Prefiled testimony
Witness: William Herchel and James Cerkanowicz
Files2
Cover Letter for Interconnection Customer Coalition Pre-Filed Testimony (Docket 26-05-10).pdf
PDF · 129 KB · 1 pageText searchable
Download Cover Letter for Interconnection Customer Coalition Pre-Filed Testimony (Docket 26-05-10).pdfRead the text of Cover Letter for Interconnection Customer Coalition Pre-Filed Testimony (Docket 26-05-10).pdf
ICC - Verogy Pre-Filed Testimony - Herchel Cerkanowicz - FINAL.pdf
PDF · 101 KB · 23 pagesText searchable
Download ICC - Verogy Pre-Filed Testimony - Herchel Cerkanowicz - FINAL.pdfRead the text of ICC - Verogy Pre-Filed Testimony - Herchel Cerkanowicz - FINAL.pdf
Page 7 of 23
Verogy Holdings, LLC Pre-Filed Testimony on behalf of ICC Docket No. 26-05-10 1 Q. How many Connecticut employees does Verogy have? 2 A. Verogy currently employs approximately fifty people in Connecticut, in positions 3 including project developers, interconnection and site design engineers, project managers, 4 construction managers, asset managers, and finance and administrative staff. 5 III. Eversource Interconnection Issues 6 A. Eversource Does Not Meet Its Own Deadlines 7 Q. What deadlines control the Connecticut Interconnection process? 8 A. Connecticut interconnection is generally administered under guidelines that at one time 9 were formally reviewed and approved by PURA or its predecessor, the DPUC. 10 Eversource cites to a variety of dockets in its response to ICC-2 where it says the 11 Interconnection Guidelines were filed, but it is unclear to us whether PURA has fully 12 reviewed and approved the Interconnection Guidelines since 2003. Moreover, it is 13 further unclear whether PURA ever stepped in to review and approve Eversource’s 14 Standard Fast Track and Study Process Generator Interconnection Agreement (“Standard 15 IA”). Other states use tariffs1 or form interconnection agreements that impose automatic 16 penalties for utility timeline misses.2 17 18 The Connecticut Guidelines require Eversource “to make reasonable efforts to meet the 19 stated timeframes unless the parties agree to a different schedule.”3 The Federal Energy 20 Regulatory Commission (“FERC”) recently eliminated the reasonable efforts standard in 1 See California PUC, Electric Rule 21: Generating Facility Interconnections, available at https://www.cpuc.ca.gov/rule21/. 2 See, e.g., Maine PUC, Docket No,. 2013-00531, Order Adopting Standard Form Interconnection Agreement, available at https://www.maine.gov/mpuc/sites/maine.gov.mpuc/files/inline-files/2013-531-ODR-5-28-14.pdf; see also under FERC Order No. 2023. 3 See Response to ICC-5. Page 5Page 8 of 23
Verogy Holdings, LLC Pre-Filed Testimony on behalf of ICC Docket No. 26-05-10 1 Order 2023, and in so doing acknowledged that “there were little to no consequences if 2 transmission providers missed deadlines.”4 FERC’s final rule imposes firm deadlines and 3 penalties if ISO New England (“ISO-NE”) or transmission providers fail to complete 4 interconnection studies on time (with certain limited exceptions). No similar penalties 5 can be imposed on Eversource for its interconnection failures. 6 7 Q. How do the Guidelines affect timelines and deadlines agreed to between Eversource and the interconnection customer? 8 A. Importantly, the Guidelines only tell part of the story, because Eversource’s Standard IA 9 is the ultimate contract between parties. The Standard IA is replete with deadlines and 10 protocols but lacks meaningful enforcement or consequences for Eversource’s failure to 11 communicate or act. By way of example, Section 11.0 of this standard interconnection 12 study agreement provides for a true-up of study costs within thirty business days of 13 completion of the study. In practice, these true-ups never occur within thirty business 14 days, which renders the provision meaningless. Verogy has experienced this on multiple 15 projects. In our experience, most study true ups are left until the project’s final 16 accounting stage. 17 18 Q. Does Eversource ever miss other deadlines contained in its own interconnection documents? 19 A. Yes. In our experience, Eversource routinely fails to meet deadlines that it established in 20 its own standard agreements. Pursuant to Section 5.3.2 of the Standard IA, within thirty 21 (30) days following the date on which the Facility is first connected to the electric power 22 system, Eversource must provide a final accounting report detailing any underpayment or 23 overpayment made by the Generator with respect to the Initial Payment owed under the 4 https://www.ferc.gov/explainer-interconnection-final-rule-2023-A Page 6Page 9 of 23
Verogy Holdings, LLC Pre-Filed Testimony on behalf of ICC Docket No. 26-05-10 1 contract. As of the date of this filing, Verogy has spent tens of thousands of dollars using 2 outside counsel to address issues with these final project true ups, some as many as five 3 years after the projects came online. We can provide several relevant examples of this: 4 5 Verogy also only recently (within the last month or two) came to an agreement with 6 Eversource on the true-up for three landfill projects, located in Middletown, Montville, & 7 Deep River. All three projects received PTO on November 13, 2024. Verogy and 8 Eversource were able to settle the project final accountings almost two years after an 9 agreement was reached, well beyond the 30 business day true up period. 10 11 Lastly, Verogy only recently came to an agreement with Eversource on combining the 12 true-up for four separate projects which had respective PTO dates of September 24, 2025, 13 September 30, 2025, December 5, 2025 and December 30, 2025. The delay resulted in 14 part because Eversource insisted that no single true-up would be processed until an 15 agreement was reached regarding all other prior projects submitted by Verogy. Like 16 other developers, Verogy sometimes sells its projects to other owner/operators. 17 Eversource’s arbitrary insistence on combining true-ups had no basis in the Guidelines of 18 the Standard IA and ignored that while all projects were submitted by Verogy, these 19 projects had in some cases been sold as part of portfolio transactions to other entities. 20 21 By failing to deliver final accountings of interconnection costs within the required thirty 22 business days, Eversource demonstrates that it is blithely willing to ignore its own rules 23 whenever it suits Eversource, creates unmitigated uncertainty as to final project costs, and Page 7Page 10 of 23
Verogy Holdings, LLC Pre-Filed Testimony on behalf of ICC Docket No. 26-05-10 1 in some cases effectively prohibits developers like Verogy from selling projects to other 2 owners. However, while this is a clear example, this situation occurs at the very end of 3 the process, when little can be done to rectify the issue. Moreover, this issue is 4 illustrative of systemic problems for project developers in Eversource Connecticut 5 service territory. 6 Q. How does Eversource communicate about construction timelines for your projects? 7 A. Section 5.10 of Eversource’s standard Interconnection Agreement addresses construction 8 timing. However, in our experience, Eversource never actually provides its 9 interconnection customers with a construction timeline that Eversource agrees to meet. 10 Instead, Eversource indicates only how far in advance of the interconnection customer’s 11 desired In-Service Date full payment must be made. Interconnection customers are 12 therefore required to pay in full without any commitment from Eversource as to when its 13 work will be completed. 14 15 In addition, the failure to provide and adhere to a construction timeline causes delays, 16 miscommunication and makes it very difficult to predict when a project will actually be 17 able to generate power. This uncertainty creates trickle down effects into project 18 economics, including the ability of projects to access federal tax credits, developers’ 19 ability to staff project construction teams, and ultimately increases project costs. 20 B. Eversource’s Cost Estimates Have No Certainty 21 Q. Are Eversource’s interconnection cost estimates reliable? 22 A. No. While interconnection customers are working within a dynamic industry to estimate 23 costs after significant changes at the federal level, Eversource is charged with estimating Page 8Page 11 of 23
Verogy Holdings, LLC Pre-Filed Testimony on behalf of ICC Docket No. 26-05-10 1 only its own costs, which can be distilled at their essence to parts and labor. Eversource’s 2 cost estimates provided under the Standard IA and study process are not subject to caps 3 or independent review, are often changed unilaterally by Eversource, and as a result 4 provide no meaningful certainty. This makes it extremely difficult to finance and 5 develop projects in Eversource Connecticut territory. Prior versions of Eversource 6 Interconnection Agreements capped changes in Eversource cost estimates to within 7 certain percentage ranges at certain points in the development timeline, but even this low 8 bar has been eliminated from the Standard IA. 9 Q. Please provide examples. 10 A. Here are three recent examples that illustrate the lack of prudent management of the 11 Eversource interconnection process: 12 13 Windham Landfill. The Town of Windham issued a Request for Proposal to permit and 14 develop a solar array on their closed and capped landfill. Solar is one of the few post- 15 closure uses for such a site that would allow a town to obtain additional value for a 16 property that is otherwise undevelopable. Landfills are also a preferred location to site 17 solar projects from a land use perspective. The town’s consultant directed all 18 applications to include an estimated interconnection cost of $1 million dollars, which it 19 determined would be a reasonable amount for the site and the desired system size that 20 could be constructed. Verogy’s proposal for a 0.975 MW system was ultimately selected 21 by the town, and an interconnection application was subsequently submitted to 22 Eversource. Page 9Page 12 of 23
Verogy Holdings, LLC Pre-Filed Testimony on behalf of ICC Docket No. 26-05-10 1 After receiving the application on August 1, 2024, Eversource advised that in addition to 2 new service (which at that time typically cost under $500,000), this project would trigger 3 the need for two substation transformers to be replaced at a cost of approximately $4 4 million each, or approximately $8.5 million as an initial estimated upgrade cost. Due to 5 the uncertainty of the viability of this interconnection, Eversource recommended Verogy 6 proceed with a $7,500 Feasibility Study Agreement for the purpose of providing a more 7 detailed estimate of the cost for all interconnection requirements. Verogy paid for and 8 signed the study agreement on September 25, 2024, which required the study to be 9 complete within 30 business days. 10 11 After the 30-business day mark passed, Verogy inquired on the status of the study. 12 Eversource did not respond until two months later, in December 2024, when Eversource 13 explained via email that the estimate would now exceed $18 million. Two days after that 14 estimate, Verogy received the official Feasibility Study results that indicated costs of 15 approximately $26 million. To date, Eversource has never provided an explanation as to 16 how its initial estimate of $8.5 million could be so far removed from the subsequent $18 17 million estimate or how two days later this became $26 million. 18 19 As one can imagine, an upgrade cost of $26 million dollars cannot be borne by the 20 economics of a project that is just under 1 MW AC. This result summarily terminated the 21 viability of this project. Verogy did subsequently inquire several times as to the 22 possibility of this project utilizing a proposed distribution upgrade cost sharing model 23 that would cap this project’s responsibility for those upgrades at a number that would Page 10Page 13 of 23
Verogy Holdings, LLC Pre-Filed Testimony on behalf of ICC Docket No. 26-05-10 1 make this viable. A cost sharing model, initially directed under PURA Docket 22-06- 2 29RE01, was to be enacted on or about April 2025, but Eversource subsequently issued a 3 legal challenge to this, preventing this project from progressing. To date, this project 4 remains still stranded and will not be viable without adoption of a distribution upgrade 5 cost sharing model. 6 7 Deep River Landfill. Eversource’s Interconnection Agreements previously contained 8 cost constraints for another municipal landfill project proposed in Deep River in 2023. 9 Specifically, in Appendix G, which describes the upgrades needed and provides a more 10 granular accounting of costs, the relevant interconnection agreement stated, “Price is 11 based on Impact study with an accuracy of +/- 25% (If a Facility Study was performed 12 delete this note).” Verogy and Eversource agreed to be bound by the terms of that 13 agreement. 14 15 Both parties executed the agreement in July 2023, and full payment of the costs indicated 16 in the agreement ($151,273) were remitted by Verogy to Eversource. Site construction 17 by Verogy subsequently commenced in April 2024, with the goal of placing the project in 18 service by November 2024. 19 20 That changed when in May 2024, Eversource advised Verogy that additional work would 21 be required, and the additional work was not captured in the estimated costs contained in 22 the original agreement. Eversource unilaterally determined this work to be outside of the 23 up to +/- 25% variance indicated in the agreement. In June 2024, Eversource issued a Page 11Page 14 of 23
Verogy Holdings, LLC Pre-Filed Testimony on behalf of ICC Docket No. 26-05-10 1 unilateral Amendment to the interconnection agreement with a new total cost of 2 $206,368, an increase of $109,095 (72%) over the original estimate. When Verogy 3 raised the Appendix G language to Eversource, Eversource refused to be bound by its 4 own agreement. Facing liquidated damages at that point, Verogy was ultimately left with 5 a choice of three unpalatable options: either paying the increased costs, engaging in an 6 unpredictable and uncertain dispute resolution process, or abandoning the project 7 altogether. 8 9 Verogy understands that some estimated costs are subject to minor fluctuations. 10 Although Verogy would not consider 25% to be “minor,” it still understands that 11 fluctuations at this level are possible. However, when Eversource provides a cost 12 estimate, interconnection customers need to be able to rely on the durability of such 13 estimate. Similarly, if an interconnection customer agrees to pay the initial estimate, 14 Eversource has no incentive to order the needed equipment at that time, because it can 15 pass on any and all overages to the interconnection customer. 16 17 Even more troubling is Eversource’s changes to the estimation process and the 18 contractual protections associated with cost estimates. While past agreements have 19 indicated the +/- 25% accuracy of the cost estimates provided, more recent 20 interconnection agreements remove this requirement. It is critical to note that there are 21 zero consequences for when Eversource does not adhere to these timelines.5 This means 5 See Eversource Response to ICC-8. Page 12Page 15 of 23
Verogy Holdings, LLC Pre-Filed Testimony on behalf of ICC Docket No. 26-05-10 1 captive interconnection customers now lack any recourse to require Eversource to have 2 some “skin in the game” to attempt to provide accurate estimates. 3 4 Groton Landfill. In this case, Eversource failed to indicate that the replacement of 65 5 poles by Frontier/Verizon was not included in the $3.5 million scope of work that Verogy 6 paid to Eversource.6 Verogy discovered that its project required this additional pole work 7 from Frontier/Verizon only after receiving a call from Frontier indicating that an 8 engineering cost estimation fee needed to be paid to Frontier and that a subsequent 9 Frontier/Verizon invoice would be Verogy’s responsibility. After several months of 10 direct correspondence with Frontier/Verizon, Verogy ultimately received an invoice of 11 almost $325,000. This cost was not factored into project economics, and failure to do so 12 will likely delay the project’s In-Service Date because of the time required to complete 13 the previously unknown replacement work before Eversource’s work can begin. 14 Importantly, Eversource as a Single Pole Administrator is the only party with insight into 15 whether other pole owners are implicated in a given project.7 16 C. Interconnection Customers Are Not Allowed to Engage in Self-Help 17 18 Q. Can Eversource Connecticut interconnection customers reduce costs by sourcing equipment or performing work themselves? 19 A. Generally, no. For example, recent changes in Eversource policy require a Real-Time 20 Automated Controller (“RTAC”) to be installed at each project. Eversource also began 21 charging for this equipment without explanation or transparency as to its purpose, such as 22 whether it is required for monitoring or reporting to ISO-NE. This change was mandated 6 Verogy is currently working with PURA Office of Education, Outreach and Enforcement (“EOE”) staff to mediate this dispute, and provides it here for illustrative purposes only. 7 See, e.g., Response to NECTA-8. Page 13Page 16 of 23
Verogy Holdings, LLC Pre-Filed Testimony on behalf of ICC Docket No. 26-05-10 1 without explanation or recourse. In reviewing recent final project cost accountings, 2 Verogy noted that the RTAC has been billed at a unit cost of approximately $75,000. 3 This is well in excess of what Verogy could pay to source similar equipment itself, which 4 it believes is approximately $15,000 per unit. 5 Q. Has Verogy investigated options to perform interconnection work at a lower cost? 6 A. Yes. Verogy attempted to qualify as an Eversource-vetted electric contractor in order to 7 save costs and to be pre-authorized to perform additional electrical work, including 8 reconductoring, three-phase extensions, equipment replacement, reclosers, regulators, 9 cutouts, pole installations, and site work. Despite repeated attempts to apply for this 10 program, Verogy was administratively prevented from doing so, and was discouraged by 11 Eversource to renew its attempt to qualify. 12 Q. Do other jurisdictions allow interconnection customers to engage in self-help? 13 A. Yes. Under ISO-NE standard Interconnection Procedures (Schedules 22, 23, and 25 of 14 the Open Access Transmission Tariff), if the Interconnecting Transmission Owner (i.e., 15 the utility) cannot meet the milestone dates for constructing the required point of 16 interconnection, substation or network upgrades, the Generator (i.e., the interconnection 17 customer) can invoke self-help rights, known as the Option to Build the Network 18 Upgrades in certain circumstances.8 If a generator utilizes self-help to build or upgrade a 19 substation, they must strictly follow the Transmission Cost Allocation rules governed by 20 ISO-NE. 8 See, e.g., Schedule 22, Section 5.2, available at https://www.iso-ne.com/staticassets/documents/regulatory/tariff/sect_2/sch22/sch_22_lgip.pdf. Page 14
As listed on the current system
Prefiled testimony: 10/21/2026 - Sponsor: TBD / Witness: William Herchel and James Cerkanowicz [26-05-10]