Application supplement
Exhibit CLP-ADDITIONS-4 Supplemental 2
Files3
Docket No. 26-05-10 Exhibit CLP-Additions-6 Supplemental Filing October 19 2026.pdf
PDF · 157 KB · 2 pagesText searchable
Download Docket No. 26-05-10 Exhibit CLP-Additions-6 Supplemental Filing October 19 2026.pdfRead the text of Docket No. 26-05-10 Exhibit CLP-Additions-6 Supplemental Filing October 19 2026.pdf
Exhibit CLP-ADDITIONS-4 Supplemental 2.pdf
PDF · 2.1 MB · 77 pagesText searchable
Download Exhibit CLP-ADDITIONS-4 Supplemental 2.pdfRead the text of Exhibit CLP-ADDITIONS-4 Supplemental 2.pdf
Exhibit CLP-ADDITIONS-4 Supplemental 2.xlsx
Excel · 613 KBText searchable
Download Exhibit CLP-ADDITIONS-4 Supplemental 2.xlsxRead the text of Exhibit CLP-ADDITIONS-4 Supplemental 2.xlsx
Page 48 of 77
Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-ADDITIONS-4 Supplemental 2 Page 48 of 77 The Connecticut Light and Power Company d/b/a Eversource Energy Projected 2026 Capital Spend by Project (Whole Dollars) Project Number/Description by Category CD02214:30R8 WPC Reliability Improvement CD02215:35L9 WPC Reliability Improvement FRTDRP:FORECAST PROJECT FOR TDRP PROJS Reliability-ED Distribution Line Reliability RELIABILITY IMPROVE-DR ANNUAL DR1B:OH RELIAB IMPROVE NEWTOWN DR1N:OH RELIAB IMPROVE NORWALK DR1S:OH RELIAB IMPROVE STAMFORD DR2L:OH RELIAB IMPROVE TORR CLP DR2M:OH RELIAB IMPROVE CHESHIRE/N.B DR2W:OH RELIAB IMPROVE WATERBURY DR3H:OH RELIAB IMPROVE HARTFORD Projected 2026 Capital Spend Project Long Description Project CD02214 focuses on infrastructure replacement to improve the reliability of the 30R8 circuit.The 30R8 is a 23 kV circuit out of the Green Hill 30R S/S and serves 3,791 customers in the Killingworth, Madison, and Clinton areas of Connecticut. The 30R8 was ranked #3 on the worst performing circuits list in CT. CD02214 addresses four high impact zones on the 30R8 where Eversource has experienced outages within the past four years. This includes aging infrastructure replacement, upgrading conductor sizes to increase reliability and ampacity as well as extensive 532,929 vegetation trimming. Project CD02215 focuses on infrastructure replacement to improve the reliability of the 35L9 circuit.The 35L9 is a 13.8 kV circuit out of the Stepstone 35L S/S and serves 2,234 customers in Guilford, Connecticut. The 35L9 was ranked #9 on the worst performing circuits list in CT. CD02215 addresses two high impact zones on the 30R8 where Eversource has experienced outages within the past four years. This includes aging infrastructure replacement, upgrading conductor 324,095 sizes to increase reliability and ampacity as well as extensive vegetation trimming. 934,274 FORECAST PROJECTS FOR TDRP PROJECTS 190,264,011 24,000,000 10,000,000 1,366,897 OVERHEAD RELIABILITY IMPROVEMENT ANNUAL NEWTOWN 619,404 OVERHEAD RELIABILITY IMPROVEMENT ANNUAL NORWALK 943,089 OVERHEAD RELIABILITY IMPROVEMENT ANNUAL STAMFORD 1,300,962 OVERHEAD RELIABILITY IMPROVEMENT ANNUAL TORRINGTON 751,480 OVERHEAD RELIABILITY IMPROVEMENT ANNUAL CHESHIRE 569,647 OVERHEAD RELIABILITY IMPROVEMENT ANNUAL WATERBURY 751,480 OVERHEAD RELIABILITY IMPROVEMENT ANNUAL HARTFORDPage 49 of 77
Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-ADDITIONS-4 Supplemental 2 Page 49 of 77 The Connecticut Light and Power Company d/b/a Eversource Energy Projected 2026 Capital Spend by Project (Whole Dollars) Project Number/Description by Category DR4D:OH RELIAB IMPROVE MADISON DR4M:OH RELIAB IMPROVE E Hampton DR4N:OH RELIAB IMPROVE NEW LONDON DR5D:OH RELIAB IMPROVE DANIELSON DR5T:OH RELIAB IMPROVE TOLLAND DR5W:OH RELIAB IMPROVE Danielson FRDR:PROJECTION PROJECT DR ANNUAL RELIABILITY IMPROVE SPEC PROJ CD02116:Roxbury Rd Reconductoring Projected 2026 Project Long Description Capital Spend 410,233 OVERHEAD RELIABILITY IMPROVEMENT ANNUAL MADISON 360,038 OVERHEAD RELIABILITY IMPROVEMENT ANNUAL EAST HAMPTON 1,058,938 OVERHEAD RELIABILITY IMPROVEMENT ANNUAL NEW LONDON 360,929 OVERHEAD RELIABILITY IMPROVEMENT ANNUAL DANIELSON 707,275 OVERHEAD RELIABILITY IMPROVEMENT ANNUAL TOLLAND 808,644 OVERHEAD RELIABILITY IMPROVEMENT ANNUAL DANIELSON (9,015) PROJECTION PROJECT DR ANNUAL 12,500,000 CD02116 addresses reliability concerns and aging infrastructure for the 21K2 & 21K3 backbone on Roxbury Rd in Southbury. These circuits both originate at Bates Rock 21K substation and operate at 13.8kV. This segment of double circuit pole line consists of predominately 1970 vintage infrastructure and is responsible for hosting a combined 2250 customers. There have been 3 outages along this segment of the 21K2 and 6 outages on this segment of the 21K3. Additionally, this segment of the 21K3 experienced a burn down due to ringed spacer cable and a lightning strike. The proposed work suggests reconductoring on the 21K2 and 21K3. This work involves reconductoring the 21K2 with 6,800’ of 556 spacer cable from P#S43 to P# S3 and reconductoring the 21K3 with 7,000’ of aerial cable from P#S42 to P# C3798. In addition, the side tap originating at P# S22 will be swapped from the 21K3 to 21K2 circuit creating a complete express for the 21K3 from the station to P#12176. The reconductoring of these segments will increase future reliability and load growth through the replacement of aging infrastructure, existing ringed spacer cable and the installation of 2,690,800 upgraded overhead conductor.Page 50 of 77
Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-ADDITIONS-4 Supplemental 2 Page 50 of 77 The Connecticut Light and Power Company d/b/a Eversource Energy Projected 2026 Capital Spend by Project (Whole Dollars) Project Number/Description by Category CD02405:12C4 Equip Conversion and Replace CD02480:30R15-Reconductor 336 ringed SC wit CD02723:Town Scorecard – Eastern Region CD02749:UCONN Health Protection Coord FRSPRELI:FORECAST SPEC REL IMPROVEMENTS S/S ELIMINATION-LINE WORK Projected 2026 Capital Spend Project Long Description This project adresses deficiencies on the Enfield 12C4 circuit. Ringed spacer cable was found on N. River St., Whitworth St., and Alden Ave. The project replaces this cable prone to failure. To reduce several large customer zones on the 12C4 feeder, a 4.8kV portion of the circuit will be converted to 1,544,499 23kV to allow for recloser installation. The 336 AL spacer cable is vintage and is ringed. This area has very poor reliability and has had eleven (11) interruptions over the last four years. Removing the 336 AL ringed spacer cable and 57,750 installing 477 AL tree wire will improve the performance of this circuit. Project CD02723 was established to address the Town Scorecard Initiative which identifies the top 1,453,437 10 SADI and SAFI worst performing towns in Eversource, CT. Project CD02749 was established to address reliability concerns impacting operations at UConn Health in Farmington, CT. The affected infrastructure is served by the 1C01 overhead feeder, which supplies power to several critical facilities, including UConn Health Center, UConn Health Warehouse, UConn Fire Safety Complex, State of Connecticut Medical Examiner’s Office, Town of Farmington Sewer Pumping Station, and various hospital support buildings, such as parking areas 196,100 and the UConn Health Childcare Center. 6,557,414 FORECAST PROJECT FOR SPECIFIC RELIABILTY IMPROVEMENT PROJECTS 1,500,000Page 51 of 77
Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-ADDITIONS-4 Supplemental 2 Page 51 of 77 The Connecticut Light and Power Company d/b/a Eversource Energy Projected 2026 Capital Spend by Project (Whole Dollars) Project Number/Description by Category CD00654:Eliminate 4.8 kV 12F-6X Islanded SS FRSSLNWK:S/S Elim-Line Work Forecast Project Network Reliability NETWORK XFMR + PROTECTOR REPL Projected 2026 Capital Spend Project Long Description Hanover 12F-6X Substation is located in Meriden, Connecticut, and consists of a single, 5/6.25 MVA transformer that supplies three, 4.8 kV circuits (12F2, 12F4 and 12F5) and 1,793 customers.The 12F-6X transformer and 4.8 kV switchgear was installed in 1957. If the 5/6.25 MVA transformer were to fail, then 1,793 customers would be out of power for +/- 24 hours until a mobile transformer was installed. There are no other 4.8 kV sources in the area that can be used to restore customers.Hanover 12F-6X Substation and much of its associated overhead distribution system is 60+ years old.1,793 customers on 12F-6X will be converted and transferred to new 13.8 kV circuit 12F50 and existing 13.8 kV circuit 12F52. 700 feet of 1000 MCM Cu and 4,900 feet of 556 AL TW will be installed to create the 12F50 backbone. Twenty, single phase, bare copper laterals with six or fewer transformers will be reconductored with 1/0 ASCR TW and converted to 13.8 kV.New recloser loop schemes will be created to split the number of customers per zone to approximately 500. Three new recloser loop schemes on the 12F50 which will be backed up by the 12F44, 12F52 and 12F55. The three loops will employ multiple reclosers creating six zones to limit the customer count. The six zones will have 142, 226, 241, 477, 479 and 550 customers. A new field tie with the 12F49, and an existing tie with the 12F51, will back up the 453 customers in the first zone of the 12F50.The new feeder, 12F50, will take some load from the 12F55 to mitigate a contingency overload condition that exists on the 12F55.A large, 958 customer zone on the 12F52 will be eliminated by creating a new recloser loop with the 12F50. The resulting zones will have 456 and 502 customers.The replacement of the 12F2, 1000 kcmil AL get-a-way cable (500 feet) with 1000 1,185,600 Cu mitigates a contingency overload on the 12F52. 314,400 FORECAST PROJECTS FOR OVERHEAD WORK TO ELIMINATE SUBSTATIONS. 26,100,000 1,000,000Page 52 of 77
Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-ADDITIONS-4 Supplemental 2 Page 52 of 77 The Connecticut Light and Power Company d/b/a Eversource Energy Projected 2026 Capital Spend by Project (Whole Dollars) Project Number/Description by Category CD00412:CL&P Repl Net. Xfmrs Blanket UG CABLE & EQUIPMNT REPLACEMNT CD02229:145 PILC Cable Replacement CD02393:NW Hartford 2N18 PILC Cbl Repl FRUGCBLR:FORECAST PROJECT FOR NETWORK CBL RE UG Network Automation CD01276:New Switchgear for SMH Waterbury Projected 2026 Capital Spend Project Long Description This project is for replacement of inoperable/condemned/failed network transformers and network 1,000,000 transformer protectors. 14,187,500 Project CD02229 is being established to replace the remaining paper-insulated lead covered (PILC) cable on the South Meadow 145 circuit. This project is part of an overall strategy to address poor 6,400,000 performing PILC cable in the underground distribution system. Project CD02393 is being established to replace the 19,803’ of paper-insulated lead covered (PILC) cable on the Northwest Hartford 2N18 circuit. This project is part of an overall strategy to address 5,848,300 poor performing PILC cable in the underground distribution system 1,939,200 FORECAST BUDGET PROJ FOR NETWORK CABLE REPLACEMENTS 5,412,500 This project proposes installation of a set of 4-way solid dielectric switchgear on the line side of the existing feed to the existing switchgear at St Mary's Hospital 201B.The existing switchgear at St Mary's Hospital 201B is owned by the customer, but operated by Eversource, based on an agreement made years ago. This switchgear must be operated periodically, since both incoming feeders at St Mary's Hospital 201B are network feeders.Procedure NB-150 (in CT) discourages utility employees from operating customer-ownedhigh-voltage equipment. Because it does not own or maintain this equipment, the utility does not know its condition, nor can the utility be responsible for it. Installation of the new switchgear enables the utility to disconnect, test, and ground its system at switchgear it owns and maintains, without the need to access or operate non-utility-owned 2,289,300 equipment.Page 53 of 77
Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-ADDITIONS-4 Supplemental 2 Page 53 of 77 The Connecticut Light and Power Company d/b/a Eversource Energy Projected 2026 Capital Spend by Project (Whole Dollars) Project Number/Description by Category Projected 2026 Capital Spend Project Long Description CD01537:25 Laurel St Htfd - Automate Svc The primary electric service at 25 Laurel Street in Hartford consists of two manual PMH-5 switches (309B) which serve seven pad-mounted transformers (3,850 KVA Connected) and 607 customers (586 residential / 21 commercial). The manual switches are fed by two underground feeders (47N9 normal, 47N7 - alternate) out of Southwest Hartford 47N substation (23 KV).In the past five years, these customers have experienced three feeder outages averaging approximately 150 minutes/outage.This project proposes to automate the service to this location by replacing the manual switches with automatic switches.The expected benefits upon completion of this project 250,001 include improved reliability and customer satisfaction. CD02059:Man to Auto Tuttle Rd Middletown This project was established to address the manual switchgear at Tuttle Rd., Middletown. This project will replace one of the two existing PMH-9 switchgear units with a new DSCADA capable PME-9 switch, to be operated as a single unit auto-transfer switch. This proposal will automate 121 customers on Tuttle Rd., Middletown.The preferred feeder is the Westside 7A79 circuit and the alternate feeder is the Westside 7A71 circuit. The 7A71 has the capacity to accept the automatic transfer from the 7A79 without causing overload.This project is part of an overall program to eliminate manual switchgear in order to eliminate the need to manually transfer customers to their 224,699 alternative source for loss of the preferred source.Page 54 of 77
Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-ADDITIONS-4 Supplemental 2 Page 54 of 77 The Connecticut Light and Power Company d/b/a Eversource Energy Projected 2026 Capital Spend by Project (Whole Dollars) Project Number/Description by Category CD02092:Make 13H93 & 13H94 Non-Network CD02107:Switch Gear Autom 21P1 Kirkland Pl CD02543:Chelsea Piers Switchgear Isolation UNDERGROUND STRUCTURE ISSUE Projected 2026 Capital Spend Project Long Description This project is being established to convert the Noera 13H93 and 13H94 feeders into non-network feeders. This will allow the 13H93 and 13H94 feeders to have multi-grounded primary connections, such as automatic switchgear or line-to-ground connected load, without the exposure of high voltage that can happen if a network feeder were to fault and a network protector failed to open.The Palace Theater 225P and UCONN 256D switchgear are both automatic switchgear that have the Noera 13H94 circuit as the alternate source. Under a separate project, the preferred source to these switchgear locations will become a non-network feeder via transfer to the Freight 11W44 circuit.The scope of this project includes transferring the two existing network transformers on the N185 network from the 13H94 & 13H93 to the Freight 11W43 and 11W76 respectively. This will require extending the 11W76 to manhole 147 on E Main St., a distance of 1,320’. The total load on the N185 network is less than 300kVA. The 11W43 and 11W76 has the capacity to accept the added 402,800 load without causing overload. This project replaces a manual PMH 3 pair switch gear, located on Kirtland Place, Meriden, with an automatic PME 5 pair. PMH gear is live front while PME switch gear is dead front and is DSCADA capable offering both safety and operational flexibility.The switch gear is fed by the East Meriden 683,100 21P1 and the backup is the 21P4. 121 customers are fed from this switchgear. This project addresses single point failures on feeders (Glenbrook 1K08 & 1K18) feeding NBC. A splice failed on the overhead system on Maher Rd causing an outage at the NBC facility during the Olympics. On post event investigation, it was deemed necessary to eliminate single point failures by isolating customer owned switchgear feeding Chelsea Piers with Vista Green 422’s to avoid future 1,562,600 failures. 5,500,001Page 55 of 77
Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-ADDITIONS-4 Supplemental 2 Page 55 of 77 The Connecticut Light and Power Company d/b/a Eversource Energy Projected 2026 Capital Spend by Project (Whole Dollars) Project Number/Description by Category 101610:REPAIR & REPL OF CL&P UG STRUCTURES CD01821:Greenwich Ave Structural Upgrade Projected 2026 Capital Spend Project Long Description REPAIR & REPLACE MANHOLE AND VAULT (STRUCTURE) ROOFS AND DUCTLINE 1,201,100 DUE TO OBSOLESCENCE &/OR WEAR & TEAR. The Town of Greenwich is planning a streetscape project along Greenwich Avenue where they will reconstruct sidewalks and completely repave Greenwich Avenue from Putnam Avenue to Railroad Avenue. The Town has made it quite clear to all subsurface utility owners that all underground infrastructure must be installed or upgraded as necessary prior to their planned project. After careful review of Eversource’s existing infrastructure, it was determined that 2 manhole enlargements, 4 service box enlargements, and 5 lateral duct banks should be installed given the opportunity described above. The locations that were chosen for manhole enlargements are locations where there is insufficient room to properly splice and rack the three 27.6 kV feeders within the manhole, and to properly support the secondary mains and limited crab joints. The service box enlargements are required for potential service upgrades. The lateral duct bank extensions are required for two purposes. First, these ducts will accept additional or replacement secondary cable as required for network secondary voltage service. Second, each new duct bank will be extended to a side street where there is the potential to install a primary voltage loop cable that may eventually be used to 903,400 convert the existing network to load loops from the existing open wire overhead distribution system.Page 56 of 77
Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-ADDITIONS-4 Supplemental 2 Page 56 of 77 The Connecticut Light and Power Company d/b/a Eversource Energy Projected 2026 Capital Spend by Project (Whole Dollars) Project Number/Description by Category CD02332:Tresser Blvd Duct Bank CD02511:Manchester Bridge Conduit Replace CD02580:Stamford Vault 292 Replacement CD02619:Cedar Heights Rd Shallow Duct Bank CD02691:Franklin Drive 1B Duct-bank Repair Projected 2026 Capital Spend Project Long Description During a new service project, the contractors encountered blocked/ insufficient conduits between MH#700 and MH#731 on Tresser Blvd when trying to tap 1G02 feeder to the customer’s switchgear on Tresser Blvd. Repairs were attempted but to no avail. Furthermore, blocked ducts were encountered in the past in other sections of the duct bank on Tresser Blvd between Canal Street and Elm Street. A more accessible feeder (1G19) was used to complete the new service project. However, the fear is that should the need arise to install cable in this area in the future, it cannot be done because of issues with the duct bank.This project is being initiated to install a new 8-position 1,000,000 duct bank along Tresser Blvd between Canal Street and Elm Street to facilitate future needs. The project is for electrical conduit replacement on two Manchester bridges that are over the I-384 1,739,000 highway. The State notified the Civil Engineering team of steel conduit bank deficiencies. This project replaces vault #292 which is in the roadway at the very busy junction of North St. and 625,500 Summer St. in Stamford, CT. An inspection revealed that vault #292 deteriorated extensively. This project has been created to address the shallow duct bank that occurred on Cedar Heights Rd in 30,000 Stamford CT during work performed under CD00728. This project address the replacement of deteriorated steel conduits that are location within an existing duct-bank with a horizontal 2 x 4 array on Main Street in Torrington, CT. This duct-bank spans the Naugatuck River and is located under the bridge. These conduits presently penetrates through a concrete support structure of the bridge which is adjacent to manholes MH# 9 and MH# 21 and has a span length of 110' with very limited room. The age of the duct-bank is over 65 years old and due to its exposure to a harsh environment, these conduits within the duct-bank have deteriorated to the point of either having large, elongated holes in their perimeter or they have 1,000 deteriorated to the point of becoming separated into two pieces.Page 57 of 77
Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-ADDITIONS-4 Supplemental 2 Page 57 of 77 The Connecticut Light and Power Company d/b/a Eversource Energy Projected 2026 Capital Spend by Project (Whole Dollars) Project Number/Description by Category Substation Reliability GENERAL MODERNIZATION CS00023:GOODWIN LANE 22 - REMOVE SUBSTATION CS00070:Naugatuck 19K - Remove Substation CS00072:Guilford 29F - Remove Substation CS00105:Meadow 28J - Remove Substation CS00119:Oakville 17Q - Remove Deenergized S CS00269:Race Hill 15D - Remove S/S CS00412:Newtown 12N Station Modernization CS00450:Clayton CT 21W Remove 21W-1X XF CS00451:Carver 19R-1X and Oil Removal Projected 2026 Capital Spend 35,164,001 11,183,000 Project Long Description This project is to complete equipment removals, environmental monitoring, remediation, and site 25,665 restoration for the de-energized Goodwin Lane 22 substation located in East Hartford, CT. This project is to perform control house demolition, concrete foundation and pad removal, soil excavation, environmental remediation, groundwater monitoring, civil removal work, and site 42,775 restoration for the de-energized Naugutuck 19K substation located in Naugutuck, CT. This project is to complete site removals and environmental remediation for the de-energized 32,200 Guilford 29F substation located in Guilford, CT. This project is to complete equipment and structure removals, environmental monitoring, remediation, and site restoration for the de-energized Meadow 28J substation located in Branford, 68,440 CT. This project is to perform soil excavations, environmental remediation, concrete foundation and pad removal, shed removal, and site restoration for the de-energized Oakville 17Q substation located in 316,535 Watertown, CT. This project is to complete removals, environmental remediation, and site restoration for the de51,330 energized Race Hill 15D substation located in Madison, CT. This project is to replace nine 23kV oil circuit breakers (OCBs) at Newtown 12M substation located in Newtown, CT. The OCBs may cause harm to the environment if leakage occurs, or spills occur 75,556 during maintenance. This project is to decommission and retire the de-energized Clayton Court 21W substation located in 316,535 New Britain, CT. This project is to complete equipment removals and to complete environmental testing for the de42,775 energized Carver 19R substation in New Britain, CT.
As listed on the current system
Supplement for New App [Filed: 10/19/2026]