Prefiled testimony
Witness: Nikhil Balakumar
Files2
26-05-10_Direct Testimony Eclipse FINAL.pdf
PDF · 1.4 MB · 105 pagesText searchable
Download 26-05-10_Direct Testimony Eclipse FINAL.pdfRead the text of 26-05-10_Direct Testimony Eclipse FINAL.pdf
Attachment 1 - Nikhil Balakumar_Resume.pdf
PDF · 126 KB · 2 pagesText searchable
Download Attachment 1 - Nikhil Balakumar_Resume.pdfRead the text of Attachment 1 - Nikhil Balakumar_Resume.pdf
Words on different pages
Every word of Eversource rate increase is in the text below, but not all on one page. Pages with any of them are listed and highlighted. Clear highlighting
Page 59 of 105
1 deploy DERMS across its system and how it will prioritize specific locations and 2 use cases. 3 4 Q55 What should be included in this roadmap on the coordination of other grid modernization investments? 5 A. The Company should detail how the DERMS deployment will be coordinated and 6 sequenced with other investments including Advanced forecasting capabilities 7 and AMI. Specifically, advanced forecasting and AMI should ideally be deployed 8 iteratively at specific locations aligned with where DERMS can enable specific 9 flexibility approaches. 10 Q56 What is your recommendation? 11 A. If PURA approves a version of the TSP, I recommend the proposed DERMS 12 investment be approved only conditional on the development of an iterative 13 roadmap with annual updates that details following: 14 • How and when dynamic flexible interconnection, DER distribution grid 15 services and DER bulk power services will be demonstrated and scaled as 16 further described above. 17 • A broader strategy for how DERMS locational deployment will be 18 prioritized across the company’s service territory to balance the 19 implementation of various use cases as further described above. 20 21 22 • Details on how various grid modernization investments will be coordinated with DERMS including advanced planning & forecasting tools and AMI 23 Direct Testimony of Nikhil Balakumar Page 56Page 60 of 105
1 Grid Services Compensation Fund 2 Q57 Please describe scope of the proposed investment. 3 A. The Company is proposing $38m for the Grid Service Compensation Fund 4 (“GSCF”) to compensate customer-owned front of the meter and behind the meter 5 dispatchable DER and flexible loads for providing local grid services dispatched 6 by real-time system operators using the Company’s grid and aggregator 7 Distributed Energy Resource Management System. These offerings intend to 8 leverage existing DER capacity to reduce distribution system infrastructure costs 9 relative to traditional solutions. Specifically, DERs can provide valuable grid 10 services for: 1) deferral of infrastructure investments when DER dispatch can 11 reliably reduce peak demand on local infrastructure that is slated for upgrade due 12 to load growth; 2) for bridge-to-wires opportunities when DERs can provide 13 flexible capacity to mitigate local reliability risks for which traditional 14 infrastructure solutions cannot be deployed in time to meet need; and 3) provide 15 voltage support services in support of increasing electricity delivery efficiency. Direct Testimony of Nikhil Balakumar Page 57Page 61 of 105
1 The program would leverage the Grid Compensation Study developed for that 2 program to inform compensation for grid services. The GSCF is intended to be 3 implemented over a four-year period with learnings would supporting a regulatory 4 process to develop a longer-term mechanism to compensate customers for 5 providing local grid services. The Company would provide annual updates to 6 PURA and stakeholders on implementation of the GSCF, including amounts spent 7 on incentives and administration relative to the value created by the various use 8 cases, including infrastructure deferral.155 9 Q58 Please describe your position on the proposed investment. 10 A. As previously stated, I believe demonstrating and scaling DER distribution grid 11 services is foundational to transitioning to a flexibility first approach. The GSCF 12 serves as a good starting point to build upon within the TSP to realize this vision. 13 Specifically, there are several areas the Company’s proposal does not address: 155 OCC-581, (b), at 1-2. Direct Testimony of Nikhil Balakumar Page 58Page 62 of 105
• 1 Socialization & Iteration on Compensation Framework: The Grid 2 Compensation Study and the framework that governs compensation has 3 not been implemented in Connecticut. Similar initiatives in other states, 4 however, have shown the value of using this framework to accelerate 5 demonstrations. If it moves forward with the TSP, PURA should establish 6 appropriate milestones guiding the Company in its work with stakeholders 7 to evolve this into a scalable framework that supports a market for DER 8 distribution grid services. • 9 Procurement Processes: The process by which grid services are procured 10 is a critical component to the long-term success of DER distribution grid 11 services. There are several factors including lead time, procurement speed, 12 data access etc. that all can play a role in whether grid services are 13 successfully procured. The current proposal does not address this and 14 should be scoped as part of the program. • 15 Consolidation of Flexibility and DERMS Filings: Given the Company 16 commits to an annual filing, PURA may want to consider consolidating 17 this filing with the DERMS roadmap described above. This annual filing 18 could serve as a broader update on the Company’s progress towards a 19 flexibility-first approach that addresses DERMS, dynamic flexible 20 interconnection and DER distribution grid services. 21 Q59 Please elaborate on the impact of the procurement process. 22 A. NWS approaches more broadly have achieved only limited success and have not 23 led to the scale of distribution services or deferred infrastructure seen 24 internationally. In contrast, the United Kingdom has scaled up distribution grid 25 services through “flexibility markets” with significant success.156 156 United Kingdom Power Networks avoided or deferred infrastructure at 91 million pounds in 2023/2024 with a total of 563 million pounds expected from 2023-2028. Direct Testimony of Nikhil Balakumar Page 59Page 63 of 105
1 While the Company’s NWS framework is a constructive starting point, it remains 2 fundamentally reactive and project-specific, which limits its ability to scale. 3 Under the RIIO-ED2 regulatory framework157, distribution system operators like 4 UK Power Networks (“UKPN”) are mandated to market-test 100% of all new 5 high-voltage network requirements before investing in traditional 6 reinforcement.158 Flexibility is not an “alternative” in the UK; it is the default 7 standard for procurement. 8 Q60 What are the core challenges with US based frameworks? 9 A. There are three primary systemic barriers that prevent non-wires alternatives from 10 becoming a viable, scalable affordability lever: • 11 Procurement Speed & Insufficient Lead Time: Most U.S. frameworks, 12 including the Company’s, are reactive. Utilities identify a grid need and then 13 screen for NWAs, often leaving only a narrow window for procurement. 14 The lifecycle for an NWS solution can take three years, effectively 15 disqualifying many near-term reliability needs. Moreover, the reliance on 16 project-by-project RFPs can create significant administrative drag with a 17 manual approach making it difficult to capture short-term grid needs or 18 aggregate smaller resources. • 19 Lack of Operational Trust and Verification: There is a persistent trust 20 gap regarding whether flexible assets—particularly residential VPPs—will 21 show up when called. Without robust, automated monitoring and 22 verification (“M&V”) and standardized performance penalties, utilities 23 default to traditional solutions even when DERs are more cost-effective. 157 RIIO-ED2 is five-year electricity distribution price control (1 April 2023 – 31 March 2028), setting revenue allowances for 14 UK network operators. It focuses on enabling net zero, investing efficiently, and improving network resilience, with a strong emphasis on customer value, supporting innovation, and transitioning to smarter, flexible energy systems. 158 UK Power Networks, Distribution System Operation (DSO) Strategy: RIIO-ED2 Business Plan Annex 5.1, (2021). https://library.ukpowernetworks.co.uk/library/en/RIIO/. Direct Testimony of Nikhil Balakumar Page 60Page 64 of 105
• 1 The “Pilot Mentality” and Lack of Regulatory Mandate: Unlike the 2 United Kingdom, where the regulator (Ofgem) mandated that flexibility be 3 tested for every high-voltage requirement, U.S. utilities typically treat NWS 4 as experimental add-ons. This creates a fragmented market where 5 developers cannot justify the investment to participate because the pipeline 6 of opportunities is uncertain and sporadic. 7 Q61 How can the insufficient lead time gap be addressed? 8 A. Leading Distribution System Operators in the United Kingdom, such as UKPN, 9 have transitioned to a “Continuous Market” model159 through two key 10 mechanisms: 11 • Long-Term Forecasting & Data Sharing: UK DSOs publish a Distribution 12 Network Options Assessment (DNOA) that provides a 60-month “look ahead" 13 map of forecasted capacity needs. By sharing locational data through 14 automated processes, this gives DER developers years of lead time to 15 proactively market DER solutions to customers and ultimately site them 16 before a formal tender is triggered.160 • 17 Standardized Framework Agreements: Instead of bespoke RFPs for every 18 project, UK providers “pre-qualify” once via a national Standard Flexibility 19 Services Agreement. This lowers the barrier to entry, allowing even small- 20 scale 10kW residential batteries to compete.161 159 UK Power Networks, Distribution Network Options Assessment (DNOA) Methodology, (March 2025) Energy Networks Association (ENA), Open Networks Project: Launch Document, (2023). https://www.energynetworks.org/assets/images/Resource%20library/2023/Jan/ENA_23LaunchDoc_v6.pdf 161 Energy Networks Association (ENA), Standard Flexibility Services Agreement & Version 3.2 Updates, (April 2024). https://www.energynetworks.org/industry/flexibility-services. 160 Direct Testimony of Nikhil Balakumar Page 61Page 65 of 105
1 Q62 How can the lack of operational trust and verification be addressed? 2 A. The Company can evaluate several mechanisms including the following: • 3 Automated Monitoring and Verification: DSOs in the United Kingdom 4 use automated platforms to verify DER performance against a real-time 5 meter baseline. • 6 Commercial Penalties: Standard UK agreements include financial 7 penalties for non-delivery, incentivizing aggregators to maintain reserve 8 capacity within their portfolios to guarantee a firm response. • 9 Target high-loading but not fully loaded infrastructure: Rather than 10 waiting to address system constraints once they reach near maximum 11 loading (e.g 95% loading), the Company could target locations that are not 12 currently constrained but expected to be constrained in the future (e.g 75% 13 loading feeders) which would have lower risk of being overloaded if the 14 market can’t respond to the full need. 15 16 Q63 Is it possible for the Company to conduct demonstrations on a flexibility market in the near-term? 17 A. Yes. We do not need to repeat the decade of incremental, manual steps taken in 18 the UK. National Grid has already leapfrogged this learning curve by bringing the 19 Piclo Flex platform into Massachusetts and New York to manage its NWS and 20 Commercial System Relief Programs.162 By adopting an independent flexibility 21 marketplace platform today, National Grid is skipping the manual RFP phase and 22 moving directly to automated, locational procurement. The Company should 162 National Grid US, Independent Marketplace for Non-Wires Alternatives (Piclo Flex). https://www.canarymedia.com/articles/virtual-power-plants/massachusetts-national-grid-piclomarketplace-grid-costs Direct Testimony of Nikhil Balakumar Page 62Page 66 of 105
1 follow National Grid’s lead by evaluating similar digital solutions to test and scale 2 a “Flexibility First” grid. 3 Q64 What is your recommendation? 4 A. If PURA approves a version of the TSP, I recommend the proposed Grid 5 Compensation Fund be approved conditional on the following: • 6 7 The Company commits to evaluating the grid services procurement process and allocate funds to testing a flexibility market platform • 8 The Company commits to a midpoint milestone (i.e., 2 years into 9 implementation) where they will work with stakeholders to iterate on and 10 develop a scalable grid services framework inclusive of an updated 11 compensations framework • 12 The Company consolidates its filings into a single annual filing that will 13 serve as a broader update on the Company’s progress towards a flexibility 14 first approach that addresses DERMS, dynamic flexible interconnection 15 and DER distribution grid services 16 Advancing Forecasting Tools & Circuit Planning Capabilities to manage planning models 17 Q65 Please describe the scope of the proposed investment. 18 A. The Company requests a total of $15 million163 collectively for Advancing 19 Forecasting Tools & Circuit Planning Capabilities to manage planning models. 20 Advanced forecasting tools enable the Company to generate forecasted 8760 load 21 shapes across all levels: substation, transformer, and at circuit levels.164 Such 163 $8 million for Advanced Forecasting and $7 million for Circuit Planning Capabilities to manage planning models. 164 Exhibit CLP-TSP-3, at 138. Direct Testimony of Nikhil Balakumar Page 63Page 67 of 105
1 profiles are useful for evaluating and sizing certain solutions (e.g., battery storage 2 as an NWA, for which the Company can and does create 24-hour load profiles).165 3 Circuit planning capabilities provide the compute resources to allow the modeling 4 and simulation of granular models with 8760 data under various scenarios for 5 every circuit and circuit configuration.166 6 Q66 Please describe your position on this investment. 7 A. As the Company states, these investments are proposed to align with Integrated 8 Distribution System Planning (“Authority's Version”) from 2025 in Docket No. 9 21-05-15RE03. These capabilities will be critical to transitioning to a flexible, 10 cost-effective grid and especially to implement the granular forecasting necessary 11 to implement dynamic flexible interconnection (i.e., forecasting expected 12 curtailment) and DER grid services (i.e., forecasting not only the magnitude but 13 duration of load constraints). However, while the Company does indicate it will 14 take 12-18 months for the tools to be in full production, it does not detail where 15 and when forecasting can be implemented. 16 17 Q67 How could the Company implement advanced forecasting to drive benefits as quickly as possible? 18 A. Upon deployment of these tools, the Company should focus on implementing 19 these tools at locations with expected DER and load constraints to support the 20 implementation of dynamic flexible interconnection and DER distribution grid 21 services. Specifically, where forecasting is initially implemented should be 22 informed by locations identified as part of implementing dynamic flexible 23 interconnection, the Grid Compensation Fund and the DERMS rollout. 165 166 OCC-587, (b), at 2. Exhibit CLP-TSP-3, at 139. Direct Testimony of Nikhil Balakumar Page 64Page 68 of 105
1 Moreover, the Company states it currently develops load forecasts only at the 2 substation level,167 which are determined from 15 min SCADA data by substation 3 and at the system level168. The rollout of AMI should provide sufficient data to 4 support advanced forecasting at the feeder level. Thus, the locational development 5 of forecasts should also be coordinated with the AMI rollout such that the 6 forecasting tools can leverage AMI to develop feeder level forecasts on an 7 iterative basis as AMI is deployed regionally. 8 Q68 What is your recommendation? 9 A. If PURA approves a version of the TSP, I recommend the proposed Advancing 10 Forecasting Tools & Circuit Planning Capabilities be approved conditional on the 11 following: 12 • The Company begins advanced forecasting in an iterative manner once 13 tools are available and be informed by locations identified as part of 14 implementing dynamic flexible interconnection, the Grid Compensation 15 Fund and the DERMS rollout. 16 If the Authority approves AMI deployment in this rate case, the Company will 17 coordinate its deployment with AMI such that AMI prioritizes deployment at 18 locations that can support advanced forecasting. 19 Shared Hosting for Advancement of Renewable Energy (SHARE) 20 Q69 Please describe the scope of the proposed investment. 21 A. The Company requests $47.6 million within this TSP term to implement SHARE 22 which is the Company’s proposed approach to resolving DER substation 23 saturation and queue stagnation due to the current cost-causation principle for 167 168 OCC-574, (a), at 1. OCC-575, (a), at 1. Direct Testimony of Nikhil Balakumar Page 65