Prefiled testimony
Witness: DONALD J. SCACCO, JR., DIGAUNTO CHATTERJEE AND DOUGLAS P. HORTON
Files2
Docket No. 26-05-10 CLP Rebuttals Filing Letter (11.18.26).pdf
PDF · 152 KB · 3 pagesText searchable
Download Docket No. 26-05-10 CLP Rebuttals Filing Letter (11.18.26).pdfRead the text of Docket No. 26-05-10 CLP Rebuttals Filing Letter (11.18.26).pdf
Exhibit CLP-LEADERSHIP-REBUTTAL-1.pdf
PDF · 712 KB · 100 pagesText searchable
Download Exhibit CLP-LEADERSHIP-REBUTTAL-1.pdfRead the text of Exhibit CLP-LEADERSHIP-REBUTTAL-1.pdf
Page 23 of 100
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-LEADERSHIP-REBUTTAL-1 November 18, 2026 Page 21 of 98 1 ⇒ Like the CT-Bar, the Company’s F-Factor links the capital investments 2 needed to achieve the electric grid’s target performance, as set out in the 3 Company’s TSP, to the revenues required to support those investments. In 4 developing the F-Factor, the Company aimed to directly tie revenue 5 allowances to the capital investment forecasts discussed in this docket. This 6 approach keeps the TSP focused on system needs and objectives while 7 recognizing that these goals inherently require revenue support. The F-Factor 8 thus serves as the essential connection between the system needs evaluated in 9 this proceeding and the revenues necessary to meet them. 10 ⇒ Like the CT-Bar, annual reconciliation of the revenue requirement ensures 11 that customers pay only for prudent capital investments, while also 12 allowing the utility to cover the ongoing costs of providing service. 13 Importantly, the Company’s F-Factor proposal does not bypass prudence 14 reviews—essential components of effective regulatory frameworks—nor 15 diminish their value to customers. The Company fully recognizes that any 16 capital investment must withstand rigorous prudence review. Any findings of 17 imprudence regarding current capital investments can have significant financial 18 consequences, regardless of timing. As a result, the expectation of future 19 prudence reviews reinforces prudent decision-making today. Furthermore, the 20 risk of a future finding of imprudence and the associated financial penalties 21 eliminates any perceived incentive for the Company to “over-invest” now.Page 24 of 100
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-LEADERSHIP-REBUTTAL-1 November 18, 2026 Page 22 of 98 1 ⇒ To aid in clarity on the operation of the F Factor: The Company is 2 submitting EXHIBIT CLP-RATES-REBUTTAL-2, as part of Rates rebuttal 3 testimony to assist in responding to the claims of the various parties and 4 intervenors. The Company’s Rate Application originally anticipated that rate 5 year capital would be reflected in base rates effective July 1, 2027, and that the 6 first F-Factor would take place a year later on July 1, 2028. To both conform 7 to the design contemplated by the CT Bar, and in order to assure that plant 8 additions included in base rates as a result of this proceeding have sufficient 9 time for review in this proceeding, the Company has modified the PBMRP 10 Tariff to reflect the fact that the F-Factor would go into effect on July 1, 2027, 11 commensurate with new base rates in this proceeding and would capture the 12 prospective revenue requirement on plant additions after the base-rate cutoff, 13 subject to the same review reconciliation procedures which are components of 14 the Company’s F-Factor proposal. 15 Accordingly, the Company’s proposed F-Factor is substantially aligned with the CT- 16 Bar in both structure and intent. The modifications to the F-Factor proposed by the 17 Company are needed to address three key deficiencies in the CT-Bar framework: 18 (1) exclusion of the cost of capital associated with incremental plant additions; 19 (2) exclusion of the cost of removal; and (3) a mechanical error in deducting 20 depreciation expense from new plant additions rather than from the rate base. The F-Page 25 of 100
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-LEADERSHIP-REBUTTAL-1 November 18, 2026 Page 23 of 98 1 Factor remedies the first two issues by incorporating them into the revenue requirement 2 calculation and corrects the third. 3 Inclusion of Cost of Capital. A bedrock principle of ratemaking is that rates must 4 allow a utility to fully recover its cost of service, including its cost of capital. As 5 currently designed, the CT-Bar does not meet this requirement, and adopting it would 6 significantly impair the Company’s ability to make the investments needed to maintain 7 safe and reliable service throughout the PBMRP term. 8 Although the cost of capital is less visible than other service costs, such as maintaining 9 aging equipment or fueling line trucks, it is just as real. The Company frequently faces 10 a cash deficit, where the funds needed for ongoing operations exceed customer 11 revenues. This shortfall must be financed by debt and equity investors, those who 12 provide capital through financial markets. These investors have nearly unlimited 13 alternatives and consider many factors when deciding where to allocate their funds, 14 such as competing utilities, industries, markets, investment durations, expected returns, 15 dividends, and risk. The Company cannot expect investors to supply capital without 16 adequate compensation, given the many other available opportunities. Therefore, the 17 cost of securing the capital required for the system’s ongoing investments is a genuine 18 and unavoidable cost of service. 19 Moreover, including the cost of capital in the F-Factor does not result in the Company 20 inappropriately earning on capital additions before they are placed into service for thePage 26 of 100
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-LEADERSHIP-REBUTTAL-1 November 18, 2026 Page 24 of 98 1 benefit of customers, or before a prudence determination. The operation of the F-Factor 2 provides a level of revenue support that appropriately balances the interests of 3 customers and of the Company by providing a level of revenue support (based on the 4 forecasted capital presented in the TSP), while limiting that revenue support in the 5 event the Company is required to invest more than it expects to today, crediting to 6 customers any over-recovery in the event the Company spends less than it expects to 7 today, or in the event of a future prudence disallowance by PURA. In the current 8 environment, highlighted on the one hand by a need for sustained, elevated, and 9 growing capital infrastructure requirements and on the other hand by a world with 10 relatively flat overall sales volume increases, and with full revenue decoupling in any 11 event, the Company is not able to support the cost of ongoing investment without the 12 added revenue support of a mechanism substantially similar to the F-Factor. 13 In fact, implementation of an F-Factor mechanism has the added benefit of instituting 14 a form of regulatory lag, as used to exist naturally for utilities when operating at the 15 time (i.e., two or more decades ago) when sales volumes (and associated customer 16 revenues) were generally increasing at a fairly steady clip year over year to provide 17 added revenues to support incremental capital investments that were not directly 18 reflected in utility rates in the period between rate cases. 19 Inclusion of Cost of Removal and Deducting Depreciation Expense. The F-Factor 20 calculation captures the impact of ongoing depreciation accumulating in rate base, 21 which has the effect of reducing overall revenue requirements. Additionally, thePage 27 of 100
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-LEADERSHIP-REBUTTAL-1 November 18, 2026 Page 25 of 98 1 Company’s F-Factor calculation captures the reduced revenue requirement resulting 2 from plant retirements and accumulated deferred income taxes, while also 3 incorporating the effect of cost of removal on rate base. 4 Thus, the Company has designed its proposed F-Factor to follow the CT-Bar 5 framework as closely as practicable, while the CT-Bar’s fundamental defects make its 6 full adoption unworkable for the reasons discussed above. The Company cannot 7 responsibly proceed with the PBMRP under a mechanism that, by design, fails to 8 provide even a perfectly operating utility, and with the benefit of hindsight, with the 9 opportunity for revenues that reflect its costs, including its cost of capital. Such a 10 mechanism undermines necessary capital investment and threatens the performance 11 objectives the PBMRP is intended to achieve. 12 As discussed extensively in Docket No. 21-05-15RE01, a workable performance-based 13 regulatory framework requires both an appropriate going-in revenue requirement and 14 a mechanism for ongoing recovery of the revenue requirement associated with 15 incremental capital investment. Without sufficient revenues to cover the cost of service 16 (including the cost of capital and cost of removal), the Company would be forced to 17 absorb significant capital costs without a reasonable opportunity to earn its authorized 18 ROE and would not be in a position to commit to a stay-out of any duration. A multi- 19 year rate stay-out would be unworkable under such a framework, given the substantial 20 system investments needed to maintain and improve customer service. In the absence 21 of a multi-year rate plan, the Company anticipates filing rate cases on a rolling basis,Page 28 of 100
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-LEADERSHIP-REBUTTAL-1 November 18, 2026 Page 26 of 98 1 with base rate changes effective January 1, 2029, July 1, 2030, and January 1, 2032 2 (Exh. EOE-156, at 3). 3 4 5 6 7 8 Q. Ms. Griffin states that the Company’s proposal “does not recognize that some capital additions would already be covered by what is provided in base rates” and that CT-Bar “would more appropriately recognize the recovery of such infrastructure replacement programs” because it “was designed to deduct depreciation expense already included in going-in rates from plant additions eligible for supplemental recovery.” Is that accurate? 9 A. No. Both propositions are incorrect. As stated in the Company’s responses to multiple 10 interrogatories, including OCC-859, OCC-423, OCC-436, OCC-427, EOE-156, and 11 UPA-082, among others, the Company’s F-Factor expressly accounts for ongoing 12 depreciation reflected in base rates, which reduces the rate base on which a return is 13 calculated and, therefore, the resulting revenue requirement. 14 Company’s F-Factor reflects ongoing depreciation consistent with the underlying 15 accounting, whereas CT-Bar does not. 16 In addition, the Company’s response to OCC-423 explains that CT-Bar nets ongoing 17 depreciation against new plant additions before calculating depreciation expense on the 18 new investment, thereby understating the resulting depreciation expense. For example, 19 if the Company has $100 million of new plant additions, $20 million of ongoing 20 depreciation, and an applicable depreciation rate of 3.75%, new depreciation expense 21 related to the investment would be $100 million × 3.75%, or $3.75 million. CT-Bar 22 instead nets the $20 million of ongoing depreciation against the $100 million of new 23 plant and calculates depreciation expense on the resulting $80 million, producing $3.0 Moreover, thePage 29 of 100
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-LEADERSHIP-REBUTTAL-1 November 18, 2026 Page 27 of 98 1 million of depreciation expense. Ongoing depreciation properly reduces the 2 investment base on which a return is calculated. It does not reduce the amount of new 3 plant that generates new depreciation expense. 4 3. Distribution System Planning 5 6 7 Q. As discussed above, the OCC’s witnesses and Ms. Griffin contend that the TSP is inadequate because it was not developed through the IDSP framework developed in Docket No. 21-05-15. What is your response to that contention? 8 A. The OCC’s witnesses and Ms. Griffin’s arguments are unavailing for several reasons. 9 First, the IDSP framework proposed in Docket No. 21-05-15RE03 was never adopted 10 as a mandatory planning requirement for the Company. There is no requirement for 11 the Company to implement that framework, nor do the OCC or Ms. Griffin provide any 12 justification for treating it as a prerequisite to PURA’s review of the Company’s 13 proposed capital investments in this proceeding. That a separate planning framework 14 was proposed in another proceeding does not make it the exclusive or required method 15 for evaluating the Company’s capital investment plan. PURA should assess the 16 Company’s TSP on its own merits, rather than comparing it to an unapproved 17 framework in a separate uncontested docket. 18 Second, the claim that the TSP results from an inadequate or insufficiently robust 19 planning process is not supported by the record. 20 attachments demonstrate that the TSP is a data-driven, strategic plan for distribution 21 system investment, designed to move the system toward a defined future state while 22 balancing performance and customer affordability. Exhibit CLP-TSP-1 and its The Company's proposedPage 30 of 100
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-LEADERSHIP-REBUTTAL-1 November 18, 2026 Page 28 of 98 1 investments aim to improve reliability and resiliency, expand capacity for future 2 growth, address aging infrastructure, and reduce both the frequency and duration of 3 customer interruptions. Some investments deliver near-term benefits, however, many 4 will yield results over time as projects are completed and integrated into the distribution 5 system. The fact that these benefits accrue over multiple years does not lessen the 6 necessity of the investments or the soundness of the underlying planning analysis and 7 decisions. 8 Third, the OCC’s and Ms. Griffin’s proposed approach overlooks that the Company’s 9 capital investment plan must encompass all investments required to operate the 10 business and serve customers—not just those addressed in a proposed IDSP 11 framework. While distribution system modernization is a significant and expanding 12 need, it is only one part of the Company’s capital responsibilities. The Company must 13 also prioritize other essential investments to ensure safe, reliable, and effective service. 14 These investments must be evaluated collectively, considering the Company’s overall 15 capital requirements and the core obligation to provide affordable service for 16 customers. An IDSP process limited to a specific subset of distribution system 17 investments cannot substitute for the comprehensive capital planning needed to operate 18 the business and serve our customers’ needs holistically. 19 Lastly, the OCC’s and Ms. Griffin’s arguments wrongly treat the proposed IDSP 20 framework as a universal solution for utility capital planning. This view conflicts with 21 the flexibility built into a performance-based regulatory framework, which is designedPage 31 of 100
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-LEADERSHIP-REBUTTAL-1 November 18, 2026 Page 29 of 98 1 to adapt to each utility’s unique circumstances, investment needs, and operating 2 priorities. Merely identifying differences between the TSP and IDSP frameworks as 3 the OCC and Ms. Griffin have done does not, by itself, prove that the Company’s 4 approach is deficient or that its proposed investments are unreasonable. 5 The need for increased investment in Connecticut’s electric distribution system is well 6 supported by the testimony of the Company’s Leadership Panel and TSP Panel. These 7 investments are essential to maintain and improve customer service, regardless of 8 whether the Company is subject to a multi-year rate plan. The central issue in this 9 proceeding is whether the Company’s proposed investments are reasonable and 10 necessary to fulfill its obligations and address identified system needs—not whether it 11 followed a proposed planning framework from a separate uncontested proceeding that 12 was never concluded and that is not required to adopt. The OCC and Ms. Griffin have 13 not shown that the TSP is an inadequate basis for evaluating the Company’s proposed 14 capital investments. Accordingly, PURA should reject their recommendation to defer 15 consideration of the Company’s capital plan pending completion of an IDSP process. 16 17 Q. Would you like to address any other specific criticisms raised by the parties and intervenors regarding the Company’s proposed TSP? 18 A. Yes. We would like to briefly address a few of the arguments raised by Mr. Balakumar 19 regarding the Company’s proposed TSP.Page 32 of 100
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-LEADERSHIP-REBUTTAL-1 November 18, 2026 Page 30 of 98 1 Historical Spending as a Benchmark 2 Mr. Balakumar argues that the Company’s Sustained Performance Tier averages about 3 $722 million per year, compared with $434 million per year in actual Connecticut 4 Distribution capital spending from 2017 through 2024 (Balakumar Testimony at 18, 5 20). 6 “minimum” (id. at 4, 20, 21, 33, 35). However, this is not correct. 7 The Company’s historical capital expenditures do not reflect the investment needed to 8 maintain the distribution system in the future. Current asset conditions, anticipated 9 customer and demand growth, and evolving reliability standards are driving the 10 Company’s future investment requirements. Mr. Balakumar incorrectly assumes that 11 past spending sets an appropriate benchmark for future investment and fails to account 12 for changing system needs and rising construction costs. The proper standard for 13 PURA to apply when evaluating the Company’s TSP proposal in this proceeding is 14 whether the investments are reasonable and necessary to address current and forecasted 15 system needs, not simply whether they exceed historical spending levels. 16 Company cannot sustain the system with yesterday’s dollars and Mr. Balakumar does 17 not provide any analysis to substantiate his claim that everything that needs to be done 18 can be done at historical levels of investment. He argues that this gap undercuts the Company’s claim that the tier is a The
As listed on the current system
Prefiled testimony: 11/18/2026 - Sponsor: TBD / Witness: DONALD J. SCACCO, JR., DIGAUNTO CHATTERJEE AND DOUGLAS P. HORTON [26-05-10]