Prefiled testimony
Witness: BRENDAN J. O’BRIEN AND GARRETT J. MURRAY
Files2
Docket No. 26-05-10 CLP Rebuttals Filing Letter (11.18.26).pdf
PDF · 152 KB · 3 pagesText searchable
Download Docket No. 26-05-10 CLP Rebuttals Filing Letter (11.18.26).pdfRead the text of Docket No. 26-05-10 CLP Rebuttals Filing Letter (11.18.26).pdf
Exhibit CLP-REVREQ-REBUTTAL-1.pdf
PDF · 644 KB · 96 pagesText searchable
Download Exhibit CLP-REVREQ-REBUTTAL-1.pdfRead the text of Exhibit CLP-REVREQ-REBUTTAL-1.pdf
Page 11 of 96
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-REVREQ-REBUTTAL-1 November 18, 2026 Page 8 of 93 1 The Company’s actual 2025 test year rate base, excluding storms, was approximately 2 $6.198 billion. 7 Thus, Mr. Defever’s proposed rate base for a rate year ending 30 3 months after the test year is approximately $515 million, or 8 percent, below the 4 Company’s actual 2025 rate base. 5 This result is particularly difficult to reconcile with the individual components of Mr. 6 Defever’s calculation. Specifically, Mr. Defever increases accumulated depreciation 7 by approximately $254.9 million, or 16 percent, and accumulated deferred income 8 taxes (“ADIT”) by approximately $207.4 million, or 17 percent, relative to the actual 9 2025 test year balances. Both accumulated depreciation and ADIT are deductions from 10 rate base that are principally driven by the underlying investment in utility plant. As 11 additional utility plant is placed in service, accumulated depreciation increases as those 12 assets are depreciated, while the ADIT liability increases as accelerated tax 13 depreciation recognized under MACRS typically exceeds straight-line book 14 depreciation recognized under the generally accepted accounting principles (“GAAP”). 15 What is unusual about Mr. Defever’s calculation is that these substantial increases in 16 accumulated depreciation and ADIT are not accompanied by a corresponding increase 17 in utility plant in-service. To the contrary, his calculation reflects utility plant in- 18 service that is approximately $44.1 million, or 0.5 percent, below the Company’s actual 19 2025 test year balance. In other words, the OCC’s rate base calculation appears to 20 assume substantial growth in two rate base deductions that are primarily generated by 7 Exhibit CLP-REVREQ-2, Schedule B-1.0, row 36, column (1) less Schedule B-6.2, rows 52, column (B) and 53 column (B).Page 12 of 96
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-REVREQ-REBUTTAL-1 November 18, 2026 Page 9 of 93 1 in-service plant additions, while simultaneously assuming that the underlying plant 2 balance should be reduced relative to actual levels, and those levels proposed by the 3 Company in this proceeding. 4 This inconsistency becomes even more pronounced when Mr. Defever’s calculation is 5 compared with the testimony of OCC witness Nikhil Balakumar concerning interim- 6 period capital additions. Mr. Balakumar recommends the inclusion of capital additions 7 in rate base that are “completed, in service and documented as of the last supplemental 8 filing before the record closed.” 8 Based on his current estimate, approximately $645.3 9 million of the Company’s requested $847.8 million of interim-period plant additions 10 would be included in utility plant in-service at the close of the record. 9 11 accounting for Mr. Balakumar’s proposed disallowance of approximately $26.5 million 12 associated with direct-buried cable projects, 10 his testimony actually supports a 13 significant increase to the actual 2025 test year utility plant in-service balance. 11 Thus, 14 based on the Company’s understanding of the two witnesses testimonies there appears 15 to be a substantial and material difference between Mr. Defever’s revenue requirements 16 calculation and Mr. Balakumar’s testimony supporting capital additions. After 8 Balakumar Testimony at 93. 9 Balakumar Testimony at 93. 10 Balakumar Testimony at 92. 11 Mr. Balakumar does highlight potential disallowances of Peak Load / Capacity projects totaling $145.4 million placed in service between 2023 and 2025, which in his opinion if certain non-wires alternative documentation is not provided should not be approved and PURA should “disallow the cost above the least-cost alternative, where one was available.” Balakumar Testimony at 92.Page 13 of 96
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-REVREQ-REBUTTAL-1 November 18, 2026 Page 10 of 93 1 Accordingly, the OCC’s proposed rate base appear to be internally inconsistent. Said 2 simply, the Company is not able to reconcile a rate base calculation that simultaneously 3 (1) reduces utility plant in-service below the actual 2025 test year balance, (2) 4 substantially increases accumulated depreciation and ADIT associated with that plant, 5 and (3) is accompanied by separate OCC testimony that supports a net increase in utility 6 plant in-service through the close of the evidentiary record. These inconsistencies raise 7 fundamental concerns regarding the mathematical accuracy and conceptual basis for 8 the OCC’s proposed $1.151 billion reduction to the Company’s average rate base for 9 the rate year. The Company addresses the OCC’s proposed adjustments to each 10 individual rate base component in greater detail below. A. Materials and Supplies 11 12 Q. What is the Company’s request for materials and supplies in rate base? 13 A. The Company computed a test year five-quarter average (Q4 2024 – Q4 2025) materials 14 and supplies balance of $161.732 million, which was adjusted for inflation using the 15 Moody’s Analytics Inc. Gross Domestic Product – Price Index (“GDP-PI”) forecast for 16 both the interim and rate periods. 17 adjustment of $7.643 million ($161.732 million * 4.73% = $7.643 million) and a rate 18 year inflation adjustment of $2.779 million ([$161.732 million + $7.643 million] * 19 1.64% = $2.779 million). Adjusting for inflation results in a total interim period 20 materials and supplies balance of $169.375 million ($161.732 million + $7.643 million 21 = $169.375 million) and a total rate year ending materials and supplies balance of 22 $172.154 million ($161.732 million + $7.643 million + $2.779 million = $172.154 This resulted in an interim period inflationPage 14 of 96
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-REVREQ-REBUTTAL-1 November 18, 2026 Page 11 of 93 1 million). The average of both the ending interim and rate year balance is $170.765 2 million ([$169.375 million + $172.154 million] / 2 = $170.765 million), which 3 represents the Company’s proposed materials and supplies balance included in rate 4 base. The Company provides detailed information on this request in Schedule WP B- 5 4.0, at 1 and the Revenue Requirement Panel’s pre-filed testimony, Exhibit CLP- 6 REVREQ-1, at 27-30. 7 Q. What is Mr. Defever’s response to this proposal? 8 A. Mr. Defever recommends the removal of all inflationary adjustments to the materials 9 and supplies balance, which results in a reduction to the amount included in rate base 10 of $9.033 million. 12 11 Q. What is Mr. Defever’s reasoning behind this reduction? 12 A. Mr. Defever concluded that inflation “is not a known and measurable increase” 13 and 13 removed the inflationary adjustment of $9.033 million in his proposed revenue 14 requirement calculation. 15 Q. Does the Company agree with Mr. Defever’s determination and conclusions? 16 A. No. The Company does not agree that inflation would not qualify as a known and 17 measurable adjustment. This argument was used consistently throughout Mr. 18 Defever’s testimony to support various adjustments and rather than rebutting the 12 Defever Testimony, at 7 and Exhibit JD-1, Schedule B-1. 13 Defever Testimony, at 7.Page 15 of 96
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-REVREQ-REBUTTAL-1 November 18, 2026 Page 12 of 93 1 argument throughout our testimony, we have consolidated our arguments in a separate 2 section of our testimony below. B. Customer Advances for Construction 3 4 Q. Please describe what is considered a customer advance for construction. 5 A. A customer advance for construction represents a cash advance from a new customer 6 to cover certain construction costs. These amounts are refundable to project owners at 7 a future date either in full or in part upon completion of project milestones. If these 8 amounts are forfeited, the balance would be credited against project costs included in 9 rate base. These amounts are reflected within FERC Account 252 Customer Advances 10 for Construction on the balance sheet. 11 Q. Has the Company’s included Customer Advances for Construction in Rate Base? 12 A. No. The Company has not included customer advances for construction in rate base in 13 either of the Company’s two most recent rate cases in both Docket No. 17-10-46 and 14 14-05-06. 15 Q. What is Mr. Defever’s recommendation for customer advances? 16 A. Mr. Defever’s recommendation is to include the “most recent balance” for customer advances for construction of $19.485 million in rate base. 14 17 14 Defever Testimony, at 9Page 16 of 96
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-REVREQ-REBUTTAL-1 November 18, 2026 Page 13 of 93 1 2 Q. What was Mr. Defever’s justification to include customer advances for construction in rate base? 3 A. Mr. Defever contends that these balances have increased substantially since March 4 2023, argues that other companies in Connecticut include refundable advances in rate 5 base (citing two water companies) and noted he believes prior to the Company’s two 6 most recent rate cases customer advances were included in rate base. 7 Q. Does the Company agree with Mr. Defever’s conclusions? 8 A. No. Consistent with recent CL&P rate case proceedings (both Docket No. 17-10-46 9 and 14-05-06) the Company has not included these amounts in rate base. As outlined 10 above, these amounts are typically refunded to customers in full and as a result do not 11 represent funds utilized by the Company to support long-term capital projects or 12 initiatives. 13 If PURA were to depart from recent rate case precedent to include these amounts in 14 rate base, simply selecting the “most recent balance”, as suggested by Mr. Defever, is 15 not a proper or supportable methodology. It is also important to highlight that the “most 16 recent balance” referenced by Mr. Defever also happens to be the largest balance in the 17 past three years by a significant margin. In fact, from March 2023 to November 2025 18 the average monthly customer advance balance was approximately $2.7 million, 19 starting in December 2025 this balance increased dramatically to the June 2026 amount 20 of $19.485 million. This increase is primarily driven by one single project initiated in 21 December 2025, where a customer paid a refundable advance of approximately $8.1Page 17 of 96
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-REVREQ-REBUTTAL-1 November 18, 2026 Page 14 of 93 1 million. The Company provides details on the increase in this balance in recent months 2 within both OCC-676 and OCC-936. 3 The goal of any rate case is to establish a just and reasonable level of distribution 4 revenues for the Company to operate the business by incorporating a representable 5 level of rate base and annual operating costs in rates. Mr. Defever argues a five-quarter 6 average balance is not needed for customer advances, similar to some of his other 7 proposals, because “an average would be more appropriate for amounts that 8 fluctuate.” 15 He neglects to highlight that these amounts have fluctuated significantly 9 in recent months moving from an average balance of $2.7 million from March 2023 to 10 November 2025 to an average of $18 million from December 2025 to June 2026. Thus, 11 the Company contends if such an amount were to be included in rates the significant 12 projects included in this balance outlined in both OCC-676 and OCC-936 should be 13 normalized to achieve a representative and historical level of customer advances in 14 rates. C. Utility Plant In-Service 15 16 Q. What is the Company’s request for utility plant in-service in rate base? 17 A. The Company’s test year actual utility plant in-service balance was $8.828 billion as of 18 December 31, 2025. This test year balance includes all electric plant that is used, useful 19 and providing active service to customers as of December 31, 2025, and was based on 15 Defever Testimony, at 12-13.Page 18 of 96
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-REVREQ-REBUTTAL-1 November 18, 2026 Page 15 of 93 1 the electric plant amounts included in FERC Account 101 and FERC Account 106. 2 Refer to Table 3 of Exhibit CLP-REVREQ-1 at 21 for a detailed reconciliation of the 3 test year amount to the audited Annual FERC Form 1 financial statements. 4 The Company proposed an adjustment to the test year balance for both capital additions 5 and retirements by individual plant account through the end of the rate year (June 30, 6 2028) utilizing the Company’s internal forecasts. The Company incorporated capital 7 additions of $848 million and retirements of ($152) million for a net adjustment of $696 8 million in the interim period (January 1, 2026 – June 30, 2027) and capital additions of 9 $665 million and retirements of ($116) million for a net adjustment of $549 million in 10 the Rate Year (July 1, 2027 – June 30, 2028). 11 These adjustments resulted in a beginning rate year (July 1, 2027) utility plant in- 12 service balance of $9.523 billion ($8.828 billion + 695 million = $9.523 billion) and an 13 ending rate year (June 30, 2028) utility plant in-service balance of $10.073 billion 14 ($9.523 billion + $549 million = $10.073 billion). These beginning and ending utility 15 plant in-service balances produced an average value for the rate year of $9.798 billion 16 ([9.523 billion + $10.073 billion] / 2 = $9.798 billion), which was used in calculating 17 the Company’s rate base. 18 The Company provides detailed information on this request in Exhibit CLP-REVREQ- 19 2, Schedule WP B-2.0 to WP B-2.5 and the Revenue Requirement Panel’s pre-filed 20 testimony, Exhibit CLP-REVREQ-1, at 20-24.Page 19 of 96
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-REVREQ-REBUTTAL-1 November 18, 2026 Page 16 of 93 1 Q. What is Mr. Defever’s response to this proposal? 2 A. Mr. Defever recommends an adjustment to the Company’s average utility plant inservice balance for the rate year of $1.014 billion 16 or approximately 10 percent. 3 4 5 Q. Was Mr. Defever’s recommendations based explicitly on his own findings and conclusions? 6 A. No. Mr. Defever’s adjustments to the average utility plant in-service for the rate year include recommendations from OCC witness Nikhil Balakumar. 17 7 8 Q. What were the capital recommendations from Mr. Balakumar? 9 A. Mr. Balakumar recommended the following capital adjustments in his pre-filed 10 testimony: 11 • A disallowance of $26.5 million for 2022-2023 direct-buried cable replacement costs. 18 12 13 • A potential disallowance of capacity additions for “Peak Load/Capacity project 14 placed in service from 2023 through 2025” totaling $145.4 million if the 15 Company cannot produce “contemporaneous evaluation of non-wires 16 alternatives, the load forecast and the authorization documents” for each project 16 Exhibit JD-1, Schedule B, line 1 and Schedule B-4, lines 15 - 19. 17 Defever Testimony, at 3. 18 Balakumar Testimony, at 92.Page 20 of 96
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-REVREQ-REBUTTAL-1 November 18, 2026 Page 17 of 93 1 prior to the record closing. The proposed disallowance would be calculated as 2 “the cost above the least-cost alternative where one was available.” 19 3 • To “[i]nclude in rate base only plant additions that are completed, in service 4 and documented as of the last supplemental filing before the record closed, and 5 exclude all forecasted plant.” Mr. Balakumar projected the utility plant amount 6 eligible for inclusion in rate base at $645.3 million ($847.8 million - $202.5 7 million = $645.3 million). Thus, proposing to remove approximately $202.5 8 million of interim period projected capital additions and all projected rate year 9 capital additions of $664.9 million.20 10 • Additionally, Mr. Balakumar identified areas that were open for additional 11 information from the Company and committed to providing final 12 recommendations on those additions in the surrebuttal testimony. 21 Finally, he 13 recommended it be required the Company have before-and-after storm 14 performance data for the resiliency programs and requests PURA weigh the 19 Balakumar Testimony, at 92-93. 20 Balakumar Testimony, at 93. 21 Balakumar Testimony, at 92.
As listed on the current system
Prefiled testimony: 11/18/2026 - Sponsor: TBD / Witness: BRENDAN J. O’BRIEN AND GARRETT J. MURRAY [26-05-10]