Skip to main content

A prototype public docket site for the Connecticut Public Utilities Regulatory Authority

Utility Dockets and Filings

Prefiled testimony

Witness: DAVID L. GLADEY, JOHN P. DIPAOLA-TROMBA, LEANNE M. LANDRY, AND JEFFREY D. TURANO

Files6

Search terms highlighted
Eversource rate increase is on 8 pages across 4 files of the text below, highlighted. Go to the first matchClear highlighting
Words on different pages
1 page match
Words on different pages

Text of Exhibit CLP-ADDITIONS-REBUTTAL-3.pdf

Extracted from the file · 73 pages · 332,525 characters

Text of Exhibit CLP-ADDITIONS-REBUTTAL-4.pdf

Extracted from the file · 8 pages · 21,808 characters

1 page match
  1. Page 386 of 502

    The Connecticut Light and Power Company d/b/a Eversource Energy REDACTED Docket No. 26-05-10 Exhibit CLP-ADDITIONS-REBUTTAL-8 REDACTED Page 386 of 502
  2. Page 387 of 502

    The Connecticut Light and Power Company d/b/a Eversource Energy REDACTED Docket No. 26-05-10 Exhibit CLP-ADDITIONS-REBUTTAL-8 REDACTED Page 387 of 502
  3. Page 388 of 502

    The Connecticut Light and Power Company d/b/a Eversource Energy REDACTED Docket No. 26-05-10 Exhibit CLP-ADDITIONS-REBUTTAL-8 REDACTED Page 388 of 502
  4. Page 389 of 502

    The Connecticut Light and Power Company d/b/a Eversource Energy REDACTED Docket No. 26-05-10 Exhibit CLP-ADDITIONS-REBUTTAL-8 REDACTED Page 389 of 502
  5. Page 390 of 502

    The Connecticut Light and Power Company d/b/a Eversource Energy REDACTED Docket No. 26-05-10 Exhibit CLP-ADDITIONS-REBUTTAL-8 REDACTED Page 390 of 502 Project Authorization Form station, Peaceable 12N, is approaching its limit. The only transfer available without causing an overload is 3.5MVA to Triangle 11A57 for about $600K picking up the 22N6-71S zone. Not gaining capacity at will result in replacing Peaceable 12N transformers and switchgear. This project could be deferred with option 1 for 5-10 years. After the Peaceable 12N project is completed a larger offload from can be accomplished. Cost Estimate – $28.5M (Repair 22N-3X - $3.83M + Peaceable 12N - $22-24M + load transfer $600K) conceptual estimate. Advantages – None Disadvantages – The repair process would take 12-15 months and during this time the station would be on a mobile position and field ties would be in abnormal condition during peak loading conditions. Distribution design is exploring adding feeder positions to . If the transformer is repaired instead of replaced, the full benefit of the additional feeder positions would not be realized. The electromechanical relay upgrade to microprocessor isn’t included in the estimate. The Peaceable 12N station upgrade is very costly, and the cost cannot be deferred with this option. Replacement of the Peaceable 12N transformers will be challenging due to the lack of space and station arrangement. The -2X is similar vintage and condition as the 22N-3X and this option does not include the replacement of this transformer. The replacement of the 22N-3X is a much longer solution and more cost effective than repairing. This option is also the higher cost. Alternative 3 - NWA (Non-wires Alternative) Does not qualify due to poor health indexes for both transformers. Alternatives 4 - Do Nothing Not recommended to do nothing with the -3X due to it having failed once. Not recommended to do nothing with the 2X due to it having the same age, vintage, and poor health index rating. Also, the station exceeded its LCC limit in 2021 and there is limited ability to transfer load as stated above in Alternative 2. JA-AM-2001-A, Rev. 5 Page 11 of 16
  6. Page 391 of 502

    The Connecticut Light and Power Company d/b/a Eversource Energy REDACTED Docket No. 26-05-10 Exhibit CLP-ADDITIONS-REBUTTAL-8 REDACTED Page 391 of 502
  7. Page 392 of 502

    The Connecticut Light and Power Company d/b/a Eversource Energy REDACTED Docket No. 26-05-10 Exhibit CLP-ADDITIONS-REBUTTAL-8 REDACTED Page 392 of 502
  8. Page 393 of 502

    The Connecticut Light and Power Company d/b/a Eversource Energy REDACTED Docket No. 26-05-10 Exhibit CLP-ADDITIONS-REBUTTAL-8 REDACTED Page 393 of 502
  9. Page 394 of 502

    The Connecticut Light and Power Company d/b/a Eversource Energy REDACTED Docket No. 26-05-10 Exhibit CLP-ADDITIONS-REBUTTAL-8 REDACTED Page 394 of 502
  10. Page 395 of 502

    The Connecticut Light and Power Company d/b/a Eversource Energy REDACTED Docket No. 26-05-10 Exhibit CLP-ADDITIONS-REBUTTAL-8 REDACTED Page 395 of 502