  1. Page 69 of 105

    1 DER interconnections and accompanying free-ridership issues and locations with 2 high DER growth potential and insufficient electrical infrastructure to 3 accommodate large-scale DER. The Program would study DER at groups of 4 interdependent substations and develop group solutions to: 1) integrate the stalled 5 DER safely and reliably within a fixed timeframe; 2) equitably allocate group 6 solution costs between current and future DER and load customer, who benefit 7 from increased capacity and reliability; 3) solve the free-ridership problem by 8 instituting a fixed $/kW fee for current group members and all future DER that 9 would subscribe to the solution; 4) provide cost-certainty for current and future 10 developers; and 5) enable future DER growth by providing additional capacity 11 due to use of standard-size equipment. 169 The Company has identified 12 investments that would enable over 300 MW of DER while supporting capacity 13 and reliability needs for 6 substations.170 14 Q70 Please describe your position on this investment. 15 A. I strongly oppose this as investment as it is premature, carries significant 16 ratepayer risk and has not been properly vetted by stakeholders. Specifically, I 17 have the following concerns: • 18 Does not consider a flexibility first approach: Locations that are at or 19 will be at their limit for DER hosting capacity are the ideal candidates to 20 implement dynamic flexible interconnection. The Company states it has 21 not evaluated utilizing dynamic flexible interconnections to defer the 22 upgrades proposed for the SHARE program.171 • 23 Methodology and existing implementations carry significant 24 ratepayer risk: The SHARE program appears to resemble the 25 Massachusetts Capital Investment Proposal (“CIP”), which has been under 169 Exhibit CLP-TSP-1, at 60-70. Exhibit CLP-TSP-3, at 143. 171 OCC-583, (b), at 1. 170 Direct Testimony of Nikhil Balakumar Page 66
  2. Page 70 of 105

    1 implementation for several years. As described below, I have significant 2 experience with this program and outline the risks to the methodology and 3 status of the implementations to date. • 4 Program is premature and has not considered stakeholder input: 5 While the Company is requesting $47.6 million in the TSP term, the 6 proposed investments appear to total $275 million172. SHARE is 7 inherently a proactive investment proposal, and similar frameworks have 8 or are continuing to undergo significant vetting in Massachusetts, New 9 York, Minnesota and California. Even if SHARE represents a reasonable 10 framework, there should be a process to vet and ultimately approve such a 11 framework. 12 13 Q71 Please elaborate on how SHARE does not consider a flexibility first approach. 14 A. A flexibility first approach ensures that flexibility solutions are considered first 15 prior to traditional capital investments. Locations with zero or limited firm DER 16 hosting capacity are perfect locations to implement dynamic flexible 17 interconnection, fully utilize the system and integrate additional DERs. 18 The Company states the SHARE program and dynamic flexible interconnection 19 target different needs for DER developers and the Company with the SHARE 20 program intended to target larger DER development in more rural areas where the 21 available real estate for DER exceeds the load in the region and flexible 22 interconnection program intended to target underutilized hosting capacity.173 This 23 is a false dichotomy as dynamic flexible interconnection can target underutilized 24 hosting capacity in regions supporting larger DER development. In fact, this is the 25 most common use case for dynamic flexible interconnection. In Massachusetts, 172 173 Exhibit CLP-TSP-3, at 146-149. OCC-583, (b), at 1. Direct Testimony of Nikhil Balakumar Page 67
  3. Page 71 of 105

    1 the Company proposed $239 million in investments similar to those included 2 under SHARE to enable DER capacity. In my testimony, I provided an alternative 3 analysis that dynamic flexible interconnection could not only defer the proposed 4 investment but enable more DER capacity.174 Massachusetts approved $753 5 million in CIPs partially since dynamic flexible interconnection was in its infancy 6 at the time of these proposals. Connecticut can avoid this dilemma by first 7 maximizing the amount of additional DERs that can be integrated via dynamic 8 flexible interconnection and then only consider additional investment. 9 10 Q72 Please elaborate on how the proposed methodology and existing implementations carry significant ratepayer risk. 11 A. The methodology proposed inherently requires ratepayers to pay for a portion of 12 the proposed investments given that DERs on their own cannot financially 13 support these upgrades. While the Company claims that these investments will 14 benefit customers, the assumptions behind these claims are highly speculative in 15 nature. Specifically, the Company primarily uses a 2050 electrification forecast to 16 account for the benefits for customers. Such a forecast is highly speculative given 17 that the forecast projects out over 20 years and the fact that assumptions around 18 electrification could drastically change in that time period. Moreover, the benefits 19 calculation allocates cost without accounting for the fact that customers are likely 20 to not benefit from the investment (i.e., the timing by which electrification and 21 load growth would have triggered such an investment) till much later. It is unclear 22 what are the appropriate flexibility assumptions or planning criteria that should be 23 used when sizing these investments. My testimony and several intervenors in 24 Massachusetts have called for various flexibility assumptions and the relaxing of 25 planning criteria to ensure any proposed investments would be as efficient as 174 D.P.U. 25-30/-81/-82/-83, Direct Testimony of Nikhil Balakumar on behalf of the Massachusetts Attorney General’s Office, November 14 2025. https://d3i1pf1zzeh4ol.cloudfront.net/26fc0d851530-4ea9-b62a-47386c75bf42.pdf Direct Testimony of Nikhil Balakumar Page 68
  4. Page 72 of 105

    1 possible.175 Finally, it is unclear whether the current investments will be fully 2 subscribed by DERs creating the risk of stranded assets. Significant portions of 3 the Company’s ongoing investments have yet to be subscribed176, have 4 experienced group study drop outs177 and there is further uncertainty with the 5 expiration of the Investment Tax Credit (“ITC”). 6 7 Q73 Please elaborate on the importance of stakeholder input for any proactive planning framework. 8 A. As demonstrated above, there is both significant complexity and risk in 9 developing proactive investments. Such frameworks should be developed 10 carefully with stakeholder input and leverage lessons learned from other 11 jurisdictions. Moreover, the Massachusetts Department of Public Utilities is 12 currently considering an updated framework that builds upon the Company’s 13 current proposal. Given that the Company can focus on enabling additional DERs 14 via dynamic flexible interconnection, this provides Connecticut time to consider 15 rulings in Massachusetts and other jurisdictions to inform a future proactive 16 planning framework. 17 Q74 What is your recommendation? 18 A. I strongly recommend PURA reject the Company’s proposal and explicitly 19 require it to first leverage dynamic flexible interconnection in areas of high DER 20 development with limited hosting capacity. If PURA wishes to establish a 21 proactive planning framework, I recommend that a separate stakeholder process 175 D.P.U. 25-20, Direct Testimony of Nikhil Balakumar on behalf of the Massachusetts Attorney General’s Office, May 6 2026, at 14-23. https://d3i1pf1zzeh4ol.cloudfront.net/530ad5f2-aaea-437e-8c2f0ee4826b5599.pdf 176 D.P.U. 25-30/-81/-82/-83, Direct Testimony of Nikhil Balakumar on behalf of the Massachusetts Attorney General’s Office, November 14 2025, at 65. https://d3i1pf1zzeh4ol.cloudfront.net/26fc0d85-1530-4ea9-b62a-47386c75bf42.pdf 177 D.P.U. 25-30/-81/-82/-83, Direct Testimony of Nikhil Balakumar on behalf of the Massachusetts Attorney General’s Office, November 14 2025, at 49. https://d3i1pf1zzeh4ol.cloudfront.net/26fc0d85-1530-4ea9-b62a-47386c75bf42.pdf Direct Testimony of Nikhil Balakumar Page 69
  5. Page 73 of 105

    1 be established to develop such a framework and incorporate lessons learned from 2 other jurisdictions. 3 IV. ADVANCED METERING INFRASTRUCTURE 4 Q75 Please describe the Company’s proposed investment. 5 A. The Company is proposing an accelerated, systemwide deployment of AMI that 6 would be implemented over six years with a total cost of $1.253 billion.178 The 7 Company states AMI is the preferred replacement solution to ensure that the 8 Company is able to manage its distribution system effectively and safely for its 9 customers while providing the advanced capabilities that are necessary to achieve 10 Connecticut’s energy, environmental, and affordability goals.179 There are several 11 key components to this proposal: • 12 Broad set of benefits identified: The Company identifies a broad set of 13 benefits that will be enabled with AMI including power outage restoration, 14 bulk data sharing, energy efficiency and demand management analytics, 15 load research, transformer load management analytics, unbilled usage 16 detection, Volt/Var Optimization (“VVO”) analytics, remote 17 connect/disconnect functionality, advanced billing capabilities, VVO, and 18 comprehensive TLM.180 Moreover, the next generation meters have 19 distributed intelligence capabilities which enables a broader set of 20 capabilities.181 • 21 22 Benefits will be enabled iteratively for certain benefits: The Company states several capabilities can be realized with the commencement of AMI 178 Exhibit CLP-AMI-2, at 3-4. Exhibit CLP-AMI-2, at 3. 180 Exhibit CLP-AMI-2, at 3-4. 181 Exhibit CLP-AMI-2, at 22. 179 Direct Testimony of Nikhil Balakumar Page 70
  6. Page 74 of 105

    1 meter deployment while others can only be fully realized after the full 2 deployment of AMI.182 • 3 Deployment will leverage Public Carrier Cellular Networks: In 4 contrast to traditional deployments, the Company proposes to not only use 5 a mesh network but pair it with public carrier cellular networks to serve as 6 the communications backbone to transmit AMI data.183 • 7 Concurrent, Regional Deployments: The Company proposes parallel East/West deployment teams to balance rural and metro work.184 8 9 Q76 Please describe your position on the proposed investment. 10 A. I believe AMI can serve as a foundational investment for grid modernization and 11 transitioning to a flexible, cost-effective grid but only if it’s implemented in a 12 manner that fully utilizes the technology to maximize all its benefits and do so as 13 quickly as possible. The Company’s proposal represents a good starting point to 14 realize this vision. However, there are several gaps in the proposal that the 15 Company should address: • 16 Comprehensive Data Platform: The Company proposes a data access 17 platform that allows authorized third parties to access customer data. 18 However, this proposal misses certain key data and reporting requirements 19 and does not address the broader role of data access to support DER 20 integration and utilization. • 21 Iterative 8760 Profile Rollout: The Company intends to use AMI meters to create 8760 profiles.185 However, it is unclear when these profiles will 22 182 Exhibit CLP-AMI-2, at 3-4. Exhibit CLP-AMI-2, at 16-17 184 Exhibit CLP-AMI-2, at 11. 185 OCC-743, (c), at 2. 183 Direct Testimony of Nikhil Balakumar Page 71
  7. Page 75 of 105

    1 be developed as part of the existing roadmap and how this will be 2 coordinated with the proposed advanced forecasting & planning tools as 3 well as DERMS. • 4 Strategic Deployment to Target System Constraints: The Company 5 proposes parallel East/West deployment teams to balance rural and metro 6 work but does not appear to consider how a locational deployment could 7 accelerate the transition to a flexibility first approach. • 8 Detailed Distributed Intelligence Pilot: The Company commits to 9 evaluate distributed intelligence capabilities186 but does not provide a 10 concrete pilot or plan on how such capabilities will be used to support 11 planning and operations. • 12 Detailed Evaluation of Real-time AMI Data: The Company is currently 13 investigating how AMI could support real-time systems such as ADMS & 14 DERMS as well as Voltage Optimization given that a public carrier 15 cellular network is incorporated into the communications architecture. 16 However, there are no milestones in the current plan for when this 17 evaluation will be complete and reported on. 18 Comprehensive Data Platform 19 Q77 Please elaborate on your position on a comprehensive data access platform. 20 A. Automated, digitized, application programming interface (“API”) based customer 21 data access is critical to DER integration and utilization, especially when it comes 22 to scoping DER solutions, enrolling customers in programs, and ultimately being 23 able to settle in various energy markets. The Company’s proposal provides a 24 strong foundation to address these issues in explicitly centering its strategy around 186 OCC-748, at 1. Direct Testimony of Nikhil Balakumar Page 72
  8. Page 76 of 105

    1 a Green Button Connect protocol and API-based architecture. I provide minor 2 recommendations to incorporate certain lessons learned from other jurisdictions 3 below. 4 However, DER integration and utilization not only requires automated, digitized, 5 API based access to customer data (i.e. upon customer authorization), but also 6 system data and rates/tariff information. DER providers and aggregators often 7 need to use this data together to enable a broad set of use cases including DER 8 and EV charging integration, enrollment and settlement in various programs. As 9 such, this data should be accessible together and in a modern, scalable manner. 10 The figure below outlines the core set of use cases, data needed and the associated 11 benefits. 12 13 Figure 8: Comprehensive Data Platform: Use Cases, Data Needs & Benefits 14 The Company acknowledges this, stating the platform can support future 15 expansion and additional use cases including DER programs, demand response 16 initiatives and additional authorized customer energy data services approved Direct Testimony of Nikhil Balakumar Page 73
  9. Page 77 of 105

    1 through future regulatory proceedings.187 I provide recommendations on how the 2 Company can take steps towards this vision below. 3 4 5 Q78 What modifications do you propose to the Company’s existing proposal for a customer data access platform that leverages the Green Button Connect standard? 6 A. I propose two modifications: 1) providing access to raw meter usage data and 7 enrolled programs; and 2) including and publishing additional metrics to report on 8 platform performance. The Company states it will provide access to: (1) Customer 9 account and service information; (2) Billing-quality usage data, including 10 validated consumption and demand information; (3) Interval usage data from 11 AMI meters; and (4) Supplier and service relationship information. However, the 12 Company states it anticipates providing validated, estimated, and edited ("VEE") 13 billing-quality AMI data rather than raw meter data.188 Moreover, while the 14 Company will provide the “rate class/rate code,” it does not appear to provide any 15 other programs the customer may be enrolled in. Raw meter usage data has been 16 identified in several regions including MISO for Ameren Missouri & Illinois189 17 and PJM for ComEd190 as critical to support DER aggregator settlement in 18 wholesale markets. Specifically, billing quality is often not available quickly 19 enough to support initial settlement submission requirements, hence the need for 20 raw meter usage data. Moreover, customer program data was also identified and 21 scoped into the data requirements by the same utilities as this will be critical to 22 inform what programs DER providers and aggregators can enroll customers in 23 and avoid conflicts where possible. 187 OCC-742, (e), at 5. OCC-742. (a)(3), at 3. 189 Ameren Illinois 2028-2031 Integrated Grid Plan, January 20, 2026, at 111. https://icc.illinois.gov/docket/P2026-0051/documents/375149/files/657593.pdf 190 ComEd, Integrated Data Platform: Proposed Implementation Plan , December 20, 2024, at 7. Integrated Data Platform: Proposed Implementation Plan 188 Direct Testimony of Nikhil Balakumar Page 74
  10. Page 78 of 105

    1 Regarding metrics, the Company proposes tracking (1) API transaction activity, 2 (2) Data request volumes, (3) Request completion status, (4) Successful and failed 3 transactions, (4) Error reporting and exception tracking and (4) User activity and 4 transaction history. I support these metrics but also recommend the Company 5 track total number of registrants; the average time it takes for the Company to 6 approve a registration request; and platform uptime. Legacy platforms often take 7 unreasonable amounts of time to approve registration requests, causing third 8 parties to miss windows for various deadlines including wholesale market 9 settlement. Finally, the Company should publish these metrics publicly on the 10 platform so there is transparency in platform performance. 11 12 Q79 What steps can the Company take to support an expanded vision for the data platform? 13 A. Data access is often addressed in silos across a broad set of venues and 14 proceedings, which often leads to siloed and one-off solutions. The Company 15 should view this platform as a one-stop shop for future data access, provided that 16 it is cost effective and valuable to provide such data on an ongoing basis. 17 Specifically, system data and rates/tariff information have been identified by both 18 ComEd191 and Ameren192 as high priority and complimentary datasets to customer 19 data to support DER integration and utilization. While the Company has hosting 20 capacity maps193, these maps (1) don’t provide sufficiently granular data and (2) 21 don’t provide API access to such data limiting the usefulness of the platform. 22 ComEd has committed to providing a comprehensive set of system data from the 23 hosting capacity values all the way down to the underlying data, including 8760 24 profiles and the system model as shown below. 191 ComEd has proposed an Integrated Data Platform including all three data types as part of their MultiYear Integrated Grid Plan. 192 Ameren is currently scoping and has committed to propose an Integrated Data Platform to include all three data types. 193 https://www.eversource.com/residential/about/doing-business-withus/interconnections/connecticut/connecticut-hosting-capacity-map Direct Testimony of Nikhil Balakumar Page 75