Prefiled testimony
Witness: WARREN R. BOUTIN AND LAVELLE A. FREEMAN
Files2
Docket No. 26-05-10 CLP Rebuttals Filing Letter (11.18.26).pdf
PDF · 152 KB · 3 pagesText searchable
Download Docket No. 26-05-10 CLP Rebuttals Filing Letter (11.18.26).pdfRead the text of Docket No. 26-05-10 CLP Rebuttals Filing Letter (11.18.26).pdf
Exhibit CLP-INTERCONNECTION-REBUTTAL.pdf
PDF · 272 KB · 25 pagesText searchable
Download Exhibit CLP-INTERCONNECTION-REBUTTAL.pdfRead the text of Exhibit CLP-INTERCONNECTION-REBUTTAL.pdf
Page 15 of 25
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-INTERCONNECTION-REBUTTAL-1 November 18, 2026 Page 13 of 23 B. 1 2 PURA Should Not Require Binding Cost Estimates and Construction Timelines. 3 4 Q. Do you agree with ICC’s recommendation to require binding timelines and costs 12 to be provided? 5 A. The Company reiterates that the rate case is not the appropriate forum for this 6 discussion, but, no, we do not agree. The Company always provides a good faith 7 estimate of the anticipated interconnection costs associated with a project. However, 8 the Company cannot provide “binding” cost estimates because cost estimates can 9 fluctuate for a variety of reasons, including those outside the Company’s control, such 10 as supply chain issues and customer delays. 11 A similar proposal to prevent the EDCs from issuing supplemental costs to developers 12 was considered and not approved by PURA in Docket No. 25-01-27. Docket No. 25- 13 01-27 Final Decision at 19 (2025). PURA held that the proposal to cap cost increases 14 was not in the public interest because it would “increase costs for ratepayers by shifting 15 additional interconnection expenses . . . from project developers to ratepayers.” 16 Moreover, PURA recognized some interconnection upgrade cost increases are outside 17 the Company’s control. Id. 18 The Company reiterates that this rate case is not the appropriate forum for these issues; 19 however, it disagrees with ICC's recommendation. ICC cites examples in which 20 preliminary estimates communicated by the Company differed from subsequent study 12 See ICC-Verogy at 19; ICC-Greenskies at 13Page 16 of 25
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-INTERCONNECTION-REBUTTAL-1 November 18, 2026 Page 14 of 23 1 results and characterizes those differences as evidence that the Company's estimates 2 lack durability. 13 The Company disagrees with that characterization. 3 Developers frequently seek planning-level cost information before completing the 4 applicable engineering study so they can evaluate project viability, development risk, 5 and potential interconnection constraints while engineering work remains ongoing. 6 Such information serves a different purpose than a completed engineering study. 7 Preliminary information is intended to provide an understanding of the potential 8 magnitude of interconnection costs and system modifications based on the information 9 available at that stage of the engineering review, whereas the completed study provides 10 the engineering analysis and cost estimate on which interconnection decisions are 11 ultimately based. 12 Consistent with its commitment to supporting successful interconnections, the 13 Company routinely works with customers throughout the study process to provide 14 available information regarding potential system impacts, anticipated modifications, 15 and preliminary cost expectations before all engineering activities are complete. 16 Providing such information allows developers to evaluate project viability and make 17 informed business decisions while studies remain in progress. However, the Company's 18 willingness to provide preliminary information for planning purposes should not be 13 See ICC-Earthlight at 9-12.Page 17 of 25
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-INTERCONNECTION-REBUTTAL-1 November 18, 2026 Page 15 of 23 1 construed as a representation that such information constitutes a final engineering 2 determination or binding cost estimate. 3 Consistent with Section 8.0 of the Impact Study Agreement, the Company provides a 4 non-binding good faith estimate of cost responsibility and time to construct the 5 facilities required to accommodate an interconnection request. While a System Impact 6 Study identifies the system modifications required to accommodate an interconnection 7 request, detailed engineering, equipment specification, and construction planning are 8 generally completed later in the process. As a result, these estimates are intended to 9 provide a reasonable projection of expected costs based on the information available at 10 the time but are often refined as project development progresses and additional 11 information becomes available. The interconnection process also provides customers 12 the option to obtain a Facility Study, through which additional engineering is performed 13 and project scope and cost estimates may be further refined. Neither the Impact Study 14 Agreement nor the Facility Study Agreement characterizes these estimates as binding. 15 The fact that a preliminary estimate differs from a subsequent completed study result 16 does not demonstrate that the preliminary estimate lacked value or that the 17 interconnection process was deficient. Rather, it reflects the inherent distinction 18 between planning-level information developed during an ongoing study process and 19 the completed engineering analysis that forms the basis of the final study results. 20 Preliminary estimates and completed study results serve different purposes, and 21 differences between the two are completely reasonable and explainable.Page 18 of 25
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-INTERCONNECTION-REBUTTAL-1 November 18, 2026 Page 16 of 23 1 The Feasibility Study is intended to provide developers early visibility into potentially 2 significant system upgrades preliminarily identified through the interconnection review 3 process. Such upgrades may include major distribution or substation modifications that 4 the developer did not previously anticipate. The study provides a high-level assessment 5 of anticipated upgrade requirements and associated costs based upon the information 6 available at the time the study is performed. Because those upgrades have not yet 7 undergone detailed engineering review, internal project development, procurement 8 review, and other technical evaluation, the identified facilities and associated cost 9 estimates remain preliminary, non-binding, and subject to refinement as additional 10 engineering and analysis are completed. 11 More broadly, ICC's testimony relies heavily on a limited number of project-specific 12 examples to support broad changes to the interconnection framework, including 13 binding cost estimates, binding construction timelines, and revisions to existing 14 interconnection procedures. The Company does not believe those examples support the 15 conclusions advanced by ICC. Interconnection projects involve unique engineering, 16 construction, procurement, scheduling, permitting, and customer-development 17 circumstances that must be evaluated based upon the specific facts associated with each 18 project. Accordingly, project-specific outcomes should not be generalized into 19 conclusions regarding the overall effectiveness of the Company's interconnection 20 process or the need for broad regulatory changes.Page 19 of 25
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-INTERCONNECTION-REBUTTAL-1 November 18, 2026 Page 17 of 23 1 Many of the policy issues raised by ICC, including interconnection cost responsibility, 2 dispute resolution, process improvements, and project timelines, have already been 3 considered through prior PURA proceedings, stakeholder working groups, complaint 4 processes, and revisions to the Interconnection Guidelines. The Company believes 5 those forums remain the appropriate venue for consideration of interconnection policy 6 issues rather than this rate proceeding. 7 Q. Can the Company provide more firm construction timelines? 8 A. For similar reasons articulated above, the Company cannot provide binding 9 construction timelines. Many factors outside the Company’s control would make 10 binding, firm construction timelines prohibitive. For example, supply chain delays, 11 weather, scheduling constraints, and other factors may all affect construction timelines. 12 Moreover, while the Company strives to efficiently interconnect DG, the Company’s 13 first priority is ensuring the interconnecting facility does not jeopardize the safe, 14 reliable operation of the EPS for all customers. 15 Recently, PURA established new permission to operate (“PTO”) timeline requirements 16 for the EDCs. Docket No. 25-01-27 Final Decision at 30. PURA directed the EDCs to 17 issue PTO within 20 business days of Authority Having Jurisdiction (“AHJ”) approval 18 for all residential projects under 50 kW, and within 30 business days for all Level 2 19 projects, provided that all developer requirements have been satisfied and none of the 20 seven operational exceptions apply. Id.Page 20 of 25
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-INTERCONNECTION-REBUTTAL-1 November 18, 2026 Page 18 of 23 1 2 Q. Do you agree with ICC’s claims 14 that Eversource frequently oversteps AHJ causing unnecessary delays? 3 A. We do not. First, as stated above, the Company’s rate case is not the appropriate forum 4 for the interconnection concerns raised. Second, ICC Earthlight’s claim that the 5 Company oversteps AHJ and refuses NEC-compliant design options was already raised 6 and denied by PURA. Docket No. 25-01-27 Final Decision at 34-35 (2025). PURA 7 concluded that “EDC oversight and inspection of certain interconnection components 8 beyond the transformer remain necessary” and noted municipal inspectors may lack the 9 technical expertise required to assess an interconnection. Id. Additionally, in 10 compliance with PURA’s Final Decision, the Company has incorporated jurisdiction 11 examples into the DER Specific Metering Supplement to the Eversource Information 12 and Requirements Book 2024. 15 13 Q. Do you agree developers should be permitted to self-help? 16 14 A. No, we do not. Verogy cites the telecommunications space as an example where self- 15 help is permitted; however, the telecommunications sector is not an appropriate 16 comparison. Self-help is only permitted in the communications gain, not the electric 17 gain. The Company’s first and foremost responsibility is to maintain the safe, reliable 18 operation of the EPS. To reduce the risk of service impacts to all customers supplied 14 15 16 ICC-Earthlight at 18. See Docket No. 25-01-27, CL&P Supplement to Motion No. 17 (Jan. 23, 2026). ICC-Verogy at 20; ICC-Greenskies at 13.Page 21 of 25
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-INTERCONNECTION-REBUTTAL-1 November 18, 2026 Page 19 of 23 1 by the EPS, the Company must maintain strict control over certain construction 2 elements associated with interconnection that can impact distribution operations. 3 The electric utility distribution system is a highly complex and integrated network, 4 requiring specialized expertise and strict adherence to established safety, reliability, 5 and operational control protocols. Not all contractors possess the necessary training, 6 equipment, or authorization to perform work on these critical facilities, and permitting 7 customers to independently select such personnel could compromise system safety and 8 reliability. Eversource’s interconnection practices are specifically designed to ensure 9 proper oversight and control, safeguarding workers, customers, the public, and the 10 overall integrity of the electric grid. 11 Q. Do you agree with the recommendation to require pre-applications? 12 A. No, we do not. The pre-application review does not offer any additional information 13 that is not already accessible through the Hosting Capacity Map and Grid Twin tools. 14 Eversource has previously argued before PURA that these tools should serve as the 15 primary source of such information, allowing developers to obtain it on a self-service 16 basis without paying for a separate review. 17 Q. Do you agree with the recommendation to improve hosting capacity maps? 18 A. First, the Company reiterates this recommendation is not appropriate for the 19 Company’s rate case proceeding. Second, the Company does not agree that further 20 hosting capacity improvements are needed. The Company recently implementedPage 22 of 25
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-INTERCONNECTION-REBUTTAL-1 November 18, 2026 Page 20 of 23 1 hosting capacity map improvements with additional data points and automation. 17 In 2 Docket No. 25-01-27, PURA rejected a hosting capacity map upgrade proposal, 3 referring to this recent improvement project and stating that it is prudent to first assess 4 the impact of this project before approving any efforts that may be redundant. Docket 5 No. 25-01-27 Final Decision at 21 (2025). This assessment has not yet occurred. In 6 addition, PURA suggested that once these improvements have been implemented, the 7 Interconnection Working Group could submit a new, consensus proposal for PURA’s 8 consideration in Docket No. 25-01-27. See id. 9 Further, the Company notes the hosting capacity values presented in the hosting 10 capacity maps are dynamic and change as the interconnection queue and real-time 11 conditions evolve. The hosting capacity maps are a snapshot in time of the hosting 12 capacity available at the time of review based on a level analysis that is not as detailed 13 or definitive as a system impact study. The hosting capacity map is a useful 14 informational tool but does not represent a guarantee the hosting capacity remains 15 available. 16 17 18 17 See Docket No. 24-08-06, Eversource Compliance with Order 18 (May 6, 2026).Page 23 of 25
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-INTERCONNECTION-REBUTTAL-1 November 18, 2026 Page 21 of 23 C. 1 Dispute Resolution Already Exists 2 3 Q. Do you agree with ICC’s recommendation for PURA to create a “binding” dispute resolution process 18? 4 A. No, we do not. There is already a dispute resolution process in place. As recently as 5 August of 2025, PURA reviewed and rejected a proposal to revise the dispute 6 resolution process to be more structured prior to escalation to PURA. PURA found a 7 dispute resolution process has already been established through Docket No. 17-12- 8 03RE06 and incorporated into the Interconnection Guidelines. Docket No. 25-01-27 9 Final Decision at 27 (2025). Moreover, if a dispute is not resolved through discussion 10 between EDCs and developers or to PURA EOE in its role as the Ombudsperson, the 11 dispute may be elevated for formal adjudication before PURA. 12 Subsequent to the filing of the Company’s rate case application, two members of the 13 ICC each requested mediation of dispute with PURA EOE. 19 Verogy requested 14 mediation of a dispute involving the Groton Landfill project described in their pre-filed 15 testimony. 20 Earthlight requested mediation of a dispute involving the issues of 16 contingent approval, cost causation, and line-side taps described in their pre-filed 17 testimony. 21 18 testimony, and Eversource continues to participate in these mediations in good faith, 19 which in one instance includes the consideration of potential changes to the Company’s These mediations are still ongoing as of the date of this pre-filed See ICC-Greenskies at 13; ICC-Earthlight at 30; ICC-Verogy at 19 Additionally, on November 17, 2026, the Company received a notice of dispute from an ICC member; however, at this time, the Company has not reviewed the contents of the notice. 20 ICC-Verogy at 13. 21 ICC-Earthlight at 7-9 & 13-14 18 19Page 24 of 25
The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-INTERCONNECTION-REBUTTAL-1 November 18, 2026 Page 22 of 23 1 processes to avoid similar disputes in the future. Prior to these two disputes, for which 2 mediation is still ongoing, PURA EOE has not mediated any dispute between 3 Eversource and any ICC member. None of the other complaints described in ICC 4 member pre-filed testimony has been mediated by PURA EOE. At this point, the 5 Company does not believe a new dispute resolution process is merited. 6 Q. Is ICC’s proposed recommendation appropriate for this proceeding? 7 A. No, it is not. The dispute resolution process would need to be revised statewide, and all 8 interested stakeholders would need to be involved in those discussions. In addition, 9 “binding” dispute resolution would not be appropriate for all disputes, such as disputes 10 that implicate the safe, reliable operation of the EPS. PURA would therefore need to 11 determine which disputes are appropriate for a binding resolution process and which 12 disputes are not. Also, if engineering support for developers is part of any dispute 13 resolution process, PURA will need to determine how such support is to be funded. 14 D. Alleged Staffing Issues 15 16 17 Q. Do you agree with ICC’s claim Eversource is understaffed in the Distributed Generation Customer Care department and should be directed to hire additional staff? 22 18 A. No. The Company routinely evaluates staffing and resource needs and makes the 19 adjustments needed to meet interconnection process requirements and timelines within 20 its control. 22 See ICC-Greenskies at 12
As listed on the current system
Prefiled testimony: 11/18/2026 - Sponsor: TBD / Witness: WARREN R. BOUTIN AND LAVELLE A. FREEMAN [26-05-10]