Prefiled testimony
Witness: DAVID L. GLADEY, JOHN P. DIPAOLA-TROMBA, LEANNE M. LANDRY, AND JEFFREY D. TURANO
Files6
Docket No. 26-05-10 CLP Rebuttals Filing Letter (11.18.26).pdf
PDF · 152 KB · 3 pagesText searchable
Download Docket No. 26-05-10 CLP Rebuttals Filing Letter (11.18.26).pdfRead the text of Docket No. 26-05-10 CLP Rebuttals Filing Letter (11.18.26).pdf
Exhibit CLP-ADDITIONS-REBUTTAL-1.pdf
PDF · 361 KB · 34 pagesText searchable
Download Exhibit CLP-ADDITIONS-REBUTTAL-1.pdfRead the text of Exhibit CLP-ADDITIONS-REBUTTAL-1.pdf
Exhibit CLP-ADDITIONS-REBUTTAL-2.pdf
PDF · 872 KB · 6 pagesText searchable
Download Exhibit CLP-ADDITIONS-REBUTTAL-2.pdfRead the text of Exhibit CLP-ADDITIONS-REBUTTAL-2.pdf
Exhibit CLP-ADDITIONS-REBUTTAL-3.pdf
PDF · 6.7 MB · 73 pagesText searchable
Download Exhibit CLP-ADDITIONS-REBUTTAL-3.pdfRead the text of Exhibit CLP-ADDITIONS-REBUTTAL-3.pdf
Exhibit CLP-ADDITIONS-REBUTTAL-4.pdf
PDF · 1.1 MB · 8 pagesText searchable
Download Exhibit CLP-ADDITIONS-REBUTTAL-4.pdfRead the text of Exhibit CLP-ADDITIONS-REBUTTAL-4.pdf
Exhibit CLP-ADDITIONS-REBUTTAL-8 REDACTED.pdf
PDF · 52 MB · 502 pagesText searchable
Download Exhibit CLP-ADDITIONS-REBUTTAL-8 REDACTED.pdfRead the text of Exhibit CLP-ADDITIONS-REBUTTAL-8 REDACTED.pdf
Page 17 of 34
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-ADDITIONS-REBUTTAL-1 November 18, 2026 Page 15 of 32 1 time for construction and the inconvenience to customers associated with planned 2 outages to accommodate the construction, helping to mitigate construction cost 3 increases driven by increases in labor and materials costs. 4 5 Q. What was the basis for the Company’s decision to transition to a full-scale replacement program for direct-buried cable beginning in 2019? 6 A. Capital additions made through the Company’s URD/DB Cable Reliability program 7 were completed to address direct buried cable for reliability performance and repetitive 8 events. The distribution system encompasses a substantial component of direct-buried 9 cable in residential areas, which was placed in the ground in the 1970s and 1980s. At 10 the time, the installation of the cable did not include any conduit. Utility companies 11 simply dug a trench, put the cable into the ground, and hooked it up to the system. In 12 the last 10 to 20 years, the direct-buried cable has been failing at an exponentially 13 increasing rate. Historically, the Company would repair the cable when it failed rather 14 than replacing it because the cable could generally continue to be used and did not 15 require elimination. 16 In 2018, it became clear that the repair strategy was no longer a viable method to triage 17 direct-buried cable failures given that engineering analysis showed that the cable was 18 failing repeatedly in the same areas requiring multiple field visits and repeat outages to 19 customers. Through this assessment, the Company determined that the repair strategy 20 should be substituted for a replacement strategy to achieve a more cost-effective 21 outcome as well as address the cable asset condition as a result in being direct buriedPage 18 of 34
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-ADDITIONS-REBUTTAL-1 November 18, 2026 Page 16 of 32 1 installed where the soil conditions have accelerated the degradation of the cable 2 integrity. A repair strategy works if the repairs are occasional and the remainder of the 3 cable remains in good condition. However, the analysis showed that replacement of 4 this failing cable over the long term was a superior, permanent solution that would 5 greatly improve reliability of service, and replacement of this faulty equipment would 6 eliminate the need to continue to remediate temporary repairs that require additional 7 work in the future. From a customer and operations perspective, the issue with the 8 failing direct-buried cable is resolved when the Company replaces it. Accordingly, 9 starting in 2019, it was necessary to institute a course of replacement with annual 10 replacement targets. The replacement program was designed to improve system 11 reliability by minimizing the likelihood of recurring outages on the same cable and 12 eliminating recurring field responses. The Company provided additional details about 13 its URD-DB cable reliability program in its December 11, 2019 compliance filing in 14 Docket No. 17-10-46 at Exhibit 1(b), Pages 2-3, which is reproduced as Exhibit CLP- 15 ADDITIONS-REBUTTAL-4, with this testimony. 16 17 18 Q. What information did the Company rely on in making its decision to change its program approach in 2024 to implement a hybrid repair and replacement approach? 19 A. In 2024, based on its experience over the previous five years, the Company decided to 20 make a change to its program approach to mitigate the impact on customers and to 21 reduce the overall cost of the program. This change resulted primarily from an 22 assessment of customer impact rather than any technical assessment. The Company’sPage 19 of 34
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-ADDITIONS-REBUTTAL-1 November 18, 2026 Page 17 of 32 1 experience over the years 2019 to 2024 was that customers were highly inconvenienced 2 by the planned service outages that are necessary to accommodate the replacement of 3 underground electric facilities providing service to customer premises. To address this 4 inconvenience, the Company found it necessary to use temporary on-site generation to 5 maintain a level of service to the affected customers during the replacement work, 6 adding unanticipated complications and cost to the overall project. The Company 7 determined that, with the hybrid approach, the Company can be more strategic about 8 where and when it implements a replacement approach and can do so within 9 implicating the need for on-site generation to mitigate the impacts of the work on 10 customers. 11 Q. What is the inherent flaw in Mr. Balakumar’s cost-per-mile view on prudence? 12 A. Mr. Balakumar’s cost-per-mile approach is not a reasonable or valid perspective to 13 determine the merits of the Company’s operational strategy. For one thing, Mr. 14 Balakumar’s approach quite simply compares a pre-COVID program cost (2019-2021) 15 to a post-COVID program cost (2022-2023), which is a cost change that had nothing 16 to do with the Company’s 2019 transition to a replacement approach, but rather 17 coincides directly with the supply chain issues and inflation trends that occurred in 18 2022 and 2023. Reproducing the cost-per-mile information submitted by the Company 19 in response to OCC-798, it is clear that there is a break between the 2019-2021 period 20 and the 2022-2025 period, which coincides directly with the post-COVID inflation 21 impacts on construction costs.Page 20 of 34
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-ADDITIONS-REBUTTAL-1 November 18, 2026 Page 18 of 32 Cost Per Mile 1 Year 2017 2018 2019 2020 2021 2022 2023 2024 2025 Cost Per Mile $399,571 $653,419 $567,974 $906,990 $803,309 $1,229,449 $1,050,430 $1,190,929 $1,250,441 2 3 Based on these figures, the average cost-per-mile in the 2019 to 2021 timeframe was 4 approximately $750,000, as noted by Mr. Balakumar (Balakumar Testimony at 89), 5 increasing to approximately $1,140,000 in the 2022 to 2023 timeframe, and now 6 stabilized ($1,180,000 for the time frame 2022 through 2025). In this time period, the 7 primary drivers of cost increased in the range of 50 percent between the pre-COVID 8 and post-COVID time frame. The drivers of program costs reflect this increase, as 9 follows: Cost Element 10 Materials Contractors Engineering, supervision, lobby stock and vehicles Average Cost per Mile 2019-2021 $24,633 $401,808 $320,211 Average Cost per Mile 2022-2023 $35,653 $604,828 $474,706 Percent Change 45% 51% 48% 11 In addition, the “cost-per-mile” is not simply the labor and material to replace a direct- 12 buried cable, but for this program, it is the total cost to restore power to customer asPage 21 of 34
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-ADDITIONS-REBUTTAL-1 November 18, 2026 Page 19 of 32 1 part of the replacement project, including the cost of civil work, on-site generation and 2 other efforts that require additional cost to get the work done. 3 Thus, the central flaw of Mr. Balakumar’s theory is that the changes in cost-per-mile 4 do not coincide with the years in which the Company made changes to its replacement 5 strategy. In the years 2017-2019, the Company’s costs per mile were stable – in the 6 range of $600,000 per mile, until COVID occurred in 2020, starting the upward cost 7 trend. Similarly, the cost-per-mile in 2024 and 2025 is the same as in 2022 – in the 8 range of $1.1 to $1.2 million per mile, although the Company transitioned to a hybrid 9 repair/replacement strategy in 2024. As a result, it is not the Company’s change in 10 program strategy that is driving the cost change. Instead, the Company decided to 11 transition to the repair/replacement strategy to mitigate the impact and inconvenience 12 of the program for customers, while reducing the overall cost of the program as 13 compared to other priorities that the Company has. This is a feasible transition because 14 the Company can maintain reliability through the hybrid repair without needing to rely 15 on as much replacement work as in the past. 16 Without accounting for the impact of post-COVID construction cost changes, Mr. 17 Balakumar’s extrapolation of historical average costs to subsequent years does not 18 demonstrate that the additional expenditures were unreasonable or could have been 19 avoided. Nor does the Company’s adoption of a hybrid replacement and repair strategy 20 suggest that the prior replacement program was imprudent – after COVID, the cost- 21 per-mile for replacement is the same for the hybrid strategy as it was for thePage 22 of 34
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-ADDITIONS-REBUTTAL-1 November 18, 2026 Page 20 of 32 1 replacement strategy. Instead, the Company’s decision reflected a prudent 2 reassessment of its approach in light of operating experience with customer impacts 3 and changing system needs, calling for a reprioritization and reallocation of capital 4 resources. The Company’s modification of the program in response to new information 5 does not mean the original decisions were unreasonable or imprudent when they were 6 made. 7 As a result, Mr. Balakumar’s proposed adjustment lacks a sound factual and analytical 8 basis for concluding that the Company’s expenditures were imprudent. 9 C. Capacity Projects 10 11 12 Q. Please summarize the portion of Mr. Balakumar’s testimony that is specific to his conclusions and recommendations regarding certain capacity projects placed into service between 2023 and 2025. 13 A. Mr. Balakumar argues that PURA should require the Company produce, before the 14 record closes, the contemporaneous evaluation of non-wires alternatives (“NWAs”), 15 the load forecast and the authorization documents for each Peak Load/Capacity project 16 placed in service from 2023 through 2025 with a total investment of $145.4 million 17 (Balakumar Testimony at 92). In the event that the Company cannot provide the 18 relevant documentation, Mr. Balakumar recommends that PURA determine that the 19 project(s) were imprudent and disallow the cost above the least-cost alternative where 20 one was available (id. at 92-93). We do not agree with this conclusion.Page 23 of 34
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-ADDITIONS-REBUTTAL-1 November 18, 2026 Page 21 of 32 1 Q. What does Mr. Balakumar rely on to support this recommendation? 2 A. Mr. Balakumar contends that the record currently does not contain sufficient evidence 3 to determine if the Company evaluated lower-cost alternatives before it built the 4 capacity projects placed in service from 2023 through 2025 (Balakumar Testimony at 5 86). In reaching this conclusion, Mr. Balakumar relies primarily on the Company’s 6 response to OCC-805, which requested that the Company address each substation 7 capacity project undertaken during 2017 through 2025, with the load forecast and 8 planning criterion relied upon at authorization; the measured peak load in the five years 9 after in-service; the total cost; and any non-wires alternative evaluation. 10 According to Mr. Balakumar, capacity needs that are modest in size or short in duration 11 are where lower-cost alternatives are most likely to be viable (id. at 86). He references 12 the Company’s Project Authorization Forms (“PAFs”), as well as the 2021 NWA 13 Framework (OCC-578, Attachment 1), as requiring NWA analyses for capacity 14 projects (id.). 15 Next, Mr. Balakumar refers to the Company’s response to OCC-805, Attachment 1, to 16 arrive at the conclusion that the record does not show that the Company applied the 17 required NWA analyses to the capacity projects included in OCC-805, Attachment 1 18 (id. at 88). This conclusion underpins his recommendations to PURA. 19 Q. Are his conclusions regarding the 2021 NWA Framework accurate? 20 A. No. In his testimony, Mr. Balakumar claims that the Company’s response to OCC- 21 805, Attachment 1 does not identify the NWAs considered, their cost relative to thePage 24 of 34
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-ADDITIONS-REBUTTAL-1 November 18, 2026 Page 22 of 32 1 wires solution, or why they were not selected (Balakumar Testimony at 88). However, 2 this statement rests on the presumption that the Company develops full NWA cost 3 estimates for all capacity projects, which it does not – in accordance with the 4 Company’s screening framework. 5 Importantly, the Company endeavored to submit its 2021 NWA Framework to PURA 6 as part of PURA’s Docket No. 17-12-03RE07 several times and PURA chose not to 7 engage with the Company on this framework, instead opting to create an entirely new 8 process, which took several years to develop (PURA did not require Eversource to 9 follow a PURA-mandated formal NWS framework until 1/1/2025). Consequently, the 10 Company applied its own screening process to review solutions while PURA 11 deliberated on its new process. Thus, as set out in OCC-578, Attachment 1, at 7, the 12 Company utilized an NWA Screening Tool as part of its own 2021 NWA Framework 13 to quickly evaluate the potential applicability of NWA solutions to meet capacity 14 project needs at specific locations, with the intent that only sites that are suitable and 15 viable for NWA solutions will move to a more detailed, engineering analysis stage. 16 The NWA Screening Tool enables rapid initial screening of NWA options against 17 traditional system upgrade projects but does not provide detailed and accurate costing 18 or technical solution design (id.). Once an NWA solution passes the NWA Screening 19 stage as a suitable and technically viable solution, the Company will perform detailed 20 steady-state and transient analysis studies as well as develop engineering designs and 21 cost estimates for the identified solution (id.). It is important to note that it is stillPage 25 of 34
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-ADDITIONS-REBUTTAL-1 November 18, 2026 Page 23 of 32 1 possible that an NWA solution will ultimately not be selected as the preferred solution 2 due to inferior technical or cost elements (id.). 3 Consistent with the Company’s focus on using finite resources efficiently and 4 effectively, Eversource uses this initial screening to ensure that, from a practical and 5 Company policy standpoint, the identified capital project does not pose any 6 insurmountable obstacles for an NWA solution before further analysis is conducted (id. 7 at 9). To this end, the Critical Suitability Criteria included in the NWA Screening Tool 8 poses a go-no-go decision point in the NWA screening process. Any project site that 9 does not pass both criteria listed below will be disqualified from further NWA 10 consideration and the Company will move forward with developing a traditional 11 solution: 12 • 13 14 Asset Health Index < 0.5: Any substation with a transformer’s asset health index above 0.5 will not be considered as an NWA candidate; and • Year of First Violation ≥ 2: Any constraint that appears with two or fewer years 15 from the base year will not be considered for an NWA solution, as the 16 timeframes for solution design and procurement would not be amenable, and a 17 traditional solution provides a faster and safer alternative to address the issues 18 identified at the site (id.). 19 Based on the design of the NWA Framework, as well as the Company’s commitment 20 to cost-effective utilization of its resources, no further analysis will be performed toPage 26 of 34
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-ADDITIONS-REBUTTAL-1 November 18, 2026 Page 24 of 32 1 engineer or design an NWA solution for an identified capital project if the NWA 2 solution does not pass the NWA Screening stage, and is therefore considered non- 3 viable. 4 Accordingly, Mr. Balakumar is incorrect in concluding that NWA analyses will always 5 be accompanied by well-developed designs and cost estimates. 6 7 Q. Were all of the capacity projects included in OCC-805, Attachment 1 required to be screened under the 2021 NWA Framework? 8 A. No. A review of the 10 in-service capacity projects included in OCC-805, Attachment 9 1 indicates that five of the projects (CS00273, CS00272, CS00247, 201444, and 10 CS00061) were placed into service in either 2018 or 2019, well before the Company, 11 on its own initiative, developed and implemented the 2021 NWA Framework. Further, 12 the 2021 NWA Framework, which the Company developed and implemented on its 13 own initiative, could not be utilized retroactively as the wires solutions were already 14 placed into service. 15 Although Projects CS00273, CS00272, CS00247, 201444, and CS00061 could not be 16 screened under the 2021 NWA Framework, the Company still identified and evaluated 17 wires alternatives to the selected wires solution. All of the PAFs associated with 18 Projects CS00273, CS00272, CS00247, 201444, and CS00061 include alternatives 19 along with a technical and/or operational explanation supporting the chosen solution. 20 The PAFs also include explanations regarding the limits or deficiencies associated with 21 the alternatives that ultimately led the Company’s subject matter experts to discard the
Text of Exhibit CLP-ADDITIONS-REBUTTAL-4.pdf
Extracted from the file · 8 pages · 21,808 characters
Text of Exhibit CLP-ADDITIONS-REBUTTAL-8 REDACTED.pdf
Extracted from the file · 502 pages · 144,946 characters
As listed on the current system
Prefiled testimony: 11/18/2026 - Sponsor: TBD / Witness: DAVID L. GLADEY, JOHN P. DIPAOLA-TROMBA, LEANNE M. LANDRY, AND JEFFREY D. TURANO [26-05-10]