  1. Page 1 of 17

    APS 1 - Project Authorization Policy Supplement Request Form Supplement Request Form Approved at March 04, 2020 EPAC Link to Meeting Minutes Date Prepared: 2/18/2020 Company/Companies: Eversource CT Organization: Asset Management Project Initiator: Project Manager: Project Sponsor: Current Authorized Amount: $599K Supplement Request: $1,832K Total Request: $2,431K Project Title: 14K CBA Project ID Number: CS00187 Plant Class/(F.P. Type): Distribution Substation Project Type: Specific Capital Investment Part of Original Operating Plan? Yes O&M Expenses Part of the Original Operating Plan? No Estimated in service date(s): 5/31/2020 Other: Supplement Justification Summary The has a current authorized budget of $599K that was approved in PowerPlan on 9/6/2017. The project is not complete and has an estimated in service date of 5/31/2020. The remaining work to complete is the lock out relay installation detailed on drawing transmittal 12123. This supplement requests and additional $1,832K for an updated total request of $2,431K for the reasons discussed below. Scope The scope of work in the Issued For Construction (IFC) drawings was much larger than the original scope. There were wiring issues with the existing panels compared to the IFC drawings that forced extensive contractor effort to reconcile before work could proceed. There were also constructability issues that required the lock out scheme to be re-designed and delayed the project completion. Page 1 of 5 Issued 10/27/17 Rev. 5
  2. Page 2 of 17

    APS 1 - Project Authorization Policy Supplement Request Form Justification for Additional Resources A Decision Making Estimate (DME) could not be located for the previous authorization for this project. The IFC drawings included The reasons for the increased budget are described below. The 14K5-2 recloser replacement added $120K to the project. This replacement is complete. added $64K to the project. A This added $284K to the project. This portion of the project is complete. has cost approximately $168K to oversee the contract test group and support protection implementation for this project. were issued on 6/20/2019 under drawing transmittal number 12123 Contractor estimates for this additional installation are $140K for testing and $82K for electrical installation. This will also result in additional six (6) weeks of charges for an LCE during the performance of this work. Page 2 of 5 Issued 10/27/17 Rev. 5
  3. Page 3 of 17

    APS 1 - Project Authorization Policy Supplement Request Form Engineering - $64K Engineering costs were higher due to increased scope of adding the six (6) 23kV circuit breaker automation, 14K5-2 recloser replacement, DSCADA installation, and replacing an oil filled recloser and issues discovered during construction as noted above. 1. Labor - ($21K) Labor costs were lower due to the use of contract resources versus in house resources. 2. Materials - $31K Material costs were higher due to the scope increase requiring more materials, including a vacuum recloser and control, extra wiring to connect the 23kV circuit breakers, an additional relay for communications, as well as wire and miscellaneous hardware. 3. Outside Services - $858K Outside services were higher due to increased scope and using contract labor for installation and testing related work, which was originally budgeted for in house resources. 4. Indirects - $675K Indirect costs were higher due to increased scope, project delays and a change in the rate during 2018. 5. AFUDC - $225K AFUDC costs were higher due to the increased project scope, project delays and higher direct spending. The estimated in service date was extended from 12/31/2017 to 5/31/2020. Page 3 of 5 Issued 10/27/17 Rev. 5
  4. Page 4 of 17

    No text on this page. It may be a picture of a page, such as a scan or a chart.
  5. Page 5 of 17

    APS 1 - Project Authorization Policy Supplement Request Form Note: Dollar values are in thousands: Total Supplement Request by year view: Capital Additions Direct 2016 $38 2017 -$246 2018 $553 2019 $123 2020+ $227 Total $695 $0 $0 $0 $0 $0 $0 Less Customer Contribution Removals Net of Salvage 17.7% Total Direct Spending $8 $34 $119 $27 $49 $237 $46 -$212 $672 $150 $276 $932 Capital Additions - Indirect $16 -$66 $523 $76 $126 $675 AFUDC $0 $4 $57 $99 $65 $225 Subtotal Request $62 -$274 $1,252 $325 $467 $1,832 O&M $0 $0 $0 $0 $0 $0 Total Request $62 -$274 $1,252 $325 $467 $1,832 Page 5 of 5 Issued 10/27/17 Rev. 5
  6. Page 6 of 17

    Superseded Project Authorizations and Estimates
  7. Page 7 of 17

    No text on this page. It may be a picture of a page, such as a scan or a chart.
  8. Page 8 of 17

    No text on this page. It may be a picture of a page, such as a scan or a chart.
  9. Page 9 of 17

    No text on this page. It may be a picture of a page, such as a scan or a chart.
  10. Page 10 of 17

    Project Authorization Policy Operations Project Authorization Financial Evaluation Direct Capital Costs 2017 2018 2019+ Total Straight Time Labor 57 0 0 $57 Overtime Labor 0 0 0 $0 Outside Services 210 0 0 $210 Materials 60 0 0 $60 Other, including contingency amounts 39 0 0 $39 $366 $0 $0 $366 Total Indirect Capital Costs 2017 2018 2019+ Total Indirects/Overheads (including benefits) 117 0 0 $117 Capitalized interest or AFUDC, if any 4 0 0 $4 $121 $0 $0 $121 $487 $0 $0 $487 0 0 0 $0 Total Capital Project Costs $487 $0 $0 $487 Total O&M Project Costs $0 $0 $0 $0 Total Total Capital Costs Less Total Customer Contribution 2 03/19/2020
1 page match
No matches
Words on different pages

Text of 4-IT17426 Approval_redacted.pdf

Extracted from the file · 1 page · 2,265 characters

Text of 4-CTARAIT APPROVAL 1_redacted.pdf

Extracted from the file · 1 page · 1,013 characters

Scanned pages of 5-CD01192 Approval_Redacted.pdf

Read by machine from a scan · 1 page · may contain errors, especially in numbers

Scanned pages of 5-IT17426 Approval_redacted.pdf

Read by machine from a scan · 1 page · may contain errors, especially in numbers