Prefiled testimony
Witness: William Herchel and James Cerkanowicz
Files2
Cover Letter for Interconnection Customer Coalition Pre-Filed Testimony (Docket 26-05-10).pdf
PDF · 129 KB · 1 pageText searchable
Download Cover Letter for Interconnection Customer Coalition Pre-Filed Testimony (Docket 26-05-10).pdfRead the text of Cover Letter for Interconnection Customer Coalition Pre-Filed Testimony (Docket 26-05-10).pdf
ICC - Verogy Pre-Filed Testimony - Herchel Cerkanowicz - FINAL.pdf
PDF · 101 KB · 23 pagesText searchable
Download ICC - Verogy Pre-Filed Testimony - Herchel Cerkanowicz - FINAL.pdfRead the text of ICC - Verogy Pre-Filed Testimony - Herchel Cerkanowicz - FINAL.pdf
Page 13 of 23
Verogy Holdings, LLC Pre-Filed Testimony on behalf of ICC Docket No. 26-05-10 1 make this viable. A cost sharing model, initially directed under PURA Docket 22-06- 2 29RE01, was to be enacted on or about April 2025, but Eversource subsequently issued a 3 legal challenge to this, preventing this project from progressing. To date, this project 4 remains still stranded and will not be viable without adoption of a distribution upgrade 5 cost sharing model. 6 7 Deep River Landfill. Eversource’s Interconnection Agreements previously contained 8 cost constraints for another municipal landfill project proposed in Deep River in 2023. 9 Specifically, in Appendix G, which describes the upgrades needed and provides a more 10 granular accounting of costs, the relevant interconnection agreement stated, “Price is 11 based on Impact study with an accuracy of +/- 25% (If a Facility Study was performed 12 delete this note).” Verogy and Eversource agreed to be bound by the terms of that 13 agreement. 14 15 Both parties executed the agreement in July 2023, and full payment of the costs indicated 16 in the agreement ($151,273) were remitted by Verogy to Eversource. Site construction 17 by Verogy subsequently commenced in April 2024, with the goal of placing the project in 18 service by November 2024. 19 20 That changed when in May 2024, Eversource advised Verogy that additional work would 21 be required, and the additional work was not captured in the estimated costs contained in 22 the original agreement. Eversource unilaterally determined this work to be outside of the 23 up to +/- 25% variance indicated in the agreement. In June 2024, Eversource issued a Page 11Page 14 of 23
Verogy Holdings, LLC Pre-Filed Testimony on behalf of ICC Docket No. 26-05-10 1 unilateral Amendment to the interconnection agreement with a new total cost of 2 $206,368, an increase of $109,095 (72%) over the original estimate. When Verogy 3 raised the Appendix G language to Eversource, Eversource refused to be bound by its 4 own agreement. Facing liquidated damages at that point, Verogy was ultimately left with 5 a choice of three unpalatable options: either paying the increased costs, engaging in an 6 unpredictable and uncertain dispute resolution process, or abandoning the project 7 altogether. 8 9 Verogy understands that some estimated costs are subject to minor fluctuations. 10 Although Verogy would not consider 25% to be “minor,” it still understands that 11 fluctuations at this level are possible. However, when Eversource provides a cost 12 estimate, interconnection customers need to be able to rely on the durability of such 13 estimate. Similarly, if an interconnection customer agrees to pay the initial estimate, 14 Eversource has no incentive to order the needed equipment at that time, because it can 15 pass on any and all overages to the interconnection customer. 16 17 Even more troubling is Eversource’s changes to the estimation process and the 18 contractual protections associated with cost estimates. While past agreements have 19 indicated the +/- 25% accuracy of the cost estimates provided, more recent 20 interconnection agreements remove this requirement. It is critical to note that there are 21 zero consequences for when Eversource does not adhere to these timelines.5 This means 5 See Eversource Response to ICC-8. Page 12Page 15 of 23
Verogy Holdings, LLC Pre-Filed Testimony on behalf of ICC Docket No. 26-05-10 1 captive interconnection customers now lack any recourse to require Eversource to have 2 some “skin in the game” to attempt to provide accurate estimates. 3 4 Groton Landfill. In this case, Eversource failed to indicate that the replacement of 65 5 poles by Frontier/Verizon was not included in the $3.5 million scope of work that Verogy 6 paid to Eversource.6 Verogy discovered that its project required this additional pole work 7 from Frontier/Verizon only after receiving a call from Frontier indicating that an 8 engineering cost estimation fee needed to be paid to Frontier and that a subsequent 9 Frontier/Verizon invoice would be Verogy’s responsibility. After several months of 10 direct correspondence with Frontier/Verizon, Verogy ultimately received an invoice of 11 almost $325,000. This cost was not factored into project economics, and failure to do so 12 will likely delay the project’s In-Service Date because of the time required to complete 13 the previously unknown replacement work before Eversource’s work can begin. 14 Importantly, Eversource as a Single Pole Administrator is the only party with insight into 15 whether other pole owners are implicated in a given project.7 16 C. Interconnection Customers Are Not Allowed to Engage in Self-Help 17 18 Q. Can Eversource Connecticut interconnection customers reduce costs by sourcing equipment or performing work themselves? 19 A. Generally, no. For example, recent changes in Eversource policy require a Real-Time 20 Automated Controller (“RTAC”) to be installed at each project. Eversource also began 21 charging for this equipment without explanation or transparency as to its purpose, such as 22 whether it is required for monitoring or reporting to ISO-NE. This change was mandated 6 Verogy is currently working with PURA Office of Education, Outreach and Enforcement (“EOE”) staff to mediate this dispute, and provides it here for illustrative purposes only. 7 See, e.g., Response to NECTA-8. Page 13Page 16 of 23
Verogy Holdings, LLC Pre-Filed Testimony on behalf of ICC Docket No. 26-05-10 1 without explanation or recourse. In reviewing recent final project cost accountings, 2 Verogy noted that the RTAC has been billed at a unit cost of approximately $75,000. 3 This is well in excess of what Verogy could pay to source similar equipment itself, which 4 it believes is approximately $15,000 per unit. 5 Q. Has Verogy investigated options to perform interconnection work at a lower cost? 6 A. Yes. Verogy attempted to qualify as an Eversource-vetted electric contractor in order to 7 save costs and to be pre-authorized to perform additional electrical work, including 8 reconductoring, three-phase extensions, equipment replacement, reclosers, regulators, 9 cutouts, pole installations, and site work. Despite repeated attempts to apply for this 10 program, Verogy was administratively prevented from doing so, and was discouraged by 11 Eversource to renew its attempt to qualify. 12 Q. Do other jurisdictions allow interconnection customers to engage in self-help? 13 A. Yes. Under ISO-NE standard Interconnection Procedures (Schedules 22, 23, and 25 of 14 the Open Access Transmission Tariff), if the Interconnecting Transmission Owner (i.e., 15 the utility) cannot meet the milestone dates for constructing the required point of 16 interconnection, substation or network upgrades, the Generator (i.e., the interconnection 17 customer) can invoke self-help rights, known as the Option to Build the Network 18 Upgrades in certain circumstances.8 If a generator utilizes self-help to build or upgrade a 19 substation, they must strictly follow the Transmission Cost Allocation rules governed by 20 ISO-NE. 8 See, e.g., Schedule 22, Section 5.2, available at https://www.iso-ne.com/staticassets/documents/regulatory/tariff/sect_2/sch22/sch_22_lgip.pdf. Page 14Page 17 of 23
Verogy Holdings, LLC Pre-Filed Testimony on behalf of ICC Docket No. 26-05-10 1 IV. Why This Is a Rate Case Customer Service Issue 2 Q. Why are these interconnection issues relevant to this rate case? 3 A. Eversource’s failure to meet its own self-imposed rules outlined in its policy documents 4 demonstrates a lack of appropriate Company resources dedicated to this function and 5 shows imprudent management. Eversource appears to lack the internal controls and 6 structure necessary to achieve its existing milestones, and its failure to achieve those 7 milestones carries no consequences. These actions have direct and profound impacts on 8 interconnection customers, many of whom are Connecticut businesses and by extension 9 ratepayers. 10 11 Moreover, by introducing such large uncertainties in the costs of interconnection, project 12 developers are forced to place significant contingencies on interconnection costs. Many 13 of Connecticut’s renewable energy projects (including most of the projects Verogy has 14 developed in Connecticut) are the result of a competitive procurement process that is 15 ultimately paid for by the ratepayer. Because the developers need to factor in an outsized 16 interconnection cost when submitting bids for various programs, it is the Connecticut 17 ratepayer that ultimately pays for Eversource’s failure to adhere to its own rules and 18 PURA’s regulations. 19 Q. Are these issues common across Connecticut utilities? 20 A. No. In our experience, these issues arise primarily in Eversource’s Connecticut service 21 territory. By comparison, Verogy’s experience with The United Illuminating Company 22 (“UI”) and Central Maine Power Company (“CMP”) has been much more predictable, 23 transparent and collaborative. For instance, CMP communicates effectively the Page 15Page 18 of 23
Verogy Holdings, LLC Pre-Filed Testimony on behalf of ICC Docket No. 26-05-10 1 timeframes required to complete studies and typically delivers the results in the 2 timeframe indicated in the study agreement. It is also standard practice by CMP to hold a 3 meeting at the conclusion of the study to review the study results, discuss the estimated 4 costs for new service and upgrade work, answer questions, and ensure both parties are on 5 the same page, prior to the issuance of an Interconnection Agreement. 6 7 In contrast, Eversource typically goes well beyond the timeframes indicated in 8 completing the studies, does not give notice that results will be delayed, and the 9 developer must send repeated emails just to get updates on new delivery dates that 10 continue to slip without explanation. Recent PURA-driven consensus proposals were 11 adopted and included in the most recent revision to the Interconnection Guidelines, 12 including the request to hold a meeting after the study is completed and prior to the 13 issuance of the Interconnection Agreement, like the CMP model. However, in Verogy’s 14 experience to date, not a single such meeting has occurred. Eversource continues to 15 provide study results and costs without review or explanation and issues Interconnection 16 Agreements with terms, such as payment schedules, that are not in line with the finance 17 and development needs of developers. Within the bounds of the same CT 18 interconnection guidelines, UI has shown a willingness to correspond regularly with 19 developers during the study process, provide updates, and meet when either necessary or 20 helpful. By contrast, Eversource prefers to engage in discussions with developer only 21 when it suits their needs, and simply issues study results and resulting Interconnection 22 Agreements with little to no prior discussion. Page 16Page 19 of 23
Verogy Holdings, LLC Pre-Filed Testimony on behalf of ICC Docket No. 26-05-10 1 2 Q. Does Eversource have adequate staffing to respond to today’s interconnection queue? 3 A. No. Eversource DER Customer Care has typically relied on three “Senior Account 4 Executives” to be single points of contact with developers for all non-residential 5 interconnection applications throughout the interconnection and study process. The level 6 of responsiveness, training, work ethic, and tenure within the group varies greatly among 7 those individuals. Even when copied at times on repeated email messages to these staff 8 members that have gone unanswered, management of the group has rarely stepped in to 9 assist the developer or seemingly hold staff accountable to deadlines or showing the 10 courtesy of timely responses. 11 12 After developers remit payments indicated in the interconnection agreement, the project 13 is typically transferred to another staff member to be the single point of contact through 14 the process of construction and successful interconnection to the grid. While that 15 individual is typically advocating for the developer when coordinating with other 16 departments within Eversource, there are limitations to their ability to get other 17 departments to adhere to deadlines, schedules, and provide other information critical to 18 the final parts of the interconnection process. Some of this may be hampered by that 19 individual’s status as a part-time contract worker. Previously, this position was staffed 20 by a direct employee with a full 40-hour-a-week commitment to this role. It has appeared 21 at times that contract employees lack incentive or motivation to respond or collaborate 22 with interconnection customers. The plan to increase staffing to up to 11 full-time 23 employees as described in Eversource’s responses to ICC-6 and ICC-9 could be a good 24 step, but only if the employees are appropriately trained and resourced. Page 17Page 20 of 23
Verogy Holdings, LLC Pre-Filed Testimony on behalf of ICC Docket No. 26-05-10 1 V. Why This Is an Eversource Ratepayer Problem 2 Q. How do these issues affect Eversource ratepayers? 3 A. As alluded to above, ratepayers are harmed in several ways. First, cost overruns make 4 ratepayer-funded programs designed to meet the State’s renewable energy mandates more 5 expensive. Second, inaccurate project cost estimates kill projects in later stages, and in 6 doing so waste the collective time and money of developers, Eversource, the Connecticut 7 Siting Council, and the Authority. Third, Eversource has no incentive to get it right or to 8 be efficient at the lowest cost in this space. The cost of the installation directly translates 9 to the cost of the kWh. Performance-based ratemaking may eventually help over time, 10 but interconnection customers cannot wait. 11 Q. Is the existing dispute resolution process adequate? 12 A. No. The existing dispute resolution process is imperfect. Generally, the current process 13 requires parties to attempt to informally resolve the dispute, then to have PURA EOE in 14 its role as Interconnection Ombudsperson attempt to “mutually resolve” the dispute.9 15 The parties may also use a third-party mediator or bring a formal complaint at PURA. 16 While EOE staff can act as mediators for some matters, they do not have the necessary 17 resources or support to address the universe of pending complaints that relate to 18 contractual disagreements or technical disputes. In addition, they only have the power to 19 mutually resolve issues. Simply put, some issues cannot be mediated and instead require 20 adjudication. In our experience, EOE has also declined to mediate matters where they 21 felt they did not have the requisite knowledge or expertise – in some cases, technical 22 engineering expertise – to effectively address disputes. Moreover, there is no 9 See ICC-1, Attachment 1, Section 3.2. Page 18Page 21 of 23
Verogy Holdings, LLC Pre-Filed Testimony on behalf of ICC Docket No. 26-05-10 1 requirement that the Parties working through the dispute resolution procedures in the 2 guidelines be bound by any resolution achieved in the process.10 3 VI. Necessary Changes 4 Q. What changes do you recommend? 5 A. First and foremost, rapid, binding dispute resolution procedures are needed. Multiple 6 examples exist for the Authority’s consideration and are used with great success in other 7 jurisdictions.11 If the Authority ultimately directs EOE or the Sustainable Energy 8 Advantage NRES/RRES/SCEF Ombudsperson to step in to facilitate these disputes, they 9 need to have the technical and legal expertise to fully adjudicate the issues, and 10 Eversource must agree – or be ordered by the Authority – to be bound by their 11 determination in order for the process to have any chance at success. 12 13 Second, interconnection customers need to be able to rely on Eversource’s timelines and 14 estimates. We recommend that the Authority: 15 • Standardize Eversource interconnection agreement timelines and institute 16 consequences for failure to meaningfully achieve contractual milestones. In doing 17 so, the Authority should avoid rules that merely incentivize Eversource to “check 18 the box” without substantive compliance; 19 • 20 Require that cost estimates be real and accurate within defined percentages, as was the case as recently as 2023, and that those defined percentages be binding; 10 See, for example, ISO New England Open Access Transmission Tariff, Schedule 22, Large Generator Interconnection Procedures, Section 13.5.3, available at https://www.iso-ne.com/staticassets/documents/regulatory/tariff/sect_2/sch22/sch_22_lgip.pdf (“The decision of the arbitrator(s) shall be final and binding upon the Parties…”). 11 See, e.g., Maine https://www.maine.gov/mpuc/regulated-utilities/telecom/approved-companies/rapid-response; see also California https://docs.cpuc.ca.gov/PublishedDocs/Published/G000/M197/K421/197421608.pdf. Page 19Page 22 of 23
Verogy Holdings, LLC 1 • 2 Pre-Filed Testimony on behalf of ICC Docket No. 26-05-10 Institute a meaningful review of Eversource’s interconnection customer disputes; and 3 • Recognize that time is of the essence. 4 5 Last, in times of dynamic costs, interconnection customers should be able to self-help in a 6 variety of ways. Like in the telecommunications space, Eversource should facilitate a list 7 of approved contractors and equipment that can be vetted and pre-approved if Eversource 8 fails to meet its own milestones or cannot timely secure necessary equipment to facilitate 9 its own interconnection agreement. 10 Q. Does the Authority have the power to order these changes in this proceeding? 11 A. Yes. The Authority, through its broad oversight of utility plant and prudency, can order 12 changes to utility customer service practices. See Conn. Gen. Stat. §§ 16-11 and 16-19 as 13 examples. In other recent electric rate cases, such as Dockets 22-08-08 and 24-10-04, 14 PURA has ordered changes to utility customer service procedures and has recommended 15 changes and even penalties for failures to adhere to PURA orders and regulations. In 16 those proceedings the Authority audited and monitored Company-customer interactions 17 for failure to adhere to policies and regulations. In the same rate case proceedings, the 18 Authority has also vetted and ordered changes to the cost sharing policies of electric 19 utilities and other third parties, such as third party attachers to utility distribution poles. 20 PURA can therefore also do the same here. 21 VII. Conclusion 22 Q. Please summarize your testimony. 23 A. Based on the foregoing, Verogy respectfully submits that: Page 20
As listed on the current system
Prefiled testimony: 10/21/2026 - Sponsor: TBD / Witness: William Herchel and James Cerkanowicz [26-05-10]