Witness: DOUGLAS P. HORTON, LAVELLE A. FREEMAN, DR. ELLI NTAKOU, JESS CAIN, JARED A. LAWRENCE, ANDREW C. BELDEN, MARC J. RICHARDS, AND CLARE B. CONNOLLY

Files2

Words on different pages
Every word of Eversource rate increase is in the text below, but not all on one page. Pages with any of them are listed and highlighted. Clear highlighting
Words on different pages
Words on different pages
  1. Page 7 of 39

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-METRICS-REBUTTAL-1 November 18, 2026 Page 5 of 37 1 discrete cost efficiency reporting metrics to increase transparency on the Company’s 2 changes in controllable costs. 3 IV. RESPONSE TO INTERVENORS A. 4 OCC Witnesses – Gennelle Wilson and Oliver Tully 5 6 Q. What recommendations does the OCC’s witnesses make with respect to the Company’s proposed PIMS and metrics? 7 A. Witnesses Wilson and Tully recommend that PURA adopt a Performance Evaluation 8 System untethered to the PBMRP (Wilson and Tully Testimony at 51). Witnesses Wilson 9 and Tully also recommend that PURA approve a suite of PIMs and metrics that more 10 closely align with the draft proposal issued in July 2026 in Docket No. 21-05-15RE02 11 (“RE02”) (Wilson and Tully Testimony, at 52). Specifically, the OCC witnesses make the 12 following recommendations: 13 14 • Include planned outages in the calculation of the Blue-Sky SAIDI and SAIFI PIMs (Wilson and Tully Testimony at 56-58); 15 16 17 18 19 • Incorporate annual CEMI-5 and CELID-6 performance into the Customer Reliability PIM, while adding a weighting of the components to address the Company’s valid concern with how the magnitude of CEMI-5 and CELID-6 could disproportionately distort and drive the composite score (Wilson and Tully Testimony at 58-60); 20 21 22 • Modify the Customer PIM Suite so that the Level 1 DER Interconnection Processing metric is the only PIM and the other metrics are standalone reporting metrics (Wilson and Tully Testimony at 60-61); 23 24 25 26 27 • Revise the Digital Customer Engagement component from encouraging additional use of digital transactions that can increase cost efficiencies, to tracking whether customers view and share with third-parties their electricity usage data provided by advanced metering infrastructure (“AMI”) to provide insights into customer behavior (Wilson and Tully Testimony at 62-64);
  2. Page 8 of 39

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-METRICS-REBUTTAL-1 November 18, 2026 Page 6 of 37 1 2 3 • Include a Non-Wires Solutions (“NWS”) Shared Savings Mechanism based on PURA’s ongoing redesign of the NWS process (Wilson and Tully Testimony at 6768); 4 5 • Revise the Cost Efficiency reporting metrics to adopt the preliminary metrics contemplated in RE02 (Wilson and Tully Testimony at 71-72); and 6 7 • Incorporate all other proposed RE02 metrics into the PBMRP and develop a publicly accessible PBR dashboard (Wilson and Tully Testimony at 70-71, 74-77). 8 Witnesses Wison and Tully also make various recommendations regarding the proposed 9 incentive and penalty levels for proposed PIMs, which the Company addresses in the 10 Leadership Panel Rebuttal testimony, jointly prepared by Company Witnesses Scacco, 11 Horton and Chatterjee. 12 13 Q. Does the Company agree with the OCC’s recommendation to include planned outages in the calculation of SAIDI and SAIFI for the purposes of PIMs under the PBMRP? 14 A. No, the Company disagrees with this recommendation. The OCC witnesses argue that 15 calculation of SAIDI and SAIFI for the purpose of PIMs should more closely align with 16 IEEE’s methodology (Wilson and Tully Testimony at 57). However, this argument fails 17 to recognize important distinctions in the purpose of IEEE benchmarking and PIMs, and 18 how incorporating planned outages in a PIM could have unintended consequences. 19 IEEE annually benchmarks reliability performance of utilities across the nation. IEEE has 20 developed a standardized methodology for creating a comparison across utilities 21 nationally. This is unlike the proposed PIM, which is designed to penalize the Company 22 if its reliability falls below a threshold established based on the Company’s own historical 23 performance. The purpose of the PIM is therefore to encourage the Company to make cost 24 effective investments to maintain system level reliability during the PBMRP term while
  3. Page 9 of 39

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-METRICS-REBUTTAL-1 November 18, 2026 Page 7 of 37 1 the Company pursues cost efficiencies. The Company’s proposed calculation of SAIDI 2 and SAIFI is designed to measure whether system reliability due to the Company’s 3 decisions on whether repairs or upgrades are necessary results in declining reliability 4 during the PBMRP term. Distorting these metrics to align with the IEEE method would 5 lose the critical measurement purpose of this metric. 6 Planned outages are known, isolated outages typically necessitated to enable critical 7 reliability improvements, infrastructure replacements and system modernization that 8 directly benefit customers through improved long-term reliability and reduced unplanned 9 outages. Including planned outages in the calculation of SAIDI and SAIFI as OCC 10 proposes could drive fluctuations in year-over-year performance that have nothing to do 11 with the reliability of service delivered by the Company and, rather, are associated with 12 work undertaken by the Company to improve reliability or provide service. 13 Company’s construction work on the system routinely requires service interruptions that 14 the Company handles by notifying customers in advance of the planned work and keeping 15 the outage windows as narrow as possible. The Company also manages the timing and 16 duration of planned outages to minimize customer impacts and inconveniences. Including 17 planned outages would distort the performance results in a given year because the metric 18 would capture outages that have nothing to do with the ability of the system to deliver 19 reliable power and withstand events that drive customer outages. Including planned 20 outages in the metric could also encourage a utility to delay implementation of beneficial 21 system-reliability projects in order to avoid triggering a penalty threshold. The
  4. Page 10 of 39

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-METRICS-REBUTTAL-1 November 18, 2026 Page 8 of 37 1 Excluding planned outages from the calculation of SAIDI and SAIFI ensures the metric 2 reflects changes in the reliability and resiliency of the electric distribution system driven 3 by failed equipment, rather than necessary system improvements. Since planned outages 4 represent proactive system improvements that benefit customers through enhanced long- 5 term reliability and service, not performance deficiencies that warrant penalties, they 6 should be excluded from the calculation of SAIDI and SAIFI for the purpose of PIMs. 7 8 Q. Does the Company agree with the OCC’s recommendation regarding expansion of the proposed Customer Reliability PIM to include annual CEMI-5 and CELID-6? 9 A. No, as witnesses Wilson and Tully acknowledge, there are significant flaws in including 10 annual CEMI-5 and CELID-6 in a Customer Reliability PIM, including valid issues with 11 the disproportionate impact these metrics could have on the PIM. 12 reasonable to focus on repeat customers as the Company proposes (Wilson and Tully 13 Testimony at 59). As explained in response to OCC-525, the frequency and/or duration of 14 interruptions for CEMI-5 and/or CELID-6 customers in a particular year can be due to one- 15 off events without repeat in a subsequent year. Since the purpose of a PIM should be to 16 motivate beneficial actions by the Company, including annual CEMI-5 and CELID-6 as a 17 component of a PIM would drive capital investments to prevent one-off events, potentially 18 increasing costs to customers with minimal benefits. The Company’s proposed Customer 19 Reliability PIM focuses on customers that experience long duration or frequent service 20 interruptions in multiple years, which are circumstances that should be addressed by the 21 Company, since these situations are more likely to be due to systemic issues. Therefore, it is
  5. Page 11 of 39

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-METRICS-REBUTTAL-1 November 18, 2026 Page 9 of 37 1 As the Company also explained in responses to OCC-525, inclusion of annual CEMI-5 and 2 CELID-6 in a composite metric could have unintended consequences due to the 3 disproportionate scale of the submetrics. The percent of repeat CEMI-5 and repeat 4 CELID-6 are numerically much smaller than annual CEMI-5 and CELID-6, and therefore 5 inclusion of annual customer counts would significantly skew achievement of the PIM 6 toward whether one-off random events occurred, rather than Company controllable actions, 7 which OCC agrees is a requirement of any potential PIM (Wilson and Tully Testimony at 8 53). 9 incorporating annual CEMI-5 and CELID-6, as OCC’s witnesses suggest, does not 10 alleviate the fundamental issue with basing a PIM on random, one-off events. Accordingly, 11 the Company respectfully requests that PURA reject OCC’s proposal to include annual 12 CEMI-5 and CELID-6 as a component of the Customer Reliability PIM, regardless of any 13 weighting. 14 To the extent that OCC seeks to have the number of CEMI-5 and CELID-6 customers 15 reported each year, that value is already reported in the Transmission and Distribution 16 Reliability Performance Report each year. Accordingly, to the extent OCC seeks to 17 understand the scale of annual CEMI-5 and CELID-6, OCC has access to the data without 18 including changes in annual CEMI-5 and CELID-6 customers in the Customer Reliability 19 PIM. Assigning an undefined weighting to address the inappropriate impact of
  6. Page 12 of 39

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-METRICS-REBUTTAL-1 November 18, 2026 Page 10 of 37 1 2 3 Q. Does the Company agree with the OCC’s recommendation to eliminate the Customer PIM Suite and establish a standalone Level 1 DER Interconnection Processing PIM and convert the other components to reporting only metrics? 4 A. No. As discussed above and in Exhibit CLP-ELP-1, at 104-106, the Company’s proposed 5 performance metrics are designed to complement and support the Company’s overall 6 PBMRP. Improving customer satisfaction and engagement in the performance areas 7 within the Customer PIM Suite will provide transparency and accountability for the 8 Company to maintain and seek to improve customer service while pursuing cost 9 efficiencies through the PBMRP. 10 Interconnection Processing, Digital Customer Engagement, Controllable Average Call 11 Handle Time, Post-Transaction Survey Customer Service Representative Attributes, and 12 Average Discount Rate Enrollment Time) provide a comprehensive measure of customer 13 service performance. The Company selected a composite PIM structure for its customer 14 metrics because customer experience is multidimensional and more appropriately 15 evaluated through a balanced set of performance measures rather than singularly measuring 16 customer metrics in isolation. 17 Adopting a standalone PIM for Level 1 DER Interconnection Processing, as the OCC 18 witnesses propose, could inadvertently prioritize focus on performance for this metric, 19 which benefits a small group of customers at the possible expense of other important 20 customer outcomes effecting a broad range of customers. The composite structure instead 21 encourages the Company to maintain balanced performance across a full range of 22 customer-focused objectives. Together, the five components (Level 1 DER
  7. Page 13 of 39

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-METRICS-REBUTTAL-1 November 18, 2026 Page 11 of 37 1 2 3 Q. Does the Company agree with the OCC’s conclusion that, except for the Level 1 DER Interconnection Processing metric, the components of the Customer PIM Suite do not warrant treatment as a PIM? 4 A. Each component of the Customer PIM Suite meets the criteria for inclusion in a PIM and 5 requires Company actions that provide meaningful benefits to customers to achieve the 6 metrics. As explained in response to UPA-084, each Customer PIM component is intended 7 to drive a specific operational outcome and deliver benefits to customers through sustained 8 performance improvements. 9 There are numerous dimensions to the customer experience that no single performance 10 measure can capture, nor that would provide PURA and other stakeholders with an accurate 11 indicator of the level of service that the Company is delivering in relation to the Customer 12 Experience. 13 assessment of the Company’s performance across a variety of customer engagement points 14 to ensure focus on continuing to provide a high-level of customer service across its breadth 15 of customers while the Company pursues cost efficiencies during the PBMRP term. The 16 components collectively reflect a significant cross section of the customer service efforts 17 for the Company by reflecting customer perception of service quality, responsiveness, ease 18 of doing business, and overall satisfaction. The proposed Customer PIM Suite is intended 19 to capture and motivate sustained improvements for the benefit of all customers in order to 20 achieve the PIM, rather than focusing on benefitting one subgroup, as the OCC witnesses 21 suggest. Therefore, the Customer PIM Suite is designed to provide a holistic
  8. Page 14 of 39

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-METRICS-REBUTTAL-1 November 18, 2026 Page 12 of 37 1 Digital Customer Engagement Component 2 The Digital Customer Engagement component measures digital transactions as a 3 percentage of overall customer transactions. Digital transactions include engagement with 4 customers via self-service and alert notifications. 5 The OCC’s position regarding the Digital Customer Engagement Component appears to 6 rest on the premise that, because digital engagement levels are already high, there is little 7 additional customer benefit associated with maintaining or increasing digital engagement 8 performance. That premise overlooks both the value customers derive from continued 9 improvements in digital service channels and the significant ongoing effort required to 10 sustain high levels of customer adoption and satisfaction. 11 The achievement of high digital engagement today does not mean that future performance 12 is automatic or can be maintained without continued focus and investment. The proposed 13 target of 92.18% is based on actual 2025 performance. Maintaining digital engagement 14 levels above 90% requires continual investment in website functionality, mobile 15 capabilities, customer communications, self-service tools, outage communications, 16 payment options, system reliability, accessibility, and overall user experience. Customer 17 engagement levels are influenced by the quality of these services and can decline if 18 customer expectations are not met. 19 Contrary to the intervenor's assertion that incremental customer benefit has not been 20 demonstrated, digital engagement provides substantial value. The services offered through 21 digital channels are a cost-effective way to serve customers and ensure that the Company's
  9. Page 15 of 39

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-METRICS-REBUTTAL-1 November 18, 2026 Page 13 of 37 1 web and digital tools provide a valued and satisfying experience. Sustaining and 2 incrementally increasing digital engagement continues to provide customer benefits 3 because each additional digital interaction typically represents a customer choosing a more 4 convenient, self-service option in lieu of a more burdensome, less cost-effective alternative 5 channel. Encouraging continued and expanded use of digital channels will allow customers 6 to complete transactions and obtain information in a cost-effective manner. 7 Further, contrary to the suggestion that digital engagement will naturally remain high 8 without intervention, customer adoption is directly influenced by the Company's 9 investments in digital platforms and customer experience improvements. While customer 10 preference for digital channels is trending upward, the investments in these digital channels 11 still need to be made; the channels must still work properly; and the customer experience 12 still has to be satisfactory to a level where the customers will still make the digital channels 13 their preferred engagement options on an ongoing basis. The proposed PIM component 14 therefore aligns utility incentives with customer behavior by encouraging the Company to 15 continue investing in digital capabilities that customers find useful and beneficial, thereby 16 increasing utilization of a cost-effective approach to allowing customers to complete 17 transactions and obtain information. 18 The Digital Customer Engagement metric is an appropriate component of the Customer 19 PIM Suite that incentivizes the Company to maintain and enhance the quality of digital 20 platforms that customers increasingly prefer and rely upon. The proposed target of 92.18% 21 is not intended to reward historical performance, but rather to establish accountability for
  10. Page 16 of 39

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-METRICS-REBUTTAL-1 November 18, 2026 Page 14 of 37 1 maintaining and improving a level of performance that customers have demonstrated they 2 value. The metric directly benefits customers by ensuring continued investment in cost- 3 effective, convenient digital service channels that improve customer satisfaction and 4 operational efficiency. 5 Controllable Average Call Handle Time 6 The Controllable Average Call Handle Time component measures the average amount of 7 non-phone time associated with customer interactions. 8 The OCC witnesses recognize but dismiss the benefit of maintaining and improving 9 customer call handle time under the PBMRP (Wilson and Tully Testimony at 64-65). This 10 position seems to stem from the OCC seeking to extricate the Customer PIM Suite from 11 the PBMRP. 12 As discussed above, the primary objective of the PBMRP framework is to encourage the 13 Company to pursue cost efficiencies during the stay out term while maintaining or 14 improving in key performance areas. Lowering call center costs and improving answer 15 times will help increase cost-efficiencies while improving customer satisfaction. 16 Incorporating this component into the Customer PIM Suite provides incentives for the 17 Company to focus on improving customer service as a means to pursue cost-efficiencies 18 but also serves to penalize the Company for allowing customer service to decline in pursuit 19 of other cost efficiencies. 20

As listed on the current system

Prefiled testimony: 11/18/2026 - Sponsor: TBD / Witness: DOUGLAS P. HORTON, LAVELLE A. FREEMAN, DR. ELLI NTAKOU, JESS CAIN, JARED A. LAWRENCE, ANDREW C. BELDEN, MARC J. RICHARDS, AND CLARE B. CONNOLLY [26-05-10]

This filing on the current system (opens in a new tab)