slated for upgrade due 12 to load growth; 2) for bridge-to-wires opportunities when DERs can provide 13 flexible capacity to mitigate local reliability risks for which traditional 14 infrastructure solutions cannot be deployed in time to meet need; and 3) provide 15 voltage support services in support of increasing electricity delivery efficiency. Direct Testimony of Nikhil Balakumar Page 57
  9. Page 61 of 105

    1 The program would leverage the Grid Compensation Study developed for that 2 program to inform compensation for grid services. The GSCF is intended to be 3 implemented over a four-year period with learnings would supporting a regulatory 4 process to develop a longer-term mechanism to compensate customers for 5 providing local grid services. The Company would provide annual updates to 6 PURA and stakeholders on implementation of the GSCF, including amounts spent 7 on incentives and administration relative to the value created by the various use 8 cases, including infrastructure deferral.155 9 Q58 Please describe your position on the proposed investment. 10 A. As previously stated, I believe demonstrating and scaling DER distribution grid 11 services is foundational to transitioning to a flexibility first approach. The GSCF 12 serves as a good starting point to build upon within the TSP to realize this vision. 13 Specifically, there are several areas the Company’s proposal does not address: 155 OCC-581, (b), at 1-2. Direct Testimony of Nikhil Balakumar Page 58
  10. Page 62 of 105

    • 1 Socialization & Iteration on Compensation Framework: The Grid 2 Compensation Study and the framework that governs compensation has 3 not been implemented in Connecticut. Similar initiatives in other states, 4 however, have shown the value of using this framework to accelerate 5 demonstrations. If it moves forward with the TSP, PURA should establish 6 appropriate milestones guiding the Company in its work with stakeholders 7 to evolve this into a scalable framework that supports a market for DER 8 distribution grid services. • 9 Procurement Processes: The process by which grid services are procured 10 is a critical component to the long-term success of DER distribution grid 11 services. There are several factors including lead time, procurement speed, 12 data access etc. that all can play a role in whether grid services are 13 successfully procured. The current proposal does not address this and 14 should be scoped as part of the program. • 15 Consolidation of Flexibility and DERMS Filings: Given the Company 16 commits to an annual filing, PURA may want to consider consolidating 17 this filing with the DERMS roadmap described above. This annual filing 18 could serve as a broader update on the Company’s progress towards a 19 flexibility-first approach that addresses DERMS, dynamic flexible 20 interconnection and DER distribution grid services. 21 Q59 Please elaborate on the impact of the procurement process. 22 A. NWS approaches more broadly have achieved only limited success and have not 23 led to the scale of distribution services or deferred infrastructure seen 24 internationally. In contrast, the United Kingdom has scaled up distribution grid 25 services through “flexibility markets” with significant success.156 156 United Kingdom Power Networks avoided or deferred infrastructure at 91 million pounds in 2023/2024 with a total of 563 million pounds expected from 2023-2028. Direct Testimony of Nikhil Balakumar Page 59