  1. Page 5 of 25

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-INTERCONNECTION-REBUTTAL-1 November 18, 2026 Page 3 of 23 1 distributed energy resource (“DER”) interconnections; assessing system reliability and 2 resiliency performance and needs, and developing targeted plans for improvement; and 3 integrated energy planning to safely and reliably transition customers from the gas 4 system to the electric system. 5 Q. Please summarize your education and professional experience. 6 A. I earned a Bachelor of Science degree in Electrical Engineering from the University of 7 Alabama. Subsequently, I earned a Master of Science degree in Electrical Engineering 8 with a concentration in Power Systems from the University of North Carolina at 9 Charlotte and a Master of Science degree in Computer Engineering from North 10 Carolina State University. I joined the IEEE Power Engineering Society while in 11 graduate school and have been on the ANSI C84.1 Standard Committee. 12 I started my power systems career in 1997 as an R&D Engineer at ABB Corporate 13 Research in Raleigh, NC, where I devised innovative new products, algorithms and 14 solutions to improve the value and efficiency of transmission and distribution product 15 offerings within ABB Power T&D Inc. In 1999, I became a Senior Consulting 16 Engineer in the ABB Utility Consulting group in Raleigh, NC, where I performed 17 system studies in distribution and transmission planning for utility customers, worked 18 with customers to implement changes, and developed and supported power systems 19 software applications that improved the efficiency, marketability and cost- 20 effectiveness of the group.
  2. Page 6 of 25

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-INTERCONNECTION-REBUTTAL-1 November 18, 2026 Page 4 of 23 1 From 2003 to 2013, I was a Senior Engineer and then a Principal Engineer at General 2 Electric Energy in Schenectady, NY, where I led consulting studies in distribution 3 planning and analysis, power systems engineering, equipment applications, smart grid 4 initiatives, and renewables impact and contributed to the development of new products 5 and technology for various General Electric Energy businesses. From 2013 to 2016, I 6 was Manager of Transmission and Distribution at General Electric Energy Consulting, 7 where I directed a broad spectrum of client activities in the T&D space, with emphasis 8 on power systems operation and planning, equipment application, renewables impact, 9 and systems analysis. From 2016 through 2020, I was Technical Director at General 10 Electric Energy Consulting in Schenectady, New York. In this position, I led project 11 teams and developed business opportunities in the distribution space with emphasis on 12 DER integration, microgrid design, grid modernization, reliability, power quality and 13 resiliency. I developed and led execution of over $5M in distribution-related projects 14 in New York, New Jersey and Massachusetts. I also successfully completed four 15 ground-breaking New York Prize Stage 2 microgrid design projects and managed the 16 Distribution System Testing and Research (DSTAR) consortium, working extensively 17 with distribution planners and engineers in investor-owned, municipal and cooperative 18 utilities across the country. 19 Distribution System Planning. In 2024, I was appointed to my current position. In 2020, I joined Eversource Energy as Director, 20 Q. Have you previously testified before PURA or elsewhere on regulatory matters? 21 A. Yes. I have previously testified and participated in several proceedings before the 22 Connecticut Public Utilities Regulatory Authority (“PURA”), including: Docket No.
  3. Page 7 of 25

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-INTERCONNECTION-REBUTTAL-1 November 18, 2026 Page 5 of 23 1 17-12-03RE08, PURA Investigation Into Distribution System Planning of the Electric 2 Distribution Companies – Resilience and Reliability Standards, Docket No. 17-12- 3 03RE07, PURA Investigation into Distribution System Planning of the Electric 4 Distribution Companies – Non-Wires Alternatives, Docket No. 21-05-15RE02, PURA 5 Investigation Into Performance-Based Regulation Framework, Docket No. 21-05- 6 RE03, PURA Investigation Into the Establishment Of Integrated Distribution System 7 Planning Within a Performance-Based Regulation Framework, Docket No. 22-06- 8 29RE01, PURA Investigation Into Distributed Energy Resource Interconnection Cost 9 Allocation – Non-Residential Interconnection Upgrades, and Docket No. 22-06-05 10 PURA Implementation of Public Act 22-55. I have also testified before the 11 Massachusetts Department of Public Utilities numerous times and before the New 12 Hampshire Public Utilities Commission. 13 Q. Did you previously sponsor testimony in this proceeding? 14 A. Yes, I sponsored testimony in Exhibit CLP-TSP-1 and supporting exhibits. 15 II. PURPOSE OF TESTIMONY 16 Q. What is the purpose of your testimony? 17 A. The purpose of our testimony is to respond to the testimony of the Interconnection 18 Customer Coalition (“ICC”), which critiques the Company’s interconnection process 19 for distributed generation (“DG”) facilities and provides several recommendations to 20 PURA, which are addressed in turn below.
  4. Page 8 of 25

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-INTERCONNECTION-REBUTTAL-1 November 18, 2026 Page 6 of 23 1 Q. Are you presenting any exhibits as part of your rebuttal testimony? 2 A. No. 3 Q. How is your testimony organized? 4 A. Our testimony is organized into the following sections: 5 • Section I is the introduction; 6 • Section II provides the purpose of our testimony and overview; 7 • Section III provides an overview of DG Interconnection process; 8 • Section IV provides our response to ICC; and 9 • Section V provides our conclusion. 10 11 III. DG INTERCONNECTION OVERVIEW A. 12 Background on Company’s Interconnection Process 13 Q. What documents govern the interconnection process for Eversource? 14 A. There are three primary documents which govern the interconnection process in the 15 State of Connecticut: (1) Guidelines for the Interconnection of Residential Single Phase 16 Certified Inverter-Based Generating Facilities of 50 kW (AC) or Less; (2) Guidelines 17 for Generator Interconnection Excluding Residential Inverter Based Projects Level 1 18 50 kW or Less; and (3) Exhibit B Generator Interconnection Technical Requirements. 1 19 The applicability of these documents is dependent on the size of the interconnecting 20 project. 1 See Company’s response to ICC-002, ICC Attachments 1, 2, and 3.
  5. Page 9 of 25

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-INTERCONNECTION-REBUTTAL-1 November 18, 2026 Page 7 of 23 1 Q. How were these documents developed? 2 A. The Company and United Illuminating Company (“UI”) developed these documents together with stakeholder input through working groups. 2 3 4 Q. Were these documents reviewed and approved by PURA? 5 A. Yes. The Guidelines, including the Interconnection Agreement, were initially reviewed 6 and approved in 2004 in Docket No. 03-01-15. Order No. 2 of the Docket No. 03-01- 7 15 Decision required the Company to submit clean and redline versions of the 8 Guidelines to PURA, along with an explanation of the changes, within ten days 9 following the effective date of any revision to the Guidelines. On July 10, 2007, in 10 compliance with Order No. 2 of the Docket No. 03-01-15 Decision, the Company and 11 UI submitted proposed revisions to the Guidelines, including revisions to the form of 12 Interconnection Agreement, as compliance in Docket No. 03-01-15. 13 Q. Were these documents more recently reviewed by PURA? 14 A. Yes, these documents were filed in clean and redlined form with PURA most recently 15 in Docket Nos. 17-12-03RE06, 22-06-29, 22-06-29RE01, 24-08-05, 25-01-27, and 25- 16 08-05. 3 17 18 2 3 Company’s response to ICC-003. Company’s response to ICC-002.
  6. Page 10 of 25

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-INTERCONNECTION-REBUTTAL-1 November 18, 2026 Page 8 of 23 1 Q. At a high level, please explain the Company’s interconnection process. 2 A. For Level 2 projects, the Fast Track Process is available for certified generating 3 facilities up to 2 MW that meet Connecticut's eligibility criteria and pass the applicable 4 technical screens. Projects that pass Fast Track generally receive an Interconnection 5 Agreement within approximately 15 business days of a complete application, with an 6 optional site visit available to refine service upgrade cost estimates. 7 Projects that do not qualify for Fast Track, as well as projects larger than 2 MW, 8 proceed through the study process. Eversource generally issues the applicable study 9 agreement within 15 business days of receiving a complete application. The study 10 process evaluates system impacts and identifies any required upgrades. Depending on 11 project complexity, studies typically take 30 to 60 business days to complete. Projects 12 greater than 1 MW may also require ISO-NE, transmission, or other regional studies 13 outside PURA's jurisdiction, which can extend the overall timeline. 14 IV. RESPONSE TO ICC 15 Q. Please provide a high-level summary of the ICC’s testimonies. 16 A. ICC submitted three separate testimonies by Verogy Holdings (“Verogy”), Earthlight 17 Technologies (“Earthlight”), and Greenskies Clean Energy (“Greenskies”) 18 (collectively, “ICC”). At a high level, each of the testimonies claims the Company’s 19 interconnection process has unnecessary delays and requirements that result in 20 customer frustration, additional cost, and, at times, projects withdrawing from the
  7. Page 11 of 25

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-INTERCONNECTION-REBUTTAL-1 November 18, 2026 Page 9 of 23 1 interconnection queue. 4 ICC provides several recommendations for resolving these 2 alleged issues. 3 The Company notes that ICC members have raised individualized claims and concerns 4 relating to the circumstances, development, and treatment of their respective projects. 5 These individualized complaints and grievances are beyond the scope of this 6 proceeding and should not be addressed in the context of this rate case. This proceeding 7 is intended to address the Company’s proposed rates and related matters of general 8 applicability, not to serve as a forum for adjudicating project-specific disputes or 9 resolving individual developers’ grievances regarding the circumstances of their 10 respective projects. To the extent that any developer believes it has a legitimate project- 11 specific concern or grievance, that concern should be raised and addressed separately 12 through the appropriate resolution process. Depending on the nature of the issue, that 13 may include the applicable dispute resolution process, where the particular facts and 14 circumstances relevant to that project can be properly considered, or to the extent the 15 issues warrant broader consideration, a separate docket dedicated to addressing such 16 matters. 17 Q. Please summarize ICC’s recommendations. 18 A. ICC recommends PURA: 19 20 • 4 require interconnection rules be standardized with stakeholder input and PURA review and approval; ICC-Veogy at 6-7; ICC-Earthlight at 7, 14; ICC-Greenskies at 6, 10-11
  8. Page 12 of 25

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-INTERCONNECTION-REBUTTAL-1 November 18, 2026 Page 10 of 23 1 2 • require Eversource to provide accurate cost estimates and construction timelines; 3 • require Eversource to allow self-help; 4 • require pre-application process and improved hosting capacity maps; 5 • make dispute resolution binding; 6 7 • require Eversource to hire more full-time equivalents in the interconnection group; and 8 • impose incentives and penalties for missing deadlines. 5 9 10 11 Q. Is the Company’s rate case the appropriate venue for ICC’s critiques or recommendations related to DG interconnection? 12 A. No, it is not. As noted above, despite ICC’s claims to the contrary, the critiques and 13 recommendations outlined by ICC are statewide issues that would need to be addressed 14 in a more appropriate forum with all interested stakeholders involved, including UI and 15 other developers. 6 16 17 A. PURA Should Not Standardize Interconnection Rules or Documents in this Proceeding. 18 19 Q. Do you agree with ICC’s recommendation to “standardize” interconnection rules? 7 20 A. The interconnection rules, through the Guidelines outlined above, are already 21 standardized. Any recommended changes to the already standardized interconnection 22 rules should be through another proceeding with all interested parties having an 5 6 7 ICC-Earthlight at 30-31; ICC-Verogy at 21; ICC-Greenskies at 12-13. The Company is not replying herein to each and every issue or point raised by ICC. The Company’s silence on any point made or issue raised should not be construed as support for ICC’s perspective on that issue. See ICC-Earthlight at 31; ICC-Verogy at 19
  9. Page 13 of 25

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-INTERCONNECTION-REBUTTAL-1 November 18, 2026 Page 11 of 23 1 opportunity to participate. The Company’s rate case, which makes no proposals related 2 to Level 2 DG interconnection standards, is not the appropriate forum. 3 4 Q. Are there other more appropriate forums for discussing changes to interconnection? 5 A. Yes, there are other more appropriate forums. First, the Interconnection Working Group 6 (“Working Group”) is specifically focused on accelerating and improving DG 7 interconnection in Connecticut. Since early 2021, the Working Group has been meeting 8 almost every month to discuss various topics related to interconnection and includes 9 appropriate solar industry stakeholders. 8 In addition, per the governing framework on 10 the Working Group, solar developers constitute two of the six voting members of this 11 group. 12 Additionally, there are other active proceedings before PURA involving DG 13 interconnection that are more appropriate for this discussion. 14 Q. Have there been recent proceedings concerning interconnection issues? 15 A. Yes. There have been recent proceedings involving interconnection-related issues. In 16 Docket No. 17-12-03RE06, the 100-Day Sprint Working Group Report included 17 consensus interconnection recommendations that PURA adopted, and through Docket 18 No. 25-01-27, the Company is implementing those recommendations. Indeed, many of 19 the topics for which the ICC provided recommendations were addressed in PURA’s The Company notes that Verogy, Earthlight, and Greenskies recently participated in the Working Group, as well as stakeholders like Michaud Law Group, Honeywell, and Conn Solar. 8
  10. Page 14 of 25

    The Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-INTERCONNECTION-REBUTTAL-1 November 18, 2026 Page 12 of 23 1 recent decisions issued in 2025 in that docket. For example, ICC recommends a “chess 2 clock” functionality to PowerClerk, but this has already been adopted in Docket No. 3 25-01-27 Final Decision at 7 (Aug. 20, 2025) and implemented by the Company. 9 4 The topics raised by the ICC are more appropriate to be resolved in a reopened Docket 5 No. 25-01-27. In fact, in Docket No. 25-01-27, PURA declined to implement proposals 6 relating to some of the topics raised in ICC member testimony, such as changes to the 7 dispute resolution process. The Company does not oppose reopening Docket No. 25- 8 01-27 to reevaluate rejected proposals and/or evaluate additional proposals, if PURA 9 would like to explore these proposals further. 10 11 Q. ICC claims it is unclear if PURA has recently reviewed the Interconnection Guidelines. 10 Has PURA recently reviewed the Guidelines? 12 A. Yes. As noted above, PURA directed several revisions and updates to the Guidelines in 13 Docket No. 25-01-27. As part of Eversource’s compliance with Order No. 1 of that 14 Final Decision, the Company filed revised Guidelines on November 14, 2025. 11 Any 15 updates to the Guidelines would need to be performed jointly with United Illuminating 16 and be submitted to PURA for review and approval. 17 substantive revisions to the Guidelines by itself and without PURA’s authorization. Eversource cannot make 18 9 10 11 See Docket No. 25-01-27, Eversource responses to CAE-107 and CAE-107SP01. ICC-Verogy at 5. See Docket No. 25-01-27, Eversource Motion for Approval, Attachments 2a & 2b (Nov. 14, 2025).

As listed on the current system

Prefiled testimony: 11/18/2026 - Sponsor: TBD / Witness: WARREN R. BOUTIN AND LAVELLE A. FREEMAN [26-05-10]

This filing on the current system (opens in a new tab)