Prefiled testimony
Witness: Nikhil Balakumar
Files2
26-05-10_Direct Testimony Eclipse FINAL.pdf
PDF · 1.4 MB · 105 pagesText searchable
Download 26-05-10_Direct Testimony Eclipse FINAL.pdfRead the text of 26-05-10_Direct Testimony Eclipse FINAL.pdf
Attachment 1 - Nikhil Balakumar_Resume.pdf
PDF · 126 KB · 2 pagesText searchable
Download Attachment 1 - Nikhil Balakumar_Resume.pdfRead the text of Attachment 1 - Nikhil Balakumar_Resume.pdf
Words on different pages
Every word of Eversource rate increase is in the text below, but not all on one page. Pages with any of them are listed and highlighted. Clear highlighting
Page 86 of 105
1 • Capacity additions: The Company placed $145.4 million of Peak Load/Capacity 2 projects in service from 2023 through 2025. The record does not contain the 3 project-level evaluation of non-wires alternatives that the Company’s own 4 planning procedures, and PURA’s November 2022 Non-Wires Solutions decision, 5 contemplate for investments of this kind. 6 • Direct-buried cable: Proactive replacement of direct-buried cable cost about 7 $257 million. The cost per mile tripled, and the Company has since scaled the 8 approach back in favor of repair. The Company has not shown that the proactive 9 replacement approach it adopted in 2019 produced benefits commensurate with its 10 cost, and the record contains no benefit-cost analysis supporting that approach or 11 its continuation as unit costs rose. 12 • Areas pending Company data: Capacity additions placed in service without a 13 documented evaluation of lower-cost alternatives; the proactive direct-buried 14 cable replacement program; capitalized storm restoration from the 2018–2023 15 storms; capitalized storm restoration from the 2018–2023 storms; AMR meter 16 additions; and resiliency programs with no measured storm benefit. The record 17 does not yet contain enough information to determine whether these additions 18 were prudently incurred. I will update my recommendations in surrebuttal 19 testimony and final positions on the prudency of plant will be based on the actual 20 amounts the Company documents and supported through the close of record. 21 22 Beyond these specific items, the record shows weak cost control over the overall 23 portfolio. Spending exceeded the Board-approved plan in seven of eight years. I 24 recommend a specific adjustment for direct-buried cable, documentation 25 requirements for the capacity additions and the areas pending Company data, and 26 a limit on the planned plant additions included in rates. Direct Testimony of Nikhil Balakumar Page 83Page 87 of 105
1 2 Q87 How does actual capital spending compare with the plans approved by the Company’s Board, and what does that show about cost control? 3 A. Connecticut Distribution capital spending exceeded the plan in the Company’s 4 annual Capital Book in seven of the eight years from 2017 through 2024, by a 5 cumulative $350.8 million, or 11 percent (Table 1). 6 Table 4: Connecticut Distribution Capital Spending, Plan Compared with Actual ($ million) 204 Year 2017 2018 2019 2020 2021 2022 2023 2024 2017–2024 Plan 336.0 325.0 360.0 371.0 365.0 434.0 466.4 466.2 3,123.6 Actual 359.0 409.0 417.0 402.0 409.0 469.9 557.9 450.6 3,474.4 Variance +23.0 +84.0 +57.0 +31.0 +44.0 +35.9 +91.5 -15.6 +350.8 Variance (%) +6.8% +25.8% +15.8% +8.4% +12.1% +8.3% +19.6% -3.3% +11.2% 7 8 The overruns did not come from individual projects costing more than estimated. 9 For individually authorized projects begun before 2022, actual direct costs were 10 18 percent below their pre-construction estimates in aggregate, and nearly half 11 came in more than 10 percent under estimate.205 The overruns came from adding 12 work to the portfolio during the year. For 2023, the year with the largest overrun, 13 the two largest additions were a $22.0 million trip saver program and $20.0 14 million of circuit patrol fixes, neither of which was in the plan the Board 15 approved.206 16 This has two implications for prudence. First, project estimates that run well 17 above actual costs do not act as a control. A project can absorb scope growth 18 without triggering the supplemental authorization the Company’s policy requires. 19 Second, the real control point is the decision to add work to the year’s portfolio, 204 Exh. CLP-ADDITIONS-12 at 8, 28, 45, 65, 83, 102, 121, 145, 167. Exh. CLP-ADDITIONS-4. 206 Response to OCC-780. 205 Direct Testimony of Nikhil Balakumar Page 84Page 88 of 105
1 and that is where the record is thinnest. When requesting the documents 2 authorizing spending above plan, the Company referred OCC to its Capital Books 3 and to total-company variance analyses filed in other dockets. It did not provide 4 or identify any authorization.207 As I explain in the Sustained Tier section of my 5 testimony, the Company also cut its 2025 plan for “regulatory recovery risk” and 6 stated that the cut had no reliability consequence. Taken together, these facts 7 show that much of the Company’s capital work was discretionary in timing and 8 scope. That raises the importance of showing that each addition was selected on 9 its merits. 10 11 Q88 Did the Company’s reliability and resiliency additions deliver results, and were they properly accounted for? 12 A. As discussed in the TSP section of my testimony, Blue-Sky SAIDI worsened 13 from 70.7 minutes in 2021 to 77.5 minutes in 2025, while the Company placed 14 $984.6 million of reliability capital in service. It also shows that the Company 15 could not identify the reliability performance it expected when it authorized that 16 capital. I do not repeat that analysis here. For prudence, the more specific problem 17 is what the resiliency portion bought and how it was accounted for. 18 Of the $984.6 million, $390.4 million was placed in service under System 19 Resiliency/Expanded Reliability.208 PURA approved System Resiliency for 2018 20 through 2020, with recovery through the capital tracker. After that approval 21 ended, the Company continued the work and, in 2023, moved it from the 22 Regulatory Commitments category to Reliability. When asked for the reliability 23 benefit measured after completion of each program, the Company provided 24 budget amounts and project listings, not measured benefits.209 207 Response to OCC-779. Response to OCC-804, Attachment 1. 209 Response to OCC-802. 208 Direct Testimony of Nikhil Balakumar Page 85Page 89 of 105
1 The TSP section of the testimony explains that the Company has not measured the 2 storm-day benefits of these programs, even though it states that their benefits 3 “may not be fully reflected in Blue-Sky SAIDI.”210 OCC is requesting storm 4 outage events, customer-minutes interrupted on major event days, and storm 5 restoration cost before and after the work, for the circuits and zones where 6 resiliency work was done. If the Company cannot show a measurable benefit, 7 PURA should deny recovery for any resiliency additions placed in service after its 8 approval ended in 2020 on the basis that they were not prudently incurred. 9 10 Q89 Did the Company evaluate lower-cost alternatives before it built the capacity projects placed in service from 2023 through 2025? 11 A. The record does not contain enough information to make that determination. Peak 12 Load/Capacity spending rose sharply in 2022 and 2023 (Table 2). The Company 13 attributes the decline from 2023 to 2024 to the number of large substation 14 capacity projects (six in 2023 versus three in 2024).211 In my experience, capacity 15 needs that are modest in size or short in duration are where lower-cost alternatives 16 are most likely to be viable. Load transfers, demand response, energy storage and 17 flexible interconnection can defer or avoid a new transformer or feeder when an 18 overload is small or lasts only a few hours a year. 19 210 211 Response to OCC-804 at 2. Exh. CLP-ADDITIONS-12 at 121, 145. Direct Testimony of Nikhil Balakumar Page 86Page 90 of 105
1 Table 5: Peak Load/Capacity Capital, 2017–2025 ($ million) 212 Year 2017 2018 2019 2020 2021 2022 2023 2024 2025 Placed in service, 2017–2025 total Large substation capacity projects (count) Plan 26.0 36.0 24.0 21.0 17.0 20.0 58.9 49.0 46.1 – – Actual spending 19.0 38.0 20.0 18.0 27.0 54.0 80.0 45.9 Not reported 278.9 6 in 2023; 3 in 2024 2 The Company’s own procedures call for that evaluation. Its project authorization 3 form includes an “Alternatives Considered” section.213 Its approval process 4 requires the project initiator to evaluate “the potential use of non-wires 5 alternatives (‘NWA’) solutions,” to prepare cost estimates for the preferred 6 solution and the leading alternative, and to present them to the Solutions Design 7 Committee before a solution is selected.214 The Company also developed a written 8 Non-Wires Alternative Framework in 2021215 and states that “since 9 implementation of the new NWA process under Docket No. 24-08-08 Final 10 Decision,” it “has been adhering to the process and criteria outlined therein.”216 11 PURA’s November 9, 2022 Non-Wires Solutions decision likewise bases its 12 prudence review on “a contemporaneous record of utility information and 13 decision-making,”217 as I discuss in the TSP section of my testimony. Because the 14 first formal cycle of that process began only in 2025,218 and only “[p]rojects 15 approved after January 2025 have undergone the newly established NWA 212 Exh. CLP-ADDITIONS-12 at 8, 28, 45, 65, 83, 102, 121, 145, 167; Response to OCC-811 at 2 (inservice total). Capital spending and in-service additions are on different bases. 213 Exh. CLP-ADDITIONS-1 at 19. 214 Id. at 36. 215 Response to OCC-578, Attachment 1 at 1. 216 Response to OCC-578. 217 Docket No. 17-12-03RE07, PURA Investigation into Distribution System Planning of the Electric Distribution Companies – Non-Wires Alternatives, Decision (Nov. 9, 2022), Appendix A, NonWires Solutions Process Design Document, p. 2. 218 Id., p. 3. Direct Testimony of Nikhil Balakumar Page 87Page 91 of 105
1 process,”219 the screening that applied to the projects at issue was the Company’s 2 own. 3 The record does not show how that screening was applied. OCC asked the 4 Company to identify each substation capacity project undertaken from 2017 5 through 2025 together with “any non-wires alternative evaluation.” The 6 Company’s Attachment 1 lists the projects’ load forecasts and post-in-service 7 peak loads and references non-wires alternatives, but it does not identify the 8 alternatives considered, their cost relative to the wires solution, or why they were 9 not selected.220 The Company also describes permanent load transfers as, in many 10 cases, the preferred and “typically substantially lower cost” solution, yet states 11 that “[h]istorically these load transfers were not explicitly tracked.”221 When 12 asked for actual substation capacity violations since 2016, it identified none, 13 stating that “[a]ll substation forecasted violations are mitigated by using pre- 14 contingent load transfers to adjacent substations with remaining capacity.”222 15 Without these records, PURA cannot determine whether these projects were the 16 least-cost means of meeting an identified need. Eversource has the burden of 17 demonstrating this for each Peak Load/Capacity project with its own project 18 authorization placed in service from 2023 through 2025, including line capacity 19 projects. 20 If after further discovery, the record shows that the Company built capacity 21 without evaluating lower-cost alternatives, or that the forecast overloads did not 22 occur, I will recommend that PURA disallow the difference between the cost of 23 the project and the cost of the least-cost alternative. 219 Response to OCC-590. Response to OCC-805 and Attachment 1. 221 Response to OCC-599(b) at 2. 222 Response to OCC-599(c) at 3. 220 Direct Testimony of Nikhil Balakumar Page 88Page 92 of 105
1 B. Direct-Buried Cable Replacement 2 3 Q90 Was the Company’s proactive direct-buried cable replacement program prudent? 4 A. Direct-buried cable replacement is the clearest example of a proactive program 5 for which the record does not show that cost was tested against the alternative. 6 Historically, the Company repaired direct-buried cable as failures occurred. In 7 2019, it adopted a proactive approach to “replace and upgrade longer segments of 8 cable around failure points.”223 9 The cost per mile more than doubled between 2019 and 2022, while the failure 10 rate on the system changed only modestly. The Company has now changed 11 course. Beginning in 2024, it adopted “a hybrid approach combining proactive 12 replacements with repair work.” For 2025, it reduced replacement because it “can 13 maintain safety and reliability in the short run with repairs rather than 14 replacement,” and because its “investment approach is changing now based on its 15 experience with the proactive replacement program.”224 Repair was the 16 Company’s practice before 2019 and again forms part of its approach today. The 17 record does not contain any analysis, at the 2019 decision or when unit costs rose 18 sharply in 2020 and 2022, comparing full replacement with repair. 19 I do not suggest that every mile replaced was imprudent. In my view, a prudent 20 utility would have re-evaluated the program when its unit cost doubled. In 2022 21 and 2023, the Company replaced 67.6 miles at a cost of $76.45 million. At the 22 2019–2021 average of about $750,000 per mile, the same work would have cost 23 about $50.0 million. PURA should disallow the difference of about $26.5 million, 24 net of any cost increase the Company demonstrates was due to general inflation, 25 unless the Company produces, before the record closes, a contemporaneous 223 224 Response to OCC-798. Responses to OCC-781 and OCC-798. Direct Testimony of Nikhil Balakumar Page 89Page 93 of 105
1 analysis supporting full replacement at the higher cost.225 I will update this 2 recommendation in surrebuttal testimony if the Company provides that analysis. 3 C. Planned Plant Additions for 2026 and 2027 4 5 Q91 What does the Company propose for planned plant additions in 2026 and 2027? 6 A. The Company proposes to add interim and forecasted plant to the Test Year rate 7 base through June 30, 2028. It uses annual forecasted additions of $544.1 million 8 for 2026, $632.1 million for 2027 and $700.5 million for 2028. From those, it 9 derives $847.8 million of interim additions for January 2026 through June 2027 10 and $664.9 million of Rate Year additions for July 2027 through June 2028.226 It 11 allocated the annual totals to plant accounts and months “using historical and 12 forecasted information.”227 The forecast is not built from a list of projects with 13 scopes, cost estimates and in-service dates. 14 The Company does not ask PURA to find these additions prudent now, and 15 anticipates that determination “in the next rate case at such time that those 16 projects are placed in-service.” It nonetheless asks that they be included in rates 17 “subject to reconciliation,” and ties its proposed PBMRP to “the planned capital 18 investment plan described in the TSP Plan.”228 The Company will update actual 19 in-service additions during this proceeding, through October 31, 2026 in its 20 December 15, 2026 filing,229and it is my understanding that the final update will 21 be included in LFE-1. 22 The forecast is high relative to the Company’s record. Net distribution additions 23 averaged $479.8 million a year from 2017 through 2025. The 2027 forecast 225 Response to OCC-798. OCC calculations. Exh. CLP-ADDITIONS-1 at 52. 227 Id. 228 Exh. CLP-ADDITIONS-1 at 54. 229 Exh. CLP-ADDITIONS-1 at 51–52. 226 Direct Testimony of Nikhil Balakumar Page 90Page 94 of 105
1 exceeds every year in that period, and the 2028 forecast is about 11 percent above 2 the previous peak of $629.9 million in 2023 (Table 4). 3 Table 6: Net Distribution Plant Additions, Actual 2017–2025 and Company Forecast 2026–2028 ($ million) 230 Year 2017 2018 2019 2020 2021 2022 2023 2024 2025 2017–2025 average 2026 2027 2028 Additions 375.6 426.1 425.6 466.4 413.7 478.2 629.9 527.4 575.1 479.8 544.1 632.1 700.5 Basis Actual Actual Actual Actual Actual Actual Actual Actual Actual Actual Interim Forecast Forecast 4 5 Q92 Has the Company supported including these planned additions in rates? 6 A. No. PURA has consistently declined to set rates on forecasted plant that is not yet 7 in service and used and useful by the close of the evidentiary record in a given 8 single rate year case. In UI’s most recent electric rate case, it included only plant 9 found to be used and useful, explaining that “it is an impossibility to provide 10 sufficient evidence that a future plant addition is used and useful and that the 11 investment was prudent.”231 In the CNG and SCG rate case, it allowed only plant 12 completed and in service through the last supplemental filing before the record 13 closed, and found the companies’ reconciliation mechanism insufficient to protect 14 ratepayers.232 230 Exh. CLP-ADDITIONS-2 (2017–2025 net distribution plant in service additions); Exh. CLPADDITIONS-1 at 52 (2026–2028 annual forecasted capital plant additions). 231 Docket No. 22-08-08, Application of The United Illuminating Company to Amend Its Rate Schedules, Decision (Aug. 25, 2023). 232 Docket No. 23-11-02, Applications of Connecticut Natural Gas Corporation and The Southern Connecticut Gas Company to Amend Their Rate Schedules, Decision (2024). Direct Testimony of Nikhil Balakumar Page 91Page 95 of 105
1 The Company’s request raises the same concerns. It seeks no prudence finding 2 now, its reconciliation would apply only downward and only to overall plant in 3 service,233 and much of its 2027 and all of its 2028 forecasts are tied to the TSP 4 and PBMRP, which OCC recommends PURA not approve.234 PURA should 5 therefore include in rate base only plant completed, in service and documented 6 through the Company’s final supplemental filing before the record closes, and 7 exclude all forecasted additions. My recommendations on plant will be finalized 8 based on that filing. 9 D. Conclusion 10 Q93 Please summarize your recommendations. 11 A. I recommend that PURA: 12 • Direct-buried cable: Disallow about $26.5 million of 2022–2023 replacement 13 costs above the 2019–2021 unit cost, net of demonstrated inflation, absent a 14 contemporaneous analysis supporting full replacement. 15 • Areas pending Company data: Require the Company to provide, before the record 16 closes, the information OCC is requesting on capitalized vegetation work, the 17 proactive direct-buried cable replacement program, capitalized storm restoration 18 from the 2018–2023 storms, AMR meter additions, and the measured benefits of 19 the resiliency programs. I will provide my recommendations on these additions in 20 surrebuttal testimony. 21 • Capacity additions: Require the Company to produce, before the record closes, 22 the contemporaneous evaluation of non-wires alternatives, the load forecast and 23 the authorization documents for each Peak Load/Capacity project placed in 24 service from 2023 through 2025 ($145.4 million), do not find a project prudent 233 234 Response to OCC-579. Exh. CLP-ADDITIONS-1 at 52–54. Direct Testimony of Nikhil Balakumar Page 92
As listed on the current system
Prefiled testimony: 10/21/2026 - Sponsor: TBD / Witness: Nikhil Balakumar [26-05-10]