  1. Page 1 of 25

    STATE OF CONNECTICUT PUBLIC UTILITIES REGULATORY AUTHORITY Docket No. 26-05-10 APPLICATION OF THE CONNECTICUT LIGHT AND POWER COMPANY D/B/A EVERSOURCE ENERGY TO AMEND ITS RATE SCHEDULES JOINT REBUTTAL TESTIMONY OF WARREN R. BOUTIN AND LAVELLE A. FREEMAN Interconnection of Distributed Generation On behalf of The Connecticut Light and Power Company d/b/a Eversource Energy November 18, 2026
  2. Page 2 of 25

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-INTERCONNECTION-REBUTTAL-1 November 18, 2026 Table of Contents 1 I. INTRODUCTION...........................................................................................................1 2 II. PURPOSE OF TESTIMONY ........................................................................................5 3 III. DG INTERCONNECTION OVERVIEW....................................................................6 A. 4 Background on Company’s Interconnection Process ...............................................6 5 IV. RESPONSE TO ICC ......................................................................................................8 6 7 A. PURA Should Not Standardize Interconnection Rules or Documents in this Proceeding. .........................................................................................................................10 8 9 B. PURA Should Not Require Binding Cost Estimates and Construction Timelines. 13 10 C. Dispute Resolution Already Exists ...........................................................................21 11 D. Alleged Staffing Issues ...............................................................................................22 12 E. Incentives and Penalties ............................................................................................23 13 V. CONCLUSION .............................................................................................................23
  3. Page 3 of 25

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-INTERCONNECTION-REBUTTAL-1 November 18, 2026 Page 1 of 23 STATE OF CONNECTICUT PUBLIC UTILITIES REGULATORY AUTHORITY JOINT REBUTTAL TESTIMONY OF WARREN R. BOUTIN AND LAVELLE A. FREEMAN 1 I. INTRODUCTION 2 Q. Please state the names of the witnesses on the Interconnection Rebuttal Panel. 3 A. The Interconnection Rebuttal Panel is comprised of Warren R. Boutin and Lavelle A. 4 Freeman. We are providing this rebuttal testimony on behalf of The Connecticut Power 5 and Light Company d/b/a Eversource Energy (“CL&P” or the “Company”). 6 Q. Mr. Boutin, please state your name and business address. 7 A. My name is Warren Boutin. My business address is 247 Station Drive, Westwood, 8 Massachusetts, 02090. 9 Q. By whom are you employed and in what capacity? 10 A. I am employed by Eversource Service Company (ESC), and I am the Vice President of 11 Customer Grid Electrification Solutions and Experience. 12 Q. Please summarize your education and professional experience. 13 A. I received my Bachelor of Science in Mechanical Engineering from Norwich 14 University and my Master of Business Administration from Bentley University. I have 15 been employed by ESC for over 30 years. I have held various positions with ESC 16 including Manager of Electric Strategic Accounts and the Director of Electric Service 17 Support, Distributed Energy Resources and Supplier Services. I assumed my current
  4. Page 4 of 25

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-INTERCONNECTION-REBUTTAL-1 November 18, 2026 Page 2 of 23 1 position of Vice President of Customer Grid Electrification Solutions and Experience 2 in January 2024. In my current position I am responsible for establishing valued 3 business relationships, providing grid electrification solutions, and a superior customer 4 experience to the company’s strategic accounts, national accounts, large, medium and 5 small customers, builders and developers, including our Distributed Energy Resource 6 (DER) developers, Electric Vehicle (EV) customers, third party communication fiber 7 and antenna attachers. 8 Q. Have you previously testified before PURA or elsewhere on regulatory matters? 9 A. No. 10 Q. Did you previously sponsor pre-filed testimony in this proceeding? 11 A. No, I did not. 12 Q. Mr. Freeman, please state your name and business address. 13 A. My name is Lavelle A. Freeman. My business address is 107 Selden Street, Berlin, 14 Connecticut. 15 Q. By whom are you employed and in what capacity? 16 A. I am the Vice President of Distribution System Planning for ESC. I am responsible for 17 overseeing all activities in Eversource’s service areas in Connecticut, Massachusetts 18 and New Hampshire related to: capacity expansion for bulk distribution substations and 19 supporting circuits, including developing ten-year load forecasts and detailed system 20 models; performing system impact studies and developing solutions for large
  5. Page 5 of 25

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-INTERCONNECTION-REBUTTAL-1 November 18, 2026 Page 3 of 23 1 distributed energy resource (“DER”) interconnections; assessing system reliability and 2 resiliency performance and needs, and developing targeted plans for improvement; and 3 integrated energy planning to safely and reliably transition customers from the gas 4 system to the electric system. 5 Q. Please summarize your education and professional experience. 6 A. I earned a Bachelor of Science degree in Electrical Engineering from the University of 7 Alabama. Subsequently, I earned a Master of Science degree in Electrical Engineering 8 with a concentration in Power Systems from the University of North Carolina at 9 Charlotte and a Master of Science degree in Computer Engineering from North 10 Carolina State University. I joined the IEEE Power Engineering Society while in 11 graduate school and have been on the ANSI C84.1 Standard Committee. 12 I started my power systems career in 1997 as an R&D Engineer at ABB Corporate 13 Research in Raleigh, NC, where I devised innovative new products, algorithms and 14 solutions to improve the value and efficiency of transmission and distribution product 15 offerings within ABB Power T&D Inc. In 1999, I became a Senior Consulting 16 Engineer in the ABB Utility Consulting group in Raleigh, NC, where I performed 17 system studies in distribution and transmission planning for utility customers, worked 18 with customers to implement changes, and developed and supported power systems 19 software applications that improved the efficiency, marketability and cost- 20 effectiveness of the group.
  6. Page 6 of 25

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-INTERCONNECTION-REBUTTAL-1 November 18, 2026 Page 4 of 23 1 From 2003 to 2013, I was a Senior Engineer and then a Principal Engineer at General 2 Electric Energy in Schenectady, NY, where I led consulting studies in distribution 3 planning and analysis, power systems engineering, equipment applications, smart grid 4 initiatives, and renewables impact and contributed to the development of new products 5 and technology for various General Electric Energy businesses. From 2013 to 2016, I 6 was Manager of Transmission and Distribution at General Electric Energy Consulting, 7 where I directed a broad spectrum of client activities in the T&D space, with emphasis 8 on power systems operation and planning, equipment application, renewables impact, 9 and systems analysis. From 2016 through 2020, I was Technical Director at General 10 Electric Energy Consulting in Schenectady, New York. In this position, I led project 11 teams and developed business opportunities in the distribution space with emphasis on 12 DER integration, microgrid design, grid modernization, reliability, power quality and 13 resiliency. I developed and led execution of over $5M in distribution-related projects 14 in New York, New Jersey and Massachusetts. I also successfully completed four 15 ground-breaking New York Prize Stage 2 microgrid design projects and managed the 16 Distribution System Testing and Research (DSTAR) consortium, working extensively 17 with distribution planners and engineers in investor-owned, municipal and cooperative 18 utilities across the country. 19 Distribution System Planning. In 2024, I was appointed to my current position. In 2020, I joined Eversource Energy as Director, 20 Q. Have you previously testified before PURA or elsewhere on regulatory matters? 21 A. Yes. I have previously testified and participated in several proceedings before the 22 Connecticut Public Utilities Regulatory Authority (“PURA”), including: Docket No.
  7. Page 7 of 25

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-INTERCONNECTION-REBUTTAL-1 November 18, 2026 Page 5 of 23 1 17-12-03RE08, PURA Investigation Into Distribution System Planning of the Electric 2 Distribution Companies – Resilience and Reliability Standards, Docket No. 17-12- 3 03RE07, PURA Investigation into Distribution System Planning of the Electric 4 Distribution Companies – Non-Wires Alternatives, Docket No. 21-05-15RE02, PURA 5 Investigation Into Performance-Based Regulation Framework, Docket No. 21-05- 6 RE03, PURA Investigation Into the Establishment Of Integrated Distribution System 7 Planning Within a Performance-Based Regulation Framework, Docket No. 22-06- 8 29RE01, PURA Investigation Into Distributed Energy Resource Interconnection Cost 9 Allocation – Non-Residential Interconnection Upgrades, and Docket No. 22-06-05 10 PURA Implementation of Public Act 22-55. I have also testified before the 11 Massachusetts Department of Public Utilities numerous times and before the New 12 Hampshire Public Utilities Commission. 13 Q. Did you previously sponsor testimony in this proceeding? 14 A. Yes, I sponsored testimony in Exhibit CLP-TSP-1 and supporting exhibits. 15 II. PURPOSE OF TESTIMONY 16 Q. What is the purpose of your testimony? 17 A. The purpose of our testimony is to respond to the testimony of the Interconnection 18 Customer Coalition (“ICC”), which critiques the Company’s interconnection process 19 for distributed generation (“DG”) facilities and provides several recommendations to 20 PURA, which are addressed in turn below.
  8. Page 8 of 25

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-INTERCONNECTION-REBUTTAL-1 November 18, 2026 Page 6 of 23 1 Q. Are you presenting any exhibits as part of your rebuttal testimony? 2 A. No. 3 Q. How is your testimony organized? 4 A. Our testimony is organized into the following sections: 5 • Section I is the introduction; 6 • Section II provides the purpose of our testimony and overview; 7 • Section III provides an overview of DG Interconnection process; 8 • Section IV provides our response to ICC; and 9 • Section V provides our conclusion. 10 11 III. DG INTERCONNECTION OVERVIEW A. 12 Background on Company’s Interconnection Process 13 Q. What documents govern the interconnection process for Eversource? 14 A. There are three primary documents which govern the interconnection process in the 15 State of Connecticut: (1) Guidelines for the Interconnection of Residential Single Phase 16 Certified Inverter-Based Generating Facilities of 50 kW (AC) or Less; (2) Guidelines 17 for Generator Interconnection Excluding Residential Inverter Based Projects Level 1 18 50 kW or Less; and (3) Exhibit B Generator Interconnection Technical Requirements. 1 19 The applicability of these documents is dependent on the size of the interconnecting 20 project. 1 See Company’s response to ICC-002, ICC Attachments 1, 2, and 3.
  9. Page 9 of 25

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-INTERCONNECTION-REBUTTAL-1 November 18, 2026 Page 7 of 23 1 Q. How were these documents developed? 2 A. The Company and United Illuminating Company (“UI”) developed these documents together with stakeholder input through working groups. 2 3 4 Q. Were these documents reviewed and approved by PURA? 5 A. Yes. The Guidelines, including the Interconnection Agreement, were initially reviewed 6 and approved in 2004 in Docket No. 03-01-15. Order No. 2 of the Docket No. 03-01- 7 15 Decision required the Company to submit clean and redline versions of the 8 Guidelines to PURA, along with an explanation of the changes, within ten days 9 following the effective date of any revision to the Guidelines. On July 10, 2007, in 10 compliance with Order No. 2 of the Docket No. 03-01-15 Decision, the Company and 11 UI submitted proposed revisions to the Guidelines, including revisions to the form of 12 Interconnection Agreement, as compliance in Docket No. 03-01-15. 13 Q. Were these documents more recently reviewed by PURA? 14 A. Yes, these documents were filed in clean and redlined form with PURA most recently 15 in Docket Nos. 17-12-03RE06, 22-06-29, 22-06-29RE01, 24-08-05, 25-01-27, and 25- 16 08-05. 3 17 18 2 3 Company’s response to ICC-003. Company’s response to ICC-002.
  10. Page 10 of 25

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-INTERCONNECTION-REBUTTAL-1 November 18, 2026 Page 8 of 23 1 Q. At a high level, please explain the Company’s interconnection process. 2 A. For Level 2 projects, the Fast Track Process is available for certified generating 3 facilities up to 2 MW that meet Connecticut's eligibility criteria and pass the applicable 4 technical screens. Projects that pass Fast Track generally receive an Interconnection 5 Agreement within approximately 15 business days of a complete application, with an 6 optional site visit available to refine service upgrade cost estimates. 7 Projects that do not qualify for Fast Track, as well as projects larger than 2 MW, 8 proceed through the study process. Eversource generally issues the applicable study 9 agreement within 15 business days of receiving a complete application. The study 10 process evaluates system impacts and identifies any required upgrades. Depending on 11 project complexity, studies typically take 30 to 60 business days to complete. Projects 12 greater than 1 MW may also require ISO-NE, transmission, or other regional studies 13 outside PURA's jurisdiction, which can extend the overall timeline. 14 IV. RESPONSE TO ICC 15 Q. Please provide a high-level summary of the ICC’s testimonies. 16 A. ICC submitted three separate testimonies by Verogy Holdings (“Verogy”), Earthlight 17 Technologies (“Earthlight”), and Greenskies Clean Energy (“Greenskies”) 18 (collectively, “ICC”). At a high level, each of the testimonies claims the Company’s 19 interconnection process has unnecessary delays and requirements that result in 20 customer frustration, additional cost, and, at times, projects withdrawing from the

As listed on the current system

Prefiled testimony: 11/18/2026 - Sponsor: TBD / Witness: WARREN R. BOUTIN AND LAVELLE A. FREEMAN [26-05-10]