Application supplement

Exhibit CLP-Additions-6 Supplemental 3 and Exhibit CLP-Additions-4 Supplemental 3

Files3

Search terms highlighted
Eversource rate increase is on 2 pages across 2 files of the text below, highlighted. Go to the first matchClear highlighting
Words on different pages
1 page match
  1. Page 59 of 73

    Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-ADDITIONS-4 Supplemental 3 Page 59 of 73 The Connecticut Light and Power Company d/b/a Eversource Energy Projected 2026 Capital Spend by Project (Whole Dollars) Project Number/Description by Category ETTCF26:ETT Customer Focused 2026 POLE INTEGRITY PROGRAM CD02444:2025 Pole Integrity CD02449:2025 Frontier Pole Shifts CD02545:2026 Pole Integrity Projected 2026 Capital Spend Project Long Description The Customer Focus Enhanced Tree Trimming project addresses system reliability by providing greater clearances and removing risk limbs and trees that are outside of the normal maintenance trim 2,000,000 zone in areas of emergent reliability concerns. 18,500,000 This initiative replaces or reinforces wood poles found during the annual pole inspections that cannot remain in service due to loss of strength from decay or insect infestation. This initiative also captures the replacement of leaning poles that were identified during the pole inspection process, and they are prone to failure posing a risk to public safety and the system’s reliability. Leaning pole locations are created when soil disturbances and pole attachments affect the original pole’s orientation because of accumulation of moisture in the ground, severe weather and or storm 3,079,200 damages. The Frontier Pole Shifts project supports the 45-day PURA mandated timeframe for Eversource transfers to new pole sets. This project includes the transfer of Eversource equipment onto Frontier Defective Pole Replacements. As Frontier replaces defective poles, Eversource will receive an 300,000 automatic design request through Notify to create a WR for the equipment transfer. This project captures the cost necessary to replace wooden poles that were found during the 2025 annual pole inspections. These poles cannot remain in service due to loss of strength from decay or insect infestation.This initiative also captures the replacement of leaning poles that were identified during the pole inspection process, and they are prone to failure posing a risk to public safety and the system’s reliability. Leaning pole locations are created when soil disturbances and pole attachments affect the original pole’s orientation because of accumulation of moisture in the ground, severe 12,499,999 weather and or storm damages. P
  2. Page 60 of 73

    Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-ADDITIONS-4 Supplemental 3 Page 60 of 73 The Connecticut Light and Power Company d/b/a Eversource Energy Projected 2026 Capital Spend by Project (Whole Dollars) Project Number/Description by Category CD02546:2026 Frontier Pole Shifts RIGHT OF WAY LINES CD01246:Fry Brook 13B21/13B27 ROW Pole Repl Projected 2026 Capital Spend Project Long Description The Frontier Pole Shifts project supports the 45-day PURA mandated timeframe for Eversource transfers to new pole sets. This project includes the transfer of Eversource facilities onto Frontier Defective Poles that will be replaced in the year 2026.As Frontier replaces defective poles, Eversource will receive an automatic design request through Notify to create a WR for the 2,620,800 equipment transfer. 12,000,000 The Fry Brook 13B21/13B27 ROW is an approximately 3-mile express feed from the substation to the towns of Plainfield and Killingly. 13B21 serves 3,607 customers and 13B27 serves 1,963 customers. For a double circuit fault from the substation to Plainfield Road 100% of customers are automatically restored. This is accomplished via ties with 13B10, 15C8 and 30Y10. While travelling along I-395 several crossarms were observed to be cocked and/or racked and upon a physical walk through, much more damage was recorded. A majority of the poles are 66+ years old and most crossarms were replaced in 1973. All crossarms are installed with bow braces. The project will perform 100% pole and conductor replacement from the substation to the Moosup 19Y Substation north of Route 14.The aim of this project is to install a new double circuit pole line adjacent to the existing pole line where easement restrictions allow, with all new 50-foot class 1 64,664 poles, 556 ACSR TW and 2/2/2 construction.
  3. Page 61 of 73

    Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-ADDITIONS-4 Supplemental 3 Page 61 of 73 The Connecticut Light and Power Company d/b/a Eversource Energy Projected 2026 Capital Spend by Project (Whole Dollars) Project Number/Description by Category CD01308:Saybrook 22D Triple Circuit ROW CD01720:ROW 006 Remediation CD02211:13K57, 32P3 ROW Removal CD02376:2025 ROW Priority 3 Poles - Central Projected 2026 Capital Spend Project Long Description This project addresses two right-of-way (ROW) issues in the Town of Old Saybrook. The first issue is a triple circuit pole line south of Saybrook 22D station extending 2,700 ft from Elm St to Ingham Hill Rd, Saybrook. This triple circuit pole line consists of the 15L46, 15L70, and 22D4 Circuits with 1,450 ft of pole line through a marsh. The Bokum 15L46 (27.6kV) supplies Cedar La 41L and Westbrook 20S. The Bokum 15L70 (27.6kV) backs-up the 15L46. Westbrook 20S is backed up by Green Hill 30R9 and Cedar La 41L is backed up by Bokum 15L5 and Saybrook 22D4. Having three circuits on one pole line that is difficult to access creates a risk extended abnormality should reliability issues occur. The second issue is a split pole top (vertical corner construction) on the Bokum 15L70 (27.6kV) circuit located in the Bokum-Old Saybrook ROW between I-95 and a marsh. This circuit supplies the Saybrook 22D-2X Substation Transformer. The existing conductor spans ~500 ft over I-95 and then goes for another 850 ft over a marsh. This project will replace this structure with three new steel structures (to Transmission Crossing Specs) due to the lengthy spans of 3ph 556 ACSR wire and the hazard it will create if the lines were downed across I-95. The 386,508 project will resolve both issues by relocating the circuits along town roads. Eversource has completed drone patrols of all distribution ROWs and has categorized all findings into five priority levels. ROW 006 had 76 total findings, 3 priority 1 poles, 26 priority 2 poles, 42 priority 3 poles, 4 priority 4 poles, and 1 priority 5 pole. This project will maintain the ROW and 3,273,900 rebuild in place with steel poles and 556 tree wire. This project is for the removal of the 13K57 and 32P3 obsolete and de-energized ROWs in Stonington, CT. These ROWs are hazardous assets that have resulted in customer complaints and 488,013 have warranted repairs to inoperative circuits. This project will address 103 priority 3 damages found during ROW drone inspections. All ROW 3,130,200 poles will be replaced with Class 1 or larger steel poles.
  4. Page 62 of 73

    Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-ADDITIONS-4 Supplemental 3 Page 62 of 73 The Connecticut Light and Power Company d/b/a Eversource Energy Projected 2026 Capital Spend by Project (Whole Dollars) Project Number/Description by Category CD02377:2024 ROW Priority 3 Poles - Eastern CD02631:2026 ROW Priority 3 Poles FRPROW:Projection Proj for ROW SMART SWITCHES PROGRAM CD01278:12C4-71S Smart Switch Program CD01921:Willamantic 14S31 Smart Switch Proj CD02007:2B5 Smart Switch Projected 2026 Capital Spend Project Long Description Approximately 500 linear miles of Distribution ROW were inspected by drones in Connecticut. The damage found was recorded and prioritized. This project will address 55 Priority 3 findings. All 1,146,126 ROW poles will be replaced with Class 1 or larger steel poles. Approximately 500 linear miles of Distribution ROW were inspected by drones in Connecticut. The damage found was recorded and prioritized. This project will address 34 Priority 3 findings. All 1,498,100 ROW poles will be replaced with Class 1 or larger steel poles. 2,012,490 Projection Project for Right of Way Lines 15,000,000 Project CD01278 will sectionalize a 2,397 customer zone located beyond the Enfield 12C4-71S into 1,006,700 smaller automatic zones. With these changes, customers will experience increased reliability. This project will install an automatic loop scheme between the 14S31 and 14S32 circuits. By 225,099 automating the loop scheme, power can be restored to customer quickly. Project CD02007 seeks to address large customer zones on the 2B5 circuit in Thomaston, CT. The 2B5 currently has two zones over 500 customers. The first zone is the 2B5-70S which hosts 511 customers. This zone has experienced three outages over the last four years. The second zone is the 2B5-60R which hosts 681 customers and has experienced two outages over the last four years. This project suggests the installation of two new sectionalizing devices to reduce large customer zones. One device, a radial recloser, will be installed on P# 830, Main St. Plymouth. This device will reduce the 2B5-70S zone from 511 to 145 customers and will simultaneously create a new 366 customer zone. The second device, a smart switch, will be installed in the 1B5-60R zone on P# 1181 along N Harwinton Ave, Plymouth. The installation of this device will reduce the 2B5-60R zone from 681 customers to 319 customers while also creating a new zone of 362 customers. With these 1,700,900 changes, customers will experience increased reliability.
  5. Page 63 of 73

    Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-ADDITIONS-4 Supplemental 3 Page 63 of 73 The Connecticut Light and Power Company d/b/a Eversource Energy Projected 2026 Capital Spend by Project (Whole Dollars) Project Number/Description by Category CD02008:12J38 Smart Switch CD02201:Large Customer Zones RWO Central CD02318:2025 Large Customer Zones RWO West CD02319:2025 Eastern Large Customer Zone >1 Projected 2026 Capital Spend Project Long Description This project is being established to address two large customer zones on the 12J38 circuit in Mansfield, CT. The 12J38-71S zone has 693 customers at risk and this project proposes adding a smart switch in the 12J38-71S zone, dividing it into a 365 and 328 customer zones. The 12J38-71S zone has experienced seven outages in the last four years. The 12J38-80M zone has 648 customers at risk which will be divided into zones of 286 and 362 customer zones. The zone reduction will be performed by adding a new recloser and reprogramming the existing 12J38-80M as a smart switch. The 12J38-80M zone has experienced one outage in the last four years. With these changes, 205,400 customers will experience increased reliability. The installation of multiple smart switches will reduce the customers affected in the event of future outages. Project CD02201 addresses 13 large customer zones in the Central Division with the 1,144,500 installation of 24 viper reclosers. The installation of multiple smart switches will reduce the customers affected in the event of future outages. Project CD02318 addresses 8 large customer zones in the Western Division with the 1,868,834 installation of 15 viper reclosers. The installation of multiple smart switches will reduce the customers affected in the event of future outages. Project CD02319 addresses 3 large customer zones in the Eastern Division with the 341,300 installation of 4 viper reclosers.
  6. Page 64 of 73

    Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-ADDITIONS-4 Supplemental 3 Page 64 of 73 The Connecticut Light and Power Company d/b/a Eversource Energy Projected 2026 Capital Spend by Project (Whole Dollars) Project Number/Description by Category CD02340:2024 Trip Saver Program CD02475:2025 Western Large Cusomer Zone 900 Projected 2026 Capital Spend Project Long Description Project CD02340 proposes to install Trip Savers at 1155 fused lateral locations in Connecticut to reduce the number of outages caused by transient type events (Tree, Animal, Lightning, Patrolled Nothing Found).A Trip Saver is a self-powered, electronically controlled, single-phase, cutoutmounted vacuum interrupter recloser. The Trip Saver is designed to eliminate the sustained interruption that occurs when a lateral fuse cutout operates in response to a transient fault. It also can eliminate momentary circuit interruptions that occur when a substation circuit breaker or source-side line recloser would otherwise trip to prevent a lateral fuse cutout from operating in response to a 500,009 transient fault. Smart Switch projects address circuit zones that serves more than 500 customers. Limiting circuit zones to less than 500 customers where possible limits the number of customers that loses power 1,588,100 during a single outage. Project CD02475 addresses circuit zones that serves 900 - 999 customers. CD02519:2025 Htfd Lg Customer Zones SS Smart Switch projects address circuit zones that serves more than 500 customers. Limiting circuit zones to less than 500 customers where possible limits the number of customers that loses power during a single outage. Project CD02519 addresses circuit zones that serves more than 500 244,000 customers. CD02520:2025 Norwalk AWC Smart Switch RWO Smart Switch projects address circuit zones that serves more than 500 customers. Limiting circuit zones to less than 500 customers where possible limits the number of customers that loses power during a single outage. Project 2520 address zones that are ranked in the top 100 in terms of 128,500 customer interruptions in the Norwalk AWC.
  7. Page 65 of 73

    Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-ADDITIONS-4 Supplemental 3 Page 65 of 73 The Connecticut Light and Power Company d/b/a Eversource Energy Projected 2026 Capital Spend by Project (Whole Dollars) Project Number/Description by Category CD02521:Vacufuses Program 2025 Projected 2026 Capital Spend Project Long Description Project CD02521 proposes to install Vacufuses on Distribution transformer locations in Connecticut to reduce the number of outages caused by transient type events (Limbs, Animal, Lightning, Patrolled Nothing Found). A Vacufuse is a self-powered, electronically controlled, single-phase, cutout-mounted vacuum interrupter recloser. The Vacufuse is designed to eliminate the sustained interruption that occurs when a transformer fuse cutout operates in response to a transient fault. This device will save 200,120 outages and reduce trips by troubleshooters by reclosing after a transient fault occurs. CD02538:2025 Eastern-New London SS CI Rank CD02542:2025 Cent. Cheshire AWC SS (CI) - 1 Smart Switch projects address circuit zones that serves more than 500 customers. Limiting circuit zones to less than 500 customers where possible limits the number of customers that loses power during a single outage. Project CD02538 addresses circuit zones ranked in the top 100 due to 36,200 customer outages over the past 4 years. Smart Switch projects address circuit zones that serve more than 500 customers. Limiting circuit zones to less than 500 customers where possible limits the number of customers that will lose power during a single outage. Project CD02542 addresses circuit zones that serve more than 500 customers 846,700 and is ranked in the top 100 based on customers interrupted over the past 4 years.
  8. Page 66 of 73

    Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-ADDITIONS-4 Supplemental 3 Page 66 of 73 The Connecticut Light and Power Company d/b/a Eversource Energy Projected 2026 Capital Spend by Project (Whole Dollars) Project Number/Description by Category CD02562:2025 Single Phase Recloser Project CD02583:Barnes Aerospace 14K9 Windsor Locks CD02717:Eastern TripSaver Optimization FRSMRTSW:FRCST PROJ REL IMPRV SMART SWITCHES SR DOUBLE POLE REMOVALS Projected 2026 Capital Spend Project Long Description Project CD02562 proposes to install Viper SP single phase reclosers at fused lateral locations in Connecticut to reduce the number of outages caused by transient type events (Limbs, Animal, Lightning, Patrolled Nothing Found).A Viper SP recloser is a pole mounted electronically controlled interrupter recloser with full SCADA control and visibility utilizing an SEL 351 control. The Viper SP recloser is designed to eliminate the sustained interruption that occurs when a lateral fuse cutout operates in response to a transient fault. It also can eliminate momentary circuit interruptions that occur when a substation circuit breaker or source-side line recloser would otherwise trip to prevent a lateral fuse cutout from operating in response to a transient fault.In 2025 Viper SP recloser will be installed on fused single-phase laterals that have high fault current magnitudes which would exceed 210,177 other single phase reclosing equipment ratings. This project addresses a customer inquiry into the poor reliability performance of the Windsor Locks 14K9 circuit. The customer is Barnes Aerospace located on Old Kennedy Rd in Windsor, CT. This project will address the 14K9 backbone and the lateral that feeds the customer. The improvements will include adding a new 3-phase recloser and replacing one existing 3-phase recloser with a smart switch. In addition, all pole-top transformers along Old Kennedy Rd that are not already fused will 136,000 be fused. This project addresses trip saver locations where the minimum load requirement is not met year round. Minimum load is required in order for trip savers to operate properly in response to fault 738,387 conditions. 3,879,074 Forecast Project Reliability Improvement Smart Switches 5,000,010
  9. Page 67 of 73

    Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-ADDITIONS-4 Supplemental 3 Page 67 of 73 The Connecticut Light and Power Company d/b/a Eversource Energy Projected 2026 Capital Spend by Project (Whole Dollars) Project Number/Description by Category CD02547:2026 Double Pole Removals UCONN RESILIENT ENERGY CENTER Projected 2026 Capital Spend This initiative captures the cost necessary to perform bare pole removals at double pole locations and is required to the meet the orders of PURA Docket No. 03-03-07. Double pole locations are commonly created when these instances occur: I.Structural and electrical upgrades. II.Pole Integrity projects. III.Other programs including the replacement of poles with third party attachments that cannot be removed or transferred to the new pole during replacement. Attachments are removed or transferred by third parties later following a notification through the Alden 1 database, managed by the single pole administrator. Once all pole attachments have been transferred 5,000,010 to the new pole, the old pole is bare and ready to be removed. 500,000 The proposed project is needed to fund the continuation of the operations of the Eversource Energy Center at the University of Connecticut and the development and operation of the UConn Predictive Storm and Outage models for Eversource Connecticut service territory for the period June 1, 2023, through May 31st, 2028, by regularly updating and improving the model integrating utility specific infrastructure and outage data from the Outage Management System (OMS). This project is part of the 2023-2028 Eversource-UConn Master Agreement for the Eversource Energy Center. EEC23-28:Eversource Energy Center 2023-2028 URD/DB Cable Improvements DB CABLE REPLACE-SPECIFIC PROJ 101395:DIRECT BURIED CABLE REPLACEMENT PRO CD02388:Bristol DB Cable Replacement 15U4 Project Long Description 500,000 26,000,000 26,000,000 This program funds the replacement of direct buried distribution cables in underground residential and commercial developments that are reaching the end of their useful lives or have failed. This 22,684,443 improves reliability for customers served by these cables. 66,200 This project is to address the poor reliabilty of direct buried cable in downtown Bristol.
  10. Page 68 of 73

    Connecticut Light and Power Company d/b/a Eversource Energy Docket No. 26-05-10 Exhibit CLP-ADDITIONS-4 Supplemental 3 Page 68 of 73 The Connecticut Light and Power Company d/b/a Eversource Energy Projected 2026 Capital Spend by Project (Whole Dollars) Project Number/Description by Category CD02438:33M1 Woodridge Lake Cable Replace CD02750:2026 DB Fault Indicator Replacement CD02751:2026 DB Fault Indicator Replacement CD02752:2026 DB Fault Indicator Replacement 5-Facilities Basic Business-FAC Acquisition and Sale LAND - AS 26715:2026 CL&P-D RE & ROW LOB Replacements Projected 2026 Capital Spend Project Long Description Project CD02438 addresses underground reliability issues within the Woodridge Lake community in Goshen, CT. The identified portion of the housing community is fed via the Goshen 33M1 circuit at 23.0kV off Milton Rd, Goshen. The two lateral taps located at P#1372 & P#1373 are comprised a mixture of direct buried #1 AL and 1972-vintage #1 AL Concentric UG conductor. Both taps have experienced a combined 8 outages due to underground equipment failures in 4 years. This poor underground reliability ended up resulting in a customer complaint from the Woodridge Lake Housing Association. New direct buried cable will be installed in conduit to reduce future 994,600 deterioration and to ensure reliable service to the portion of the housing community. The purpose of this project is to fund the 2026 Direct Buried (DB) inspection program and replace approximately 2,390 fault indicators in the Eastern Region and perform inspections of the DB 547,526 equipment. The purpose of this project is to fund the 2026 Direct Buried (DB) inspection program and replace approximately 3,628 fault indicators in the Central Region and perform inspections of the DB 819,499 equipment. The purpose of this project is to fund the 2026 Direct Buried (DB) inspection program and replace approximately 3,778 fault indicators in the Western Region and perform inspections of the DB 887,731 equipment. 28,004,045 26,154,036 200,000 200,000 200,000 CL&P-D Real Estate & Right of Way 2026 Line of Business (LOB) 1,255,000
1 part match

As listed on the current system

Supplement for New App [Filed: 11/18/2026]