  1. Page 69 of 100

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-LEADERSHIP-REBUTTAL-1 November 18, 2026 Page 67 of 98 1 outage outcomes that may not accurately represent restoration efforts or the related 2 costs, the need for external resources directly aligns with the actual resources required 3 for restoration and the associated costs. 4 The magnitude of incremental restoration costs, driven in significant part by the use of 5 external crews, has to remain a factor in the determination of whether an event 6 surpasses “normal” operating conditions and qualifies for catastrophic storm cost 7 recovery under the SCRAF, although the Company is evaluating whether the IEEE 8 methodology could factor into this analysis. Because catastrophic storms and the 9 associated costs are inherently unpredictable, it is impractical to establish a 10 representative amount of costs for these events in base rates. In addition, incremental 11 storm costs may be prudently incurred in accordance with the ERP, even when the 12 proposed impact-based thresholds discussed above are not met. For example, the 13 Company may prudently prepare for a catastrophic storm event by securing additional 14 resources in advance, even if the storm ultimately does not materialize as forecast. 15 Therefore, eligibility for SCRAF cost recovery should be based on the costs incurred, 16 as measured relative to a monetary threshold, rather than strictly on impact-based 17 measures. 18 The number of crews required, the duration of their deployment, and the resources 19 needed to support them are driven by the scope of storm damage and the Company’s 20 obligation to restore service as quickly and safely as reasonably possible. Fulfilling 21 that obligation means responding not only to the physical damage caused by a storm,
  2. Page 70 of 100

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-LEADERSHIP-REBUTTAL-1 November 18, 2026 Page 68 of 98 1 but also to the expectations of customers, local and state officials, and regulators. These 2 expectations directly shape the scale, speed, and intensity of restoration efforts, as well 3 as the workforce and resources required to carry them out. As a result, the Company 4 must ensure it can deploy sufficient personnel and resources to meet these operational 5 demands. 6 The storm cost recovery mechanism must reflect these operational realities. It should 7 recognize that restoration costs are primarily determined by the resources necessary to 8 fulfill the Company’s service restoration obligations. At the same time, it should 9 provide a reasonable and predictable process for recovering prudently incurred costs 10 and ensure robust regulatory oversight and accountability. 11 monetary threshold should continue to be used as the primary criterion for determining 12 whether a storm qualifies for reserve funding because that criterion is consistent with 13 the purpose of the reserve itself. The reserve is intended to provide funding for 14 extraordinary storm restoration expenditures, including the incremental costs necessary 15 to procure additional crews and other resources to assist with restoration. Accordingly, 16 the threshold for accessing those funds should be tied primarily to the extraordinary 17 costs incurred in responding to the storm event. 18 Nevertheless, the Company agrees that the recovery mechanism could benefit from an 19 additional, objective criterion reflecting impact-based criteria. As discussed above, the 20 impact-based criteria proposed by the OCC’s witnesses, if used alone and without 21 adjustment, do not sufficiently capture the actual damage from a storm event or the For these reasons, a
  3. Page 71 of 100

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-LEADERSHIP-REBUTTAL-1 November 18, 2026 Page 69 of 98 1 circumstances in which the Company prudently prepares for a catastrophic storm that 2 ultimately does not materialize as anticipated. Therefore, any impact-based criteria 3 incorporated into the SCRAF must be refined to address these shortcomings and used 4 in conjunction with a monetary threshold to ensure the mechanism continues to fulfill 5 its primary purpose, i.e., providing funding for extraordinary storm restoration costs. 6 As discussed at the November 2, 2026 Technical Session, any adjustment to the storm 7 threshold requires additional analysis and adjustment to base distribution rates to ensure 8 the level of storm costs included in base distribution rates is set at the appropriate level, 9 ensuring that costs are not ‘trapped’ with no opportunity for recovery, either through 10 base rates, the SCRAF, or a combination thereof. 11 Q. Please describe the alternative threshold that the Company is working to develop. 12 A. In light of the expressed interest during the technical session in developing an 13 alternative methodology for determining when a storm event qualifies as catastrophic 14 for purposes of accessing reserve funding, the Company is actively and diligently 15 developing a hybrid approach that it believes will provide an appropriate and objective 16 basis for making that determination. Consistent with this objective, the Company 17 supports the use of an objective threshold measure based, in part, on SAIDI, as part of 18 the proposed methodology. The Company only recently received the transcript of the 19 technical session and requires a small amount of additional time to consider the 20 discussion and further develop its proposal. Although work remains ongoing, the 21 Company is committed to advancing this effort and will present its proposed
  4. Page 72 of 100

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-LEADERSHIP-REBUTTAL-1 November 18, 2026 Page 70 of 98 1 methodology to PURA and the parties once the approach has been sufficiently 2 developed to permit a complete and fully supported presentation, and as soon as 3 possible. 4 2. Carrying Cost Recovery and Regulatory Lag 5 6 7 8 9 Q. The RMI witnesses challenge the Company’s proposal to accrue carrying charges from the date costs are incurred. They argue that carrying charges should only begin accruing after a prudence review and maintain that annual prudence reviews would reduce regulatory lag, thereby encouraging more efficient spending. How do you respond to these assertions? 10 A. The OCC witnesses’ positions are internally inconsistent. On one hand, they argue that 11 regulatory lag should be reduced to minimize the carrying costs customers pay. On the 12 other, they characterize regulatory lag as an important mechanism for promoting cost 13 discipline and efficient spending. These positions are difficult, if not impossible, to 14 reconcile. Moreover, the OCC witnesses’ assertion that regulatory lag incentivizes cost 15 discipline is misplaced in this context. 16 discretionary, nor does the Company have meaningful discretion over when they must 17 be incurred. Instead, they result from catastrophic storms that demand immediate 18 action to restore electric service and protect public safety. For example, when a storm 19 destroys a utility pole, the Company cannot defer its replacement to reduce costs—the 20 pole must be replaced promptly to restore power and ensure safe and reliable service. 21 When the power goes out following a catastrophic storm, municipal officials are not 22 calling the Company to engage in an academic debate about the theoretical merits or 23 shortcomings of regulatory lag. They are calling because their communities are in the The expenditures at issue here are not
  5. Page 73 of 100

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-LEADERSHIP-REBUTTAL-1 November 18, 2026 Page 71 of 98 1 dark, critical services are disrupted, and they need to know one thing: When is the 2 power coming back on? 3 recognizes that storm restoration is not simply a matter of discretionary spending or 4 cost management. Connecticut Gen. Stat. §§ 16-32h and 16-32i establish specific 5 emergency preparedness and restoration performance standards for electric distribution 6 companies, with the potential for substantial civil penalties when those standards are 7 not met. 8 Electricity is a critical service and the restoration of that service cannot reasonably be 9 delayed, postponed, or deferred. At the same time, the Company is required to make 10 staffing and resource decisions in advance of upcoming weather events, based on 11 forecasts that are far from perfect. The Company firmly agrees it should have (and 12 does have) strong incentives to control expenditures to the greatest extent possible, 13 because the Company perceives that it is better off where it can demonstrate that cost 14 efficiency is incorporated into the costs incurred and subject to the prudence review. 15 However, the regulatory framework needs to recognize that there is a constant and 16 persistent requirement for the Company to prepare adequately in advance for weather 17 events that, in the end, may not materialize. Regulatory lag as a concept is inapplicable, 18 certainly not in the traditional sense of the phrase, when the Company may need to 19 respond to multiple successive weather events in a condensed period, each requiring 20 their own unique response and expenditures. 21 expenditures immediately and as they are incurring. That urgency is reflected in Connecticut law, which The Company must finance those Therefore, imposing
  6. Page 74 of 100

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-LEADERSHIP-REBUTTAL-1 November 18, 2026 Page 72 of 98 1 uncompensated financing costs on the Company as suggested by the OCC does not 2 encourage greater efficiency; it merely shifts the entire financial burden of emergency 3 restoration onto the Company without recognizing the real cost of that emergency 4 restoration. 5 The Company’s proposed annual prudence reviews and carrying-charge treatment are 6 not competing approaches—they are complementary components of a balanced 7 recovery framework. The annual reviews provide a predictable process for timely 8 regulatory oversight of storm-related expenditures and carrying costs recognize the 9 financing costs the Company incurs between the time those expenditures are made and 10 the time recovery begins. 11 accountability while ensuring the Company is appropriately compensated for the cost 12 of financing storm restoration. OCC’s regulatory lag discussion is not the appropriate 13 focus in this context, and it adds little, if anything to the evaluation of the Company’s 14 proposal. Together, these mechanisms promote regulatory 15 16 17 Q. Why is it appropriate to accrue carrying costs from the date those expenditures are incurred, rather than from the point at which PURA issues a prudence determination? 18 A. The Company has already explained in testimony and discovery responses why the 19 Company incurs carrying charges from the date storm-related expenditures are 20 incurred, and why a storm framework should recognize the costs incurred by the 21 Company, inclusive of the carrying costs of capital, so it will not repeat all of that 22 information here. In short, the Company faces substantial costs when responding to
  7. Page 75 of 100

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-LEADERSHIP-REBUTTAL-1 November 18, 2026 Page 73 of 98 1 storm events, and it must finance these expenditures as they occur, regardless of when 2 PURA completes its prudence review. 3 Just as the timing of the expenditure reflects when the Company begins financing these 4 expenditures, the applicable carrying charge should reflect the actual cost of that 5 financing. When substantial balances remain outstanding for extended periods, the 6 Company’s weighted average cost of capital (“WACC”) accurately represents the mix 7 of debt and equity financing required to support these obligations. This approach aligns 8 with the ratemaking treatment of long-term utility assets, which earn a return based on 9 the Company's authorized WACC. This is true for long-term utility assets in the same 10 way it is true for long-term regulatory assets, such as storm costs. 11 Utilities earn their WACC on rate base (long-term utility assets) because the utility 12 must finance assets recovered over an extended period with an appropriate mix of debt 13 and equity, each of which comes with its own unique set of risks and costs. Although 14 the cost of debt is generally lower than the cost of equity of the same firm due to the 15 different financial risk parameters associated with each financing option, utilities are 16 not able to finance any single long-term asset (be it a physical asset like a pole or 17 substation, or a regulatory asset like a storm cost expenditure, required to be financed 18 and recovered over an extended period) with any single, dedicated source of funding. 19 Credit rating agencies, as well as debt and equity investors, evaluate companies as a 20 whole, taking into consideration all sources and uses of cash, and all financing 21 arrangements supporting the firm’s balance sheet. It is not possible for the Company
  8. Page 76 of 100

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-LEADERSHIP-REBUTTAL-1 November 18, 2026 Page 74 of 98 1 to finance storm costs exclusively with debt, just like it is not possible for the Company 2 to finance storm costs over an extended period of time and not incur a cost of financing. 3 In summary, the cost to the Company to finance storm cost expenditures is the 4 Company’s WACC, from the date the costs are incurred through the time of full cost 5 recovery, when such recovery extends longer than one year. 6 The Company acknowledges that adopting a more systematic approach to storm-cost 7 review and recovery would help to reduce carrying costs and provide efficiency 8 benefits customers. To that end, the Company’s proposed framework includes annual 9 funding contributions through distribution rates to cover catastrophic storm and 10 prestaging costs, coupled with more frequent prudence reviews and timely recovery. 11 Under this structure, it is not expected that deferred storm balances will accumulate 12 over multiple years to the extent they have since 2018, which enables the Company to 13 accept a lower carrying charge, such as the Prime rate, rather than its WACC, to reflect 14 the shorter financing period. 15 Accordingly, the Company is willing to accept the Prime rate from the date costs are 16 incurred if PURA adopts the SCRAF, enabling more timely review and recovery. The 17 Company clarifies that its proposal to accept a carrying cost other than its WACC 18 includes another important technical detail: when applying the WACC, it is appropriate 19 to offset ADIT from the balance subject to carrying charges. This is methodologically 20 appropriate since the WACC reflects the combined cost of all sources of long-term 21 capital to the Company: (a) long-term debt; (b) shareholder equity; and (c) ADIT,
  9. Page 77 of 100

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-LEADERSHIP-REBUTTAL-1 November 18, 2026 Page 75 of 98 1 which reflects a cost-free source of financing to the utility that appropriately reduces 2 rate base, or reduces the balance of costs subject to the WACC (since the cost of ADIT 3 is zero). When applying the Prime rate, or another proxy for carrying charges, such as 4 a cost-of-debt proxy, the Company does not propose to offset the balance with ADIT. 5 In an alternative carrying cost scenario, the Prime rate would be applied to the over or 6 under recovery balance symmetrically (over recovery in a scenario where customer 7 reserve funding exceeds storm costs) on the balance, without netting ADIT. 8 Importantly, the Company agrees that carrying charges should be recoverable only on 9 those costs found to have been prudently incurred. If any deferred costs are later 10 deemed imprudent, any related carrying charges would not be recoverable. Thus, the 11 Company’s proposed framework balances financing costs with customer interests by 12 ensuring timely, systematic review and recovery, rather than arbitrarily denying the 13 recognition of carrying charges before a prudence determination. 14 The OCC witnesses’ proposal to eliminate the accrual of carrying charges before a 15 prudence determination ignores the fact that the Company’s financing obligations 16 begin when expenditures are incurred, not when regulatory review concludes. Under 17 the OCC’s approach, customers would benefit from the Company’s financing of storm 18 restoration costs during the review period while avoiding the associated financing 19 expense. However, the underlying cost and the costs incurred in financing that expense 20 are inextricably intertwined and cannot be treated as distinct. Nor can the date of
  10. Page 78 of 100

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-LEADERSHIP-REBUTTAL-1 November 18, 2026 Page 76 of 98 1 PURA’s prudence determination serve as an arbitrary dividing line between 2 recoverable and unrecoverable financing costs. 3 PURA’s prudence determination establishes whether the underlying costs are 4 recoverable; it does not alter when the Company incurred those costs or the related 5 financing expense. The most appropriate protection for customers is to ensure carrying 6 charges are recovered only for expenditures ultimately deemed prudent—not to 7 eliminate recognition of carrying costs during the period the Company must finance 8 those expenditures. 9 As a final matter on carrying costs, at the November 2, 2026 technical session, there 10 was discussion over the viability of a ‘pay as you go’ model, which, based on the 11 Company’s understanding, would essentially either (1) establish an annual funding 12 level that matches the expected annual storm cost level, thereby limiting amounts 13 subject to deferral; or (2) allow for a near ‘immediate’ change in rates to align with the 14 incurrence of costs, rather than accruing a storm balance for a period of time, 15 undertaking a prudency review, and then subsequently amortizing the recovery of 16 storm costs deemed prudently incurred over a number of years. 17 wholeheartedly supports this framework as it is truly the only mechanism that could 18 eliminate, or at least substantially reduce, the need to consider recovery of carrying 19 costs altogether. If the Company is able to match revenues with costs, it does not need 20 to issue debt or equity to finance the costs over an extended period (i.e., during the 21 period from the cost is first incurred through when the cost is ultimately and fully The Company