Page 107 of 130
Exhibit JRD-4 Page 64 of 87 Conservation Law Foundation and Sierra Club PURA Docket No. 26-05-10 Set CIEC-02 Date Issued: October 29, 2026 CIEC-012 Page 1 of 2 Date Filed: November 16, 2026 Witness: Request from: Juan-Pablo Velez Connecticut Industrial Energy Consumers Question CIEC-12: Please refer to Velez Direct Testimony at page 7, lines 3-8; page 93, lines 7-12; and page 96, lines 1-12. a. Does Mr. Velez agree that the load of existing heat pump customers is already on the Company’s system and reflected in the sales used to set the Company’s rates in this proceeding? If not, explain why not. b. Please identify any new load, or any reduction in the Company’s costs, that would result from enrolling existing heat pump customers in Rate HP. c. Please provide Mr. Velez’s estimate of the annual reduction in distribution and transmission revenue attributable solely to the automatic enrollment of existing heat pump customers. d. Please explain how the “pre-heat-pump T&D bill” referenced at page 85, lines 5-7 would be determined for an existing heat pump customer. Response: a. Yes. This is why I attribute the entire revenue reduction from Rate HP to existing heat pump customers, and none to new heat pump customers, who add load and revenue when they install (CIEC-1(a)). It is also why I recommend that the Authority set Rate 1 and Rate HP in this proceeding on billing determinants that already assign existing heat pump customers’ load to Rate HP (CIEC-2(d)). That their load is reflected in the sales used to set rates does not mean that their rates reflect the costs they cause. Under Rate 1, they overpay for T&D by an average of $1,040 a year (CIEC-1(a)). 1 b. None. When existing heat pump customers enroll in Rate HP, their usage does not change; they pay a lower winter rate on the same usage (CIEC-2(d)). The purpose of enrolling them is to end the overpayment described in part (a), not to change the Company’s load or costs. c. As stated in CIEC-1(a), auto-enrolling the roughly 55,000 existing heat pump customers who received Energize CT rebates (CIEC-1(b)) would reduce the Company’s revenue by about $39.8 million in distribution and $17.4 million in transmission a year, or $1,040.34 per customer. Tables 1 and 2 in CIEC1(a) report this reduction separately from the revenue increase from new heat pump customers, in the “Revenue reduced” columns. If the Authority does not auto-enroll existing heat pump customers, I would expect the reduction to be an order of magnitude smaller (CIEC-1(a)). d. It would not need to be determined. The pre-heat-pump T&D bill on page 85 is the population-average bill of the modeled fossil fuel-heated homes, which I used to calibrate the rate: I found the single winter 1 Direct Testimony of Juan-Pablo Velez on behalf of Conservation Law Foundation and Sierra Club (“Velez Direct”), at 23:9–10 (Oct. 21, 2026) (“fossil fuel-heated customers that install heat pumps overpay by an average of $1,040 a year”).Page 108 of 130
Exhibit JRD-4 Page 65 of 87 Conservation Law Foundation and Sierra Club PURA Docket No. 26-05-10 Set CIEC-02 Date Issued: October 29, 2026 CIEC-012 Page 2 of 2 rate that makes their average T&D bill after installing a heat pump equal to that pre-heat-pump bill plus the incremental marginal T&D cost.2 That one rate then applies to every enrolled customer, new or existing, without determining any individual customer’s pre-heat-pump bill. Charging only each customer’s incremental heat pump load at its marginal cost, while ideal, would indeed require a baseline for each customer, and is not practical. As my testimony explains, there are three ways to set one, and each adds complexity. A separate meter on the heat pump would add cost and friction to enrollment, and rule out auto-enrollment entirely. Circuit-level energy monitors installed with each new heat pump could be compatible with auto-enrolling new customers, but not existing ones, and their savings would likely have to be delivered as credits by a third party rather than through the Company’s bill. Billing software that estimates each customer’s baseline from their past usage would avoid both problems, but only if the Company committed to building it. 3 Because the first two approaches would make auto-enrollment difficult or impossible, they would lead to low enrollment and leave the crosssubsidy largely in place. 4 I therefore propose a seasonal rate, which achieves largely the same result without a per-customer baseline.5 2 Id. at 85:2–10 (“I found the single winter ¢/kWh rate that, applied to a sample of post-heat-pump load profiles, produces a population-average T&D bill equal to the customer’s pre-heat-pump T&D bill plus the incremental marginal T&D cost”; “[b]ecause this is a single rate applied to all customers, it zeroes out overpayment on average”). 3 Id. at 79:14–81:4 (“There are at least three ways to implement per-customer thresholds.”; “in order to achieve a block rate with per-customer thresholds that heat pump customers could be auto-enrolled into, the Company would either need to commit to a software-based solution, or to EnergizeCT contractors installing circuit-level energy monitors whenever they install heat pumps”). 4 Id. at 80:16–18 (“The first two make auto-enrollment difficult to impossible, which would lead to single-digit rate enrollment and leave the cross-subsidy largely in place.”). 5 Id. at 81:5–7 (“a simpler alternative to per-customer thresholds exists that achieves largely the same result: a seasonal rate design that lowers volumetric charges for heat pump customers in winter, without relying on a block threshold at all”).Page 109 of 130
Exhibit JRD-4 Page 66 of 87 Conservation Law Foundation and Sierra Club PURA Docket No. 26-05-10 Set CIEC-02 Date Issued: October 29, 2026 CIEC-016 Page 1 of 1 Date Filed: November 16, 2026 Witness: Request from: Juan-Pablo Velez Connecticut Industrial Energy Consumers Question CIEC-16: Please refer to Velez Direct Testimony at page 5, lines 10-13, and page 30, lines 9-17. a. Please confirm that the cross-subsidy Mr. Velez identifies is a cross-subsidy within the residential class. b. Please explain why any revenue reduction resulting from a remedy for a cross-subsidy within the residential class should, or should not, be borne by customers outside the residential class. Response: a. Confirmed. The passage CIEC cites says so (5:11–13), as does my response to CIEC-2(b). b. It should not. My responses to CIEC-2(b) and (c) explain why, and my response to CIEC-2(d) explains how to keep it within the residential class between rate cases.Page 110 of 130
Exhibit JRD-4 Page 67 of 87 Conservation Law Foundation and Sierra Club PURA Docket No. 26-05-10 Set CIEC-02 Date Issued: October 29, 2026 CIEC-017 Page 1 of 1 Date Filed: November 16, 2026 Witness: Request from: Juan-Pablo Velez Connecticut Industrial Energy Consumers Question CIEC-17: Please refer to Velez Direct Testimony at page 100, lines 11-13. a. Please explain what Mr. Velez means by pricing incremental heat pump loads at “(closer to)” marginal cost, and state whether he believes incremental heat pump load should make any contribution to the recovery of embedded T&D costs. b. If Mr. Velez believes incremental heat pump load should make some contribution to embedded T&D costs, please quantify the contribution reflected in Rate HP. Response: a. “(Closer to)” means at marginal cost on average rather than for every customer: Rate HP is a single rate calibrated to the average heat pump customer, as I explained in my response to CIEC-12(d). No, incremental heat pump load should not contribute to embedded T&D costs. I answered this in full in my response to CIEC-4(b): heat pump customers keep paying their pre-heat-pump share of embedded costs, and charging their new load for more shifts other customers’ embedded costs onto them. b. Not applicable (part (a)).Page 111 of 130
Exhibit JRD-4 Page 68 of 87 CIEC-4 The Office of Consumer Counsel Witness: Melissa Whited Docket No. 26-05-10 Page 1 of 1 Date Submitted: November 11, 2026 CIEC-4 Please refer to Whited Direct Testimony at page 11, lines 6-9, and page 12, line 1 (Table 1, rows “VVO” and “Asset Optimization”). a. Please state and explain in detail whether the VVO and Asset Optimization benefits shown in Table 1 would be realized if the Company installed AMI meters but did not make the VVO enablement investment included in its AMI cost estimates. b. To the extent those benefits depend on the VVO enablement investment, please explain why they are an appropriate basis for classifying the cost of AMI meters. Response: a. No. Other investments such as line devices such as voltage regulators, capacitors, and LTC controllers at substations must also be installed to unlock these benefits. b. The benefits associated with the VVO enablement investment also depend on the installation of AMI meters, as shown in Figure 16 on page 198 of Exhibit CLP-AMI-3. Because the benefits arise from multiple investments (i.e., in the meters themselves as well as other VVO enablement investments), it would be reasonable to only attribute a portion of these benefits to the meters themselves. However, to Ms. Whited’s knowledge, the benefits have not been divided across the various investments, so it is unclear what proportion should be attributed to the meters themselves. The benefits of Asset Optimization are more clearly attributable to the meters themselves, as AMI enables the Company to avoid the cost associated with line sensors. As explained on page 40 of Exhibit CLP-AMI-3, “Asset Optimization details the benefits of avoided cellular charges and avoided line-sensor capital associated with the AMI supported VVO program.”Page 112 of 130
Exhibit JRD-4 Page 69 of 87 CIEC-5 The Office of Consumer Counsel Witness: Melissa Whited Docket No. 26-05-10 Page 1 of 1 Date Submitted: November 11, 2026 CIEC-5 Please refer to Whited Direct Testimony at page 11, lines 8-9, and page 12, line 1 (Table 1, row “Improved Restoration – Significant Storms”). a. Please explain specifically how the cost of storm restoration, or the value of reduced customer outage time during significant storms, varies with class peak demand, and provide any study or analysis supporting the classification of this $162.4 million benefit as demand-related. b. Please identify any regulatory decision or cost allocation authority that classifies storm restoration costs as demand-related. Response: a. Avoided storm restoration expense relates to reduced operation and maintenance (O&M) expense such as repairing or replacing poles, conductors, and line transformers on the distribution system. Such O&M expense is classified on the same basis as the plant it maintains or restores. This plant is primarily classified as demand-related in the Company’s cost of service study. Under the basic customer method I recommend, distribution poles, conductors, and line transformers (FERC Accounts 364–368) are classified as 100 percent demand-related. The expense of restoring that plant is therefore demand-related as well. b. Ms. Whited is not aware of how other jurisdictions classify storm-related costs; however her understanding is that these costs may be allocated using allocators associated with distribution or transmission plant, and that such allocators are typically based on various measures of demand. For example: a. In dockets E-7, SUB 1243 and E-2, SUB 1262, the North Carolina Utilities Commission approved Duke’s storm recovery cost allocation as follows: the distribution-related costs are allocated based on a composite distribution plant allocator and the transmission-related costs are allocated based on a transmission demand factor, both from the 2019 Rate Cases. b. Texas law requires that “system restoration costs shall be functionalized and allocated to customers in the same manner as the corresponding facilities and related expenses are functionalized and allocated in the electric utility's current base rates.” 2025 Texas Statutes, Utilities Code, Section 36.403(g).Page 113 of 130
Exhibit JRD-4 Page 70 of 87 CIEC-6 The Office of Consumer Counsel Witness: Melissa Whited Docket No. 26-05-10 Page 1 of 1 Date Submitted: November 11, 2026 CIEC-6 Please refer to Whited Direct Testimony at page 4, lines 13-15, and page 11, lines 4-5 and 12-15. a. Please explain how a classification proportional to projected benefits reflects the causes of the costs being classified, particularly where the projected benefits of the AMI program are less than its projected costs (see Exhibit CLP-AMI-3 at 17-18, Figure 7). b. If the Company’s benefit estimates are revised in a future proceeding, or actual benefits differ from those projected, would Ms. Whited’s proposed classification of AMI meter costs change accordingly? Please explain the answer in detail. Response: a. Please see the response to CIEC-2 (d). As noted in that response, the additional cost of AMI is incurred to obtain capabilities beyond billing, such as enablement of time-varying rates, outage detection, and voltage optimization. Classifying costs in proportion to the quantified benefits therefore assigns them according to the functions the investment is designed to serve. This is the same principle that underlies classification generally: costs are classified according to the purpose for which they are incurred. The fact that projected benefits are less than projected costs does not change this conclusion. b. Yes, if the estimated or actual benefits were to change, it would be appropriate to update the classification of the AMI meters.Page 114 of 130
Exhibit JRD-4 Page 71 of 87 CIEC-7 The Office of Consumer Counsel Witness: Melissa Whited Docket No. 26-05-10 Page 1 of 1 Date Submitted: November 11, 2026 CIEC-7 Please refer to Whited Direct Testimony at page 9, lines 13-18. a. Please identify each AMI capability referenced at lines 14-16 that Ms. Whited contends is not currently available to customers served under Rate 39 and Rate 57 through their existing metering. b. Has Ms. Whited reviewed the number, type or cost of the meters currently serving Rate 39 and Rate 57 customers? If so, provide the information reviewed. Response: a. Ms. Whited has not conducted a review of the specific metering capabilities for customers on Rates 39 or 57. b. Ms. Whited has not conducted this review.Page 115 of 130
Exhibit JRD-4 Page 72 of 87 CIEC-8 The Office of Consumer Counsel Witness: Melissa Whited Docket No. 26-05-10 Page 1 of 1 Date Submitted: November 11, 2026 CIEC-8 Please refer to Whited Direct Testimony at page 4, lines 11-15, and page 12, lines 3-4. a. Please identify the allocation factors Ms. Whited would use to allocate the demand-related and energy-related portions of AMI meter costs to rate classes. b. Please provide, by rate class (including Rate 39 and Rate 57), the allocation of an illustrative $1 million AMI meter revenue requirement under (i) Ms. Whited’s proposed classification and (ii) the weighted meter cost allocator used for Account 370 in the Company’s ACOSS (Exhibit CLP-ACOS-2 at 16-20). Provide workpapers for the foregoing in Excel format. c. If Ms. Whited has not performed such an analysis, please explain why not. Response: a. As described in her testimony on pages 20-22, Ms. Whited recommends that the Company develop equipment-level allocators for its next base rate case. However, until such allocators are available, she recommends that AMI demand-related costs should be allocated on the same basis as other demand-related distribution costs. It is Ms. Whited’s understanding that most of the distribution system benefits would relate to the primary system, and thus primary demand would likely be the appropriate allocator. However, it could also be reasonable to develop a blended allocator if it can be demonstrated that a portion of benefits would also accrue to the secondary system and line transformers, which have different allocators. For energy-related AMI costs, Ms. Whited proposes to use kilowatt-hour sales as the allocator. For customer-related AMI costs, Ms. Whited proposes to use the weighted cost of meters. b. See attachment “Response to CIEC-8 (b) Allocation of AMI meter costs.xlsx” c. N/APage 116 of 130
Exhibit JRD-4 Page 73 of 87 OCC response to CIEC-8(b) Illustrative AMI Meter Costs Demand Energy Customer OCC PROPOSED ALLOCATION 9 ALLOCATOR NAME 22 Demand-non station 35 Sales kWh 92 47% 15% 38% ALLOCATOR NCP_P ENERGY METER_370 $1,000,000 $470,000 $150,000 $380,000 SOURCE WORKSHEET ALLOCATOR_INPUT ALLOCATOR_INPUT Meter Costs weights Demand Energy Customer AMI Meter Cost Allocation CLP CURRENT ALLOCATION 92 METER_370 DIFFERENCE Source: Exhibit CLP-ACOS-2, APPENDIX 1A. ALLOCATORS. Meter Costs weights AMI Meter Cost Allocation SYSTEM Rate 1 1.00 1.00 1.00 49.99% 42% 66% Rate 7 Rate 5 Rate 18 Rate 27 Rate 30 Rate 27A Rate 30A Rate 29 Rate 35 Rate 37 Rate 39 Rate 40 Rate 41 Rate 55 Rate 56 Rate 57 Rate 58 Rate 115 Rate 116 Rate 117 Rate 119 - Rate EV-S Rate EV-M Rate EV-L Special Contracts 0.05% 10.35% 0.00% 0.62% 14.53% 0.06% 0.74% 0.09% 1.76% 5.14% 0.29% 0.37% 0.07% 2.48% 6.01% 2.44% 4% 0.194% 0.127% 0.098% 0% 0% 0% 0% 0% 8% 0% 1% 16% 0% 1% 0% 2% 6% 1.12% 0% 0% 3% 8% 4% 7% 0.277% 0.137% 0.110% 0% 0% 0% 0% 0.22% 8.85% 0.03% 0.37% 18.02% 0.05% 0.75% 0.07% 0.82% 1.66% 0.02% 0.58% 0.01% 0.47% 1.01% 0.31% 0.43% 0.00% 0.00% 0.00% 0.02% 0.02% 0.02% 0.03% SYSTEM Rate 1 Rate 7 Rate 5 Rate 18 Rate 27 Rate 30 Rate 27A Rate 30A Rate 29 Rate 35 Rate 37 Rate 39 Rate 40 Rate 41 Rate 55 Rate 56 Rate 57 Rate 58 Rate 115 Rate 116 Rate 117 Rate 119 - Rate EV-S Rate EV-M Rate EV-L Special Contracts $470,000 $234,947 $230 $48,658 $15 $2,937 $68,303 $286 $3,496 $446 $8,254 $24,181 $1,372 $1,742 $319 $11,638 $28,262 $11,455 $20,457 $913 $596 $460 $18 $52 $100 $863 $150,000 $62,606 $66 $11,802 $5 $1,193 $24,096 $89 $1,139 $13 $3,344 $9,738 $1,678 $562 $88 $4,777 $12,325 $5,646 $9,791 $415 $206 $165 $13 $6 $24 $215 $380,000 $251,740 $841 $33,628 $132 $1,404 $68,466 $191 $2,853 $262 $3,121 $6,318 $69 $2,200 $39 $1,789 $3,821 $1,174 $1,619 $0 $0 $0 $71 $81 $78 $102 $1,000,000 $549,293 $1,136 $94,088 $152 $5,535 $160,865 $567 $7,488 $721 $14,718 $40,236 $3,118 $4,505 $447 $18,204 $44,407 $18,276 $31,867 $1,328 $802 $624 $102 $139 $202 $1,180 1.00 $1,000,000 SYSTEM 66% $662,474 0.22% $2,213 8.85% $88,494 0.03% $347 0.37% 18.02% $3,695 $180,175 0.05% $504 0.75% $7,507 0.07% $691 0.82% $8,212 1.66% $16,626 0.02% $182 0.58% $5,790 0.01% $103 0.47% $4,707 1.01% $10,055 0.31% $3,090 0.43% $4,261 0.00% $0 0.00% $0 0.00% $0 0.02% $188 0.02% $213 0.02% $205 0.03% $268 EV-S Rate EV-M Rate EV-L Rate 1 Rate 7 Rate 5 Rate 18 Rate 27 Rate 30 Rate 27A Rate 30A Rate 29 Rate 35 Rate 37 Rate 39 Rate 40 Rate 41 Rate 55 Rate 56 Rate 57 Rate 58 Rate 115 Rate 116 Rate 117 Rate 119 - Rate Special Contracts ($113,181) ($1,077) $5,594 ($195) $1,839 ($19,309) $63 ($19) $30 $6,506 $23,610 $2,937 ($1,286) $344 $13,498 $34,352 $15,186 $27,606 $1,328 $802 $624 ($86) ($74) ($4) $912