  1. Page 8 of 105

    1 • Line capacity: Require documented NWS screening results or justified 2 exclusions for each project, using updated battery cost assumptions rather 3 than the $2 million/MWh assumption previously rejected by PURA. 4 • Transformer replacements: Limit replacements to transformers with 5 documented poor condition, along with the failed Stevenson 14A unit, 6 supported by unit-level condition assessments, evaluated alternatives, and 7 cost estimates. 8 • New Customer investments: Require the Company to substantiate the 9 proposed budget with a documented forecast of customer service requests. 10 These recommendations are consistent with OCC Witnesses Wilson’s and Tully’s 11 recommendation that PURA reject the TSP and use the IDSP process to inform 12 any future multi-year capital investment plan. 13 Targeted System Performance 14 PURA should not approve the $374 million in additional revenue requested to 15 implement the Targeted System Performance tier. The Company calls the 16 Sustained tier the minimum needed to maintain reliability, so based on their 17 categorization, the entire increment is discretionary. Before any TSP-tier 18 resiliency spending is approved, the Company should provide a benefit-cost 19 analysis under PURA's resilience framework, including a separate estimate of 20 avoided storm restoration costs. 21 Advancing the Grid 22 PURA should not approve $770 million in additional revenue requested to 23 implement the Advancing the Grid tier, as the Company has not sufficiently 24 quantified incremental benefits beyond the sustained tier. Direct Testimony of Nikhil Balakumar Page 5
  2. Page 9 of 105

    1 PURA should reject the Company’s approach to “advancing the grid” and if it 2 approves a multi-year framework and approves a version of the TSP, the approach 3 to both should instead include a coordinated set of investments grounded in key 4 goals and associated use cases to realize such goals. Grid modernization should 5 serve the purpose of enabling a flexible, optimized, cost-effective grid that 6 maximizes the utilization of the system leading to the deferral and/or efficient 7 buildout of infrastructure. Fostering and scaling a robust market for the cost- 8 effective integration and utilization of DERs is central to achieving this vision. 9 My recommendations below outline such a coordinated approach. 10 Distributed Energy Resource Management System (DERMS) 11 If PURA moves ahead with a multi-year rate plan and approves a version of the 12 TSP to more cost-effectively promote grid-modernization, I recommend the 13 proposed DERMS investment be approved conditional on the development of an 14 iterative roadmap with annual updates that details the following: 15 • How and when dynamic flexible interconnection, DER distribution grid 16 services and DER bulk power services will be demonstrated and scaled as 17 further described below. 18 • A broader strategy for how DERMS locational deployment will be 19 prioritized across the company’s service territory to balance the 20 implementation of various use cases as further described above. 21 • Details on how various grid modernization investments will be 22 coordinated with DERMS including advanced planning & forecasting 23 tools and AMI. 24 25 Direct Testimony of Nikhil Balakumar Page 6
  3. Page 10 of 105

    1 Grid Compensation Fund 2 If PURA moves ahead with a multi-year rate plan and approves a version of the 3 TSP, I recommend the proposed Grid Compensation Fund be approved 4 conditional on the following: 5 • 6 7 The Company commits to evaluating the grid services procurement process and allocating funds to testing a flexibility market platform. • The Company commits to a midpoint milestone (i.e. two years into 8 implementation) where they will work with stakeholders to iterate on and 9 develop a scalable grid services framework inclusive of an updated 10 compensations framework. 11 • The Company consolidates its filings into a single annual filing to serve as 12 a broader update on the Company’s progress towards a flexibility first 13 approach that addresses DERMS, dynamic flexible interconnection and 14 DER distribution grid services. 15 Advanced Forecasting Tools & Circuit Planning Capabilities 16 If PURA moves ahead with a multi-year rate plan and approves a version of the 17 TSP, I recommend the proposed Advancing Forecasting Tools & Circuit Planning 18 Capabilities be approved conditional on the following: 19 • The Company begins advanced forecasting in an iterative manner once 20 tools are available and be informed by locations identified as part of 21 implementing dynamic flexible interconnection, the Grid Compensation 22 Fund and the DERMS rollout. 23 24 • The Company will coordinate its deployment with AMI such that AMI prioritizes deployment at locations that can support advanced forecasting. Direct Testimony of Nikhil Balakumar Page 7
  4. Page 11 of 105

    1 Shared Hosting for Advancement of Renewable Energy (SHARE) 2 I strongly recommend PURA reject the Company’s proposal related to SHARE 3 and explicitly require it first to leverage dynamic flexible interconnection in areas 4 of high DER development with limited hosting capacity, consistent with PURA’s 5 recent decision in Docket 25-01-27. If PURA is interested in establishing a 6 proactive planning framework, I recommend that a separate stakeholder process 7 be established to develop such a framework and incorporate lessons learned from 8 other jurisdictions. 9 10 Q9 Please summarize your conclusions and recommendations regarding the Company’s proposed AMI investment. 11 A. I recommend the Company’s proposed AMI investment be approved conditional 12 on the following requirements: 13 • The Company must: a) provide access to raw meter usage data and enrolled 14 programs; and b) include and publish additional metrics to report on platform 15 performance as described above. 16 • The Company must commit to leveraging this platform as a one stop shop for 17 future data access and propose solutions to integrate system and rates/tariff 18 information into such platform. 19 • 20 21 The Company must iteratively enable 8760 profiles at feeders and substations as sufficient AMI is deployed at specific regions. • The Company must use the locations it identified to prioritize dynamic 22 flexible interconnection, the DER compensation fund, and DERMS 23 deployment to inform where AMI should first be strategically deployed and 24 enable 8760 profiles in these regions. Direct Testimony of Nikhil Balakumar Page 8
  5. Page 12 of 105

    • 1 2 The Company must propose a concrete distributed intelligence pilot with specific use cases within one year of approval of the AMI deployment. • 3 The Company must include an evaluation of the potential of AMI to defer or 4 replace sensor investments and report as part of investigating how AMI can 5 support real-time operations and report on the progress of this investigation as 6 part of ongoing AMI updates. 7 8 Q10 Please summarize your conclusions and recommendations regarding the Company’s in-service investments. 9 A. I recommend that PURA: 10 • Direct-buried cable: Disallow about $26.5 million of 2022–2023 replacement 11 costs above the 2019–2021 unit cost, net of demonstrated inflation, absent a 12 contemporaneous analysis supporting full replacement. 13 • Capacity additions: Disallow capacity additions where the Company fails, by 14 the close of the record, to prove prudence of these investments by providing 15 the contemporaneous evaluation of non-wires alternatives, the load forecast 16 and the authorization documents for each Peak Load/Capacity project placed 17 in service from 2023 through 2025 ($145.4 million), do not find a project 18 prudent where the Company cannot make that showing, and disallow the cost 19 above the least-cost alternative where one was available. 20 • Resiliency additions: Require before-and-after storm performance data for the 21 resiliency programs and weigh the absence of measured benefits in deciding 22 whether resiliency additions placed in service after 2020 were prudently 23 incurred. 24 25 • Areas pending Company data: OCC is requesting additional data on capitalized vegetation work, the proactive direct-buried cable replacement Direct Testimony of Nikhil Balakumar Page 9
  6. Page 13 of 105

    1 program, capitalized storm restoration costs from the 2018–2023 storms, 2 AMR meter additions, and the measured benefits of the resiliency programs. I 3 will provide my recommendations on these additions and whether they should 4 be included in rate base in full or in part in surrebuttal testimony. • 5 Planned plant additions: Include in rate base only plant additions that are 6 completed, in service and documented before the close of the record and 7 exclude all forecasted plant additions that are not in service and used and 8 useful. Our current estimate is that of the $847.8 million of interim period 9 plant the Company requested from January 2026 through June 2028 10 approximately $202.5 million will still be forecasted plant at the close of the 11 record and therefore should not be included in rate base, as well as the full 12 $664.9 million requested for the Rate Year. 13 These recommendations do not deny the Company recovery of prudent 14 investment. They remove an amount the record shows was not justified, defer a 15 finding where the record does not yet contain the information needed to 16 adequately assess prudency, and sets forth what OCC needs to evaluate the 17 Company’s forward-looking capital requests, including the TSP. 18 19 Q11 Please summarize your conclusions and recommendations regarding the Company’s storm recovery investments. 20 A. Storm recovery should be impact-based, not exclusively spend-based. Meeting the 21 monetary threshold alone should not make a storm “catastrophic.” I recommend 22 that PURA: 23 • Add to the monetary threshold an impact-based test, using the Connecticut Major 24 Storm criterion and IEEE 1366 Major Event Days or other impact-based criteria, 25 to decide which events qualify for extraordinary storm recovery. 26 • When seeking recovery for crew levels that exceed benchmarks for each ELM 27 event level in the ERP, require the Company to demonstrate the reasons at the 28 time and justify the excess, beyond the forecast alone, tied to individual Direct Testimony of Nikhil Balakumar Page 10
  7. Page 14 of 105

    1 forecasted trouble spots. The Company may exceed a benchmark when conditions 2 require but should demonstrate the reasons at the time and justify the excess, 3 beyond the forecast alone, when seeking recovery. 4 • Disallow recovery of, at minimum, the portion of the $62.0 million requested for 5 storms MS24A, MS24B, MS24C, MS24D, MS24H, and MS24K that exceeds 6 established spending benchmarks. Consistent with OCC’s prior recommendation, 7 PURA should disallow costs above these benchmarks, particularly where the 8 Company has not demonstrated that its storm staging and resource decisions were 9 prudent. This proceeding should establish clear guardrails to prevent excessive 10 storm spending in the future. Customers should pay for prudent storm preparation 11 and restoration, not excessive pre-staging or costs driven by overstated forecasts 12 without demonstrated benefits. For these six events, the Company acknowledged 13 that forecasts overstated storm severity, contributing to higher costs. Our final 14 disallowance on these storms will depend on the subsequent information provided 15 by the Company in the record. 16 • Reject the Company’s storm-related programs and system hardening investments 17 until the Company demonstrates how it will improve its storm response and 18 reduce storm costs for customers. At a minimum, the Company should reconcile 19 its storm forecasts with actual outcomes and establish measurable performance 20 metrics for storm response costs, forecast accuracy, crew staging, restoration time 21 and lessons learned from each event, using the storm costs in this filing as a 22 baseline for future accountability. 23 Direct Testimony of Nikhil Balakumar Page 11
  8. Page 15 of 105

    1 III. 2 TARGETED SYSTEM PERFORMANCE PLAN A. Purpose and Overview 3 Q12 What is the purpose of this portion of your testimony? 4 A. This portion of my testimony addresses the Company’s proposed five-year TSP 5 Plan for 2027 through 2031. I rely on the testimony and exhibits of the 6 Company’s TSP panel and the Company’s responses to OCC’s interrogatories. 7 My testimony examines whether the Company has shown that the plan is needed, 8 sufficiently developed to fund, and the lowest reasonable cost way to meet system 9 needs, including whether the Company evaluated non-wires solutions before 10 seeking funding for capacity projects. It supports the recommendation of OCC 11 Witnesses Wilson and Tully that PURA reject the TSP as a basis to establish a 12 multi-year capital plan and use the Integrated Distribution System Planning 13 (“IDSP”) process to inform any future multi-year capital plan.6 14 Q13 Please summarize the purpose of the proposed TSP. 15 A. The TSP should serve as a thoughtful and data-driven strategic plan for the 16 distribution system that deliberately and steadily progresses toward a vision for 17 the future state, while balancing performance and affordability for customers and 18 covers the planning horizon for operations and investment in the Company’s 19 distribution system over the timeframe of January 1, 2027 through December 31, 20 2031.7 Specifically, the TSP describes a broader approach to maintain or improve 21 performance with the focus on six goals including (1) safety, (2) high levels of 22 reliability, (3) sufficient capacity, (4) resiliency, (5) accommodating DERs, (5) a 23 transformation unto a dynamic modern grid and (6) affordability.8 6 Direct Testimony of OCC Witnesses Wilson and Tully. Exhibit CLP-TSP-1, at 16. 8 Exhibit CLP-TSP-1, at 15. 7 Direct Testimony of Nikhil Balakumar Page 12
  9. Page 16 of 105

    1 The Company further elaborates on its goals of DERs and a dynamic modern grid 2 stating: (a) the system must be positioned to accommodate interconnected DER to 3 allow for renewable generation of electric power, as well as support of the 4 distribution system where those facilities can be leveraged as distribution assets 5 to defer traditional electric delivery infrastructure buildout; and (b) over the next 6 ten years and beyond, the system must be transformed into a dynamic modern 7 grid, leveraging cutting-edge technologies, equipment and controls, combined 8 with innovative engineering strategies and tools to increase functionality, capture 9 efficiencies and meet the challenges of a modern society with virtually zero 10 tolerance for electric interruptions.9 11 Q14 Please elaborate on how the proposed TSP is structured. 12 A. The Company has structured three levels of potential investment for the CL&P distribution system over the next five years:10 13 • 14 Sustained: The Company states the baseline investment plan is the 15 minimum level of investment needed to maintain reliability performance; 16 meet regulatory obligations; and maintain asset health and foundational 17 system planning capacity for safety and reliable operations. • 18 Targeted System Performance: The Company states this is a 19 supplementary tier of investment directed at achieving an escalating level 20 of asset-health replacements and enhanced reliability performance, while 21 also commencing a system resiliency initiative. • 22 Advancing the Grid: The Company is presenting an investment plan that 23 would build on the 5-Year TSP Plan over the longer term, accounting for 24 investments related to state policy initiatives and higher standards of 9 Exhibit CLP-TSP-1, at 15-16. Exhibit CLP-TSP-1, at 17-18. 10 Direct Testimony of Nikhil Balakumar Page 13
  10. Page 17 of 105

    1 innovation and software tools including those to support DER integration, 2 clean-energy advancement and advancing the grid toward modernization. 3 Q15 What is your understanding of the Company’s request? 4 A. In the Targeted System Performance tier, the Company asks PURA to approve 5 $3.985 billion of capital spending over five years, from 2027 through 2031. This 6 includes $3.611 billion in the Sustained tier, which increases from $667 million in 7 2027 to $757 million in 2031.11 The Company describes the sustained tier as “the 8 minimum level of investment needed to maintain reliability performance; meet 9 regulatory obligations; and maintain asset health and foundational system 10 planning capacity for safety and reliable operations.”12 The second tier, Targeted 11 System Performance, adds $374 million, including $155.0 million for resilience, 12 $143.3 million for asset health, and $75.8 million for enhanced reliability.13 In 13 this second tier, the Company also proposes approximately $71 million of 14 incremental O&M, including a $38 million Grid Services Compensation Fund.14 15 The third tier, Advancing the Grid, builds off of the first two tiers then adds an 16 additional $396 million for a total of $4.381 billion. Under all three tiers, 17 vegetation management spending would increase from $59 million to $91 million 18 a year beginning in 2028.15 19 The Company presents the three tiers as “budget options” to allow PURA to 20 consider the appropriate balance between system needs and customer costs16, 21 while recommending the second tier, a.k.a. the Targeted System Performance 22 tier.17 However, if PURA considers the proposed TSP, it should evaluate the 11 Exh. CLP-TSP-3 at 10. Exh. CLP-TSP-1 at 17. 13 Response to OCC-809. 14 Exh. CLP-TSP-3 at 43. 15 Id. at 11. 16 Exh. CLP-TSP-1 at 47. 17 Exh. CLP-TSP-3 at 7, 11. 12 Direct Testimony of Nikhil Balakumar Page 14