Prefiled testimony
Witness: Nikhil Balakumar
Files2
26-05-10_Direct Testimony Eclipse FINAL.pdf
PDF · 1.4 MB · 105 pagesText searchable
Download 26-05-10_Direct Testimony Eclipse FINAL.pdfRead the text of 26-05-10_Direct Testimony Eclipse FINAL.pdf
Attachment 1 - Nikhil Balakumar_Resume.pdf
PDF · 126 KB · 2 pagesText searchable
Download Attachment 1 - Nikhil Balakumar_Resume.pdfRead the text of Attachment 1 - Nikhil Balakumar_Resume.pdf
Words on different pages
Every word of Eversource rate increase is in the text below, but not all on one page. Pages with any of them are listed and highlighted. Clear highlighting
Page 83 of 105
1 latency will be included in this investigation.199 AMI provides the most granular 2 data available on the system and should be leveraged where possible to support 3 not just billing but planning and operations. Specifically, there may be potential to 4 defer or eliminate the needs for other sensor investments if AMI can truly be 5 integrated into real-time operations. I support this investigation and request that 6 the Company also investigate the potential of AMI to defer or replace sensor 7 investments and report on its progress as part of any reporting supporting the 8 ongoing deployment. 9 Q84 What is your recommendation? 10 A. I recommend the Company’s proposed AMI investment be approved conditional 11 on the following requirements: • 12 The Company should be required to also a) provide access to raw meter 13 usage data and enrolled programs and b) include and publish additional 14 metrics to report on platform performance as described above. 199 OCC-747, (a), at 1. Direct Testimony of Nikhil Balakumar Page 80Page 84 of 105
• 1 The Company should be required to commit to leveraging this platform as 2 a one-stop shop for future data access and propose solutions to integrate 3 system and rates/tariff information into such a platform. • 4 5 The Company should be required to iteratively enable 8760 profiles at feeders and substations as sufficient AMI is deployed at specific regions. • 6 The Company should be required to use the locations it identified to 7 prioritize dynamic flexible interconnection, the DER compensation fund 8 and DERMS deployment to inform where AMI should first be 9 strategically deployed and enable 8760 profiles in these regions. • 10 The Company should be required to propose a concrete distributed 11 intelligence pilot with specific use cases within 1 year of approval of the 12 AMI deployment. • 13 The Company should be required to include an evaluation of the potential 14 of AMI to defer or replace sensor investments as part of investigating how 15 AMI can support real-time operations and report on the progress of this 16 investigation as part of ongoing AMI updates. 17 V. 18 IN-SERVICE INVESTMENTS A. Purpose and Overview 19 Q85 What is the purpose of this portion of your testimony? 20 A. This portion of my testimony addresses the Company’s request to include in rate 21 base the capital additions it placed in service from January 1, 2017, through 22 December 31, 2025, and its request to include planned plant additions for 2027 23 through the end of the Rate Year in rates. I rely on the joint testimony of the 24 Company’s Additions Panel, the project-level data in its exhibits, and the Direct Testimony of Nikhil Balakumar Page 81Page 85 of 105
1 Company’s responses to interrogatories. I examine whether specific additions 2 were prudent: whether the Company made reasonable decisions about what to 3 build, how to build it, and how to account for it, and whether it had reasonable 4 documentation, vetting and approval processes in place before committing the 5 funds. Where my testimony on the TSP Plan already addresses an issue, I refer to 6 it rather than repeat it. 7 The Company states that it placed approximately $4.3 billion of capital additions 8 in service over this eight year period, and that the costs “were reasonably and 9 prudently incurred.”200 Of the $4.318 billion of net distribution additions, $2.290 10 billion, or 53 percent, was placed in service through annual programs and annual 11 work orders rather than individually authorized projects.201 The Company also 12 asks to include in rates $847.8 million of planned additions for January 2026 13 through June 2027 and $664.9 million for the Rate Year ending June 30, 2028.202 14 15 Q86 What must the Company show to demonstrate the additions were prudently incurred? 16 A. The Company bears the burden of demonstrating that each addition is used and 17 useful and that its cost was prudently incurred. That is, the decision to undertake 18 the work, and the cost of carrying it out, must have been reasonable in light of 19 what the Company knew or should have known at the time.203 20 I have concerns with the prudency of several of the Company’s additions. My 21 review identifies two groups of additions for which the record does not support a 22 finding of prudence, and several areas where the record does not yet contain the 23 information needed to complete the review: 200 Exh. CLP-ADDITIONS-1 at 445. Exh. CLP-ADDITIONS-2; Exh. CLP-ADDITIONS-3. 202 Exh. CLP-ADDITIONS-1 at 52. 203 Conn. Gen. Stat. §§ 16-19e(a) and 16-22. 201 Direct Testimony of Nikhil Balakumar Page 82Page 86 of 105
1 • Capacity additions: The Company placed $145.4 million of Peak Load/Capacity 2 projects in service from 2023 through 2025. The record does not contain the 3 project-level evaluation of non-wires alternatives that the Company’s own 4 planning procedures, and PURA’s November 2022 Non-Wires Solutions decision, 5 contemplate for investments of this kind. 6 • Direct-buried cable: Proactive replacement of direct-buried cable cost about 7 $257 million. The cost per mile tripled, and the Company has since scaled the 8 approach back in favor of repair. The Company has not shown that the proactive 9 replacement approach it adopted in 2019 produced benefits commensurate with its 10 cost, and the record contains no benefit-cost analysis supporting that approach or 11 its continuation as unit costs rose. 12 • Areas pending Company data: Capacity additions placed in service without a 13 documented evaluation of lower-cost alternatives; the proactive direct-buried 14 cable replacement program; capitalized storm restoration from the 2018–2023 15 storms; capitalized storm restoration from the 2018–2023 storms; AMR meter 16 additions; and resiliency programs with no measured storm benefit. The record 17 does not yet contain enough information to determine whether these additions 18 were prudently incurred. I will update my recommendations in surrebuttal 19 testimony and final positions on the prudency of plant will be based on the actual 20 amounts the Company documents and supported through the close of record. 21 22 Beyond these specific items, the record shows weak cost control over the overall 23 portfolio. Spending exceeded the Board-approved plan in seven of eight years. I 24 recommend a specific adjustment for direct-buried cable, documentation 25 requirements for the capacity additions and the areas pending Company data, and 26 a limit on the planned plant additions included in rates. Direct Testimony of Nikhil Balakumar Page 83Page 87 of 105
1 2 Q87 How does actual capital spending compare with the plans approved by the Company’s Board, and what does that show about cost control? 3 A. Connecticut Distribution capital spending exceeded the plan in the Company’s 4 annual Capital Book in seven of the eight years from 2017 through 2024, by a 5 cumulative $350.8 million, or 11 percent (Table 1). 6 Table 4: Connecticut Distribution Capital Spending, Plan Compared with Actual ($ million) 204 Year 2017 2018 2019 2020 2021 2022 2023 2024 2017–2024 Plan 336.0 325.0 360.0 371.0 365.0 434.0 466.4 466.2 3,123.6 Actual 359.0 409.0 417.0 402.0 409.0 469.9 557.9 450.6 3,474.4 Variance +23.0 +84.0 +57.0 +31.0 +44.0 +35.9 +91.5 -15.6 +350.8 Variance (%) +6.8% +25.8% +15.8% +8.4% +12.1% +8.3% +19.6% -3.3% +11.2% 7 8 The overruns did not come from individual projects costing more than estimated. 9 For individually authorized projects begun before 2022, actual direct costs were 10 18 percent below their pre-construction estimates in aggregate, and nearly half 11 came in more than 10 percent under estimate.205 The overruns came from adding 12 work to the portfolio during the year. For 2023, the year with the largest overrun, 13 the two largest additions were a $22.0 million trip saver program and $20.0 14 million of circuit patrol fixes, neither of which was in the plan the Board 15 approved.206 16 This has two implications for prudence. First, project estimates that run well 17 above actual costs do not act as a control. A project can absorb scope growth 18 without triggering the supplemental authorization the Company’s policy requires. 19 Second, the real control point is the decision to add work to the year’s portfolio, 204 Exh. CLP-ADDITIONS-12 at 8, 28, 45, 65, 83, 102, 121, 145, 167. Exh. CLP-ADDITIONS-4. 206 Response to OCC-780. 205 Direct Testimony of Nikhil Balakumar Page 84Page 88 of 105
1 and that is where the record is thinnest. When requesting the documents 2 authorizing spending above plan, the Company referred OCC to its Capital Books 3 and to total-company variance analyses filed in other dockets. It did not provide 4 or identify any authorization.207 As I explain in the Sustained Tier section of my 5 testimony, the Company also cut its 2025 plan for “regulatory recovery risk” and 6 stated that the cut had no reliability consequence. Taken together, these facts 7 show that much of the Company’s capital work was discretionary in timing and 8 scope. That raises the importance of showing that each addition was selected on 9 its merits. 10 11 Q88 Did the Company’s reliability and resiliency additions deliver results, and were they properly accounted for? 12 A. As discussed in the TSP section of my testimony, Blue-Sky SAIDI worsened 13 from 70.7 minutes in 2021 to 77.5 minutes in 2025, while the Company placed 14 $984.6 million of reliability capital in service. It also shows that the Company 15 could not identify the reliability performance it expected when it authorized that 16 capital. I do not repeat that analysis here. For prudence, the more specific problem 17 is what the resiliency portion bought and how it was accounted for. 18 Of the $984.6 million, $390.4 million was placed in service under System 19 Resiliency/Expanded Reliability.208 PURA approved System Resiliency for 2018 20 through 2020, with recovery through the capital tracker. After that approval 21 ended, the Company continued the work and, in 2023, moved it from the 22 Regulatory Commitments category to Reliability. When asked for the reliability 23 benefit measured after completion of each program, the Company provided 24 budget amounts and project listings, not measured benefits.209 207 Response to OCC-779. Response to OCC-804, Attachment 1. 209 Response to OCC-802. 208 Direct Testimony of Nikhil Balakumar Page 85Page 89 of 105
1 The TSP section of the testimony explains that the Company has not measured the 2 storm-day benefits of these programs, even though it states that their benefits 3 “may not be fully reflected in Blue-Sky SAIDI.”210 OCC is requesting storm 4 outage events, customer-minutes interrupted on major event days, and storm 5 restoration cost before and after the work, for the circuits and zones where 6 resiliency work was done. If the Company cannot show a measurable benefit, 7 PURA should deny recovery for any resiliency additions placed in service after its 8 approval ended in 2020 on the basis that they were not prudently incurred. 9 10 Q89 Did the Company evaluate lower-cost alternatives before it built the capacity projects placed in service from 2023 through 2025? 11 A. The record does not contain enough information to make that determination. Peak 12 Load/Capacity spending rose sharply in 2022 and 2023 (Table 2). The Company 13 attributes the decline from 2023 to 2024 to the number of large substation 14 capacity projects (six in 2023 versus three in 2024).211 In my experience, capacity 15 needs that are modest in size or short in duration are where lower-cost alternatives 16 are most likely to be viable. Load transfers, demand response, energy storage and 17 flexible interconnection can defer or avoid a new transformer or feeder when an 18 overload is small or lasts only a few hours a year. 19 210 211 Response to OCC-804 at 2. Exh. CLP-ADDITIONS-12 at 121, 145. Direct Testimony of Nikhil Balakumar Page 86Page 90 of 105
1 Table 5: Peak Load/Capacity Capital, 2017–2025 ($ million) 212 Year 2017 2018 2019 2020 2021 2022 2023 2024 2025 Placed in service, 2017–2025 total Large substation capacity projects (count) Plan 26.0 36.0 24.0 21.0 17.0 20.0 58.9 49.0 46.1 – – Actual spending 19.0 38.0 20.0 18.0 27.0 54.0 80.0 45.9 Not reported 278.9 6 in 2023; 3 in 2024 2 The Company’s own procedures call for that evaluation. Its project authorization 3 form includes an “Alternatives Considered” section.213 Its approval process 4 requires the project initiator to evaluate “the potential use of non-wires 5 alternatives (‘NWA’) solutions,” to prepare cost estimates for the preferred 6 solution and the leading alternative, and to present them to the Solutions Design 7 Committee before a solution is selected.214 The Company also developed a written 8 Non-Wires Alternative Framework in 2021215 and states that “since 9 implementation of the new NWA process under Docket No. 24-08-08 Final 10 Decision,” it “has been adhering to the process and criteria outlined therein.”216 11 PURA’s November 9, 2022 Non-Wires Solutions decision likewise bases its 12 prudence review on “a contemporaneous record of utility information and 13 decision-making,”217 as I discuss in the TSP section of my testimony. Because the 14 first formal cycle of that process began only in 2025,218 and only “[p]rojects 15 approved after January 2025 have undergone the newly established NWA 212 Exh. CLP-ADDITIONS-12 at 8, 28, 45, 65, 83, 102, 121, 145, 167; Response to OCC-811 at 2 (inservice total). Capital spending and in-service additions are on different bases. 213 Exh. CLP-ADDITIONS-1 at 19. 214 Id. at 36. 215 Response to OCC-578, Attachment 1 at 1. 216 Response to OCC-578. 217 Docket No. 17-12-03RE07, PURA Investigation into Distribution System Planning of the Electric Distribution Companies – Non-Wires Alternatives, Decision (Nov. 9, 2022), Appendix A, NonWires Solutions Process Design Document, p. 2. 218 Id., p. 3. Direct Testimony of Nikhil Balakumar Page 87Page 91 of 105
1 process,”219 the screening that applied to the projects at issue was the Company’s 2 own. 3 The record does not show how that screening was applied. OCC asked the 4 Company to identify each substation capacity project undertaken from 2017 5 through 2025 together with “any non-wires alternative evaluation.” The 6 Company’s Attachment 1 lists the projects’ load forecasts and post-in-service 7 peak loads and references non-wires alternatives, but it does not identify the 8 alternatives considered, their cost relative to the wires solution, or why they were 9 not selected.220 The Company also describes permanent load transfers as, in many 10 cases, the preferred and “typically substantially lower cost” solution, yet states 11 that “[h]istorically these load transfers were not explicitly tracked.”221 When 12 asked for actual substation capacity violations since 2016, it identified none, 13 stating that “[a]ll substation forecasted violations are mitigated by using pre- 14 contingent load transfers to adjacent substations with remaining capacity.”222 15 Without these records, PURA cannot determine whether these projects were the 16 least-cost means of meeting an identified need. Eversource has the burden of 17 demonstrating this for each Peak Load/Capacity project with its own project 18 authorization placed in service from 2023 through 2025, including line capacity 19 projects. 20 If after further discovery, the record shows that the Company built capacity 21 without evaluating lower-cost alternatives, or that the forecast overloads did not 22 occur, I will recommend that PURA disallow the difference between the cost of 23 the project and the cost of the least-cost alternative. 219 Response to OCC-590. Response to OCC-805 and Attachment 1. 221 Response to OCC-599(b) at 2. 222 Response to OCC-599(c) at 3. 220 Direct Testimony of Nikhil Balakumar Page 88Page 92 of 105
1 B. Direct-Buried Cable Replacement 2 3 Q90 Was the Company’s proactive direct-buried cable replacement program prudent? 4 A. Direct-buried cable replacement is the clearest example of a proactive program 5 for which the record does not show that cost was tested against the alternative. 6 Historically, the Company repaired direct-buried cable as failures occurred. In 7 2019, it adopted a proactive approach to “replace and upgrade longer segments of 8 cable around failure points.”223 9 The cost per mile more than doubled between 2019 and 2022, while the failure 10 rate on the system changed only modestly. The Company has now changed 11 course. Beginning in 2024, it adopted “a hybrid approach combining proactive 12 replacements with repair work.” For 2025, it reduced replacement because it “can 13 maintain safety and reliability in the short run with repairs rather than 14 replacement,” and because its “investment approach is changing now based on its 15 experience with the proactive replacement program.”224 Repair was the 16 Company’s practice before 2019 and again forms part of its approach today. The 17 record does not contain any analysis, at the 2019 decision or when unit costs rose 18 sharply in 2020 and 2022, comparing full replacement with repair. 19 I do not suggest that every mile replaced was imprudent. In my view, a prudent 20 utility would have re-evaluated the program when its unit cost doubled. In 2022 21 and 2023, the Company replaced 67.6 miles at a cost of $76.45 million. At the 22 2019–2021 average of about $750,000 per mile, the same work would have cost 23 about $50.0 million. PURA should disallow the difference of about $26.5 million, 24 net of any cost increase the Company demonstrates was due to general inflation, 25 unless the Company produces, before the record closes, a contemporaneous 223 224 Response to OCC-798. Responses to OCC-781 and OCC-798. Direct Testimony of Nikhil Balakumar Page 89
As listed on the current system
Prefiled testimony: 10/21/2026 - Sponsor: TBD / Witness: Nikhil Balakumar [26-05-10]