  1. Page 21 of 34

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-ADDITIONS-REBUTTAL-1 November 18, 2026 Page 19 of 32 1 part of the replacement project, including the cost of civil work, on-site generation and 2 other efforts that require additional cost to get the work done. 3 Thus, the central flaw of Mr. Balakumar’s theory is that the changes in cost-per-mile 4 do not coincide with the years in which the Company made changes to its replacement 5 strategy. In the years 2017-2019, the Company’s costs per mile were stable – in the 6 range of $600,000 per mile, until COVID occurred in 2020, starting the upward cost 7 trend. Similarly, the cost-per-mile in 2024 and 2025 is the same as in 2022 – in the 8 range of $1.1 to $1.2 million per mile, although the Company transitioned to a hybrid 9 repair/replacement strategy in 2024. As a result, it is not the Company’s change in 10 program strategy that is driving the cost change. Instead, the Company decided to 11 transition to the repair/replacement strategy to mitigate the impact and inconvenience 12 of the program for customers, while reducing the overall cost of the program as 13 compared to other priorities that the Company has. This is a feasible transition because 14 the Company can maintain reliability through the hybrid repair without needing to rely 15 on as much replacement work as in the past. 16 Without accounting for the impact of post-COVID construction cost changes, Mr. 17 Balakumar’s extrapolation of historical average costs to subsequent years does not 18 demonstrate that the additional expenditures were unreasonable or could have been 19 avoided. Nor does the Company’s adoption of a hybrid replacement and repair strategy 20 suggest that the prior replacement program was imprudent – after COVID, the cost- 21 per-mile for replacement is the same for the hybrid strategy as it was for the
  2. Page 22 of 34

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-ADDITIONS-REBUTTAL-1 November 18, 2026 Page 20 of 32 1 replacement strategy. Instead, the Company’s decision reflected a prudent 2 reassessment of its approach in light of operating experience with customer impacts 3 and changing system needs, calling for a reprioritization and reallocation of capital 4 resources. The Company’s modification of the program in response to new information 5 does not mean the original decisions were unreasonable or imprudent when they were 6 made. 7 As a result, Mr. Balakumar’s proposed adjustment lacks a sound factual and analytical 8 basis for concluding that the Company’s expenditures were imprudent. 9 C. Capacity Projects 10 11 12 Q. Please summarize the portion of Mr. Balakumar’s testimony that is specific to his conclusions and recommendations regarding certain capacity projects placed into service between 2023 and 2025. 13 A. Mr. Balakumar argues that PURA should require the Company produce, before the 14 record closes, the contemporaneous evaluation of non-wires alternatives (“NWAs”), 15 the load forecast and the authorization documents for each Peak Load/Capacity project 16 placed in service from 2023 through 2025 with a total investment of $145.4 million 17 (Balakumar Testimony at 92). In the event that the Company cannot provide the 18 relevant documentation, Mr. Balakumar recommends that PURA determine that the 19 project(s) were imprudent and disallow the cost above the least-cost alternative where 20 one was available (id. at 92-93). We do not agree with this conclusion.
  3. Page 23 of 34

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-ADDITIONS-REBUTTAL-1 November 18, 2026 Page 21 of 32 1 Q. What does Mr. Balakumar rely on to support this recommendation? 2 A. Mr. Balakumar contends that the record currently does not contain sufficient evidence 3 to determine if the Company evaluated lower-cost alternatives before it built the 4 capacity projects placed in service from 2023 through 2025 (Balakumar Testimony at 5 86). In reaching this conclusion, Mr. Balakumar relies primarily on the Company’s 6 response to OCC-805, which requested that the Company address each substation 7 capacity project undertaken during 2017 through 2025, with the load forecast and 8 planning criterion relied upon at authorization; the measured peak load in the five years 9 after in-service; the total cost; and any non-wires alternative evaluation. 10 According to Mr. Balakumar, capacity needs that are modest in size or short in duration 11 are where lower-cost alternatives are most likely to be viable (id. at 86). He references 12 the Company’s Project Authorization Forms (“PAFs”), as well as the 2021 NWA 13 Framework (OCC-578, Attachment 1), as requiring NWA analyses for capacity 14 projects (id.). 15 Next, Mr. Balakumar refers to the Company’s response to OCC-805, Attachment 1, to 16 arrive at the conclusion that the record does not show that the Company applied the 17 required NWA analyses to the capacity projects included in OCC-805, Attachment 1 18 (id. at 88). This conclusion underpins his recommendations to PURA. 19 Q. Are his conclusions regarding the 2021 NWA Framework accurate? 20 A. No. In his testimony, Mr. Balakumar claims that the Company’s response to OCC- 21 805, Attachment 1 does not identify the NWAs considered, their cost relative to the
  4. Page 24 of 34

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-ADDITIONS-REBUTTAL-1 November 18, 2026 Page 22 of 32 1 wires solution, or why they were not selected (Balakumar Testimony at 88). However, 2 this statement rests on the presumption that the Company develops full NWA cost 3 estimates for all capacity projects, which it does not – in accordance with the 4 Company’s screening framework. 5 Importantly, the Company endeavored to submit its 2021 NWA Framework to PURA 6 as part of PURA’s Docket No. 17-12-03RE07 several times and PURA chose not to 7 engage with the Company on this framework, instead opting to create an entirely new 8 process, which took several years to develop (PURA did not require Eversource to 9 follow a PURA-mandated formal NWS framework until 1/1/2025). Consequently, the 10 Company applied its own screening process to review solutions while PURA 11 deliberated on its new process. Thus, as set out in OCC-578, Attachment 1, at 7, the 12 Company utilized an NWA Screening Tool as part of its own 2021 NWA Framework 13 to quickly evaluate the potential applicability of NWA solutions to meet capacity 14 project needs at specific locations, with the intent that only sites that are suitable and 15 viable for NWA solutions will move to a more detailed, engineering analysis stage. 16 The NWA Screening Tool enables rapid initial screening of NWA options against 17 traditional system upgrade projects but does not provide detailed and accurate costing 18 or technical solution design (id.). Once an NWA solution passes the NWA Screening 19 stage as a suitable and technically viable solution, the Company will perform detailed 20 steady-state and transient analysis studies as well as develop engineering designs and 21 cost estimates for the identified solution (id.). It is important to note that it is still
  5. Page 25 of 34

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-ADDITIONS-REBUTTAL-1 November 18, 2026 Page 23 of 32 1 possible that an NWA solution will ultimately not be selected as the preferred solution 2 due to inferior technical or cost elements (id.). 3 Consistent with the Company’s focus on using finite resources efficiently and 4 effectively, Eversource uses this initial screening to ensure that, from a practical and 5 Company policy standpoint, the identified capital project does not pose any 6 insurmountable obstacles for an NWA solution before further analysis is conducted (id. 7 at 9). To this end, the Critical Suitability Criteria included in the NWA Screening Tool 8 poses a go-no-go decision point in the NWA screening process. Any project site that 9 does not pass both criteria listed below will be disqualified from further NWA 10 consideration and the Company will move forward with developing a traditional 11 solution: 12 • 13 14 Asset Health Index < 0.5: Any substation with a transformer’s asset health index above 0.5 will not be considered as an NWA candidate; and • Year of First Violation ≥ 2: Any constraint that appears with two or fewer years 15 from the base year will not be considered for an NWA solution, as the 16 timeframes for solution design and procurement would not be amenable, and a 17 traditional solution provides a faster and safer alternative to address the issues 18 identified at the site (id.). 19 Based on the design of the NWA Framework, as well as the Company’s commitment 20 to cost-effective utilization of its resources, no further analysis will be performed to
  6. Page 26 of 34

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-ADDITIONS-REBUTTAL-1 November 18, 2026 Page 24 of 32 1 engineer or design an NWA solution for an identified capital project if the NWA 2 solution does not pass the NWA Screening stage, and is therefore considered non- 3 viable. 4 Accordingly, Mr. Balakumar is incorrect in concluding that NWA analyses will always 5 be accompanied by well-developed designs and cost estimates. 6 7 Q. Were all of the capacity projects included in OCC-805, Attachment 1 required to be screened under the 2021 NWA Framework? 8 A. No. A review of the 10 in-service capacity projects included in OCC-805, Attachment 9 1 indicates that five of the projects (CS00273, CS00272, CS00247, 201444, and 10 CS00061) were placed into service in either 2018 or 2019, well before the Company, 11 on its own initiative, developed and implemented the 2021 NWA Framework. Further, 12 the 2021 NWA Framework, which the Company developed and implemented on its 13 own initiative, could not be utilized retroactively as the wires solutions were already 14 placed into service. 15 Although Projects CS00273, CS00272, CS00247, 201444, and CS00061 could not be 16 screened under the 2021 NWA Framework, the Company still identified and evaluated 17 wires alternatives to the selected wires solution. All of the PAFs associated with 18 Projects CS00273, CS00272, CS00247, 201444, and CS00061 include alternatives 19 along with a technical and/or operational explanation supporting the chosen solution. 20 The PAFs also include explanations regarding the limits or deficiencies associated with 21 the alternatives that ultimately led the Company’s subject matter experts to discard the
  7. Page 27 of 34

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-ADDITIONS-REBUTTAL-1 November 18, 2026 Page 25 of 32 1 alternatives in favor of the selected solution. The relevant PAFs are being provided as 2 Exhibit CLP-ADDITIONS-REBUTTAL-8 for ease of review. 3 4 Q. Are Mr. Balakumar’s conclusions about the remaining projects on OCC-805, Attachment 1 correct? 5 A. No. Again, a review of the project documentation the Company provided for Projects 6 CS00365, CS00284, CS00516, CS00261, and CS00166 demonstrates that these 7 projects either failed to pass the NWA Screening or were presented to and approved by 8 the Solution Design Committee (“SDC”) 3 prior to the development and implementation 9 of the 2021 NWA Framework. Given its focus on efficiently and effectively utilizing 10 its resources and funds to ensure that customers receive safe and reliable service, the 11 Company does not retroactively apply the 2021 NWA Framework to wires solutions 12 that have already been approved by the SDC and are progressing through final design 13 and construction. Due to this, a number of the projects were not analyzed under the 14 2021 NWA Framework based on the year they were presented to and approved by the 15 SDC. We address each of the projects below. The relevant PAFs are being provided 16 as Exhibit CLP-ADDITIONS-REBUTTAL-8 for ease of review. 17 3 The SDC’s role is to ensure that the best solution for the identified need is selected (Exhibit CLPADDITIONS-1, at 36). The SDC reviews the selected solution, as well as the project alternatives, scope and conceptual grade cost estimates during the solution vetting process (id.). Following its review, the SDC will confirm that the project initiator has selected the best solution for the identified need (id.).
  8. Page 28 of 34

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-ADDITIONS-REBUTTAL-1 November 18, 2026 Page 26 of 32 1 • Project CS00166 – as shown on page 27 of the PAF, this project was presented 2 to the SDC on November 13, 2019. The SDC reviewed the preferred solution, 3 as well as the alternative solutions described on pages 27 through 29 of the PAF. 4 Following this review, the SDC approved the chosen wires solution. Even if 5 Project CS00166 had been subject to the 2021 NWA Framework, the 6 information included in the PAF’s project need and justification sections 7 demonstrates that the capacity needs associated with the project could not be 8 characterized as modest in size or short in duration, making them suitable for 9 lower-cost alternatives such as NWAs (Balakumar Testimony at 86). 10 • Project CS00261 – As shown on pages 1 and 18 of the PAF, this project was 11 presented to the SDC on February 19, 2020. The SDC reviewed the preferred 12 solution, as well as the alternative solutions described on pages 18 through 21 13 of the PAF. Following this review, the SDC approved the chosen wires 14 solution. Even if Project CS00261 had been subject to the 2021 NWA 15 Framework, the information included in the PAF’s project need and 16 justification sections demonstrates that the capacity needs associated with the 17 project could not be characterized as modest in size or short in duration, making 18 them suitable for lower-cost alternatives such as NWAs (Balakumar Testimony 19 at 86). 20 21 • Project CS00516 – As shown on page 1 of the PAF, the alternatives and complete preferred project scope was presented to the SDC on December 8,
  9. Page 29 of 34

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-ADDITIONS-REBUTTAL-1 November 18, 2026 Page 27 of 32 1 2021. The information provided on pages 5 and 10 of the PAF demonstrate that 2 this project did not pass the NWA Screening Tool due to the poor health index 3 of the transformers at issue in connection with this project, meaning that an 4 NWA was not viable to address the capacity issues identified by the Company. 5 Accordingly, since the project did not pass the NWA Screening Tool, the 6 Company did not expend further resources or funds on analyzing NWA 7 solutions. The SDC reviewed the preferred solution, as well as the alternative 8 solutions described on pages 9 and 10 of the PAF. Following this review, the 9 SDC approved the chosen wires solution. 10 • Project CS00284 - As shown on page 21 of the PAF, this project was presented 11 to the SDC on July 8, 2020. The SDC reviewed the preferred solution, as well 12 as the alternative solutions described on pages 21-27 of the PAF. Following 13 this review, the SDC approved the chosen wires solution. Even if Project 14 CS00284 had been subject to the 2021 NWA Framework, the information 15 included in the PAF’s project need and justification sections demonstrates that 16 the capacity needs associated with the project could not be characterized as 17 modest in size or short in duration, making them suitable for lower-cost 18 alternatives such as NWAs (Balakumar Testimony at 86). 19 Project CS00365 – following extensive technical review, the Company’s 20 subject matter experts (“SMEs”) determined that 21 appropriate solution for this project. an NWA was not an Specifically, the Company’s SMEs
  10. Page 30 of 34

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-ADDITIONS-REBUTTAL-1 November 18, 2026 Page 28 of 32 1 determined that a battery energy storage system (“BESS”) was not feasible for 2 a number of reasons, including: (1) the size of the BESS that would be required 3 to address the identified capacity issues; (2) that the transformer assets, given 4 their age and condition, would not pass the NWA screening; and (3) the fact 5 that a BESS would not provide any of the same benefits that the Company, and 6 its customers, would realize through converting the substation from 27.6 kV 7 voltage to 23 kV. Following a review of the preferred project scope, as well as 8 the alternatives, the SDC approved the preferred scope on May 26, 2021. 9 10 11 Q. Do you agree with Mr. Balakumar’s recommendation that PURA disallow certain costs associated with the capacity projects listed OCC-805, Attachment 1 if the overload forecasts supporting those projects did not occur? 12 A. No, we do not agree with that. On page 88 of his testimony, Mr. Balakumar states that 13 if after further discovery, the record shows that the Company built capacity without 14 evaluating lower-cost alternatives, or that the forecast overloads did not occur, he plans 15 to recommend that PURA disallow the difference between the cost of the project and 16 the cost of the least-cost alternative. As discussed above, the Company did consider 17 lower-cost alternatives to the chosen capacity solutions, either through its 2021 NWA 18 Framework, which the Company implemented years prior to PURA establishing an 19 NWS mandate showcasing the Company’s commitment to evaluating all options 20 (noting that the authority refused to discuss and admit into evidence the Company’s 21 NWA Framework in the original 17-12-03RE07 docket), or its analysis of alternate 22 wires solutions. Moreover, the Company’s forecast already considers a load offset for
Words on different pages
1 page match

Text of Exhibit CLP-ADDITIONS-REBUTTAL-4.pdf

Extracted from the file · 8 pages · 21,808 characters

Text of Exhibit CLP-ADDITIONS-REBUTTAL-8 REDACTED.pdf

Extracted from the file · 502 pages · 144,946 characters