Application supplement

Exhibit CLP-Additions-6 Folder 1 - 7 of 7

Files401

Search terms highlighted
Eversource rate increase is on 1 page of the text below, highlighted. Go to the first matchClear highlighting
Words on different pages
  1. Page 3 of 17

    APS 1 - Project Authorization Policy Supplement Request Form Engineering - $64K Engineering costs were higher due to increased scope of adding the six (6) 23kV circuit breaker automation, 14K5-2 recloser replacement, DSCADA installation, and replacing an oil filled recloser and issues discovered during construction as noted above. 1. Labor - ($21K) Labor costs were lower due to the use of contract resources versus in house resources. 2. Materials - $31K Material costs were higher due to the scope increase requiring more materials, including a vacuum recloser and control, extra wiring to connect the 23kV circuit breakers, an additional relay for communications, as well as wire and miscellaneous hardware. 3. Outside Services - $858K Outside services were higher due to increased scope and using contract labor for installation and testing related work, which was originally budgeted for in house resources. 4. Indirects - $675K Indirect costs were higher due to increased scope, project delays and a change in the rate during 2018. 5. AFUDC - $225K AFUDC costs were higher due to the increased project scope, project delays and higher direct spending. The estimated in service date was extended from 12/31/2017 to 5/31/2020. Page 3 of 5 Issued 10/27/17 Rev. 5
  2. Page 4 of 17

    No text on this page. It may be a picture of a page, such as a scan or a chart.
  3. Page 5 of 17

    APS 1 - Project Authorization Policy Supplement Request Form Note: Dollar values are in thousands: Total Supplement Request by year view: Capital Additions Direct 2016 $38 2017 -$246 2018 $553 2019 $123 2020+ $227 Total $695 $0 $0 $0 $0 $0 $0 Less Customer Contribution Removals Net of Salvage 17.7% Total Direct Spending $8 $34 $119 $27 $49 $237 $46 -$212 $672 $150 $276 $932 Capital Additions - Indirect $16 -$66 $523 $76 $126 $675 AFUDC $0 $4 $57 $99 $65 $225 Subtotal Request $62 -$274 $1,252 $325 $467 $1,832 O&M $0 $0 $0 $0 $0 $0 Total Request $62 -$274 $1,252 $325 $467 $1,832 Page 5 of 5 Issued 10/27/17 Rev. 5
  4. Page 6 of 17

    Superseded Project Authorizations and Estimates
  5. Page 7 of 17

    No text on this page. It may be a picture of a page, such as a scan or a chart.
  6. Page 8 of 17

    No text on this page. It may be a picture of a page, such as a scan or a chart.
  7. Page 9 of 17

    No text on this page. It may be a picture of a page, such as a scan or a chart.
  8. Page 10 of 17

    Project Authorization Policy Operations Project Authorization Financial Evaluation Direct Capital Costs 2017 2018 2019+ Total Straight Time Labor 57 0 0 $57 Overtime Labor 0 0 0 $0 Outside Services 210 0 0 $210 Materials 60 0 0 $60 Other, including contingency amounts 39 0 0 $39 $366 $0 $0 $366 Total Indirect Capital Costs 2017 2018 2019+ Total Indirects/Overheads (including benefits) 117 0 0 $117 Capitalized interest or AFUDC, if any 4 0 0 $4 $121 $0 $0 $121 $487 $0 $0 $487 0 0 0 $0 Total Capital Project Costs $487 $0 $0 $487 Total O&M Project Costs $0 $0 $0 $0 Total Total Capital Costs Less Total Customer Contribution 2 03/19/2020
  9. Page 11 of 17

    No text on this page. It may be a picture of a page, such as a scan or a chart.
  10. Page 12 of 17

    No text on this page. It may be a picture of a page, such as a scan or a chart.
1 page match
No matches
Words on different pages

Text of 4-IT17426 Approval_redacted.pdf

Extracted from the file · 1 page · 2,265 characters

Text of 4-CTARAIT APPROVAL 1_redacted.pdf

Extracted from the file · 1 page · 1,013 characters

Scanned pages of 5-CD01192 Approval_Redacted.pdf

Read by machine from a scan · 1 page · may contain errors, especially in numbers

Scanned pages of 5-IT17426 Approval_redacted.pdf

Read by machine from a scan · 1 page · may contain errors, especially in numbers

As listed on the current system

Supplement for New App [Filed: 09/25/2026]