  1. Page 93 of 105

    1 analysis supporting full replacement at the higher cost.225 I will update this 2 recommendation in surrebuttal testimony if the Company provides that analysis. 3 C. Planned Plant Additions for 2026 and 2027 4 5 Q91 What does the Company propose for planned plant additions in 2026 and 2027? 6 A. The Company proposes to add interim and forecasted plant to the Test Year rate 7 base through June 30, 2028. It uses annual forecasted additions of $544.1 million 8 for 2026, $632.1 million for 2027 and $700.5 million for 2028. From those, it 9 derives $847.8 million of interim additions for January 2026 through June 2027 10 and $664.9 million of Rate Year additions for July 2027 through June 2028.226 It 11 allocated the annual totals to plant accounts and months “using historical and 12 forecasted information.”227 The forecast is not built from a list of projects with 13 scopes, cost estimates and in-service dates. 14 The Company does not ask PURA to find these additions prudent now, and 15 anticipates that determination “in the next rate case at such time that those 16 projects are placed in-service.” It nonetheless asks that they be included in rates 17 “subject to reconciliation,” and ties its proposed PBMRP to “the planned capital 18 investment plan described in the TSP Plan.”228 The Company will update actual 19 in-service additions during this proceeding, through October 31, 2026 in its 20 December 15, 2026 filing,229and it is my understanding that the final update will 21 be included in LFE-1. 22 The forecast is high relative to the Company’s record. Net distribution additions 23 averaged $479.8 million a year from 2017 through 2025. The 2027 forecast 225 Response to OCC-798. OCC calculations. Exh. CLP-ADDITIONS-1 at 52. 227 Id. 228 Exh. CLP-ADDITIONS-1 at 54. 229 Exh. CLP-ADDITIONS-1 at 51–52. 226 Direct Testimony of Nikhil Balakumar Page 90
  2. Page 94 of 105

    1 exceeds every year in that period, and the 2028 forecast is about 11 percent above 2 the previous peak of $629.9 million in 2023 (Table 4). 3 Table 6: Net Distribution Plant Additions, Actual 2017–2025 and Company Forecast 2026–2028 ($ million) 230 Year 2017 2018 2019 2020 2021 2022 2023 2024 2025 2017–2025 average 2026 2027 2028 Additions 375.6 426.1 425.6 466.4 413.7 478.2 629.9 527.4 575.1 479.8 544.1 632.1 700.5 Basis Actual Actual Actual Actual Actual Actual Actual Actual Actual Actual Interim Forecast Forecast 4 5 Q92 Has the Company supported including these planned additions in rates? 6 A. No. PURA has consistently declined to set rates on forecasted plant that is not yet 7 in service and used and useful by the close of the evidentiary record in a given 8 single rate year case. In UI’s most recent electric rate case, it included only plant 9 found to be used and useful, explaining that “it is an impossibility to provide 10 sufficient evidence that a future plant addition is used and useful and that the 11 investment was prudent.”231 In the CNG and SCG rate case, it allowed only plant 12 completed and in service through the last supplemental filing before the record 13 closed, and found the companies’ reconciliation mechanism insufficient to protect 14 ratepayers.232 230 Exh. CLP-ADDITIONS-2 (2017–2025 net distribution plant in service additions); Exh. CLPADDITIONS-1 at 52 (2026–2028 annual forecasted capital plant additions). 231 Docket No. 22-08-08, Application of The United Illuminating Company to Amend Its Rate Schedules, Decision (Aug. 25, 2023). 232 Docket No. 23-11-02, Applications of Connecticut Natural Gas Corporation and The Southern Connecticut Gas Company to Amend Their Rate Schedules, Decision (2024). Direct Testimony of Nikhil Balakumar Page 91
  3. Page 95 of 105

    1 The Company’s request raises the same concerns. It seeks no prudence finding 2 now, its reconciliation would apply only downward and only to overall plant in 3 service,233 and much of its 2027 and all of its 2028 forecasts are tied to the TSP 4 and PBMRP, which OCC recommends PURA not approve.234 PURA should 5 therefore include in rate base only plant completed, in service and documented 6 through the Company’s final supplemental filing before the record closes, and 7 exclude all forecasted additions. My recommendations on plant will be finalized 8 based on that filing. 9 D. Conclusion 10 Q93 Please summarize your recommendations. 11 A. I recommend that PURA: 12 • Direct-buried cable: Disallow about $26.5 million of 2022–2023 replacement 13 costs above the 2019–2021 unit cost, net of demonstrated inflation, absent a 14 contemporaneous analysis supporting full replacement. 15 • Areas pending Company data: Require the Company to provide, before the record 16 closes, the information OCC is requesting on capitalized vegetation work, the 17 proactive direct-buried cable replacement program, capitalized storm restoration 18 from the 2018–2023 storms, AMR meter additions, and the measured benefits of 19 the resiliency programs. I will provide my recommendations on these additions in 20 surrebuttal testimony. 21 • Capacity additions: Require the Company to produce, before the record closes, 22 the contemporaneous evaluation of non-wires alternatives, the load forecast and 23 the authorization documents for each Peak Load/Capacity project placed in 24 service from 2023 through 2025 ($145.4 million), do not find a project prudent 233 234 Response to OCC-579. Exh. CLP-ADDITIONS-1 at 52–54. Direct Testimony of Nikhil Balakumar Page 92
  4. Page 96 of 105

    1 where the Company cannot make that showing, and disallow the cost above the 2 least-cost alternative where one was available. 3 • Resiliency additions: Require before-and-after storm performance data for the 4 resiliency programs, and weigh the absence of measured benefits in deciding 5 whether resiliency additions placed in service after 2020 were prudently incurred. 6 • Planned plant additions: Include in rate base only plant additions that are 7 completed, in service and documented as of the last supplemental filing 8 before the record closed, and exclude all forecasted plant. My current 9 estimate is that of the $847.8 million of interim period plant the Company 10 requested from January 2026 through June 2028 approximately $202.5 11 million will still be forecasted plant at the close of the record and therefore 12 should not be included in rate base, as well as the full $664.9 million 13 requested for the Rate Year. The final position will be based on the actual 14 amounts the Company documents and supported through the late-filing 15 exhibit date/close of record. 16 These recommendations do not deny the Company recovery of prudent 17 investment. They remove an amount the record shows was not justified, defer a 18 finding where the record does not yet contain the information needed, and they 19 give PURA the record it needs to evaluate the Company’s forward capital 20 requests, including the TSP. 21 VI. STORM COST RECOVERY 22 E. Purpose and Overview 23 Q94 What is the purpose of this portion of your testimony? 24 A. This portion of my testimony addresses the Company’s request to recover the 25 incremental costs of 14 storm events that occurred between January 2024 and 26 March 2025. I rely on the joint testimony of the Company’s Storm Panel, the Direct Testimony of Nikhil Balakumar Page 93
  5. Page 97 of 105

    1 exhibits that support it, and the Company’s responses to OCC’s interrogatories. I 2 also address the Company’s proposed storm-related programs to the extent they 3 relate to storm cost recovery. My testimony focuses on whether the Company’s 4 current storm cost recovery framework adequately protects customers from 5 excessive pre-staging, forecast risk, duplicative investments, or costs that are not 6 tied to actual major storm impacts. I also identify additional information PURA 7 may require to determine whether the requested costs were prudently incurred. 8 Q95 What is your understanding of the Company’s request? 9 A. The Company asks PURA to review approximately $157.3 million in incremental 10 expense for 14 weather events, each of which it states exceeded the $4 million 11 threshold for “catastrophic” storm recovery.235 The filing also includes costs 12 associated with “eight pre-staging events.”236 Approximately 68 percent of the 13 total cost was for external line and tree crews.237 As a result, the decision on how 14 many outside crews to bring onto the system before and during each storm is a 15 major driver of the overall request. 16 Q96 What standard does the Company say applies to these costs? 17 A. The Company understands that PURA asks whether the Company’s decision- 18 making process was in good faith and reasonable under the circumstances at the 19 time the costs were incurred.238 The Company also states that its Emergency 20 Response Plan (“ERP”) and Event Level Matrix (“ELM”) “do not prescribe a 21 single, fixed resource plan for each emergency event.”239 The event level, the 22 number of crews secured, and the timing of crew release are therefore judgment 23 decisions. The burden to demonstrate that each of those decisions was reasonable 235 Exh. CLP-STORM-1 at 8–9. Id. at 80. 237 Id. at 62, 81. 238 Exh. CLP-STORM-1 at 61. 239 Response to OCC-545 at 1. 236 Direct Testimony of Nikhil Balakumar Page 94
  6. Page 98 of 105

    1 rests with the Company, and that showing should be supported by the 2 contemporaneous record of each event. 3 Q97 What are your primary concerns regarding the Company’s storm costs? 4 A. Utilities must prepare for and respond to severe weather, and storm costs that 5 Eversource can demonstrate it prudently incurred should be recoverable, but for 6 several of the 14 events, the record does not currently provide enough support to 7 conclude that all of the requested costs were prudently incurred. My concern is 8 that the Company’s current approach can allow extraordinary recovery based 9 largely on the amount spent, without clearly showing whether the crews secured 10 in advance were reasonable in light of the storm impacts that actually occurred. 11 F. How the Events Are Classified 12 13 Q98 What is your concern with using a dollar threshold for extraordinary recovery? 14 A. A dollar threshold by itself can become circular. If a utility mobilizes a large 15 number of external crews before a storm, the related travel, lodging, and standby 16 costs can push the event above the recovery threshold even when the actual 17 reliability impacts are more limited. In that situation, customers may end up 18 bearing costs driven by conservative or excessive storm staffing, rather than 19 solely by the severity of the storm itself. 20 Q99 Why is that an affordability concern for customers? 21 A. Storm costs are significant and can vary widely from year to year. The Company 22 reports average storm costs of about $130 million annually,240 and this proceeding 23 seeks $157.3 million for 14 events over 15 months, with roughly two-thirds of the 24 total attributed to external crews.241 Under a dollar-based recovery threshold, 240 241 Exh. CLP-TSP-3 at 31. Exh. CLP-STORM-1 at 8–9, 62. Direct Testimony of Nikhil Balakumar Page 95
  7. Page 99 of 105

    1 staging more crews can increase both event cost and likelihood that the event 2 qualifies for extraordinary recovery, even if the forecasted damage does not 3 occur. This places much of the forecasting risk on customers. While the company 4 may argue that it adjusts crew levels as forecasts change, such adjustments do not 5 necessarily mean staffing levels are reasonable. Without a clear benchmark 6 linking the number of crews secured to forecasted damage, both initial and 7 revised staffing levels may be excessive. For the six events the Company 8 describes as less severe than forecast, the cost per trouble spot was roughly twice 9 that of the other eight events. Customers should bear this forecast risk only if the 10 Company demonstrates that its staffing, initial and revised, was proportionate to 11 the information available at each decision point 12 This is especially important because customers are also being asked to fund 13 programs that the Company justifies in part as improving the storm performance. 14 The Company describes its Targeted System Performance tier as one that 15 “[h]ardens the system and reduces storm costs,”242 states that hardening “reduces 16 the cost and duration of restoration,”243 and points to expanded distribution 17 automation, storm and outage analytics, and other technologies as supporting 18 future storm response.244 The Company has not quantified the expected storm- 19 cost reductions from these programs or explained how those savings will be 20 reflected in future storm recovery. Customers should not have to pay for ever- 21 increasing storm recovery while also paying for storm-mitigation 22 programs/investments without a clear way to measure whether those investments 23 are actually reducing storm performance and costs. 242 Exh. CLP-TSP-3 at 8. Exh. CLP-TSP-1 at 62. 244 Exh. CLP-STORM-1 at 77–80; Exh. CLP-TSP-3 at 129. 243 Direct Testimony of Nikhil Balakumar Page 96
  8. Page 100 of 105

    1 Q100 Is there an impact-based standard PURA could use instead? 2 Yes, and PURA already has two. Connecticut’s Major Storm criterion, established A. 3 in Docket No. 86-12-03, identifies a Major Storm when the number of locations 4 requiring restoration work in a day exceeds the 98.5th percentile of the 5 Company’s most recent four years of data.245 Additionally, IEEE Standard 1366 6 identifies a Major Event Day from the Company’s own five-year history of daily 7 outage duration. PURA has directed the Company to use both for reliability 8 reporting,246 and the Company relies on Major Event Days in this docket to 9 describe the purpose of its Targeted System Performance tier and to measure its 10 proposed performance incentives.247 Both tests measure what the storm did to the 11 system, not what the Company spent. 12 PURA should use these impact-based tests, coupled with a monetary threshold, to 13 decide which events qualify for extraordinary storm recovery, rather than relying 14 exclusively a monetary threshold. An event that does not qualify under both an 15 impact-based test and a monetary threshold may still have required some prudent 16 spending, but its costs should be treated as normal operating expense unless the 17 Company demonstrates why extraordinary recovery is warranted. 18 G. What the Company’s Own Data Show 19 Q101 What does the Company’s own explanation of its highest-cost storms show? 20 The Company identifies seven storms with a cost per event above its average of A. 21 $7,489.248 For six of those seven, the Company explains that the storm was 22 ultimately less severe than the forecast used to stage crews. Those six events are 23 MS24A, MS24B, MS24C, MS24D, MS24H and MS24K. The company describes 24 these events using statements such as “the damage was not as severe as 245 Decision, Docket No. 17-12-03RE08 (Aug. 31, 2022) at 36. Id. at 55 n.30. 247 Exh. CLP-TSP-1 at 17, 74, 83. 248 Exh. CLP-STORM-1 at 64. 246 Direct Testimony of Nikhil Balakumar Page 97
  9. Page 101 of 105

    1 anticipated” and “the actual impacts proved less severe than anticipated.”249 For 2 MS24D, the Company states that the cost “reflects the risk profile presented by 3 the forecasts and conditions leading up to the event, rather than the ultimate 4 severity of the weather that occurred.”250 The seventh storm, MS24G, was a fast- 5 moving thunderstorm with little advance warning, and the Company describes 6 widespread damage consistent with the higher cost.251 7 Together, these six events account for about 39 percent of the requested storm 8 costs but only about 22 percent of the trouble spots (5,650 of 25,550). The 9 average cost per trouble spot for these six events was roughly twice that of the 10 other eight events.252 In other words, a significant share of the requested costs 11 relates to storms where the actual impacts were lower than forecast. 12 Q102 What should PURA require in those circumstances? 13 PURA should require a forecast-to-actual reconciliation for each storm. The A. 14 reconciliation should show whether the crews staged were reasonable based on 15 data from previous storms and the information available at each decision point, 16 and should show how quickly the Company adjusted the plan once the actual 17 damage became known. 18 For each storm, and each point where the Company set or revised its resource 19 plan, the reconciliation should compare: 20 • 21 forecasted trouble spots and customer outages with actual trouble spots and customers interrupted; 22 • 23 the declared event level and planned crew levels with the crews actually on the system and the work available to them; 249 Id. at 64–74. Id. at 70. 251 Id. at 70–71. 252 Exh. CLP-STORM-IMT-2 at 9–22. 250 Direct Testimony of Nikhil Balakumar Page 98
  10. Page 102 of 105

    1 • the expected restoration duration with actual restoration time; and 2 • crew levels at each decision point with crew benchmark for the declared 3 event level and forecasted trouble spots. 4 The reconciliation should also distinguish the cost of crews that performed 5 restoration work from costs associated with crews that were not ultimately 6 needed, including pre-impact and standby time, travel, lodging, meals, and 7 minimum call-out payments. 8 Much of this information needed for this review already exists. The UConn 9 outage prediction model provides the Company with “a forecast range of 10 predicted trouble spots”;253 the Company’s storm summaries record the expected 11 and actual trouble spots and line resources for each event;254 and its contractor 12 terms specify a four-hour minimum payment for crews released early.255 If the 13 data provided indicates that the staffing was not prudent, then PURA should deny 14 the costs associated with the unjustified overspend on that storm. 15 H. Storm-Related Investments 16 Q103 17 Why should the Company’s storm-related programs be evaluated together with this request? 18 Because the Company relies on these same storm costs to support several A. 19 proposed investments. It asks customers to fund a Targeted System Performance 20 tier intended to “[h]arden system & reduce storm restoration costs,” along with 21 expanded vegetation management, a storm analytics platform, AMI and further 22 automation.256 Three connections are important: 23 • 24 The AMI analysis claims about $352 million in avoided storm costs over 20 years, based on “catastrophic” storms defined by the same $4 253 Exh. CLP-TSP-3 at 125. Exh. CLP-STORM-IMT-2 at 8–22. 255 Response to OCC-554 at 1. 256 Exh. CLP-TSP-3 at 7–8, 112, 122–129; Exh. CLP-AMI-3 at 65–69; Exh. CLP-STORM-1 at 77–79. 254 Direct Testimony of Nikhil Balakumar Page 99