Skip to main content

A prototype public docket site for the Connecticut Public Utilities Regulatory Authority

Utility Dockets and Filings

Prefiled testimony

Witness: DAVID L. GLADEY, JOHN P. DIPAOLA-TROMBA, LEANNE M. LANDRY, AND JEFFREY D. TURANO

Files6

Search terms highlighted
Eversource rate increase is on 8 pages across 4 files of the text below, highlighted. Go to the first matchClear highlighting
Words on different pages
1 page match
Words on different pages

Text of Exhibit CLP-ADDITIONS-REBUTTAL-3.pdf

Extracted from the file · 73 pages · 332,525 characters

Text of Exhibit CLP-ADDITIONS-REBUTTAL-4.pdf

Extracted from the file · 8 pages · 21,808 characters

1 page match
  1. Page 493 of 502

    The Connecticut Light and Power Company d/b/a Eversource Energy REDACTED Docket No. 26-05-10 Exhibit CLP-ADDITIONS-REBUTTAL-8 REDACTED Page 493 of 502
  2. Page 494 of 502

    The Connecticut Light and Power Company d/b/a Eversource Energy REDACTED Docket No. 26-05-10 Exhibit CLP-ADDITIONS-REBUTTAL-8 REDACTED Page 494 of 502
  3. Page 495 of 502

    The Connecticut Light and Power Company d/b/a Eversource Energy REDACTED Docket No. 26-05-10 Exhibit CLP-ADDITIONS-REBUTTAL-8 REDACTED Page 495 of 502 b. Distribution $2,855K - Major factors that have led to increases in the distribution construction costs are: $527K - Allowances included to cover future unexpected charges associated with test support, temporary wiring, SCADA and Network Communications, material handling, stand by time, premium time coverage, winter conditions, and rock removal. $258K - A mobile transformer installation is required per The Connecticut System Operations Center (SOC) while the ransformer is replaced due to Single Contingency Load Loss (SCLL) conditions of the ransformer. The use of a mobile transformer was not included in the original estimate. $2,168K - Testing and Commissioning vendor charges are included in the Prime Electrical Construction vendor’s contract. 8. Testing/Commissioning: ($3,534K) - Testing and Commissioning vendor charges are included in Construction vendor’s contract (Item #7 shown above). a. Transmission ($1,366K) b. Distribution ($2,168) 9. Project Management Team: $2,249K - Additional Project Management Team time is required due to the actual construction schedule exceeding the duration originally accounted for in the project estimate. The estimate considered a project duration of 45 weeks (from June 2023 until April 2024). Actual project duration is projected to be 155 weeks (from September 2023 until August 2026). The original project schedule used during estimation was unrealistic since it considered a timeline that was overly ambitious for the scope of work included in this project. a. Transmission $1,854K b. Distribution $395K 10. Removals: $385K - Removal projections have increased due to higher than anticipated project costs. a. Transmission $252K b. Distribution $133K 11. Risks: $2,319K - The project still has a significant amount of work remaining, and several risks have been identified. These are primarily related to potential challenges in the completion of planned outages due to delays in mobile transformer delivery and installation, testing and commissioning issues, late issuance of drawings, and material delivery setbacks. a. Transmission $771K Form Template Revised 03/13/2024 APS 1 – Project Authorization Policy Issued 12/31/21 Rev. 6 Policy Sponsor: EVP and CFO JA-AM-2001-A Rev. 7 Page 6
  4. Page 496 of 502

    The Connecticut Light and Power Company d/b/a Eversource Energy REDACTED Docket No. 26-05-10 Exhibit CLP-ADDITIONS-REBUTTAL-8 REDACTED Page 496 of 502 b. Distribution $1,548K 12. Indirects/Overhead: $3,964K - Indirects were higher due to the increase in direct costs. a. Transmission $1,505K b. Distribution $2,459K 13. AFUDC: $4,374K - AFUDC has increased as a result of extended project duration beyond initial schedule projections. a. Transmission $1,265K b. Distribution $3,109 Total Supplement Request: $21,993K Form Template Revised 03/13/2024 APS 1 – Project Authorization Policy Issued 12/31/21 Rev. 6 Policy Sponsor: EVP and CFO JA-AM-2001-A Rev. 7 Page 7
  5. Page 497 of 502

    The Connecticut Light and Power Company d/b/a Eversource Energy REDACTED Docket No. 26-05-10 Exhibit CLP-ADDITIONS-REBUTTAL-8 REDACTED Page 497 of 502
  6. Page 498 of 502

    The Connecticut Light and Power Company d/b/a Eversource Energy REDACTED Docket No. 26-05-10 Exhibit CLP-ADDITIONS-REBUTTAL-8 REDACTED Page 498 of 502
  7. Page 499 of 502

    The Connecticut Light and Power Company d/b/a Eversource Energy REDACTED Docket No. 26-05-10 Exhibit CLP-ADDITIONS-REBUTTAL-8 REDACTED Page 499 of 502
  8. Page 500 of 502

    The Connecticut Light and Power Company d/b/a Eversource Energy REDACTED Docket No. 26-05-10 Exhibit CLP-ADDITIONS-REBUTTAL-8 REDACTED Page 500 of 502
  9. Page 501 of 502

    The Connecticut Light and Power Company d/b/a Eversource Energy REDACTED Docket No. 26-05-10 Exhibit CLP-ADDITIONS-REBUTTAL-8 REDACTED Page 501 of 502
  10. Page 502 of 502

    The Connecticut Light and Power Company d/b/a Eversource Energy REDACTED Docket No. 26-05-10 Exhibit CLP-ADDITIONS-REBUTTAL-8 REDACTED Page 502 of 502