    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-PBR-REBUTTAL-1 November 18, 2026 Page 21 of 68 1 Regulatory precedents also demonstrate that an OM&A-specific revenue cap can be 2 implemented alongside a separate capital recovery mechanism. In D.P.U. 23-150, the 3 Massachusetts Department of Public Utilities (“MA DPU”) approved National Grid’s 4 O&M-specific productivity factor together with a composite inflation index designed to 5 reflect O&M input-price changes. The MA DPU determined that an additional adjustment 6 for differences between industry and economy-wide productivity was unnecessary because 7 the inflation index reflected utility input prices rather than broader economy-wide output 8 prices. Accordingly, the MA DPU approved an O&M X-Factor of 0.21%. 24 9 The MA DPU also approved a separate capital recovery mechanism, known as the 10 Infrastructure, Safety, Reliability, and Electrification (“ISRE”) mechanism, for core 11 distribution capital investments. The MA DPU recognized the need to provide funding for 12 capital investments necessary to maintain safe and reliable service while preserving 13 incentives for operating efficiency. The approved mechanism includes regulatory oversight 14 and a cap on annual increases in capital-related revenue requirements equal to 3% of total 15 revenues. 25 16 Similarly, the British Columbia Utilities Commission (“BCUC”) approved FortisBC Inc.’s 17 2025–2027 rate framework, which applies an O&M-specific inflation index and a 0.45% 18 productivity adjustment comprising a 0.20% industry O&M PFP component and a 0.25% 19 stretch factor, while addressing capital through separate provisions. 26 24 Massachusetts Department of Public Utilities, Massachusetts Electric Company and Nantucket Electric Company d/b/a National Grid, D.P.U. 23-150, Final Order (September 30, 2024), 83–87. 25 Massachusetts DPU, D.P.U. 23-150, Final Order, 44–50, 56. 26 British Columbia Utilities Commission, FortisBC Energy Inc. and FortisBC Inc. 2025-2027 Rate Setting Framework, Decision and Orders G-69-25 and G-70-25 (March 18, 2025), sec. 3.1.5 and Order G-70-25, item 2; CL&P, response to OCC-442.
  2. Page 24 of 70

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-PBR-REBUTTAL-1 November 18, 2026 Page 22 of 68 1 These precedents illustrate the use of an O&M-specific inflation and productivity 2 framework with separate capital-recovery provisions. Although the specific mechanisms 3 and parameters differ, both regulators recognized that operating and capital costs can be 4 addressed through different regulatory mechanisms within an integrated PBR framework. 5 The specific terms of those mechanisms must still be considered when evaluating the 6 Company’s proposed F-Factor. 7 8 9 10 11 Q. Ms. Griffin questions limiting the indexed revenue cap to OM&A costs. Dr. Taylor also recommends a TFP-based X-Factor as one alternative if the revenue cap applies to total costs, while Ms. Wilson and Mr. Tully question the use of an OM&A-specific inflation index rather than the economy-wide index. 27 Why are OM&A PFP and the proposed composite I-Factor appropriate for the Company’s OM&A-only cap? 12 A. The productivity and inflation measures in a revenue adjustment mechanism need to align 13 with the costs covered by the revenue adjustment mechanism. Since the Company’s 14 proposed I-X formula applies to covered OM&A costs, while capital-related costs are 15 addressed through a separate funding mechanism, it should be intuitive to all stakeholders 16 that OM&A PFP and an OM&A focused input price inflation index are the appropriate 17 measures. 18 OM&A PFP measures changes in industry output relative to the quantity of OM&A inputs 19 used to serve customers. In contrast, TFP measures changes in output (proxied by number 20 of customers) relative to both OM&A and capital inputs. Applying a TFP measure, as 21 suggested by Ms. Griffin and Dr. Taylor, directly to an OM&A-only revenue adjustment 22 mechanism would incorporate capital productivity trends into a formula that does not 27 Griffin, Direct Testimony, 33–37; Wilson and Tully, Direct Testimony, 45–46; Taylor, Direct Testimony, 34–35.
  3. Page 25 of 70

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-PBR-REBUTTAL-1 November 18, 2026 Page 23 of 68 1 govern capital cost recovery. This would create a mismatch between the productivity 2 adjustment and the costs to which it applies. 3 The I-Factor and X-Factor must be calibrated consistently because they jointly determine 4 the annual adjustment to the Company’s covered OM&A revenue allowance. The I-Factor 5 should reflect the input-price environment relevant to the OM&A activities whose 6 productivity is measured by the X-Factor. Otherwise, the revenue adjustment mechanism 7 may not accurately reflect changes in the industry’s OM&A input costs. 8 Consistent with these principles, LEI recommended an I-Factor that combines the 9 Employment Cost Index (“ECI”) for utility labor costs and Gross Domestic Product 10 Implicit Price Deflator for Final Sales to Domestic Purchasers (“GDP-FSDP”) for non- 11 labor OM&A costs, weighted using historical industry labor and non-labor cost shares. As 12 discussed in the LEI Industry TFP Study Report, when the I-Factor is calibrated to reflect 13 the relevant OM&A input-price changes and paired with the corresponding industry 14 OM&A PFP measure, additional adjustments for economy-wide productivity and input- 15 price differentials are not required. Such adjustments would generally be necessary if the 16 Company instead used a broad economy-wide inflation index on its own. 28 17 Accordingly, the appropriateness of a productivity factor cannot be determined 18 independently of the inflation index and the costs subject to the revenue adjustment 19 mechanism. 28 Frayer, Direct Testimony, 62-64; CL&P, response to OCC-428; response to UPA-051.
  4. Page 26 of 70

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-PBR-REBUTTAL-1 November 18, 2026 Page 24 of 68 1 2 3 Q. Ms. Wilson and Mr. Tully object to the proposed zero floor on the I-Factor because it prevents negative inflation from flowing through that component of the formula. 29 Do you share their concern? 4 A. No, I do not, because in fact many of the costs for a utility under OM&A pose limited 5 scope for deflation. For example, wage increases for CL&P’s union employees are 6 established through multi-year collective bargaining agreements and therefore do not 7 necessarily adjust downward in response to short-term changes in inflation. PURA’s 8 independent management audit of Eversource’s Connecticut companies confirms that 9 annual wage increases are stipulated in multi-year labor agreements, with negotiated 10 annual increases for CL&P’s union employees generally ranging from 2.75% to 3.5% 11 during 2019–2022. 30 Consequently, negative inflation in a particular year would not 12 necessarily translate into a corresponding reduction in the Company’s actual OM&A costs. 13 The Eversource Leadership Panel proposes a zero floor and a 5% cap on the I-Factor. As 14 discussed in their testimony, the floor limits the Company’s exposure to reductions in the 15 underlying inflation index, while the cap limits the I-Factor applied to customers during 16 higher-inflation periods. 31 Together, these provisions establish boundaries on the annual 17 inflation adjustment, protecting the Company against negative inflation adjustments that 18 may not reflect corresponding reductions in its underlying costs, while limiting customers’ 19 exposure to unusually high inflation adjustments. 29 Wilson and Tully, Direct Testimony, 46. 30 FTI Consulting, Management Audit of Eversource Energy’s Connecticut Companies, Public Version, RFP No. 2022-01 (February 11, 2025), 4-19. 31 Donald J. Scacco, Jr., Digaunto Chatterjee, and Douglas P. Horton, Joint Direct Testimony , 91–92.
  5. Page 27 of 70

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-PBR-REBUTTAL-1 November 18, 2026 Page 25 of 68 C. Capital Recovery and Efficiency Incentives under the Proposed F-Factor 1 2 3 Q. Ms. Griffin raises concerns about the Company's proposed F-Factor. Do you have any further comments on the proposed F-Factor given Ms. Griffin’s stated concerns? 4 A. Ms. Griffin’s comments around the F-Factor can be distilled to two areas: why should the 5 utility get recovery of capital costs within the PBR term and why is the F-Factor different 6 from proposed CT-Bar in RE01. 32 The proposed F-Factor is intended to provide a 7 predictable mechanism for recovering of the costs associated with capital investments 8 placed in service during the four-year PBMRP, including the cost of financing those 9 investments. As discussed in my direct testimony, capital investments involve financing 10 costs when they are undertaken. Deferring recovery of those costs (the “return” component) 11 until the next rate case may create additional financial pressure on the Company during the 12 multi-year stay-out period 33 and will likely cause more rate shock at the start of the next 13 term – which is not in the best interests of consumers. 14 Indeed, the CT-Bar contemplated in the RE01 PFD was proposing to defer recovery of the 15 return on capital investment until a subsequent rate case, and the EDCs noted in response 16 to the RE01 RFD that this would have resulted in significant under-recovery. 34, 35 17 The proposed F-Factor includes several safeguards governing the review and recovery of 18 capital expenditures. First, PURA reviews and approves the capital forecast used to 19 establish the plan’s allowance. 36 Second, the annual RAM proceeding reconciles actual 32 Griffin, Direct Testimony, 41-43, 45-46. 33 Frayer, Direct Testimony, Exhibit CLP-PBR-1, 68–71. 34 Connecticut Public Utilities Regulatory Authority (“PURA”), PURA Investigation into Revenue Adjustment Mechanisms for a Performance-Based Regulation Framework, Docket No. 21-05-15RE01, Proposed Final Decision (July 14, 2025), 31–39; Scacco, Chatterjee, and Horton, Joint Direct Testimony, 101–103. 35 PURA, RE01 Proposed Final Decision,. 32–33, and Appendix A. 36 The Company separately proposes adjusting the forecast caps if PURA approves advanced metering infrastructure (“AMI”) investment.
  6. Page 28 of 70

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-PBR-REBUTTAL-1 November 18, 2026 Page 26 of 68 1 qualifying capital placed in service with the approved forecast. Third, following PURA’s 2 determination that the investments are prudent, used, and useful, the capital revenue 3 requirement ultimately recoverable after reconciliation is limited to the lesser of the 4 approved forecasted requirement and the requirement associated with actual plant in 5 service. Downward reconciliation protects customers when actual eligible additions fall 6 short of the forecast, and excess investment cannot be recovered through the F-Factor 7 during the initial four-year term. 8 In summary, under the proposed F-Factor, the Company is not guaranteed recovery of 9 either the full capital forecast or all actual capital expenditures. Although the mechanism 10 allows the Company to recover a return on capital investments during the PBMRP term, 11 annual reconciliation and prudence review determine the amount ultimately recoverable. 12 These limits govern final recovery, while the collection schedule determines when 13 customers make payments. My support for the structure reflects the financing rationale and 14 those recovery constraints, considered together. 37 15 16 17 Q. Ms. Wilson and Mr. Tully argue that possible recovery of above-forecast expenditures in a subsequent rate case weakens capital-cost discipline. 38 Does that possibility eliminate cost containment incentives of the F-Factor? 18 A. No. As explained in my direct testimony and my response to Ms. Griffin above, the 19 approved forecast establishes a ceiling on the capital revenue requirement recoverable 20 through the F-Factor during the initial four-year PBMRP term. This limitation creates 21 financial exposure for the Company during the four-year stay-out period and provides an 37 Griffin, Direct Testimony, 42–43; Frayer, Direct Testimony, Exhibit CLP-PBR-1, 68–71. 38 Wilson and Tully, Direct Testimony, 21.
  7. Page 29 of 70

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-PBR-REBUTTAL-1 November 18, 2026 Page 27 of 68 1 incentive to develop realistic capital forecasts, prioritize necessary investments, and 2 manage project costs within the approved allowance. 3 Although above-forecast expenditures may be considered in a subsequent base rate 4 proceeding or successor PBMRP, recovery is not automatic. The Company would need to 5 justify those expenditures and obtain PURA’s approval. 39 But during the PBMRP term, 6 the Company bears the financial consequences of expenditures that are not eligible for 7 recovery through the F-Factor. Thus, the possibility of future recovery is uncertain during 8 the PBMRP term, and therefore the incentives for the Company to live within the budget 9 ceiling set by the F-Factor design are strong. 10 Downward reconciliation does, however, take away the opportunity to retain savings from 11 underspending. So as compared to a fixed capital allowance that the Company could retain 12 regardless of actual expenditure, the downward reconciliation may dampen the incentives 13 to cut costs at the margin. However, the Company realized that the reconciliation feature 14 would be necessary to accommodate PURA’s and stakeholders’ worries around using 15 forecasts. The incentive associated with the forecast ceiling is therefore principally to avoid 16 the financing and recovery risks of exceeding the allowance, while the downward 17 reconciliation creates a safeguard against inflated forecasts. Overall, I believe this is a good 18 compromise given the circumstances for the Company (i.e., the significant capital 19 investment needs over the PBMRP term) and recognition of the varying concerns that 20 PURA and stakeholders may have. 39 Scacco, Chatterjee, and Horton, Joint Direct Testimony, Exhibit CLP-ELP-1, 101–102; Wilson and Tully, Direct Testimony, 21, 23–24.
  8. Page 30 of 70

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-PBR-REBUTTAL-1 November 18, 2026 Page 28 of 68 1 Thus, the proposed F-Factor provides a meaningful constraint on capital cost recovery 2 during the PBMRP term. My support rests on that constraint, timely recovery of prudent 3 investment costs, and the customer protections discussed above, considered together. 4 5 6 7 8 Q. Ms. Griffin argues that prudence review may permit a capital project even when a cheaper operating or non-wires alternative is available. 40 Ms. Wilson and Mr. Tully also raise concerns about capital bias and capitalization of OM&A expenses. 41 In your opinion, how does the proposed framework address these investment-related concerns? 9 A. The basic reality of the Company’s PBMRP plan is that they will be facing a revenue cap 10 with various performance incentives. Moreover, to set the F-Factor, the Company will have 11 had to provide its capital investment plans and forecasts. Operating and capital 12 expenditures are inherently different and not perfect substitutes. That said, the structure of 13 the PBMRP does not change the best practices that Eversource would apply to seeking out 14 the best option – be that an operating solution, a capital investment or a non-wires 15 alternative (“NWA”). The revenue cap construct, with all the elements, will drive the 16 Company to seek the best combination of resources to operate the utility and meet, and 17 preferably surpass, its performance incentives. 18 Forecast limits, reconciliation, prudence review, and accounting requirements (which 19 require adherence to stated capitalization policies) will each contribute to limit the 20 Company’s ability to pursue more than the efficient levels of capital investment and 21 therefore should address intervenors’ witnesses’ concerns on capital bias. 22 For example, the Company acknowledges that its capital investments during the PBMRP 23 term will continue to be subject to prudency reviews by PURA. Ms. Griffin herself 40 Griffin, Direct Testimony, 24–25. 41 Wilson and Tully, Direct Testimony, 21–22.
  9. Page 31 of 70

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-PBR-REBUTTAL-1 November 18, 2026 Page 29 of 68 1 acknowledges that prudence review examines wires versus non-wires investments, 2 procurement, project design, and cost management. 42 3 4 5 6 Q. Ms. Wilson and Mr. Tully argue that annual capital reconciliation and prudence review would introduce administrative complexity and reduce the efficiencies of a multi-year rate plan. Do these reviews undermine the benefits of the Company’s PBMRP? 7 A. Annual capital reconciliation and prudence review will require regulatory resources. 8 However, a multi-year rate plan does not necessarily eliminate all annual interactions 9 between the regulator and the regulated firm. Indeed, PBR plans typically have some form 10 of annual compliance filing. These are intentionally much simpler than a full rate case, and 11 I would expect that the annual process at PURA would be simpler than a full rate case. 12 Under the Company’s proposed PBMRP, the covered OM&A allowance would be adjusted 13 through the I-X formula, while capital-related costs would be addressed through a separate 14 annual reconciliation process. This allows PURA to review actual capital additions and 15 their prudence without necessarily reopening the Company’s entire revenue requirement 16 each year. 17 Therefore, I am expecting some opportunity for administrative efficiency gains relative to 18 a counterfactual where the Company does not have a stay out provision and must file 19 frequent cost of service rate cases. 42 Griffin, Direct Testimony, 41.
  10. Page 32 of 70

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-PBR-REBUTTAL-1 November 18, 2026 Page 30 of 68 D. Alternative sources for setting the X factor 1 2 3 4 5 6 Q. Dr. Taylor recommends considering the public BLS utilities MFP estimate of 0.457% for setting the X Factor, especially if the indexed revenue cap includes both OM&A and capital costs. 43 He also questions the difference between that estimate and LEI’s industry TFP results. Does the public BLS utilities MFP index support a different XFactor? 7 A. The BLS utilities MFP index and LEI’s Industry TFP for U.S. electric distribution firms 8 examine very different activities and use different measurement approaches. As explained 9 in the written response to CLF-AC-016, the BLS utilities MFP index covers the broader 10 utilities industry (NAICS 22), including electric generation, transmission and distribution, 11 natural gas, steam, water supply, and sewage services. 44 In contrast, LEI’s study focuses 12 specifically on the U.S. electric distribution industry. It would be wholly inappropriate to 13 take productivity trends from the electric generation sector – given, for example, how fast 14 technology is evolving – and apply it to the electric distribution industry. 15 The studies also differ in their output and input measures. LEI measures distribution output 16 using the number of customers served and calculates productivity based on real OM&A 17 and capital inputs – both standard approaches in regard to TFP studies for ratemaking 18 purposes. BLS measures real sectoral output, which represents the quantity of goods and 19 services produced for delivery outside the utilities sector, adjusted to remove the effects of 20 price changes and to avoid double counting of transactions within the sector. BLS includes 21 capital, labor, energy, materials, and purchased services as inputs. 43 Taylor, Direct Testimony, 25–27, 34–35. 44 CL&P response to CLF-AC-016(a)–(c); LEI, Industry TFP Study, Exhibit CLP-PBR-2, 25.
22 pages match
2 pages match

As listed on the current system

Prefiled testimony: 11/18/2026 - Sponsor: TBD / Witness: Julia Frayer [26-05-10]