Prefiled testimony
Witness: DONALD J. SCACCO, JR., DIGAUNTO CHATTERJEE AND DOUGLAS P. HORTON
Files2
Docket No. 26-05-10 CLP Rebuttals Filing Letter (11.18.26).pdf
PDF · 152 KB · 3 pagesText searchable
Download Docket No. 26-05-10 CLP Rebuttals Filing Letter (11.18.26).pdfRead the text of Docket No. 26-05-10 CLP Rebuttals Filing Letter (11.18.26).pdf
Exhibit CLP-LEADERSHIP-REBUTTAL-1.pdf
PDF · 712 KB · 100 pagesText searchable
Download Exhibit CLP-LEADERSHIP-REBUTTAL-1.pdfRead the text of Exhibit CLP-LEADERSHIP-REBUTTAL-1.pdf
Page 56 of 100
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-LEADERSHIP-REBUTTAL-1 November 18, 2026 Page 54 of 98 1 prestaging expenses is overstated (Defever Testimony at 40). According to Mr. 2 Defever, the Company should not have adjusted historical costs to 2028 dollars when 3 calculating the five-year average used to derive the $38 million Rate Year allowance 4 for non-catastrophic storms (id. at 39). He argues that a five-year average of unadjusted 5 historical costs would smooth out annual fluctuations and yield an allowance of 6 approximately $32 million (id.). 7 Mr. Defever raises a similar objection to the proposed $4 million in annual funding for 8 the prestaging reserve. He recommends removing the inflation adjustment from the 9 five-year average of historical costs (id. at 40–41). He calculates an unadjusted average 10 of annual funding at approximately $3.4 million (id. at 41–42). 11 12 13 Q. In addition to the testimony described above addressing storm cost recovery, has PURA undertaken any other efforts to examine storm cost recovery frameworks in this proceeding? 14 A. Yes. On November 2, 2026, PURA held a technical session to facilitate discussion of 15 storm cost recovery frameworks. The session addressed, among other things, the 16 definition of catastrophic storms and pre-staging events, funding mechanisms for the 17 reserve funds, and carrying costs on regulatory assets. 18 19 Q. How is the Company’s rebuttal testimony organized to address the issues raised by the OCC witnesses regarding the Company’s storm cost recovery proposals? 20 A. The Company’s rebuttal testimony addresses the issues raised by the OCC witnesses 21 in five principal categories: (1) the design and operation of the Company’s proposed 22 storm cost recovery framework, including the criteria for catastrophic storm eligibilityPage 57 of 100
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-LEADERSHIP-REBUTTAL-1 November 18, 2026 Page 55 of 98 1 and the process for cost recovery; (2) the treatment of carrying costs on storm costs, 2 including the timing at which such charges begin to accrue; (3) the review of storm 3 costs, including cost management incentives, cost benchmarks, reporting requirements, 4 and the evaluation of storm-related investments; (4) the reasonableness of the 5 Company’s requested recovery of costs associated with the 14 catastrophic storm 6 events in 2024 and 2025; and (5) the calculation of the proposed annual allowances for 7 non-catastrophic storm and prestaging expenses. These categories are addressed in the 8 following subsections. 9 1. Design and Operation of Proposed Storm Cost Recovery Framework 10 11 12 Q. The OCC’s witnesses argue that a monetary threshold for accessing the storm reserve creates an incentive to spend more to push events over the threshold. What is your response to that argument? 13 A. From the Company’s perspective, there are a few disconnects in this thinking. First 14 and foremost, this allegation ignores the circumstances under which storm response 15 expenditures are incurred. Before and after a storm event, the Company’s attention is 16 directed toward preparing for the event, protecting public safety, assessing damage, 17 deploying personnel and resources, and restoring service as safely and efficiently as 18 possible. The Company’s operational decisions are driven by the conditions on the 19 ground and the resources necessary to address them—not by how close the Company 20 may be to reaching a predetermined monetary threshold. Indeed, the Company does 21 not have visibility into the full storm costs as those costs are being incurred. Rather,Page 58 of 100
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-LEADERSHIP-REBUTTAL-1 November 18, 2026 Page 56 of 98 1 the total costs become known only after the event, as contractors and other service 2 providers submit invoices, and the associated costs are reviewed and processed. 3 Second, this argument also presumes (incorrectly) that the Company has confidence 4 that, when it expends dollars on storm restoration, and allegedly does so in a way that 5 pushes a particular storm event into the category of incremental, catastrophic recovery, 6 there is no increase in risk in recovering those dollars, which is 100% not the case. The 7 Company has no objective whatsoever to expend dollars and to place those dollars at 8 greater risk of recovery – both in terms of the timeliness and adequacy of such 9 recovery. The incremental storm costs incurred by the Company are recoverable only 10 if PURA finds them to be prudent and storm costs incurred in relation to storms that 11 are directly on that margin of being catastrophic or non-catastrophic are the events most 12 susceptible to disallowance in the long run, as recently occurred in Docket No. 25-12- 13 13. There is no incentive for the Company to place greater dollars at risk. 14 For example, a monetary threshold does not incentivize the Company to incur 15 unnecessary expenses that are going to be totally exposed in a prudence review, 16 particularly where the storm conditions place the event on the margin. The Company 17 is always responsible for efficiently managing its resources and making prudent 18 decisions when responding to storm events. All costs incurred, regardless of whether 19 they fall above or below the threshold, must be reasonable and necessary to respond to 20 the storm and restore service. Contrary to the characterization advanced by the OCC’s 21 witnesses, the threshold is not a spending target. Rather, it is a ratemaking constructPage 59 of 100
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-LEADERSHIP-REBUTTAL-1 November 18, 2026 Page 57 of 98 1 that establishes the point at which storm-related costs become extraordinary enough to 2 justify cost recovery through the reserve mechanism. 3 The OCC witnesses’ assertion also ignores the circumstances under which 4 storm response expenditures are incurred. Before and after a storm event, the 5 Company’s attention is directed toward preparing for the event, protecting public 6 safety, assessing damage, deploying personnel and resources, and restoring service as 7 safely and efficiently as possible. The Company’s operational decisions are driven by 8 the conditions on the ground and the resources necessary to address them—not by how 9 close the Company may be to reaching a predetermined monetary threshold. Indeed, 10 the Company does not have visibility into the full storm costs as those costs are being 11 incurred. Rather, the total costs become known only after the event, as contractors and 12 other service providers submit invoices, and the associated costs are reviewed and 13 processed. 14 Ultimately, the Company’s operational interests and financial interests are aligned. The 15 best decisions from an operational standpoint, including deploying the appropriate 16 resources and restoring service efficiently, are also the best decisions from a financial 17 standpoint. Conversely, unnecessary spending does not improve storm response, it 18 simply increases costs. In fact, expenditures incurred without reasonable justification 19 would only expose the Company to a finding of imprudence and the disallowance of 20 those costs from recovery. In other words, the Company has no reasonable economic 21 incentive to incur unnecessary costs merely to access reserve funding.Page 60 of 100
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-LEADERSHIP-REBUTTAL-1 November 18, 2026 Page 58 of 98 1 That said, like other parties and PURA, the Company would prefer a non-monetary 2 metric as a way to measure qualifying events in order to reduce controversy around the 3 point of whether an event has met a threshold that signals whether the storm is a 4 “normally recurring” minor weather event contemplated in base rates, or a randomly 5 occurring, major event that requires the use of outside crews and cost incurrence not 6 intended to be recovered through base rates. To that end, the Company is evaluating 7 alternative criteria and intends to submit written comments addressing this more fully, 8 along with other proposals discussed during the November 2, 2026 technical session, 9 as described below. 10 11 12 13 Q. What is your assessment of using impact-based criteria, such as the number of trouble spots, the number of customer outages or an IEEE Major Event Day designation, to establish eligibility for accessing reserve funding for storm-related costs? 14 A. Generally speaking, the impact-based criteria, as proposed by the OCC’s witnesses, are 15 not an appropriate basis for determining eligibility to access reserve funding because 16 these types of criteria do not consistently or adequately capture the impact of the effort 17 required to restore service from a qualitative perspective, nor have any correlation to 18 the actual storm costs incurred, which would tend to consistently overstate or understate 19 the financial significance of a particular storm. Using these criteria as eligibility 20 thresholds could allow or deny access to reserve funding in circumstances that do not 21 reflect CL&P’s actual circumstances, creating a disconnect between reliability 22 objectives and cost recovery.Page 61 of 100
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-LEADERSHIP-REBUTTAL-1 November 18, 2026 Page 59 of 98 1 Because the Company’s objective in the context of a weather or storm event is to restore 2 service as quickly and safely as possible, PURA should not adopt criteria that preclude 3 a prudence review of costs prudently incurred to achieve that objective and thereby 4 prohibit their recovery. An outcome that flat-out disqualifies storm costs for a prudence 5 review, or reasonably accurate inclusion in base rates, would be directly contrary to the 6 fundamental purpose of a fair and balanced storm cost recovery framework. To reach 7 that goal it is necessary to establish a framework that permits the recovery of prudently 8 incurred costs based on the circumstances of the storm response, rather than arbitrary 9 eligibility thresholds that would unilaterally eliminate the opportunity for cost recovery 10 without any chance of recovery. 11 As discussed below, each impact-based criterion has limitations that make them 12 unsuitable as an eligibility threshold for access to reserve funding. 13 Number of Trouble Spots 14 The number of trouble spots should not be used to determine eligibility for reserve 15 funding – this has been tried before and it doesn’t work. Although the number of 16 trouble spots may seem intuitive, and does provide some insight into the extent of 17 storm-related damage, it does not reliably represent the level of restoration effort 18 required to restore the system to its steady state, the amount of resources needed, or the 19 costs associated with those efforts. For example, two storms may create the same 20 number of trouble spots but demand vastly different restoration efforts and 21 expenditures. One trouble spot could involve a broken utility pole, while another mightPage 62 of 100
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-LEADERSHIP-REBUTTAL-1 November 18, 2026 Page 60 of 98 1 be a tree limb resting on a power line. Although both are counted equally as one trouble 2 spot, the resources and time needed to address them can differ dramatically. A broken 3 pole may require multiple crews, specialized equipment, and an extended restoration 4 period, whereas clearing a tree limb may need only a single crew and minimal time 5 (Exh. OCC-905). This disparity demonstrates the fundamental flaw in using trouble 6 spots as the basis for reserve funding eligibility: the criterion treats events of different 7 severity and cost as equivalent. 8 As another example, the number of trouble spots, standing alone, fails to account for 9 the geographic dispersion of those locations. A storm resulting in trouble spots 10 concentrated within a small geographic area may impose substantially different 11 restoration demands, and costs, than a storm resulting in the same number of trouble 12 spots dispersed across a larger geographic area. 13 Number of Customers Interrupted 14 A minimum customer interruption threshold is also not an appropriate criterion for 15 determining eligibility for reserve funding because restoration costs are driven by the 16 nature and extent of system damage, rather than solely by the number of customers 17 affected. The relationship between customer interruptions and restoration costs is 18 neither direct nor consistent. For example, a fault on a heavily automated circuit may 19 affect significantly fewer customers than a similar event on a circuit without 20 automation, while requiring substantially the same field resources, equipment, and 21 repair activities (Exh. OCC-902). As system automation expands, the number ofPage 63 of 100
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-LEADERSHIP-REBUTTAL-1 November 18, 2026 Page 61 of 98 1 customers interrupted may decrease without a corresponding reduction in restoration 2 costs (id.). Similarly, significant storm response expenditures, such as clearing blocked 3 roads, removing debris, and addressing other public-safety needs, are not reflected in 4 customer outage counts (id.). 5 Conversely, the loss of a single transmission line could interrupt service to a large 6 number of customers while requiring relatively limited repair work and restoration 7 expenditures. 8 Accordingly, customer interruption counts are not a reliable measure of the magnitude 9 or cost of a storm event. The Company’s eligibility to access reserve funding should 10 instead be based on whether the Company has incurred incremental, prudently incurred 11 restoration costs, rather than whether an arbitrary customer outage threshold has been 12 met. 13 IEEE Major Event Day 14 The Company’s initial reaction to this proposal is that MED designations should not be used 15 as a criterion for determining eligibility to access reserve funding under the SCRAF, 16 because MEDs reflect system reliability performance rather than storm severity, 17 customer impacts, or restoration costs. IEEE 1366 is designed to identify days with 18 exceptionally high SAIDI values, enabling utilities to more accurately assess reliability 19 under normal conditions and to shape investment plans that target those areas of the 20 system requiring more reliability spending, rather than storm restoration spendingPage 64 of 100
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-LEADERSHIP-REBUTTAL-1 November 18, 2026 Page 62 of 98 1 (Exhs. OCC-852; OCC-902). The IEEE 2.5 Beta methodology highlights statistically 2 unusual outage durations based on historical system performance, but it does not define 3 what constitutes a major or catastrophic storm from an operational or ratemaking 4 perspective (Exhs. OCC-852; OCC-902). Moreover, further review of historical storm 5 data confirms that the IEEE 2.5 Beta methodology may exclude events that required 6 substantial operational response and incurred significant restoration costs. 7 reinforces the Company's position that storm qualification should consider operational 8 impacts and resource requirements in addition to any statistical reliability metric. 9 To that end, the IEEE methodology will fundamentally view storm events that have 10 relatively lower SAIDI values as “normal operations,” although the Company may 11 have had to bring a relatively material complement of external crews to address the 12 damage and impacts of that weather event, thereby “limiting” the SAIDI impact below 13 the level that would have been achievable had the Company’s relied exclusively on its 14 own crews. Moreover, it is the cost of those external crews that the “threshold” is 15 looking to identify because the costs of those external crews will not be included in the 16 Company’s base revenue requirement unless PURA makes an express allowance to 17 identify and provide for that cost recovery. 18 This is a consideration that PURA cannot overlook. There is no correlation between 19 an MED designation and the costs or resources required to respond to a storm (Exhs. 20 OCC-852; OCC-902). In addition, the MED threshold shifts over time with historical 21 reliability performance, so improvements in system reliability, such as investments in ThisPage 65 of 100
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-LEADERSHIP-REBUTTAL-1 November 18, 2026 Page 63 of 98 1 automation and sectionalizing, may reduce measured outage durations even when a 2 storm causes substantial damage and demands significant restoration resources (id.). 3 As a result, a storm could require extensive efforts and incur substantial costs but still 4 fail to meet the MED threshold because earlier investments have minimized customer 5 outage impacts (id.). Likewise, since MEDs are determined on a daily basis, a storm 6 may be classified as an MED on its initial day, while subsequent days of substantial 7 restoration and associated costs are not (id.). Neither scenario provides a reasonable 8 basis for determining cost recovery eligibility. 9 Furthermore, relying on MEDs as an eligibility threshold, risks creating perverse 10 incentives that penalize utilities for effective restoration efforts (Exh. OCC-852). 11 Utilities that quickly deploy resources and restore service may be less likely to meet 12 the MED criteria than those that allow outages to continue beyond typical durations 13 (id.). Over time, extended restoration periods could become embedded in historical 14 data, further reducing the methodology’s value as an indicator of truly extraordinary 15 storm events (id.). These effects are antithetical Company’s ERP obligations and the 16 best interest of customers (id.). 17 Additionally, weather events are inherently uncertain and may weaken, change course, 18 or otherwise fail to materialize with the severity originally anticipated. In such 19 circumstances, the Company may have appropriately incurred extraordinary costs to 20 prepare for the event, even though the event ultimately does not result in an MED. It 21 would be inappropriate to conclude that these expenditures are ineligible for storm