Skip to main content

A prototype public docket site for the Connecticut Public Utilities Regulatory Authority

Utility Dockets and Filings

Prefiled testimony

Witness: DONALD J. SCACCO, JR., DIGAUNTO CHATTERJEE AND DOUGLAS P. HORTON

Files2

Search terms highlighted
Eversource rate increase is on 7 pages of the text below, highlighted. Go to the first matchClear highlighting
Words on different pages
7 pages match
  1. Page 73 of 100

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-LEADERSHIP-REBUTTAL-1 November 18, 2026 Page 71 of 98 1 dark, critical services are disrupted, and they need to know one thing: When is the 2 power coming back on? 3 recognizes that storm restoration is not simply a matter of discretionary spending or 4 cost management. Connecticut Gen. Stat. §§ 16-32h and 16-32i establish specific 5 emergency preparedness and restoration performance standards for electric distribution 6 companies, with the potential for substantial civil penalties when those standards are 7 not met. 8 Electricity is a critical service and the restoration of that service cannot reasonably be 9 delayed, postponed, or deferred. At the same time, the Company is required to make 10 staffing and resource decisions in advance of upcoming weather events, based on 11 forecasts that are far from perfect. The Company firmly agrees it should have (and 12 does have) strong incentives to control expenditures to the greatest extent possible, 13 because the Company perceives that it is better off where it can demonstrate that cost 14 efficiency is incorporated into the costs incurred and subject to the prudence review. 15 However, the regulatory framework needs to recognize that there is a constant and 16 persistent requirement for the Company to prepare adequately in advance for weather 17 events that, in the end, may not materialize. Regulatory lag as a concept is inapplicable, 18 certainly not in the traditional sense of the phrase, when the Company may need to 19 respond to multiple successive weather events in a condensed period, each requiring 20 their own unique response and expenditures. 21 expenditures immediately and as they are incurring. That urgency is reflected in Connecticut law, which The Company must finance those Therefore, imposing
  2. Page 74 of 100

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-LEADERSHIP-REBUTTAL-1 November 18, 2026 Page 72 of 98 1 uncompensated financing costs on the Company as suggested by the OCC does not 2 encourage greater efficiency; it merely shifts the entire financial burden of emergency 3 restoration onto the Company without recognizing the real cost of that emergency 4 restoration. 5 The Company’s proposed annual prudence reviews and carrying-charge treatment are 6 not competing approaches—they are complementary components of a balanced 7 recovery framework. The annual reviews provide a predictable process for timely 8 regulatory oversight of storm-related expenditures and carrying costs recognize the 9 financing costs the Company incurs between the time those expenditures are made and 10 the time recovery begins. 11 accountability while ensuring the Company is appropriately compensated for the cost 12 of financing storm restoration. OCC’s regulatory lag discussion is not the appropriate 13 focus in this context, and it adds little, if anything to the evaluation of the Company’s 14 proposal. Together, these mechanisms promote regulatory 15 16 17 Q. Why is it appropriate to accrue carrying costs from the date those expenditures are incurred, rather than from the point at which PURA issues a prudence determination? 18 A. The Company has already explained in testimony and discovery responses why the 19 Company incurs carrying charges from the date storm-related expenditures are 20 incurred, and why a storm framework should recognize the costs incurred by the 21 Company, inclusive of the carrying costs of capital, so it will not repeat all of that 22 information here. In short, the Company faces substantial costs when responding to
  3. Page 75 of 100

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-LEADERSHIP-REBUTTAL-1 November 18, 2026 Page 73 of 98 1 storm events, and it must finance these expenditures as they occur, regardless of when 2 PURA completes its prudence review. 3 Just as the timing of the expenditure reflects when the Company begins financing these 4 expenditures, the applicable carrying charge should reflect the actual cost of that 5 financing. When substantial balances remain outstanding for extended periods, the 6 Company’s weighted average cost of capital (“WACC”) accurately represents the mix 7 of debt and equity financing required to support these obligations. This approach aligns 8 with the ratemaking treatment of long-term utility assets, which earn a return based on 9 the Company's authorized WACC. This is true for long-term utility assets in the same 10 way it is true for long-term regulatory assets, such as storm costs. 11 Utilities earn their WACC on rate base (long-term utility assets) because the utility 12 must finance assets recovered over an extended period with an appropriate mix of debt 13 and equity, each of which comes with its own unique set of risks and costs. Although 14 the cost of debt is generally lower than the cost of equity of the same firm due to the 15 different financial risk parameters associated with each financing option, utilities are 16 not able to finance any single long-term asset (be it a physical asset like a pole or 17 substation, or a regulatory asset like a storm cost expenditure, required to be financed 18 and recovered over an extended period) with any single, dedicated source of funding. 19 Credit rating agencies, as well as debt and equity investors, evaluate companies as a 20 whole, taking into consideration all sources and uses of cash, and all financing 21 arrangements supporting the firm’s balance sheet. It is not possible for the Company
  4. Page 76 of 100

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-LEADERSHIP-REBUTTAL-1 November 18, 2026 Page 74 of 98 1 to finance storm costs exclusively with debt, just like it is not possible for the Company 2 to finance storm costs over an extended period of time and not incur a cost of financing. 3 In summary, the cost to the Company to finance storm cost expenditures is the 4 Company’s WACC, from the date the costs are incurred through the time of full cost 5 recovery, when such recovery extends longer than one year. 6 The Company acknowledges that adopting a more systematic approach to storm-cost 7 review and recovery would help to reduce carrying costs and provide efficiency 8 benefits customers. To that end, the Company’s proposed framework includes annual 9 funding contributions through distribution rates to cover catastrophic storm and 10 prestaging costs, coupled with more frequent prudence reviews and timely recovery. 11 Under this structure, it is not expected that deferred storm balances will accumulate 12 over multiple years to the extent they have since 2018, which enables the Company to 13 accept a lower carrying charge, such as the Prime rate, rather than its WACC, to reflect 14 the shorter financing period. 15 Accordingly, the Company is willing to accept the Prime rate from the date costs are 16 incurred if PURA adopts the SCRAF, enabling more timely review and recovery. The 17 Company clarifies that its proposal to accept a carrying cost other than its WACC 18 includes another important technical detail: when applying the WACC, it is appropriate 19 to offset ADIT from the balance subject to carrying charges. This is methodologically 20 appropriate since the WACC reflects the combined cost of all sources of long-term 21 capital to the Company: (a) long-term debt; (b) shareholder equity; and (c) ADIT,
  5. Page 77 of 100

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-LEADERSHIP-REBUTTAL-1 November 18, 2026 Page 75 of 98 1 which reflects a cost-free source of financing to the utility that appropriately reduces 2 rate base, or reduces the balance of costs subject to the WACC (since the cost of ADIT 3 is zero). When applying the Prime rate, or another proxy for carrying charges, such as 4 a cost-of-debt proxy, the Company does not propose to offset the balance with ADIT. 5 In an alternative carrying cost scenario, the Prime rate would be applied to the over or 6 under recovery balance symmetrically (over recovery in a scenario where customer 7 reserve funding exceeds storm costs) on the balance, without netting ADIT. 8 Importantly, the Company agrees that carrying charges should be recoverable only on 9 those costs found to have been prudently incurred. If any deferred costs are later 10 deemed imprudent, any related carrying charges would not be recoverable. Thus, the 11 Company’s proposed framework balances financing costs with customer interests by 12 ensuring timely, systematic review and recovery, rather than arbitrarily denying the 13 recognition of carrying charges before a prudence determination. 14 The OCC witnesses’ proposal to eliminate the accrual of carrying charges before a 15 prudence determination ignores the fact that the Company’s financing obligations 16 begin when expenditures are incurred, not when regulatory review concludes. Under 17 the OCC’s approach, customers would benefit from the Company’s financing of storm 18 restoration costs during the review period while avoiding the associated financing 19 expense. However, the underlying cost and the costs incurred in financing that expense 20 are inextricably intertwined and cannot be treated as distinct. Nor can the date of
  6. Page 78 of 100

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-LEADERSHIP-REBUTTAL-1 November 18, 2026 Page 76 of 98 1 PURA’s prudence determination serve as an arbitrary dividing line between 2 recoverable and unrecoverable financing costs. 3 PURA’s prudence determination establishes whether the underlying costs are 4 recoverable; it does not alter when the Company incurred those costs or the related 5 financing expense. The most appropriate protection for customers is to ensure carrying 6 charges are recovered only for expenditures ultimately deemed prudent—not to 7 eliminate recognition of carrying costs during the period the Company must finance 8 those expenditures. 9 As a final matter on carrying costs, at the November 2, 2026 technical session, there 10 was discussion over the viability of a ‘pay as you go’ model, which, based on the 11 Company’s understanding, would essentially either (1) establish an annual funding 12 level that matches the expected annual storm cost level, thereby limiting amounts 13 subject to deferral; or (2) allow for a near ‘immediate’ change in rates to align with the 14 incurrence of costs, rather than accruing a storm balance for a period of time, 15 undertaking a prudency review, and then subsequently amortizing the recovery of 16 storm costs deemed prudently incurred over a number of years. 17 wholeheartedly supports this framework as it is truly the only mechanism that could 18 eliminate, or at least substantially reduce, the need to consider recovery of carrying 19 costs altogether. If the Company is able to match revenues with costs, it does not need 20 to issue debt or equity to finance the costs over an extended period (i.e., during the 21 period from the cost is first incurred through when the cost is ultimately and fully The Company
  7. Page 79 of 100

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-LEADERSHIP-REBUTTAL-1 November 18, 2026 Page 77 of 98 1 collected through customer rates), meaning that it will not require carrying costs at all 2 (assuming that revenues are able to be perfectly matched with costs under a pay-as- 3 you-go model). This approach is a simple yet fundamentally elegant and efficient 4 answer to the problem that Connecticut has been struggling with over the past eight 5 years. 6 7 Q. What is the Company’s response to the recommendation that storm-cost reviews be conducted through the RAM process? 8 A. Ms. Wilson and Mr. Tully’s propose to incorporate annual storm cost recovery reviews 9 into the RAM process. The Company is generally open to a schedule that enables 10 timely annual reviews, of qualifying storm costs and supports incorporating this review 11 into the RAM proceeding to the extent parties find it administratively more efficient 12 than an alternative schedule. Once the review of storm costs is reset to a relatively 13 cyclical exercise, it will become easier for all parties to accomplish this review in the 14 context of the RAM or another annual process. 15 To that end, the Company’s proposal is to establish an annual cadence of filing storm 16 costs annually in September for storms that occurred during the prior calendar year. 17 The Company’s proposal anticipates that parties would require approximately one year 18 from the filing date to conduct discovery and hearings etc., such that PURA could issue 19 a decision on the prudency by August of the following year, allowing for a rate change 20 in September, one year from the date of filing. Should PURA wish to incorporate the 21 storm review as part of the annual RAM process, the Company would endeavor to
  8. Page 80 of 100

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-LEADERSHIP-REBUTTAL-1 November 18, 2026 Page 78 of 98 1 support this, realizing that it will require approximately nine to ten months to compile 2 and review the requisite storm cost documentary evidence (such that a filing in January 3 would imply a storm cut-off of storms occurring prior to the preceding March. 4 Benchmarks and Reporting 5 6 Q. Does the Company oppose the recommendation of the OCC’s witnesses that it be required to provide post-storm reports and information to PURA? 7 A. No, not at all. The Company does not object to providing PURA with standardized 8 post-storm data and information on its storm preparedness and restoration activities, as 9 long as any reporting requirements are practical to implement and track, provide 10 meaningful information, do not impede safe and efficient storm restoration, and do not 11 impose unreasonable costs. It is far preferable, from the Company’s point of view, for 12 there to be transparent, reliable and certain instruction on the types of information 13 PURA, OCC and others want to gauge storm performance than to require the Company 14 to suppose what might be helpful in a case that comes later, multiple years after an 15 event. The Company fully acknowledges the value in providing information about 16 storm impacts, restoration efforts, resources utilized, and performance following a 17 major storm event with PURA and other stakeholders. 18 The only cautionary note is that the prudence of the Company’s decisions must be 19 evaluated based on all of the information available regarding decisions that were made 20 at the time that the decision had to be made—not based on hindsight later informed by 21 actual storm conditions or restoration outcomes. While post-storm comparisons of 22 forecasts, anticipated resource needs, and actual conditions can be valuable for
  9. Page 81 of 100

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-LEADERSHIP-REBUTTAL-1 November 18, 2026 Page 79 of 98 1 operational review and continuous improvement, they cannot be substituted for the 2 governing prudence standard. If differences between forecasts and actual outcomes 3 could be treated as evidence of imprudence, as the OCC’s witnesses suggest, it would 4 unfairly penalize the Company for taking reasonable, precautionary measures in 5 response to the risks and uncertainties of an impending storm. 6 7 Q. Are there other potential issues with the reporting requirements and benchmarks proposed by OCC’s witnesses? 8 A. Yes. Although Mr. Balakumar acknowledges that the ERP and Event Level Matrix 9 (“ELM”) do not prescribe a fixed resource plan for each emergency event, he 10 nevertheless recommends requiring the Company to justify crew levels at each decision 11 point against a benchmark tied to the declared event level and forecasted trouble spots 12 (Balakumar Testimony at 99). 13 transforming a flexible planning tool into a rigid staffing mandate. 14 The ELM is a framework for classifying events and planning resources based on a 15 range of factors, such as weather forecasts and anticipated trouble spots. Its purpose is 16 to guide advance preparation—not to prescribe fixed resource levels or impose strict 17 limits on deployment. Since emergencies rarely follow a predictable script, resource 18 needs must be reassessed continually as actual storm impacts, damage, and evolving 19 conditions become clear. This approach misconstrues the ELM’s purpose, The ELM’s overlapping resource ranges are therefore
  10. Page 82 of 100

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-LEADERSHIP-REBUTTAL-1 November 18, 2026 Page 80 of 98 1 intentional, underscoring the uncertainty of storm response and the necessity of 2 adaptive decision-making. 3 Moreover, the ELM is just one of several factors the Company weighs when 4 determining resource needs. In addition to the ELM, the Company assesses weather 5 forecasts, outage prediction models, resource availability, and environmental variables, 6 such as tree conditions, foliage, and soil saturation, that can influence storm damage. 7 Taken together, these variables yield a wide range of possible outcomes, a wide bell 8 curve, rather than a precise forecast of storm impacts and resource requirements. 9 Accordingly, deploying crews above the range associated with a given event level does 10 not mean the Company has used excessive resources. The ELM is a planning guide, 11 not a resource cap, and the declared event level does not dictate the precise number of 12 crews needed for an effective response. Mr. Balakumar’s proposed benchmark would 13 discourage deploying additional resources when justified or could potentially prompt 14 unnecessary escalation of event levels to satisfy staffing requirements. Thus, Mr. 15 Balakumar’s proposal would undermine effective storm response by replacing 16 operational flexibility with predetermined staffing mandates. 17 18 Q. Do you have any other comments regarding the reporting and benchmarking proposals offered by OCC’s witnesses? 19 A. Yes. All three OCC witnesses recommend that the Company report contractor time 20 spent on standby, travel, lodging, and meals separately. While such granular reporting 21 may be feasible and potentially useful, this recommendation appears to be based on a

As listed on the current system

Prefiled testimony: 11/18/2026 - Sponsor: TBD / Witness: DONALD J. SCACCO, JR., DIGAUNTO CHATTERJEE AND DOUGLAS P. HORTON [26-05-10]

This filing on the current system (opens in a new tab)