Text of LFE-001 GenConn.pdf

Extracted from the file · 1 page · 535 characters

Words on different pages

Text of LFE-002 GenConn .pdf

Extracted from the file · 1 page · 1,167 characters

Words on different pages
Words on different pages

Text of LFE-004 GenConn.pdf

Extracted from the file · 3 pages · 4,954 characters

Words on different pagesRead the text of LFE-004 GenConn.pdf

Text of LFE-005 GenConn.pdf

Extracted from the file · 2 pages · 2,975 characters

Text of LFE-006 GenConn.pdf

Extracted from the file · 2 pages · 4,578 characters

Text of LFE-006 Attachment 1.pdf

Extracted from the file · 115 pages · 296,451 characters

Text of LFE-007 GenConn.pdf

Extracted from the file · 1 page · 1,613 characters

Words on different pagesRead the text of LFE-007 GenConn.pdf

Text of LFE-007 Attachment 1.xlsx

Sheet names, column headings and text cells; numbers left out

Text of LFE-007 Attachment 2 (RRU-031 Attachment 1-Corrected).xlsx

Sheet names, column headings and text cells; numbers left out

Text of LFE-008 GenConn.pdf

Extracted from the file · 1 page · 2,438 characters

Text of LFE-008 Attachment 1.pdf

Extracted from the file · 42 pages · 58,655 characters

Text of LFE-008 Attachment 2.xlsx

Sheet names, column headings and text cells; numbers left out

Text of LFE-009 GenConn.pdf

Extracted from the file · 1 page · 1,386 characters

Text of LFE-010 GenConn.pdf

Extracted from the file · 2 pages · 3,322 characters

Words on different pagesRead the text of LFE-010 GenConn.pdf
Words on different pages
  1. Page 110 of 178

    GenConn Energy LLC Docket No. 26-06-02 LFE-010 Attachment 1 Page 110 of 178 NRG GenConn Middletown Unit 12 December 6, 2019 SCR Catalyst Performance Test Report APPENDIX 2: Field Records Field records received from GenConn Middletown are reproduced below CORMETECH Confidential www.cormetech.com | 16 5000 International Drive Durham, North Carolina 27712 USA
  2. Page 111 of 178

    GenConn Energy LLC Docket No. 26-06-02 LFE-010 Attachment 1 Page 111 of 178 NRG GenConn Middletown Unit 12 December 6, 2019 SCR Catalyst Performance Test Report CORMETECH Confidential www.cormetech.com | 17 5000 International Drive Durham, North Carolina 27712 USA
  3. Page 112 of 178

    GenConn Energy LLC Docket No. 26-06-02 LFE-010 Attachment 1 Page 112 of 178 NRG GenConn Middletown Unit 12 December 6, 2019 SCR Catalyst Performance Test Report APPENDIX 3: Performance Test Standard Procedure Purpose The laboratory performance testing for SCR catalyst is conducted to determine the catalytic potential of a representative sample of SCR catalyst at conditions that closely match the actual operating conditions of the SCR system. The sample should represent a typical cross section of the SCR, and the operating history should be known. The test is conducted in a controlled, laboratory environment on custom-built, rigorously validated SCR catalyst test apparatus allowing accurate determination of performance and comparisons of the sample catalytic potential to the system requirements previously tested catalyst(s). Test Equipment Description The Cormetech Laboratory SCR test reactors consist of three basic systems: Simulated flue gas generator SCR catalyst test chamber Measurement system The purpose of the simulated flue gas generator is to provide a stable controlled supply of heated gas with the required mix of gases at the required flow rate and temperature to the SCR catalyst test chamber. It consists of a bulk flue gas generator, a flue gas modification system, a flue gas heater, a reactive gas injection system, and a flue gas mixer. Bulk Flue Gas Generator -The bulk flue gas is produced by either the combustion of air in a natural gas fired water-cooled combustion chamber, the extraction of nitrogen from air via a membrane system, or the delivery of nitrogen from liquefied nitrogen. This system is adjusted to achieve the overall flue gas flow rate required for the specified test. Flue Gas Modification System – The gas stream produced by the bulk flue gas generator is modified by the addition of oxygen/air and water/steam to achieve the targeted concentrations of water vapor and oxygen in the flue gas stream. Flue Gas Heater – The flue gas stream is heated to the target test temperature by an electric pre-heater. Reactive Gas Injection System – Calibrated mass flow controllers are used to deliver SO 2, SO3, NO2, NO, and NH3 into the flue gas stream. CORMETECH Confidential www.cormetech.com | 18 5000 International Drive Durham, North Carolina 27712 USA
  4. Page 113 of 178

    GenConn Energy LLC Docket No. 26-06-02 LFE-010 Attachment 1 Page 113 of 178 NRG GenConn Middletown Unit 12 December 6, 2019 SCR Catalyst Performance Test Report The table below summarizes the range of process conditions that can be produced by various apparatus in Cormetech’s laboratory. Cormetech’s laboratory maintains multiple testing units, each with varying capabilities for temperature, flow, and gas composition. The unit selected for a given test will depend on the specific requirements for the sample tested. Parameter Gas Temperature Flow rate/Entrance velocity O2 H2O NO NO2 NH3 SO2 SO3 Units o C Nm/s volume % dry volume % ppmvd ppmvd ppmvd ppmvd ppmvd Range 200 – 600 1.25 - 7.05 1 – 20 1-201 0 - 2,000 0 - 20002 0 - 4,000 0 - 2,000 0 – 25 1: Some apparatus have the capability to control water concentration. Other units supply water as a product of combustion. When water concentration is not controlled, Cormetech corrects the results to the target concentration with a standardized correction factor. 2: NO2 addition capability is not available on all test units. Flue Gas Mixer – Following the reactive gas injection, the gases are mixed using a high efficiency static mixing element. The simulated flue gas next enters the SCR test reactor where the SCR test sample or samples are located. Each sample is sealed tightly to the walls of the test chamber to ensure that all of the flue gas passes though the sample[s]. Along the length of the test chamber there are electric heating elements that maintain the specified test temperature. There are test ports located at the entrance to the test reactor and at the exit of each sample layer to extract a sample of flue gas for analysis, measure the static pressure of the flue gas, and monitor the temperature of the catalyst samples and the flue gas. CORMETECH Confidential www.cormetech.com | 19 5000 International Drive Durham, North Carolina 27712 USA
  5. Page 114 of 178

    GenConn Energy LLC Docket No. 26-06-02 LFE-010 Attachment 1 Page 114 of 178 NRG GenConn Middletown Unit 12 December 6, 2019 SCR Catalyst Performance Test Report The process conditions of the SCR catalyst under test are monitored by the measurement system: Gas Flow Rate – The flue gas flow rate is measured by an averaging pitot tube in the exit of the simulated flue gas generator. The flow rate is also calculated from the mass flow controllers for the various gas constituents as they are added. Finally, an annubar is installed in the exhaust of the reactor which allows another cross-check of the flow rate. For the testing to be determined valid, the flow rate must be within the allowable limits from the target flow rate. Gas Temperature – The temperature of the gas and the catalyst samples is measured by a series of thermocouples throughout the test reactor. For the testing to be determined valid, both the spatial and temporal variability must be within the allowable limits from the specified set point. Component Concentration – The components of the flue gas are determined by the methods described below. Different systems may not have every type of sampling measurement system. NOx – Chemiluminescent NOx Analyzer / Infrared Spectroscopy. Average value at each sampling point recorded for each sampling cycle NH3 – Ion Chromatography/infrared spectroscopy SO2 – Precipitation Method/infrared spectroscopy SO3 – Controlled Condensation; Collective Precipitation Method O2 – Micro-fuel cell and Paramagnetic O2 Analyzer Procedure Description Summary The following stepwise description is a guideline to understand how an audit proceeds from sample receipt to reported results. 1. Upon receipt, each sample is inspected for condition and photographed. The sample dimensions are recorded. 2. The Test Plan is prepared based on the needs of audit. The appropriate test apparatus is selected based on the test requirements and the test is scheduled. 3. Each sample is prepared for testing. [This process includes cleaning the sample, and cutting to the required test sample size.] 4. The reactor is opened, inspected, and prepared for operation. 5. Each catalyst sample is loaded according to the Test Plan and sealed in the reactor. 6. An equipment leak test is performed. CORMETECH Confidential www.cormetech.com | 20 5000 International Drive Durham, North Carolina 27712 USA
  6. Page 115 of 178

    GenConn Energy LLC Docket No. 26-06-02 LFE-010 Attachment 1 Page 115 of 178 NRG GenConn Middletown Unit 12 December 6, 2019 SCR Catalyst Performance Test Report 7. The Bulk Flue Gas Generator is started and the test conditions are set for O2%, temperature, and bulk flow rate. 8. NO and NO2 injection is started and then adjusted in order to meet the test conditions. 9. Ammonia, SO2 and SO3 injection is started and then adjusted in order to meet the test conditions. 10. The catalyst is allowed to equilibrate at the test conditions specified. 11. A calibration check is run for the analyzers. 12. For each sampling cycle, the following measurements are taken, as required: Item NOX Concentration Location Measured Multiplexed to measure NOX at each sampling point NH3 Concentration At exit of sample[s] SO2 Concentration Entrance and at each sampling port Entrance and at each sampling port Exit of combustion chamber and multiplexed with NOX Analyzer Exit of combustion chamber SO3 Concentration O2 Concentration Gas Flow Gas Temperature Pressure Drop At each sampling port Entrance and at exit of testing chamber Frequency Average value at each sampling point recorded per each sampling cycle Depends on test method [Multiple analyses recorded] When SO2 oxidation performance is measured When SO2 oxidation performance is measured Continuously controlled and monitored Continuously controlled and monitored Inlet continuously controlled Continuously monitored, recorded as required 13. The results are recorded and checked per Quality Assurance requirements and compared to the Test Plan. 14. The results are reported. CORMETECH Confidential www.cormetech.com | 21 5000 International Drive Durham, North Carolina 27712 USA
  7. Page 116 of 178

    GenConn Energy LLC Docket No. 26-06-02 LFE-010 Attachment 1 Page 116 of 178 NRG GenConn Middletown Unit 13 SCR Catalyst Performance Test Report 671 Operating Hours October 2019 Audit Submitted by CORMETECH, INC. Environmental Technologies 5000 International Drive Durham, NC 27712 [phone removed] Max Morris Project Engineer John A. Nivens Sr. Engineering Technician Certifying Laboratory Representative Silas Christian, Laboratory Manager December 6, 2019 CORMETECH CONFIDENTIAL This document and attachments, if any, contain confidential/proprietary information and is submitted without consideration other than the recipient's agreement that it shall not be reproduced, copied, lent, or disposed of directly or indirectly nor used for any purpose other than that for which it is specifically furnished.
  8. Page 117 of 178

    GenConn Energy LLC Docket No. 26-06-02 LFE-010 Attachment 1 Page 117 of 178 NRG GenConn Middletown Unit 13 December 6, 2019 SCR Catalyst Performance Test Report TABLE OF CONTENTS EXECUTIVE SUMMARY ................................................................................................................ 3 PURPOSE ...................................................................................................................................... 4 BACKGROUND .............................................................................................................................. 4 FACILITY OPERATIONAL HISTORY ............................................................................................. 6 PROCEDURE OVERVIEW ............................................................................................................. 7 FIELD SAMPLING AND UNIT OPERATING CONDITIONS ............................................................ 8 LABORATORY PERFORMANCE TEST CONDITIONS .................................................................. 9 RESULTS ..................................................................................................................................... 10 FIELD DATA COMMENTARY....................................................................................................... 13 RECOMMENDATIONS ................................................................................................................. 14 APPENDIX 1: Location of Sample Retrieval .................................................................................. 15 APPENDIX 2: Field Records ......................................................................................................... 16 APPENDIX 3: Performance Test Standard Procedure .................................................................. 17 CORMETECH Confidential www.cormetech.com | 2 5000 International Drive Durham, North Carolina 27712 USA
  9. Page 118 of 178

    GenConn Energy LLC Docket No. 26-06-02 LFE-010 Attachment 1 Page 118 of 178 NRG GenConn Middletown Unit 13 December 6, 2019 SCR Catalyst Performance Test Report EXECUTIVE SUMMARY The following summarizes the key results for this audit of the NRG GenConn Middletown Unit 13 SCR after 577 operating hours since first gas-in. Observations and Predictions This audit of the GenConn Middletown Unit 13 SCR catalyst shows a measurable decrease in catalytic potential of the SCR catalyst, as measured by lab-scale testing. Based on the results of this audit, the SCR catalyst installed for GenConn Middletown Unit 13 is above the performance threshold and is projected to continue to meet the field performance requirements of 85.9% NOX reduction at 5 ppmvdc ammonia slip for at least an additional 1,300 operating hours from the date this sample was removed. Due to the low operating hours and that this is the first audit, the life prediction is likely conservative. This prediction assumes that catalyst deactivation will continue at the same rate as measured over the operating hours to date. If this rate of deactivation changes, the prediction of remaining catalyst life will change accordingly; therefore, Cormetech recommends performing regular field performance and laboratory catalyst audits. Field Data Commentary Based on the provided operational data, GenConn Middletown Unit 13 is operating well in the field and meeting permit limits. The measured ammonia slip and flow rate are lower than expected given the other parameters and lab measured activity of the catalyst, indicating good performance. In both oil fired and gas fired conditions, the outlet NOx is being driven well below the permit limit. This increases the NOx reduction efficiency resulting in a higher level of performance than the design of the catalyst. As the catalyst deactivates over time the outlet NO x will need to be maintained closer to the permit requirements to maintain ammonia slip under 5 ppmvdc. Recommendations Regular laboratory catalyst testing is recommended to refine the accuracy of the remaining catalyst life prediction. The next audit should occur after an additional 600 hours of operation or three years, whichever is first, from the time the sample for this audit was removed. Continued review of field test data to accurately confirm actual performance requirements, operating conditions, and system scale-up factors, and thereby the appropriate laboratory scale performance threshold is recommended. CORMETECH Confidential www.cormetech.com | 3 5000 International Drive Durham, North Carolina 27712 USA
  10. Page 119 of 178

    GenConn Energy LLC Docket No. 26-06-02 LFE-010 Attachment 1 Page 119 of 178 NRG GenConn Middletown Unit 13 December 6, 2019 SCR Catalyst Performance Test Report PURPOSE This test is conducted to audit the catalytic potential of an SCR catalyst by measuring the performance of a field catalyst sample that has been in operation for a known duration. The catalytic potential is measured by laboratory scale testing of field samples removed from the SCR. Performance tests are conducted in a controlled, laboratory environment allowing accurate comparisons of field sample catalytic potential to that of fresh catalyst. The deactivation rate is determined by comparing the change in catalytic potential to the operating hours of the sample. Field performance, as indicated by plant-supplied measurements and observations, is also analyzed and discussed relative to the performance of the catalyst samples tested. Measured field performance in conjunction with laboratory measurements of field sample catalytic potential is used to determine actual unit scale-up factors. Utilizing actual unit scale-up factors significantly improves the accuracy of future performance predictions. Further catalyst and/or field operation analysis may be recommended if laboratory test results are inconsistent with any of the following: Cormetech’s experience base of comparable units The plant’s reported field performance, if available The results of previous audits of the unit, if applicable The performance expectations for the unit. BACKGROUND In order to achieve the design performance requirements of a Selective Catalytic Reduction system for a specified timeframe (life) of the SCR catalyst, the catalyst formulation, structure, and volume are specifically designed to accommodate the system operating conditions, the predicted system scale-up factors, and a predicted rate of decrease in catalyst potential over time. If any of the design or operating parameters above is not realized, then the actual duration that the design performance requirements can be met may deviate from the design life. The individual contribution of each parameter on actual life is described below. In actual practice, one or more of these parameters may deviate from design and either counteract or complement each other. Performance Requirements: If the actual plant performance requirements are more severe than the design performance requirements, actual life will be less than design life. An example of this would be a unit that is required to achieve a higher NOx reduction than the unit was designed for. Operating Conditions: Flue gas flow rate, inlet NOX levels, temperature, oxygen content, and water content impact catalytic potential. If the catalyst is at an operating condition where the potential is lower than design, actual life will be less than design life. Scale-Up Factors: The full NOX reduction potential of the catalyst is not attained in the field due to non-ideal flow distribution, temperature distribution, ammonia to NOX molar ratio distribution, CORMETECH Confidential www.cormetech.com | 4 5000 International Drive Durham, North Carolina 27712 USA

Text of LFE-011 GenConn.pdf

Extracted from the file · 1 page · 2,796 characters

Words on different pagesRead the text of LFE-011 GenConn.pdf

Text of LFE-011 Attachment 1.xlsx

Sheet names, column headings and text cells; numbers left out

Text of LFE-012 GenConn.pdf

Extracted from the file · 1 page · 982 characters

Text of LFE-012 Attachment 1 REDACTED.pdf

Extracted from the file · 1 page · 2,492 characters

Text of LFE-014 GenConn.pdf

Extracted from the file · 1 page · 351 characters

Text of LFE-014 Attachment 1 (GenConn- CP2 REVISED V2).pdf

Extracted from the file · 8 pages · 12,688 characters

Text of LFE-015 GenConn.pdf

Extracted from the file · 1 page · 1,318 characters

Text of LFE-009 Attachment 1.xlsx

Sheet names, column headings and text cells; numbers left out

As listed on the current system

LFEs Filed (Avangrid) 1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 14, 15 Date Filed: 10/19/2026