  1. Page 11 of 25

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-INTERCONNECTION-REBUTTAL-1 November 18, 2026 Page 9 of 23 1 interconnection queue. 4 ICC provides several recommendations for resolving these 2 alleged issues. 3 The Company notes that ICC members have raised individualized claims and concerns 4 relating to the circumstances, development, and treatment of their respective projects. 5 These individualized complaints and grievances are beyond the scope of this 6 proceeding and should not be addressed in the context of this rate case. This proceeding 7 is intended to address the Company’s proposed rates and related matters of general 8 applicability, not to serve as a forum for adjudicating project-specific disputes or 9 resolving individual developers’ grievances regarding the circumstances of their 10 respective projects. To the extent that any developer believes it has a legitimate project- 11 specific concern or grievance, that concern should be raised and addressed separately 12 through the appropriate resolution process. Depending on the nature of the issue, that 13 may include the applicable dispute resolution process, where the particular facts and 14 circumstances relevant to that project can be properly considered, or to the extent the 15 issues warrant broader consideration, a separate docket dedicated to addressing such 16 matters. 17 Q. Please summarize ICC’s recommendations. 18 A. ICC recommends PURA: 19 20 • 4 require interconnection rules be standardized with stakeholder input and PURA review and approval; ICC-Veogy at 6-7; ICC-Earthlight at 7, 14; ICC-Greenskies at 6, 10-11
  2. Page 12 of 25

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-INTERCONNECTION-REBUTTAL-1 November 18, 2026 Page 10 of 23 1 2 • require Eversource to provide accurate cost estimates and construction timelines; 3 • require Eversource to allow self-help; 4 • require pre-application process and improved hosting capacity maps; 5 • make dispute resolution binding; 6 7 • require Eversource to hire more full-time equivalents in the interconnection group; and 8 • impose incentives and penalties for missing deadlines. 5 9 10 11 Q. Is the Company’s rate case the appropriate venue for ICC’s critiques or recommendations related to DG interconnection? 12 A. No, it is not. As noted above, despite ICC’s claims to the contrary, the critiques and 13 recommendations outlined by ICC are statewide issues that would need to be addressed 14 in a more appropriate forum with all interested stakeholders involved, including UI and 15 other developers. 6 16 17 A. PURA Should Not Standardize Interconnection Rules or Documents in this Proceeding. 18 19 Q. Do you agree with ICC’s recommendation to “standardize” interconnection rules? 7 20 A. The interconnection rules, through the Guidelines outlined above, are already 21 standardized. Any recommended changes to the already standardized interconnection 22 rules should be through another proceeding with all interested parties having an 5 6 7 ICC-Earthlight at 30-31; ICC-Verogy at 21; ICC-Greenskies at 12-13. The Company is not replying herein to each and every issue or point raised by ICC. The Company’s silence on any point made or issue raised should not be construed as support for ICC’s perspective on that issue. See ICC-Earthlight at 31; ICC-Verogy at 19
  3. Page 13 of 25

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-INTERCONNECTION-REBUTTAL-1 November 18, 2026 Page 11 of 23 1 opportunity to participate. The Company’s rate case, which makes no proposals related 2 to Level 2 DG interconnection standards, is not the appropriate forum. 3 4 Q. Are there other more appropriate forums for discussing changes to interconnection? 5 A. Yes, there are other more appropriate forums. First, the Interconnection Working Group 6 (“Working Group”) is specifically focused on accelerating and improving DG 7 interconnection in Connecticut. Since early 2021, the Working Group has been meeting 8 almost every month to discuss various topics related to interconnection and includes 9 appropriate solar industry stakeholders. 8 In addition, per the governing framework on 10 the Working Group, solar developers constitute two of the six voting members of this 11 group. 12 Additionally, there are other active proceedings before PURA involving DG 13 interconnection that are more appropriate for this discussion. 14 Q. Have there been recent proceedings concerning interconnection issues? 15 A. Yes. There have been recent proceedings involving interconnection-related issues. In 16 Docket No. 17-12-03RE06, the 100-Day Sprint Working Group Report included 17 consensus interconnection recommendations that PURA adopted, and through Docket 18 No. 25-01-27, the Company is implementing those recommendations. Indeed, many of 19 the topics for which the ICC provided recommendations were addressed in PURA’s The Company notes that Verogy, Earthlight, and Greenskies recently participated in the Working Group, as well as stakeholders like Michaud Law Group, Honeywell, and Conn Solar. 8
  4. Page 14 of 25

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-INTERCONNECTION-REBUTTAL-1 November 18, 2026 Page 12 of 23 1 recent decisions issued in 2025 in that docket. For example, ICC recommends a “chess 2 clock” functionality to PowerClerk, but this has already been adopted in Docket No. 3 25-01-27 Final Decision at 7 (Aug. 20, 2025) and implemented by the Company. 9 4 The topics raised by the ICC are more appropriate to be resolved in a reopened Docket 5 No. 25-01-27. In fact, in Docket No. 25-01-27, PURA declined to implement proposals 6 relating to some of the topics raised in ICC member testimony, such as changes to the 7 dispute resolution process. The Company does not oppose reopening Docket No. 25- 8 01-27 to reevaluate rejected proposals and/or evaluate additional proposals, if PURA 9 would like to explore these proposals further. 10 11 Q. ICC claims it is unclear if PURA has recently reviewed the Interconnection Guidelines. 10 Has PURA recently reviewed the Guidelines? 12 A. Yes. As noted above, PURA directed several revisions and updates to the Guidelines in 13 Docket No. 25-01-27. As part of Eversource’s compliance with Order No. 1 of that 14 Final Decision, the Company filed revised Guidelines on November 14, 2025. 11 Any 15 updates to the Guidelines would need to be performed jointly with United Illuminating 16 and be submitted to PURA for review and approval. 17 substantive revisions to the Guidelines by itself and without PURA’s authorization. Eversource cannot make 18 9 10 11 See Docket No. 25-01-27, Eversource responses to CAE-107 and CAE-107SP01. ICC-Verogy at 5. See Docket No. 25-01-27, Eversource Motion for Approval, Attachments 2a & 2b (Nov. 14, 2025).
  5. Page 15 of 25Match

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-INTERCONNECTION-REBUTTAL-1 November 18, 2026 Page 13 of 23 B. 1 2 PURA Should Not Require Binding Cost Estimates and Construction Timelines. 3 4 Q. Do you agree with ICC’s recommendation to require binding timelines and costs 12 to be provided? 5 A. The Company reiterates that the rate case is not the appropriate forum for this 6 discussion, but, no, we do not agree. The Company always provides a good faith 7 estimate of the anticipated interconnection costs associated with a project. However, 8 the Company cannot provide “binding” cost estimates because cost estimates can 9 fluctuate for a variety of reasons, including those outside the Company’s control, such 10 as supply chain issues and customer delays. 11 A similar proposal to prevent the EDCs from issuing supplemental costs to developers 12 was considered and not approved by PURA in Docket No. 25-01-27. Docket No. 25- 13 01-27 Final Decision at 19 (2025). PURA held that the proposal to cap cost increases 14 was not in the public interest because it would “increase costs for ratepayers by shifting 15 additional interconnection expenses . . . from project developers to ratepayers.” 16 Moreover, PURA recognized some interconnection upgrade cost increases are outside 17 the Company’s control. Id. 18 The Company reiterates that this rate case is not the appropriate forum for these issues; 19 however, it disagrees with ICC's recommendation. ICC cites examples in which 20 preliminary estimates communicated by the Company differed from subsequent study 12 See ICC-Verogy at 19; ICC-Greenskies at 13
  6. Page 16 of 25

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-INTERCONNECTION-REBUTTAL-1 November 18, 2026 Page 14 of 23 1 results and characterizes those differences as evidence that the Company's estimates 2 lack durability. 13 The Company disagrees with that characterization. 3 Developers frequently seek planning-level cost information before completing the 4 applicable engineering study so they can evaluate project viability, development risk, 5 and potential interconnection constraints while engineering work remains ongoing. 6 Such information serves a different purpose than a completed engineering study. 7 Preliminary information is intended to provide an understanding of the potential 8 magnitude of interconnection costs and system modifications based on the information 9 available at that stage of the engineering review, whereas the completed study provides 10 the engineering analysis and cost estimate on which interconnection decisions are 11 ultimately based. 12 Consistent with its commitment to supporting successful interconnections, the 13 Company routinely works with customers throughout the study process to provide 14 available information regarding potential system impacts, anticipated modifications, 15 and preliminary cost expectations before all engineering activities are complete. 16 Providing such information allows developers to evaluate project viability and make 17 informed business decisions while studies remain in progress. However, the Company's 18 willingness to provide preliminary information for planning purposes should not be 13 See ICC-Earthlight at 9-12.
  7. Page 17 of 25

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-INTERCONNECTION-REBUTTAL-1 November 18, 2026 Page 15 of 23 1 construed as a representation that such information constitutes a final engineering 2 determination or binding cost estimate. 3 Consistent with Section 8.0 of the Impact Study Agreement, the Company provides a 4 non-binding good faith estimate of cost responsibility and time to construct the 5 facilities required to accommodate an interconnection request. While a System Impact 6 Study identifies the system modifications required to accommodate an interconnection 7 request, detailed engineering, equipment specification, and construction planning are 8 generally completed later in the process. As a result, these estimates are intended to 9 provide a reasonable projection of expected costs based on the information available at 10 the time but are often refined as project development progresses and additional 11 information becomes available. The interconnection process also provides customers 12 the option to obtain a Facility Study, through which additional engineering is performed 13 and project scope and cost estimates may be further refined. Neither the Impact Study 14 Agreement nor the Facility Study Agreement characterizes these estimates as binding. 15 The fact that a preliminary estimate differs from a subsequent completed study result 16 does not demonstrate that the preliminary estimate lacked value or that the 17 interconnection process was deficient. Rather, it reflects the inherent distinction 18 between planning-level information developed during an ongoing study process and 19 the completed engineering analysis that forms the basis of the final study results. 20 Preliminary estimates and completed study results serve different purposes, and 21 differences between the two are completely reasonable and explainable.
  8. Page 18 of 25

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-INTERCONNECTION-REBUTTAL-1 November 18, 2026 Page 16 of 23 1 The Feasibility Study is intended to provide developers early visibility into potentially 2 significant system upgrades preliminarily identified through the interconnection review 3 process. Such upgrades may include major distribution or substation modifications that 4 the developer did not previously anticipate. The study provides a high-level assessment 5 of anticipated upgrade requirements and associated costs based upon the information 6 available at the time the study is performed. Because those upgrades have not yet 7 undergone detailed engineering review, internal project development, procurement 8 review, and other technical evaluation, the identified facilities and associated cost 9 estimates remain preliminary, non-binding, and subject to refinement as additional 10 engineering and analysis are completed. 11 More broadly, ICC's testimony relies heavily on a limited number of project-specific 12 examples to support broad changes to the interconnection framework, including 13 binding cost estimates, binding construction timelines, and revisions to existing 14 interconnection procedures. The Company does not believe those examples support the 15 conclusions advanced by ICC. Interconnection projects involve unique engineering, 16 construction, procurement, scheduling, permitting, and customer-development 17 circumstances that must be evaluated based upon the specific facts associated with each 18 project. Accordingly, project-specific outcomes should not be generalized into 19 conclusions regarding the overall effectiveness of the Company's interconnection 20 process or the need for broad regulatory changes.
  9. Page 19 of 25

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-INTERCONNECTION-REBUTTAL-1 November 18, 2026 Page 17 of 23 1 Many of the policy issues raised by ICC, including interconnection cost responsibility, 2 dispute resolution, process improvements, and project timelines, have already been 3 considered through prior PURA proceedings, stakeholder working groups, complaint 4 processes, and revisions to the Interconnection Guidelines. The Company believes 5 those forums remain the appropriate venue for consideration of interconnection policy 6 issues rather than this rate proceeding. 7 Q. Can the Company provide more firm construction timelines? 8 A. For similar reasons articulated above, the Company cannot provide binding 9 construction timelines. Many factors outside the Company’s control would make 10 binding, firm construction timelines prohibitive. For example, supply chain delays, 11 weather, scheduling constraints, and other factors may all affect construction timelines. 12 Moreover, while the Company strives to efficiently interconnect DG, the Company’s 13 first priority is ensuring the interconnecting facility does not jeopardize the safe, 14 reliable operation of the EPS for all customers. 15 Recently, PURA established new permission to operate (“PTO”) timeline requirements 16 for the EDCs. Docket No. 25-01-27 Final Decision at 30. PURA directed the EDCs to 17 issue PTO within 20 business days of Authority Having Jurisdiction (“AHJ”) approval 18 for all residential projects under 50 kW, and within 30 business days for all Level 2 19 projects, provided that all developer requirements have been satisfied and none of the 20 seven operational exceptions apply. Id.
  10. Page 20 of 25

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-INTERCONNECTION-REBUTTAL-1 November 18, 2026 Page 18 of 23 1 2 Q. Do you agree with ICC’s claims 14 that Eversource frequently oversteps AHJ causing unnecessary delays? 3 A. We do not. First, as stated above, the Company’s rate case is not the appropriate forum 4 for the interconnection concerns raised. Second, ICC Earthlight’s claim that the 5 Company oversteps AHJ and refuses NEC-compliant design options was already raised 6 and denied by PURA. Docket No. 25-01-27 Final Decision at 34-35 (2025). PURA 7 concluded that “EDC oversight and inspection of certain interconnection components 8 beyond the transformer remain necessary” and noted municipal inspectors may lack the 9 technical expertise required to assess an interconnection. Id. Additionally, in 10 compliance with PURA’s Final Decision, the Company has incorporated jurisdiction 11 examples into the DER Specific Metering Supplement to the Eversource Information 12 and Requirements Book 2024. 15 13 Q. Do you agree developers should be permitted to self-help? 16 14 A. No, we do not. Verogy cites the telecommunications space as an example where self- 15 help is permitted; however, the telecommunications sector is not an appropriate 16 comparison. Self-help is only permitted in the communications gain, not the electric 17 gain. The Company’s first and foremost responsibility is to maintain the safe, reliable 18 operation of the EPS. To reduce the risk of service impacts to all customers supplied 14 15 16 ICC-Earthlight at 18. See Docket No. 25-01-27, CL&P Supplement to Motion No. 17 (Jan. 23, 2026). ICC-Verogy at 20; ICC-Greenskies at 13.

As listed on the current system

Prefiled testimony: 11/18/2026 - Sponsor: TBD / Witness: WARREN R. BOUTIN AND LAVELLE A. FREEMAN [26-05-10]