Prefiled testimony

Witness: BRENDAN J. O’BRIEN AND GARRETT J. MURRAY

Files2

Search terms highlighted
Eversource rate increase is on 25 pages of the text below, highlighted. Go to the first matchClear highlighting
Words on different pages
25 pages match
  1. Page 30 of 96Match

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-REVREQ-REBUTTAL-1 November 18, 2026 Page 27 of 93 1 Illuminating’s most recent rate case in Docket No. 24-10-04 and in the CNG and SCG 2 Remand Decisions in Docket Nos. 25-12-13 and 25-11-14 respectively. 3 Importantly, however, PURA also applied the same cutoff concept to accumulated 4 depreciation. PURA expressly declined to include $38.5 million of accumulated 5 depreciation for the period June 1, 2025 through October 31, 2025 in the Final Decision 6 in Docket No. 24-12-01, stating that the amount would not be included “based on the 7 Authority’s allowed plant-in-service, for purposes of calculating rate base in this 8 proceeding.” 27 The purpose and effect of that treatment was to align the accumulated 9 depreciation included in rate base with the cutoff applied to the corresponding utility 10 plant in-service. 11 Mr. Defever does not apply that same symmetrical treatment here. He effectively 12 adopts the cutoff, suggested by Mr. Balakumar and consistent with the Final Decision 13 in Docket No. 24-12-01, to exclude projected plant additions at the close of the 14 evidentiary record, which reduces rate base, but does not apply the corresponding 15 cutoff to the projected accumulated depreciation, which, if the cutoff were applied 16 consistently, as it should be, would increase rate base. Based on the Company’s 17 analysis, applying the same treatment to accumulated depreciation would reduce the 18 Company’s forecasted average rate year accumulated depreciation balance by 19 approximately $100 million. As a result, Mr. Defever’s reduction to accumulated 27 Yankee Gas Decision, at 30
  2. Page 31 of 96Match

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-REVREQ-REBUTTAL-1 November 18, 2026 Page 28 of 93 1 depreciation would be multiple times greater than the adjustment currently reflected in 2 his analysis if the Final Decision in Docket No. 24-12-01 were applied symmetrically. 3 Taken together, these issues demonstrate a recurring lack of symmetry in Mr. Defever’s 4 calculations. His analysis removes plant without removing all of the accumulated 5 depreciation associated with that plant and applies the Yankee Gas Decision where it 6 reduces the Company’s revenue requirement without applying the corresponding 7 treatment from that same decision where it would increase the Company’s revenue 8 requirement. The result is an inconsistent rate base calculation that systematically 9 recognizes adjustments that reduce rate base without recognizing the corresponding 10 adjustments that would increase it. The Company submits that the same accounting 11 and ratemaking principles must be applied consistently in both directions. E. Accumulated Deferred Income Taxes (“ADIT”) 12 13 Q. What is the Company’s request for ADIT in rate base? 14 A. The Company’s test year actual ADIT was ($1.187) billion as of December 31, 2025. 15 This test year balance includes the tax deferrals resulting from the adoption of the 16 principle of comprehensive inter-period income tax allocation described in General 17 Instruction 18 of the Uniform System of Accounts, which are related to all property 18 other than accelerated amortization property. 19 The Company incorporated post-test year adjustments of ($88.849) million, which 20 were primarily driven by the Company’s plant in-service, including adjustments to tax 21 deferrals on existing plant and new tax deferrals on projected plant in service through
  3. Page 32 of 96Match

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-REVREQ-REBUTTAL-1 November 18, 2026 Page 29 of 93 1 the end of the Rate Year. Ultimately, the Company proposed an adjustment in the 2 interim period of ($64.507) million resulting in a Rate Year beginning ADIT balance 3 of ($1.251) billion (($1.187) billion + (64.507) million = ($1.251) billion). 4 Additionally, the Company identified a Rate Year adjustment of ($24.342) million, 5 resulting in an ending rate year balance of ($1.276) billion (($1.251) billion + ($24.342) 6 million = ($1.276) billion). As discussed above, the Company used the average rate 7 year in its calculation of rate base for the required rate year revenue requirement for 8 effect July 1, 2027. The average of the interim period ending balance and the Rate 9 Year ending balance is ($1.263) billion ([($1.251) billion + ($1.276) billion] / 2 = 10 ($1.263) billion). 11 The Company provides detailed information on this request in Exhibit CLP-REVREQ- 12 2, Schedule WP B-7.0 and the Revenue Requirement Panel’s pre-filed testimony, 13 Exhibit CLP-REVREQ-1, at 65-66. 14 Q. Did Mr. Defever make any adjustments to the average ADIT during the rate year? 15 A. Yes, although Mr. Defever did not make any direct recommendations specific to 16 ADIT, he did make one adjustment to reflect the recommendations of OCC witness 17 Nikhil Balakumar regarding capital additions 28 and his own vegetation management 18 cost recommendations. 19 ($130.759) million or 10 percent that is reflected in Exhibit JD-1, Schedule B, Line 4. 28 Defever Testimony, at 3. Mr. Defever is recommending an increase to ADIT of
  4. Page 33 of 96Match

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-REVREQ-REBUTTAL-1 November 18, 2026 Page 30 of 93 1 Q. What is Mr. Defever’s reasoning behind this increase to ADIT? 2 A. Mr. Defever does not provide any direct testimony explaining these adjustments or the 3 methodology used to calculate them. Based on the Company’s review of Exhibit JD- 4 1, Schedules B-4 and B-5, however, it appears that Mr. Defever applied an ADIT ratio 5 to the utility plant in-service adjustments reflected in his revenue requirement 6 calculation to estimate the corresponding adjustment to ADIT. Mr. Defever estimated 7 an ADIT ratio of 12.89 percent, 29 which was calculated by taking the Company’s 8 average rate year ADIT and dividing by the Company’s rate year utility plant in- 9 service. This ratio was then applied to the proposed reduction to utility plant in-service 10 to arrive at his proposed increase to ADIT. 11 Q. Does the Company agree with Mr. Defever’s calculation and conclusions? 12 A. While the Company agrees with Mr. Defever that an adjustment to ADIT is required 13 given the proposed adjustments to utility plant in-service, the Company does not agree 14 with Mr. Defever’s calculation and has identified a material mathematical error in his 15 proposal. 16 Q. Please summarize Mr. Defever’s mathematical error. 17 A. The Company identified a fundamental mathematical error in Mr. Defever’s calculation 18 of accumulated deferred income taxes (“ADIT”), which is that he applied the 19 adjustment in the opposite direction. Mr. Defever proposes to reduce average utility 20 plant in-service by approximately $1.014 billion. Because the Company’s ADIT 29 Exhibit JD-1 Schedule B-4 and B-5, line 8.
  5. Page 34 of 96Match

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-REVREQ-REBUTTAL-1 November 18, 2026 Page 31 of 93 1 liability is primarily generated by accelerated tax depreciation under IRS rules relative 2 to straight-line book depreciation under generally accepted accounting principles 3 (“GAAP”), a reduction in utility plant in-service would correspondingly reduce the 4 associated ADIT liability, not increase it. 5 Mr. Defever attempts to reflect the ADIT impact associated with his proposed reduction 6 in utility plant in-service but applies the resulting $130.759 million adjustment with the 7 incorrect sign. Rather than reducing the ADIT liability by $130.759 million, which 8 would increase rate base (or, more accurately, it would make the overall recommended 9 reduction to rate base smaller, since the reduction in plant additions would be properly 10 and partially offset by a corresponding decrease to the ADIT liability, which is an offset 11 to rate base), his calculation increases the ADIT liability by ($130.759) million, which 12 has the effect of incorrectly further reducing rate base. Correcting this sign error 13 therefore increases Mr. Defever’s calculated rate base by $261.518 million (i.e., by 14 having his proposed adjustment to ADIT changing from a proposed increase to the 15 ADIT liability (and resulting in a further reduction to rate base), to rightfully be a 16 proposed decrease to the ADIT liability (and resulting in an increase to rate base, by 17 resulting in a lower ADIT offset to rate base). This error also has a material impact on 18 the OCC’s calculated revenue requirement, as Mr. Defever’s increase to ADIT 19 contributed to approximately 11 percent of his overall proposed rate base reduction. 20 This error is straightforward but significant and importantly, this correction is separate 21 from the hundreds of millions of dollars of other mathematical errors identified above.
  6. Page 35 of 96

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-REVREQ-REBUTTAL-1 November 18, 2026 Page 32 of 93 1 Taken together, these errors demonstrate that significant portions of Mr. Defever’s 2 proposed reductions are not the result of differing ratemaking judgments or 3 assumptions, but rather critical and fundamental mathematical and computational 4 errors in the calculation of rate base and the resulting revenue requirement. The 5 Company addresses these errors collectively below. 6 III. OPERATING INCOME A. D&O Liability Insurance 7 8 9 Q. Has the Company included Directors and Officers Liability Insurance expense in the Rate Year? 10 A. Yes. The Company has requested $323,000 in the Rate Year for Directors and Officers Liability Insurance expense. 30 11 12 13 Q. What did Mr. Defever recommend in terms of the Company’s D&O Liability Insurance expense? 14 A. Mr. Defever recommended a 100 percent disallowance of Director and Officer Liability 15 Insurance expense ($323,000) based on the Yankee Gas Decision and the Final 16 Decision in Aquarion Water Company’s rate case in Docket No. 22-07-01 (“AWC 17 Decision”). 31 18 Q. What does Mr. Defever claim as the basis for his proposed reduction? 19 A. Mr. Defever argues that customers should not be responsible for subsidizing the 20 Company’s D&O Liability Insurance expense, because it primarily benefits the 30 Exhibit CLP-REVREQ-2, Work Paper C-3.19, line 25; Q-OCC-376. 31 Defever Testimony, at 14.
  7. Page 36 of 96

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-REVREQ-REBUTTAL-1 November 18, 2026 Page 33 of 93 1 Company and its officers. 32 Mr. Defever previously recommended a 75/25 sharing of 2 this cost between shareholders and ratepayers but argues that because PURA 3 disallowed 100% of the D&O liability insurance in Yankee Gas Decision and the AWC 4 Decision, the same should apply here. 33 5 Q. Does the Company agree with the recommendation for a 100% disallowance? 6 A. No. The Company respectfully submits that D&O Liability Insurance is a prudent and 7 necessary operating expense. The insurance provides direct protection of Eversource’s 8 balance sheet. The D&O Liability Insurance policy provides direct protection to 9 Eversource itself against covered securities-related claims, including eligible defense 10 costs and settlements. This transfers potentially significant corporate liabilities to 11 insurers rather than leaving Eversource and ultimately Eversource’s customers to 12 absorb the full financial impact. The policy also reimburses Eversource for covered 13 costs incurred in indemnifying its directors and officers, including defense expenses 14 and eligible settlements. These are financial obligations that Eversource might 15 otherwise fund from corporate resources which would be paid for by ratepayers. 16 Together, these coverages represent balance sheet protection and serve as a corporate 17 risk-financing tool, not merely coverage for executives. 18 It is important to note that this insurance coverage does not protect covered individuals 19 in the event that (1) they used their position to gain personal profit, financial advantage 32 Id. 33 Id.
  8. Page 37 of 96

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-REVREQ-REBUTTAL-1 November 18, 2026 Page 34 of 93 1 or remuneration to which they were not entitled or (2) where the individual committed 2 a deliberately fraudulent or criminal act or omission or any intentional violation of any 3 law, statute or regulation. Coverage by the policy primarily involves actions where the 4 costs could be included in the Company’s cost of service absent this insurance coverage 5 and, as such, the policy offers customer benefits. 6 The coverage supports the recruitment and retention of qualified directors and 7 executives. Eversource’s board oversees decisions directly affecting customers, 8 including infrastructure investment, system reliability, financial stewardship, long-term 9 capital allocation, etc. D&O Liability Insurance is a standard component of corporate 10 governance and helps attract and retain experienced, independent directors willing to 11 assume these substantial oversight responsibilities. The availability of appropriate 12 liability protection supports effective board oversight, which ultimately benefits both 13 customers and shareholders. 14 D&O Liability Insurance supports financial stability and reliable utility operations and 15 helps mitigate the financial volatility associated with potentially significant litigation, 16 preserving corporate resources, and supporting financial resilience. The policy is 17 designed to respond to covered allegations, including defense against unfounded or 18 spurious claims that ultimately prove unsuccessful. A financially stable utility is better 19 positioned to maintain access to capital, invest in infrastructure, and meet its long-term 20 service obligations with a reasonable level of D&O Liability Insurance. By transferring
  9. Page 38 of 96

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-REVREQ-REBUTTAL-1 November 18, 2026 Page 35 of 93 1 covered litigation exposures to the insurance market, Eversource reduces the potential 2 for unexpected claims costs to compete with other corporate financial priorities. 3 Maintaining D&O Liability Insurance supports access to capital and competitive 4 financing costs. D&O Liability Insurance helps protect Eversource's balance sheet 5 from covered securities litigation, reducing exposure to potentially significant, 6 unplanned corporate expenses. By limiting certain litigation-related financial shocks, 7 D&O Liability Insurance can contribute to financial stability, which is relevant to 8 creditworthiness and lenders' assessment of corporate risk. For a capital-intensive 9 utility such as Eversource, maintaining financial strength and access to competitively 10 priced financing supports infrastructure investment and can ultimately benefit 11 customers. Although D&O Liability Insurance is unlikely to produce a separately 12 identifiable reduction in borrowing rates, it forms part of the broader financial risk- 13 management framework that supports favorable financing conditions. 14 The coverage supports the recruitment and retention of qualified directors and officers, 15 promotes effective oversight of critical electric infrastructure, and advances regulatory 16 objectives related to reliability, safety, emergency preparedness, prudent capital 17 investment, etc. Because customers directly benefit from the governance activities 18 supported by this coverage, recovery of the Company's reasonable D&O Liability 19 Insurance expense is consistent with cost-of-service ratemaking principles and should 20 be included in the Company's revenue requirement.
  10. Page 39 of 96

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-REVREQ-REBUTTAL-1 November 18, 2026 Page 36 of 93 1 PURA has previously recognized that D&O Liability Insurance is not wholly 2 attributable to shareholder interests. In Docket No. 20-12-30, involving The 3 Connecticut Water Company, PURA permitted recovery of 25% of D&O insurance 4 expenses rather than disallowing the expense in its entirety. This treatment reflects the 5 recognition that utility customers benefit from effective governance, regulatory 6 compliance, risk management, and executive oversight. Those customer benefits are 7 even more pronounced in the electric industry, where directors and officers oversee 8 critical infrastructure, storm restoration, reliability programs, and substantial capital 9 investment necessary to provide safe and reliable electric service. 10 11 Q. Based on the above-mentioned considerations, is recovery of the D&O Liability Insurance expense reasonable? 12 A. Yes, recovery of the D&O Liability Insurance expense is reasonable and appropriate. 13 There is no basis for the full disallowance that Mr. Defever recommends. The fact that 14 he recommends ratepayers bear responsibility for some portion of this expense 15 demonstrates that it is a necessary business expense for an investor-owned utility. B. Board of Trustees 16 17 Q. Has the Company included a Board of Trustees expense in the Rate Year? 18 A. Yes. The Company has requested $515,000 in the Rate Year for Board of Trustees 19 expense. 34 As noted in Exhibit CLP-REVREQ-1, at 70, and the Company’s response 20 to Q-OCC-263, CL&P is only seeking recovery of trustee retainer fees and restricted 34 Exhibit CLP-REVREQ-2, WP C-3.4; Q-OCC-263.

As listed on the current system

Prefiled testimony: 11/18/2026 - Sponsor: TBD / Witness: BRENDAN J. O’BRIEN AND GARRETT J. MURRAY [26-05-10]