Prefiled testimony
Witness: DONALD J. SCACCO, JR., DIGAUNTO CHATTERJEE AND DOUGLAS P. HORTON
Files2
Docket No. 26-05-10 CLP Rebuttals Filing Letter (11.18.26).pdf
PDF · 152 KB · 3 pagesText searchable
Download Docket No. 26-05-10 CLP Rebuttals Filing Letter (11.18.26).pdfRead the text of Docket No. 26-05-10 CLP Rebuttals Filing Letter (11.18.26).pdf
Exhibit CLP-LEADERSHIP-REBUTTAL-1.pdf
PDF · 712 KB · 100 pagesText searchable
Download Exhibit CLP-LEADERSHIP-REBUTTAL-1.pdfRead the text of Exhibit CLP-LEADERSHIP-REBUTTAL-1.pdf
Page 26 of 100
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-LEADERSHIP-REBUTTAL-1 November 18, 2026 Page 24 of 98 1 benefit of customers, or before a prudence determination. The operation of the F-Factor 2 provides a level of revenue support that appropriately balances the interests of 3 customers and of the Company by providing a level of revenue support (based on the 4 forecasted capital presented in the TSP), while limiting that revenue support in the 5 event the Company is required to invest more than it expects to today, crediting to 6 customers any over-recovery in the event the Company spends less than it expects to 7 today, or in the event of a future prudence disallowance by PURA. In the current 8 environment, highlighted on the one hand by a need for sustained, elevated, and 9 growing capital infrastructure requirements and on the other hand by a world with 10 relatively flat overall sales volume increases, and with full revenue decoupling in any 11 event, the Company is not able to support the cost of ongoing investment without the 12 added revenue support of a mechanism substantially similar to the F-Factor. 13 In fact, implementation of an F-Factor mechanism has the added benefit of instituting 14 a form of regulatory lag, as used to exist naturally for utilities when operating at the 15 time (i.e., two or more decades ago) when sales volumes (and associated customer 16 revenues) were generally increasing at a fairly steady clip year over year to provide 17 added revenues to support incremental capital investments that were not directly 18 reflected in utility rates in the period between rate cases. 19 Inclusion of Cost of Removal and Deducting Depreciation Expense. The F-Factor 20 calculation captures the impact of ongoing depreciation accumulating in rate base, 21 which has the effect of reducing overall revenue requirements. Additionally, thePage 27 of 100
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-LEADERSHIP-REBUTTAL-1 November 18, 2026 Page 25 of 98 1 Company’s F-Factor calculation captures the reduced revenue requirement resulting 2 from plant retirements and accumulated deferred income taxes, while also 3 incorporating the effect of cost of removal on rate base. 4 Thus, the Company has designed its proposed F-Factor to follow the CT-Bar 5 framework as closely as practicable, while the CT-Bar’s fundamental defects make its 6 full adoption unworkable for the reasons discussed above. The Company cannot 7 responsibly proceed with the PBMRP under a mechanism that, by design, fails to 8 provide even a perfectly operating utility, and with the benefit of hindsight, with the 9 opportunity for revenues that reflect its costs, including its cost of capital. Such a 10 mechanism undermines necessary capital investment and threatens the performance 11 objectives the PBMRP is intended to achieve. 12 As discussed extensively in Docket No. 21-05-15RE01, a workable performance-based 13 regulatory framework requires both an appropriate going-in revenue requirement and 14 a mechanism for ongoing recovery of the revenue requirement associated with 15 incremental capital investment. Without sufficient revenues to cover the cost of service 16 (including the cost of capital and cost of removal), the Company would be forced to 17 absorb significant capital costs without a reasonable opportunity to earn its authorized 18 ROE and would not be in a position to commit to a stay-out of any duration. A multi- 19 year rate stay-out would be unworkable under such a framework, given the substantial 20 system investments needed to maintain and improve customer service. In the absence 21 of a multi-year rate plan, the Company anticipates filing rate cases on a rolling basis,Page 28 of 100
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-LEADERSHIP-REBUTTAL-1 November 18, 2026 Page 26 of 98 1 with base rate changes effective January 1, 2029, July 1, 2030, and January 1, 2032 2 (Exh. EOE-156, at 3). 3 4 5 6 7 8 Q. Ms. Griffin states that the Company’s proposal “does not recognize that some capital additions would already be covered by what is provided in base rates” and that CT-Bar “would more appropriately recognize the recovery of such infrastructure replacement programs” because it “was designed to deduct depreciation expense already included in going-in rates from plant additions eligible for supplemental recovery.” Is that accurate? 9 A. No. Both propositions are incorrect. As stated in the Company’s responses to multiple 10 interrogatories, including OCC-859, OCC-423, OCC-436, OCC-427, EOE-156, and 11 UPA-082, among others, the Company’s F-Factor expressly accounts for ongoing 12 depreciation reflected in base rates, which reduces the rate base on which a return is 13 calculated and, therefore, the resulting revenue requirement. 14 Company’s F-Factor reflects ongoing depreciation consistent with the underlying 15 accounting, whereas CT-Bar does not. 16 In addition, the Company’s response to OCC-423 explains that CT-Bar nets ongoing 17 depreciation against new plant additions before calculating depreciation expense on the 18 new investment, thereby understating the resulting depreciation expense. For example, 19 if the Company has $100 million of new plant additions, $20 million of ongoing 20 depreciation, and an applicable depreciation rate of 3.75%, new depreciation expense 21 related to the investment would be $100 million × 3.75%, or $3.75 million. CT-Bar 22 instead nets the $20 million of ongoing depreciation against the $100 million of new 23 plant and calculates depreciation expense on the resulting $80 million, producing $3.0 Moreover, thePage 29 of 100
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-LEADERSHIP-REBUTTAL-1 November 18, 2026 Page 27 of 98 1 million of depreciation expense. Ongoing depreciation properly reduces the 2 investment base on which a return is calculated. It does not reduce the amount of new 3 plant that generates new depreciation expense. 4 3. Distribution System Planning 5 6 7 Q. As discussed above, the OCC’s witnesses and Ms. Griffin contend that the TSP is inadequate because it was not developed through the IDSP framework developed in Docket No. 21-05-15. What is your response to that contention? 8 A. The OCC’s witnesses and Ms. Griffin’s arguments are unavailing for several reasons. 9 First, the IDSP framework proposed in Docket No. 21-05-15RE03 was never adopted 10 as a mandatory planning requirement for the Company. There is no requirement for 11 the Company to implement that framework, nor do the OCC or Ms. Griffin provide any 12 justification for treating it as a prerequisite to PURA’s review of the Company’s 13 proposed capital investments in this proceeding. That a separate planning framework 14 was proposed in another proceeding does not make it the exclusive or required method 15 for evaluating the Company’s capital investment plan. PURA should assess the 16 Company’s TSP on its own merits, rather than comparing it to an unapproved 17 framework in a separate uncontested docket. 18 Second, the claim that the TSP results from an inadequate or insufficiently robust 19 planning process is not supported by the record. 20 attachments demonstrate that the TSP is a data-driven, strategic plan for distribution 21 system investment, designed to move the system toward a defined future state while 22 balancing performance and customer affordability. Exhibit CLP-TSP-1 and its The Company's proposedPage 30 of 100
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-LEADERSHIP-REBUTTAL-1 November 18, 2026 Page 28 of 98 1 investments aim to improve reliability and resiliency, expand capacity for future 2 growth, address aging infrastructure, and reduce both the frequency and duration of 3 customer interruptions. Some investments deliver near-term benefits, however, many 4 will yield results over time as projects are completed and integrated into the distribution 5 system. The fact that these benefits accrue over multiple years does not lessen the 6 necessity of the investments or the soundness of the underlying planning analysis and 7 decisions. 8 Third, the OCC’s and Ms. Griffin’s proposed approach overlooks that the Company’s 9 capital investment plan must encompass all investments required to operate the 10 business and serve customers—not just those addressed in a proposed IDSP 11 framework. While distribution system modernization is a significant and expanding 12 need, it is only one part of the Company’s capital responsibilities. The Company must 13 also prioritize other essential investments to ensure safe, reliable, and effective service. 14 These investments must be evaluated collectively, considering the Company’s overall 15 capital requirements and the core obligation to provide affordable service for 16 customers. An IDSP process limited to a specific subset of distribution system 17 investments cannot substitute for the comprehensive capital planning needed to operate 18 the business and serve our customers’ needs holistically. 19 Lastly, the OCC’s and Ms. Griffin’s arguments wrongly treat the proposed IDSP 20 framework as a universal solution for utility capital planning. This view conflicts with 21 the flexibility built into a performance-based regulatory framework, which is designedPage 31 of 100
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-LEADERSHIP-REBUTTAL-1 November 18, 2026 Page 29 of 98 1 to adapt to each utility’s unique circumstances, investment needs, and operating 2 priorities. Merely identifying differences between the TSP and IDSP frameworks as 3 the OCC and Ms. Griffin have done does not, by itself, prove that the Company’s 4 approach is deficient or that its proposed investments are unreasonable. 5 The need for increased investment in Connecticut’s electric distribution system is well 6 supported by the testimony of the Company’s Leadership Panel and TSP Panel. These 7 investments are essential to maintain and improve customer service, regardless of 8 whether the Company is subject to a multi-year rate plan. The central issue in this 9 proceeding is whether the Company’s proposed investments are reasonable and 10 necessary to fulfill its obligations and address identified system needs—not whether it 11 followed a proposed planning framework from a separate uncontested proceeding that 12 was never concluded and that is not required to adopt. The OCC and Ms. Griffin have 13 not shown that the TSP is an inadequate basis for evaluating the Company’s proposed 14 capital investments. Accordingly, PURA should reject their recommendation to defer 15 consideration of the Company’s capital plan pending completion of an IDSP process. 16 17 Q. Would you like to address any other specific criticisms raised by the parties and intervenors regarding the Company’s proposed TSP? 18 A. Yes. We would like to briefly address a few of the arguments raised by Mr. Balakumar 19 regarding the Company’s proposed TSP.Page 32 of 100
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-LEADERSHIP-REBUTTAL-1 November 18, 2026 Page 30 of 98 1 Historical Spending as a Benchmark 2 Mr. Balakumar argues that the Company’s Sustained Performance Tier averages about 3 $722 million per year, compared with $434 million per year in actual Connecticut 4 Distribution capital spending from 2017 through 2024 (Balakumar Testimony at 18, 5 20). 6 “minimum” (id. at 4, 20, 21, 33, 35). However, this is not correct. 7 The Company’s historical capital expenditures do not reflect the investment needed to 8 maintain the distribution system in the future. Current asset conditions, anticipated 9 customer and demand growth, and evolving reliability standards are driving the 10 Company’s future investment requirements. Mr. Balakumar incorrectly assumes that 11 past spending sets an appropriate benchmark for future investment and fails to account 12 for changing system needs and rising construction costs. The proper standard for 13 PURA to apply when evaluating the Company’s TSP proposal in this proceeding is 14 whether the investments are reasonable and necessary to address current and forecasted 15 system needs, not simply whether they exceed historical spending levels. 16 Company cannot sustain the system with yesterday’s dollars and Mr. Balakumar does 17 not provide any analysis to substantiate his claim that everything that needs to be done 18 can be done at historical levels of investment. He argues that this gap undercuts the Company’s claim that the tier is a ThePage 33 of 100
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-LEADERSHIP-REBUTTAL-1 November 18, 2026 Page 31 of 98 1 2 The Tiering Framework Is “Artificial” and “Business-as-Usual” and Lacks Urgency 3 Mr. Balakumar claims that the Company’s TSP proposal is “business-as-usual,” lacks 4 urgency on grid modernization, and uses “artificial” tiers. He recommends that PURA 5 reject the tiering framework (Balakumar Testimony at 15, 16). 6 Contrary to Mr. Balakumar’s claim, each tier is grounded in specific performance 7 objectives and quantified system impacts. The Sustained Performance Tier ($3.611B) 8 maintains reliability, with a SAIDI impact of -0.7 minutes. The Targeted System 9 Performance Tier ($3.985B) hardens the system, with a SAIDI impact of -6.1 minutes. 10 The Advancing the Grid Tier ($4.381B) modernizes the grid, with a SAIDI impact of 11 -10.3 minutes. 12 As documented in Exhibit CLP-TSP-3, at pages 7, 11, and 39-49, each tier is defined 13 by a distinct set of characteristics spanning multiple dimensions, including primary 14 objectives, operational approach, reliability performance, resiliency investment, cost 15 trajectory, and alignment with regulatory requirements, including RE08. 16 Mr. Balakumar’s criticism that the Company is improperly treating grid modernization 17 as a “long-term” objective and lack urgency reflects a fundamental misunderstanding 18 of prudent infrastructure planning and the foundational investments required to support 19 advanced grid capabilities. 20 successful DER integration and the development of dynamic grid capabilities depend 21 on first ensuring sufficient baseline resiliency. The Company’s approach correctly recognizes that To proceed otherwise would bePage 34 of 100
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-LEADERSHIP-REBUTTAL-1 November 18, 2026 Page 32 of 98 1 imprudent and could jeopardize both system reliability and the effectiveness of 2 subsequent investments. 3 Limited Reliability Benefit of the Sustained Performance Tier 4 Mr. Balakumar argues that the Sustained Performance Tier’s projected net SAIDI 5 improvement of only 0.7 minutes shows that it provides limited reliability benefits 6 (Balakumar Testimony at 17, 21). 7 However, the Sustained Performance Tier is intended to preserve existing reliability 8 levels rather than deliver significant incremental improvements in SAIDI. 9 Company’s distribution system faces ongoing asset deterioration, rising capacity 10 demands, and emerging reliability challenges that require continued investment. 11 Additionally, SAIDI does not fully reflect the benefits of preventive investments, such 12 as reduced equipment failure risk, improved asset health, expanded system capacity, 13 and greater operational flexibility. 14 evaluated by its effectiveness in mitigating system degradation and maintaining the 15 reliability and quality of service customers expect, rather than solely by its projected 16 SAIDI improvement. 17 O&M Costs and Advancing the Grid Investments 18 Mr. Balakumar argues that the $71 million in O&M proposed for the Targeted System 19 Performance Tier, including the $38 million Grid Services Compensation Fund, is not 20 adequately supported (Balakumar Testimony at 14, 37-38). He also argues that the The The Sustained Performance Tier should bePage 35 of 100
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-LEADERSHIP-REBUTTAL-1 November 18, 2026 Page 33 of 98 1 Company has not quantified the incremental benefits of the $770 million Advancing 2 the Grid Tier (id. at 5-6). Mr. Balakumar further argues that DERMS and the Grid 3 Services Compensation Fund should be approved only if they are subject to conditions, 4 such as an iterative roadmap with annual updates, testing a flexibility market platform, 5 and targeted deployment at constrained locations (id. at 63). 6 The Company disagrees with Mr. Balakumar’s assertion that the proposed O&M costs 7 are insufficiently supported. The $71 million in incremental O&M costs for the 8 Targeted System Performance Tier reflects specific, well-defined investments in 9 personnel, programs, and resources essential to achieving the Company’s system 10 performance objectives. The principal components of these investments are as follows: 11 • Grid Services Compensation Fund: $38 million 12 • Control Room Labor: 7 new FTEs 13 • Field Communications Labor and Cellular: 2 new FTEs 14 • Data Innovation: 3 new FTEs 15 • Distribution Substation Asset Management: 1 new FTE 16 • Vegetation Management: 21 new FTEs to bring certain work in-house 17 • Power Quality: 5 new FTEs to investigate and resolve power quality issues 18 (Exh. CLP-TSP-3, at 43). 19 These targeted investments provide the staffing and programmatic resources needed to 20 enhance system performance, advance grid modernization, and address emerging 21 distribution system needs. 22 increases in O&M spending, they are tailored to specific operational requirements Rather than representing unsupported or generalized
As listed on the current system
Prefiled testimony: 11/18/2026 - Sponsor: TBD / Witness: DONALD J. SCACCO, JR., DIGAUNTO CHATTERJEE AND DOUGLAS P. HORTON [26-05-10]