Prefiled testimony
Witness: James R. Dauphinais
Files1
26-05-10 CIEC Rebuttal Testimony and Exhibit of James R. Dauphinais.pdf
PDF · 1.9 MB · 130 pagesText searchable
Download 26-05-10 CIEC Rebuttal Testimony and Exhibit of James R. Dauphinais.pdfRead the text of 26-05-10 CIEC Rebuttal Testimony and Exhibit of James R. Dauphinais.pdf
Search terms highlighted
Eversource rate increase is on 8 pages of the text below, highlighted. Go to the first matchClear highlighting
Page 90 of 130
Exhibit JRD-4 Page 47 of 87 Conservation Law Foundation and Sierra Club PURA Docket No. 26-05-10 Set CIEC-02 Date Issued: October 29, 2026 CIEC-004 Page 1 of 2 Date Filed: November 16, 2026 Witness: Request from: Juan-Pablo Velez Connecticut Industrial Energy Consumers Question CIEC-4: Please refer to Velez Direct Testimony at page 9, lines 1-7; page 17, lines 1-6; and page 18, lines 3-6. a. Please confirm that, based on the figures in Velez Direct Testimony, the average fossil fuelheated customer pays approximately $1,178 per year in distribution and transmission charges ($814 + $364) before installing a heat pump, while causing approximately $123 per year in marginal T&D costs. b. Please explain why, under Mr. Velez’s methodology, the difference of approximately $1,055 per year between those two amounts is not also an “overcharge” or “overpayment.” c. Please confirm that this difference represents the customer’s contribution to the recovery of the embedded costs of the Company’s existing transmission and distribution facilities. If Mr. Velez does not agree, explain what that difference represents. Response: a. Confirmed. Before installing a heat pump, the average fossil fuel-heated customer pays $1,178 a year in distribution and transmission charges, 1 while causing $123 a year in marginal T&D costs: $28 upstream distribution and $95 bulk transmission. 2 b. Confirmed that, before installing a heat pump, the average fossil fuel-heated electric customer pays $1,055 a year more than the marginal T&D costs it causes. That amount is the customer’s contribution to the embedded costs of the existing system (part (c)). Those costs are sunk: no customer’s usage today causes them, but they still have to be paid, and nearly every customer pays something toward them.3 The testimony does not call that contribution an overpayment. Installing a heat pump transfers other customers’ embedded costs onto the heat pump customer. Under Rate 1, the customer’s T&D charges go up by $1,051 a year, but the heat pump causes only $10.30 a year in new T&D costs. The remaining $1,040 goes toward the existing system, nearly doubling the customer’s contribution to it, from $1,055 to $2,095. 4 The existing system costs the same as before, so the heat pump customer has taken $1,040 of embedded costs off everyone else, who now pay that much less. 5 1 Velez Direct at 9:3–6 (distribution and transmission charges under Rate 1). 2 Velez Direct at 18:3–6. 3 Velez Direct at 13:23–14:2 (existing “infrastructure does need to be paid for, those are sunk costs tied to old investments, not marginal costs”). 4 ͑$IWHULQVWDOOLQJ LQDGGHG7 'FKDUJHV í LQDGGHGPDUJLQDO7 'FRVW Id. at 20:5–8, 23:3–5. 5 The overpayment reaches other customers through two channels. Between rate cases, the RDM credits distribution revenue collected above the approved target back to all rate classes as a flat ¢/kWh, and the TAC trues up transmission revenue to the Company’s actual transmission costs (CIEC-2(d)). At the next rate case, the heat pump customer’s added kWh, about 6,432 aPage 91 of 130
Exhibit JRD-4 Page 48 of 87 Conservation Law Foundation and Sierra Club PURA Docket No. 26-05-10 Set CIEC-02 Date Issued: October 29, 2026 CIEC-004 Page 2 of 2 That is why the testimony calls the $1,040 an overpayment and not the $1,055: the $1,040 is a transfer. 6 The $1,055 is the fossil fuel-heated customer’s pre-existing share of embedded costs, the average amount it paid before installing the heat pump. The $1,040 is part of the embedded costs that other customers used to pay, which the heat pump customer takes on without causing any new costs that would justify it. That transfer is what the testimony calls a cross-subsidy, and it violates intra-class equity.7 The transfer also works directly against state policy: Connecticut has committed to heat pumps making up 65% of residential HVAC sales by 2030 and 90% by 2040, and is spending hundreds of millions of dollars to get customers to switch. But today, Rate 1 charges the average customer who does switch $1,040 a year to lower the electric bills of customers who keep heating with fossil fuels. 8 And this transfer spoils the economics of switching for gas-heated customers: under Rate 1, only 13% would see lower total annual energy bills after installing a heat pump; without the overpayment, 86% would. 9 c. Confirmed. year for the average fossil fuel-heated home, are spread over the residential class’s total kWh, which lowers the per-kWh rates that recover its revenue requirement. [Davis-Parsons Direct, Exhibit CLP-RATES-3] at 404 (RDM), 409 (TAC). 6 Velez Direct at 24:8–10. 7 Id. at 27:11–13, 29:7–17 (the cross-subsidy “violates intra-class equity”). 8 Id. at 34:1–3 (heat pump sales targets), 35:6–9 (Connecticut “is actively spending hundreds of millions of dollars to drive heat pump adoption”), 82:5–7 (the “ultimate objective of Rate HP is to fix the intra-class equity and building electrification policy problems that Rate 1 creates”). 9 Id. at 40:12–41:2, 41:3–5 (the overpayment is “the single largest barrier to favorable bill outcomes for natural gas-heated customers considering heat pumps”).Page 92 of 130
Exhibit JRD-4 Page 49 of 87 Conservation Law Foundation and Sierra Club PURA Docket No. 26-05-10 Set CIEC-02 Date Issued: October 29, 2026 CIEC-006 Page 1 of 2 Date Filed: November 12, 2026 Witness: Request from: Juan-Pablo Velez Connecticut Industrial Energy Consumers Question CIEC-6: Please refer to Velez Direct Testimony at page 27, lines 3-8. a. Please provide all analysis supporting the statement that the Company could eliminate the entire overpayment “without negatively affecting the bills of non-heat-pump customers.” b. Please explain how that statement is consistent with recovery of the Company’s authorized revenue requirement between rate cases if revenue from heat pump customers is reduced. c. Please provide Mr. Velez’s estimate of the bill impact of Rate HP on (i) residential customers who do not take service under Rate HP and (ii) non-residential customers, including those taking service under Rate 39 and Rate 57. Response: a. The statement is about customers who heat with fossil fuels today and install a heat pump after Rate HP takes effect (“new heat pump customers”). The full sentence reads: “The Company could eliminate all of the entire overpayment — discount the rate all the way down to the floor — and customers newly installing heat pumps would still be paying their full incremental cost of service, still satisfying cost causation, without negatively affecting the bills of non-heat-pump customers” (emphasis added). 1 The supporting analysis is already in the record. A new heat pump customer on Rate HP keeps paying its pre-heat-pump contribution to embedded costs, plus the new costs its heat pump causes (as explained in CIEC-4(b) and CIEC-5(a)). The underlying calculations are in Sections III and IV of the testimony and Exhibit JPV-2, Sections 2–4. The statement does not concern customers who already heat with a heat pump and pay Rate 1 today (“existing heat pump customers”). Their effect on other customers is addressed in CIEC-1(a), CIEC-3(c), and part (c). b. The statement concerns new heat pump customers, and the revenue the Company collects from them is not reduced. Relative to what Rate 1 was set to collect from them, it rises slightly, because they keep paying their pre-heat-pump bill and add the cost of their new load (CIEC-1(a)). A revenue reduction comes only from existing heat pump customers; how that reduction would be recovered, in this rate case and between rate cases, is addressed in CIEC-2(c) and (d). c. Enrolling customers who heat with fossil fuels today and install a heat pump after Rate HP takes effect (“new heat pump customers”) would raise no other customer’s bill: they would pay the Company slightly more under Rate HP than they paid before installing their heat pumps (part (b)). Any bill impact comes from customers who already heat with a heat pump and pay Rate 1 today (“existing heat pump 1 Direct Testimony of Juan-Pablo Velez on behalf of Conservation Law Foundation and Sierra Club (“Velez Direct”), at 27:5–8 (Oct. 21, 2026).Page 93 of 130
Exhibit JRD-4 Page 50 of 87 Conservation Law Foundation and Sierra Club PURA Docket No. 26-05-10 Set CIEC-02 Date Issued: October 29, 2026 CIEC-006 Page 2 of 2 customers”). Moving them to Rate HP ends their overpayment and shifts those embedded costs back to the customers who paid them originally (CIEC-2(b) and CIEC-5(b)). 1. Residential customers not on Rate HP. If PURA auto-enrolls existing heat pump customers who have received a heat pump rebate from Energize CT, as my testimony recommends, and the resulting revenue reduction is recovered from the residential class, as I propose in CIEC-2(b), then the average residential customer not on Rate HP would pay about $4.24 more a month. That is the increase in Rate 1 distribution and transmission charges estimated in CIEC-3(c), about 0.61¢ per kWh, applied to that customer’s annual usage. 2 Massachusetts has already taken this step: its investor-owned utilities automatically enrolled Mass Save heat pump rebate recipients, and about 140,000 customers were enrolled across the utilities before the 2025–2026 heating season.3 Without auto-enrollment of existing heat pump customers, however, the increase would likely be an order of magnitude smaller, because enrollment would be voluntary, and enrollment in heat pump rates has been low (CIEC-1(a) and CIEC-3(c)). 2. Non-residential customers, including Rates 39 and 57. No increase, if the Authority adopts the steps I recommend in CIEC-2(c) and (d): setting Rate 1 and Rate HP in this rate case with existing heat pump customers’ load already moved to Rate HP, and keeping any later shortfall within the residential class. Without those steps, the RDM and TAC would pass part of the existing-customer reduction to non-residential classes until the next rate case, as quantified in CIEC-2(d). 2 Net revenue reduction ÷ residential customers not on Rate HP, in 2031 under the high estimate of new heat pump customers, the same year and estimate as CIEC-3(c). Across all five rate years and both estimates, it ranges from $50 to $51 a year. CIEC-6 Attachment 1, CIEC-6c_nonhp_bill_increase.xlsx, sheet bill_impact, row 9. 3 Order on Seasonal Heat Pump Rates, D.P.U. 25-08-A (June 1, 2026), at 30. The 140,000 total includes customers who selfenrolled, not only those enrolled automatically.Page 94 of 130
Exhibit JRD-4 Page 51 of 87 Conservation Law Foundation and Sierra Club PURA Docket No. 26-05-10 Set CIEC-02 Date Issued: October 29, 2026 CIEC-007 Page 1 of 4 Date Filed: November 16, 2026 Witness: Request from: Juan-Pablo Velez Connecticut Industrial Energy Consumers Question CIEC-7: Please refer to Velez Direct Testimony at page 15, lines 5-10; page 16, lines 1-5; and page 62, lines 1114. a. Please explain why Mr. Velez estimated marginal transmission cost using an avoided Pool Transmission Facility cost and the probability of the New England system peak, rather than the method by which regional and local network transmission costs are actually allocated to the Company. b. Please describe Mr. Velez’s understanding of how ISO New England Inc. allocates regional network transmission service costs to the Company, including whether that allocation depends on the Company’s load at the time of the peak in each month. c. Has Mr. Velez estimated the effect of heat pump adoption on the Company’s monthly peak loads during November through March, or on the transmission costs allocated to the Company? If so, provide the analysis. If not, explain why not. d. Please explain how the 75% reduction in the winter Transmission Service Rate under Rate HP would affect the Company’s recovery of its transmission costs, and identify who would pay any resulting under-recovery. Response: a. My testimony measures the cost of the new transmission facilities that a heat pump customer’s added usage requires. That is a marginal cost. The cost allocation method the question describes measures something else entirely: how the cost of facilities already built is divided among the customers who use them. It cannot tell us what new facilities added load requires.1 The Company did not compute a marginal cost of transmission in this rate case. 2 I therefore constructed one. An hourly marginal cost has two parts: an annual cost per kilowatt of peak load, and a method for allocating that annual cost to the hours of the year, in proportion to how likely each hour is to fall at the peak that drives new investment. For the annual cost, I used the standard regional estimate. For the allocation to hours, I used the same probability-of-peak method the Company used for its distribution marginal cost. Because the transmission and distribution schedules are built the same way, they can be added together into one hourly marginal delivery cost, which I compared with the delivery charges a heat pump customer pays for its added usage. 1 See Synapse Energy Economics, Avoided Energy Supply Components (AESC) in New England: 2024 Report (“AESC 2024”), at 285 (May 24, 2024) (the avoided transmission cost does “not include any impact of changes in the cost or cost allocation of already-built regional transmission facilities”), 286 (it “is the value of avoiding or deferring projects associated with load growth”). 2 CL&P Response to CLF-SC-026, at 1 (“The Marginal cost of transmission was not computed for this rate design.”).Page 95 of 130
Exhibit JRD-4 Page 52 of 87 Conservation Law Foundation and Sierra Club PURA Docket No. 26-05-10 Set CIEC-02 Date Issued: October 29, 2026 CIEC-007 Page 2 of 4 The regional estimate is the avoided Pool Transmission Facility cost of $69/kW-year from AESC 2024: the cost of deferring regional transmission investment by one year through a one-year reduction in peak load. 3 The Company sponsors that study and uses it to screen its own energy efficiency programs, valuing avoided Pool Transmission Facility cost at $70.0 per kW. 4 I inflated the value to 2026 dollars, the dollar year of the Company’s marginal cost of service study. 5 To allocate that cost to hours, I applied the Company’s method to New England system load rather than to the Company’s distribution substation load, 6 because Pool Transmission Facilities are regional: as AESC puts it, “the transmission system is built to reliably meet the total system peak, each year.” 7 b. Regional Network Service is how ISO New England charges for the region’s shared high-voltage transmission system, the Pool Transmission Facilities. ISO New England bills the Company for it every month, and each month’s bill depends on the Company’s load in a single peak hour of that month, including in November through March. 8 The bill is built in three steps. 1. One regional cost pool and one rate. Each year, the transmission owners’ revenue requirements for the Pool Transmission Facilities are added together into a single New England total. That total is divided by the region’s load at monthly peaks, averaged over the twelve months of the year, to give a rate per kilowatt-year. 9 2. One hour per month. For billing, the tariff divides New England into zones it calls Local Networks, each covering the transmission systems of one transmission owner or group of affiliated owners. 10 The Company is in Eversource’s zone, which also includes Eversource’s systems in western Massachusetts and New Hampshire. 11 Each month, ISO New England finds the hour when 3 Direct Testimony of Juan-Pablo Velez on behalf of Conservation Law Foundation and Sierra Club (“Velez Direct”), at 15:6–9 (Oct. 21, 2026); AESC 2024 at 283 (the $69 per kW-year is “the cost of deferring the PTF investment by one year as a result of a one-year reduction in peak load”). 4 AESC 2024 at 4 (listing “Eversource (Connecticut Light and Power . . .)” among the sponsors); CL&P et al., 2025–2027 Conservation & Load Management Plan, at 178 (“The electric and fossil fuel avoided costs are based on a regional avoided energy supply cost study completed in 2024 for New England (‘2024 AESC’)”) and 181 (Figure 62 lists “Pooled Transmission Facilities” at “$70.0” per kW, sourced to “2024 AESC,” on a “Connecticut counterfactual 1 using a 15-year levelized basis; all values are in 2024 dollars”) (Nov. 1, 2024). 5 Ex. JPV-2, Section 3, Step 1. 6 Velez Direct at 15:9–16:3; Ex. JPV-2, Section 3, Step 2; CL&P Response to CLF-SC-033, at 1 (reprinting the Company’s response to OCC-733, which fit the method on “historical hourly Substation Loads from January 2022, to December 2025”). 7 AESC 2024 at 283. 8 CL&P Response to CLF-SC-031, at 1 (the costs of “transmission service provided (i.e., billed) to the distribution company . . . are determined on a monthly peak demand basis, at rates determined on a 12-month average peak demand”). 9 ISO New England, Open Access Transmission Tariff, Section II, at Schedule 9, Lines 1–3 and notes (b)–(c) (the revenue requirement “equals the aggregate of the ATRRs of the PTOs,” and the denominator is “[t]he average for the twelve months of the calendar year on which the rate is based of the sum of the coincident Monthly Peaks for all Local Networks”). 10 Id. at Attachment E (listing each “Local Network of” a named transmission owner or group of companies) (effective Jan. 1, 2023, FERC Docket No. ER23-16-000). 11 Attachment E lists the zone as “[t]he Local Network of the Northeast Utilities companies,” Eversource’s former name. Id. ISO New England, Open Access Transmission Tariff, Schedule 21-ES (Part A), at Section 1.5 (the “Eversource Companies” are “The Connecticut Light and Power Company, NSTAR Electric Company (West), and Public Service Company of New Hampshire”) (effective Jan. 1, 2022, FERC Docket No. ER20-2054-001).Page 96 of 130
Exhibit JRD-4 Page 53 of 87 Conservation Law Foundation and Sierra Club PURA Docket No. 26-05-10 Set CIEC-02 Date Issued: October 29, 2026 CIEC-007 Page 3 of 4 the combined load of that zone is highest. That is the only thing the zone does in the calculation: it fixes the hour in which the Company’s load is measured. 12 3. The Company’s bill. The Company’s load in that hour, times the rate, divided by 12, is its bill for the month. 13 The monthly peaks therefore decide how the regional cost pool is shared, not how large it is. If the Company’s load in a January peak hour rises, the Company pays a larger share of the same pool, and the other utilities in New England pay a smaller one. c. No, for two reasons. First, an estimate of the transmission costs allocated to the Company would not measure what my testimony measures. My testimony measures the cost of the new transmission facilities that a customer’s added load requires (part (a)). A change in the Company’s allocation adds no new facilities. As part (b) describes, load at a monthly peak changes the Company’s share of the embedded cost of existing facilities. Second, even if heat pump adoption raised the Company’s November–March peak loads, its allocation would not necessarily grow. The Company’s share is a ratio: its load at its monthly peaks, divided by the sum of all New England transmission customers’ loads at their own monthly peaks. That share rises only if the Company’s peak load grows faster, in percentage terms, than the region’s. If peak load elsewhere grows as fast or faster, the Company’s share stays the same or falls, because the same revenue requirement is spread over more kilowatts. And winter peak load is indeed forecast to grow across all of New England: ISO New England forecasts heat pumps adding to the winter peak in every New England state, 1,600 MW across the region by 2030, of which 224 MW is in Connecticut and 322 MW in Maine. 14 d. Rate HP would not affect whether the Company recovers its transmission costs. The Transmission Adjustment Clause reconciles the Company’s transmission revenue against its actual transmission costs, and carries any difference into the next year’s rate (CIEC-2(d)). 15 Who would pay any under-recovery depends on which customers enroll, and other responses already answer it: • New heat pump customers cause no under-recovery. Even at the lower winter Transmission Service Rate, each would pay the Company $8.08 a year more in transmission than it paid before installing its heat pump (CIEC-1(a) and CIEC-6(b)). 12 ISO New England, Open Access Transmission Tariff, Section II, at Section II.21.2 (a customer’s billing load is “its hourly load . . . coincident with the coincident aggregate load of all Network Customers served in each Local Network in the hour in which the coincident load is at its maximum for the month (‘Monthly Peak’)”) (effective Sep. 1, 2021, FERC Docket No. ER21-2337002). 13 Id. at Section II.21.1 (each customer pays “an amount equal to its Monthly Regional Network Load for the month times the applicable Local Network RNS Rate”), Schedule 9 (“Amount to be Paid = ((RNS Rate per kilowatt-year) x (Transmission Customers [sic] Monthly Network Load (a)) x (1/12))”). 14 ISO New England, Final 2026 Heat Pump Forecast, at 8 (annual additions to the heat pump stock in each of the six states), 24 (Winter 50/50 Peak Demand by Load Zone: 224 MW for CT, 322 MW for ME and 1,600 MW for ISONE in 2030) (May 1, 2026). 15 Davis-Parsons Direct, Exhibit CLP-RATES-3 at 409 (the TAC recovers “the difference between the Company’s TAC revenue and the Company’s TAC costs from the prior period”).Page 97 of 130
Exhibit JRD-4 Page 54 of 87 Conservation Law Foundation and Sierra Club PURA Docket No. 26-05-10 Set CIEC-02 Date Issued: October 29, 2026 CIEC-007 Page 4 of 4 • Existing heat pump customers would each pay $316.73 a year less in transmission (CIEC-1(a)). I recommend that other residential customers bear that reduction (CIEC-2(b)), and CIEC-3(c) estimates the resulting increase in Rate 1 charges. Although the Transmission Adjustment Clause is reset every year, what changes each year is the dollars: each annual filing divides each class’s share of transmission costs by sales from a fixed past rate year, currently “RY 2020 Billed Sales,” not current sales. 16 If the billing determinants approved in this rate case place existing heat pump customers’ load on Rate HP, Rate 1’s transmission rate is set high enough to cover their reduction, and no shortfall arises. If they do not, the reduction becomes a shortfall each year until the next rate case, and each year’s true-up would spread part of it to non-residential classes, unless the Authority directs the Company to recover that shortfall from the residential class only, as I recommend in CIEC-2(d). 16 RAM Exhibit 4 at 4:11–18; see also CL&P, Docket No. 25-01-03, Attachment 1, Exhibits 1–11, to Dave Thompson Rates Testimony, Exhibit 2 at 4 (the same “RY 2020 Billed Sales” a year earlier) (Feb. 14, 2025).Page 98 of 130
Exhibit JRD-4 Page 55 of 87 Conservation Law Foundation and Sierra Club PURA Docket No. 26-05-10 Set CIEC-02 Date Issued: October 29, 2026 CIEC-008 Page 1 of 6 Date Filed: November 16, 2026 Witness: Request from: Juan-Pablo Velez Connecticut Industrial Energy Consumers Question CIEC-8: Please refer to Velez Direct Testimony at page 83, lines 3-16, and page 84, lines 1-12 and footnote 76. a. Please explain Mr. Velez’s understanding of the basis for the difference between the Rate 5 and Rate 1 Transmission Service Rates, and state whether he contends that difference reflects marginal transmission cost. b. Please explain Mr. Velez’s understanding of whether the winter transmission charges in the Massachusetts heat pump rates he describes were designed to recover a winter transmission revenue requirement or were instead set at an estimate of marginal transmission cost. c. Please identify any jurisdiction of which Mr. Velez is aware that has set the retail transmission charges for a heat pump rate at an estimate of marginal transmission cost, and provide a copy of the relevant decision or tariff. d. For each Massachusetts heat pump rate Mr. Velez describes, please explain his understanding of how any reduction in distribution or transmission revenue resulting from the rate is recovered, including whether any portion is recovered from non-residential customers. Response: a. The difference between the Rate 5 and Rate 1 Transmission Service Rates comes from the method the Company uses to divide its transmission costs among its rate class groups. It does not reflect marginal transmission cost, and I do not contend that it does. The Company has not computed a marginal cost of transmission. 1 The Company allocates transmission costs by “rate class group.” A rate class group is either a single rate class, such as Rate 5, or several rate classes combined. 2 Rate 5 (Residential Electric Heating Service) serves homes that use electricity as their primary source of space heat and has been closed to new 1 2 CL&P Response to CLF-SC-026, at 1 (“The Marginal cost of transmission was not computed for this rate design.”). Docket No. 26-01-03, PURA Annual Review of the Rate Adjustment Mechanisms of The Connecticut Light and Power Company, CL&P Rates Filing, Attachment 1, Exhibit 4 (“RAM Exhibit 4”), at 4:11–20 (Feb. 17, 2026) (column headed “12 CP kW Demands by Rate Class,” listing Rate 1, Rate 7 and Rate 5 separately); Joint Direct Testimony of Edward Davis and Kimberly R. Parsons on behalf of The Connecticut Light and Power Company d/b/a Eversource Energy (“Davis-Parsons Direct”), Exhibit CLP-RATES-3, at 429 (July 14, 2026) (table of allocators by “Rate Class Group,” including “Rate 1 & Rate 7” and “Rate 5”).Page 99 of 130
Exhibit JRD-4 Page 56 of 87 Conservation Law Foundation and Sierra Club PURA Docket No. 26-05-10 Set CIEC-02 Date Issued: October 29, 2026 CIEC-008 Page 2 of 6 applicants since December 21, 2006. 3 For transmission, Rate 5 is a rate class group of its own, and Rates 1 and 7 are combined into another. 4 The Company sets each rate class group’s Transmission Service Rate in two steps, in its annual Reconciling Adjustment Mechanism filing:5 1. A share of the Company’s transmission costs. The Company divides its total transmission revenue requirement among its rate class groups in proportion to each group’s average demand at the Company’s twelve monthly system peaks. This follows the way ISO New England bills the Company for regional transmission, based on its load at the peak hour of each month (CIEC-7(b)). 2. A rate per kWh. Each rate class group’s share is divided by the group’s annual sales, taken from a fixed past rate year (CIEC-7(d)), and grossed up for the gross earnings tax. The Rate 5 and Rate 1 rates differ because the two groups’ demand at the monthly peaks differs relative to their sales. 6 Rate HP would not be a separate rate class group with its own share of transmission costs, as Rate 5 is. It would sit within the Rate 1 and Rate 7 rate class group, and would change how that group’s share is divided among the customers in it (see CIEC-2(c)), not the size of the share relative to other rate class groups, including non-residential customer groups. Existing heat pump customers take service under Rate 1 today, so their demand at the monthly peaks is already counted in the group’s share; moving them to Rate HP would leave that demand in the share. New heat pump customers’ added demand would count toward the group’s share in the same way, whether they took service under Rate 1 or Rate HP. Moreover, rate classes within the same group can already have different Transmission Service Rates. Rate 7 is in the same group as Rate 1, but instead of Rate 1’s 5.050¢/kWh in every hour, Rate 7 customers pay 11.741¢/kWh on-peak and 2.525¢/kWh off-peak. 7 b. My testimony cites Massachusetts as precedent for a commission directing winter transmission reductions in heat pump rates. 8 The Massachusetts winter transmission charges were designed to recover a winter transmission revenue requirement. They were not set at an estimate of marginal transmission cost. 9 3 Davis-Parsons Direct, Exhibit CLP-RATES-3 at 246 (“This rate is not available to new applicants after December 21, 2006”; available “only to customers who use electric energy as the primary space heating source”). 4 CL&P Response to CLF-SC-035, at 1 (“Rate 7 is included in the cost allocation and overall revenue requirement along with Rate 1”); RAM Exhibit 4 at 4:16–20 (Rates 1 and 7 combined, Rate 5 on its own). 5 RAM Exhibit 4 at 4:11–20, 60 (each rate class group’s share of the “Transmission & TAC Revenue Target” is its share of “12 CP kW Demands by Rate Class,” defined as “Average rate class KW demands coincident to the Company’s 12 monthly system peaks,” and the rate is that share divided by “RY 2020 Billed Sales,” plus gross earnings tax). 6 RAM Exhibit 4 at 4:18, 20 (Rates 1 and 7 combined: 1,652,552.5 kW, $372,620 thousand, 7,916,705 MWh, 5.050¢/kWh with gross earnings tax; Rate 5: 338,287.6 kW, $76,278 thousand, 1,669,921 MWh, 4.901¢/kWh). 7 Davis-Parsons Direct, Exhibit CLP-RATES-3 at 256; RAM Exhibit 4 at 2:17, 34 (Rate 7’s “Transmission Target” of 5.050¢/kWh, divided into off-peak and on-peak rates using on-peak and off-peak shares of sales that are “set at Rate 1 percentages”: 27.4% × 11.741¢ + 72.6% × 2.525¢ = 5.050¢). 8 Direct Testimony of Juan-Pablo Velez on behalf of Conservation Law Foundation and Sierra Club (“Velez Direct”), at 84:3–12 (Oct. 21, 2026). 9 D.P.U. 25-08-A, Inquiry by the Department of Public Utilities on its own Motion into a Seasonal Heat Pump Rate, Order on Seasonal Heat Pump Rates (“D.P.U. 25-08-A Order”), at 19 n.4 (“‘cost-based’ means that the winter transmission charges were structured to be revenue neutral, recovering the capital costs embedded in the transmission service revenue requirement through
As listed on the current system
Prefiled testimony: 11/18/2026 - Sponsor: TBD / Witness: James R. Dauphinais [26-05-10]