Draft Decision
Files2
26-06-04 Proposed Interim Decision.pdf
PDF · 561 KB · 63 pagesText searchable
Download 26-06-04 Proposed Interim Decision.pdfRead the text of 26-06-04 Proposed Interim Decision.pdf
Notice of Written Exceptions - Docket 26-06-04.pdf
PDF · 194 KB · 1 pageText searchable
Download Notice of Written Exceptions - Docket 26-06-04.pdfRead the text of Notice of Written Exceptions - Docket 26-06-04.pdf
Search terms highlighted
Eversource rate increase is on 2 pages of the text below, highlighted. Go to the first matchClear highlighting
Page 39 of 63
Docket No. 26-06-04 Page 37 of the Modified SCEF Program Requirements. Final cost recovery will be contingent upon demonstration by the EDC that it has taken all reasonable measures to contain the costs of implementation and administration of the program . . . [C]ost recovery of implementation and administration costs is contingent upon the EDCs demonstrating that the costs were prudentlyincurred and that all reasonable measures to contain costs were taken. Lastly, The Authority directs the EDCs to submit a detailed report on the revenues generated from the sale of energy and RECs associated with the delivered output from SCEF’s in their applicable annual Revenue Adjustment Mechanism (RAM) filings. SCEF Decision, p. 19. Similarly, when establishing the RRES Program, the Authority directed the EDCs to: to maintain detailed, itemized records of all cost incurred in the establishment and implementation of the Residential Tariff program. The EDCs shall seek recovery of all reasonable and prudently incurred expenses in the applicable [RAM] proceeding (e.g., 21-01-03 or 21-01-04). All such expenses will be subject to a full prudence review. The EDCs bear the burden of proof of the reasonableness and prudence of all costs incurred. The EDCs shall provide a summary of each of the following categories of costs and revenues for the Residential Tariff program in each applicable RAM proceeding, with data for the previous calendar year: (1) REC incentive payments; (2) REC revenue; (3) EDC administrative costs; (4) fees collected; and (5) net Residential Tariff program costs or revenues based on (1) through (4). RRES Decision, p. 34. The Authority adopted a comparable approach for the NRES Program, directing the EDCs to: maintain detailed, itemized records of all cost incurred in the establishment and implementation of the Program authorized herein. The EDCs shall seek recovery of all reasonable and prudently incurred expenses in the applicable [RAM] proceeding (e.g., 21-01-03 or 21-01-04). All such expenses will be subject to a full prudence review. The EDCs bear the burden of proof of the reasonableness and prudence of all costs incurred. Additionally, until such a time as the Authority determines otherwise, the EDCs shall sell the RECs into the New England Power Pool Generation Information System renewable energy credit market and pass the revenues to ratepayers through the same RAM component through which it seeks cost recovery. The EDCs shall provide a summary of each of the following categories of costs and revenues for the Program in each applicable RAM proceeding, with data for the previous calendar year: (1) REC incentive payments; (2) REC revenue; (3) the energy costs associated with both the buy-all and netting tariffs; (4) EDC administrative costs; (5) fees collected; and (6) net Program costs or revenues based on (1) through (6).Page 40 of 63
Docket No. 26-06-04 Page 38 NRES Decision, pp. 47–48. Consistent with these precedents, all prudently incurred, uncapitalized costs associated with the implementation and administration of the successor residential, nonresidential, and community solar programs shall be eligible for recovery through the RAM, specifically the NBFMCC rate mechanism, in the proceeding associated with the year in which the costs were incurred (i.e., for 2028 costs, Docket No. 28-01-03 for Eversource and Docket No. 28-01-04 for UI). Any fees collected in connection with the programs shall offset program costs. The EDCs bear the burden of proving that all costs for which they seek recovery are reasonable and were prudently incurred. Recovery is not automatic merely because a cost relates to a program authorized by the Authority or required by statute. Rather, the EDCs must demonstrate that the costs were prudently incurred and that they took all reasonable measures to contain implementation and administration costs. The submission of cost estimates for program administration or IT billing system changes does not satisfy or otherwise relieve the EDCs of this burden. The prudence of such expenditures will be evaluated by the Authority after the costs have been incurred. These requirements ensure that ratepayers bear only those costs that are reasonably necessary to implement the programs, to the exclusion of inappropriate or excessive costs resulting from inefficient management, poor program implementation, or inadequate cost controls. To facilitate meaningful review and ensure transparency, each EDC shall separately identify the costs and revenues associated with each individual program – residential, non-residential, and community solar – in its applicable RAM filing. For each program, the EDC shall provide data for the previous calendar year and itemize, at a minimum: (1) REC revenues, if applicable, which shall be used to offset program administration costs; (2) cash compensation and billing credit compensation costs associated with each tariff under each program; (3) EDC administrative costs, broken out to the greatest practicable level of detail, including IT and billing costs, incremental staffing costs, marketing costs, and other administrative expenses; (4) any fees collected, which shall be used to offset program administration costs; and (5) net program costs or revenues based on the foregoing categories. This level of detail will enable the Authority to evaluate program costs individually, assess whether administrative expenditures are reasonable, and determine the net impact on ratepayers. Further, two clarifications to the cost-recovery practices used for the existing programs are warranted for the successor solar programs. These clarifications are intended to preserve appropriate cost recovery while preventing the RAM from becoming a mechanism for recovering capital investments outside the base distribution rate case process or recovering labor costs that do not constitute incremental program expenses. First, all capitalized project costs associated with the successor solar programs, including capital investments for billing system and IT modifications, shall not be eligible for recovery through the RAM. This limitation does not categorically preclude recovery of otherwise reasonable and prudent capital investments; rather, it preserves the distinction between recovery of operating expenses through an annual reconciling mechanism andPage 41 of 63
Docket No. 26-06-04 Page 39 recovery of capital investments through base distribution rates. The EDCs may seek recovery of eligible capital investments through a base distribution rate case, subject to the applicable review of the investments, including their prudence and appropriate treatment in rate base. The RAM is intended to provide timely recovery of eligible program expenses that the EDCs incur in implementing programs required by statute or Authority order. It is not intended to provide an alternative pathway for recovering capital investments outside the more comprehensive review conducted in a base distribution rate case. Unlike ordinary operating expenses, capital investments generally provide benefits over multiple years and may be reflected in rate base, with associated depreciation expense and a return on investment. Allowing the EDCs to recover such investments through the RAM could accelerate recovery relative to the ordinary base-rate process and diminish the opportunity for a comprehensive review of the investments and their associated costs. Accordingly, excluding capitalized project costs from RAM recovery maintains appropriate regulatory oversight, preserves the distinction between operating and capital expenditures, and reduces the risk that ratepayers will bear costs through a RAM mechanism not designed for review of capital additions. The EDCs' positions in the recent RAM proceedings further support establishing a clear distinction between RAM and base-rate recovery for capital investments. In response to discovery, Eversource stated that pre-existing capital projects included in the RAM should be transferred into rate base and recovered through base distribution rates beginning with the implementation of new distribution rates, while emphasizing the importance of gradualism to avoid rate shock. Eversource Interrog. Resp. CAE-71, Docket No. 26-01-03, Annual Review of the Rate Adjustment Mechanisms of The Connecticut Light and Power Company, p. 1. Similarly, although UI supported continued recovery of capital projects through the RAM, UI also supported transferring such projects from the RAM to base distribution rates in rate cases. UI Interrog. Resp. CAE-72, Docket No. 26-01-04, Annual Review of the Rate Adjustment Mechanisms of The United Illuminating Company, p. 1. In light of these considerations, the Authority will not extend RAM eligibility to capitalized project costs for the successor solar programs. Second, internal labor costs eligible for recovery through the RAM shall be limited to incremental labor costs directly attributable to the implementation and administration of the successor solar programs. The EDCs shall not recover through the RAM the costs of existing personnel whose labor would otherwise be incurred in the absence of the successor programs, nor may they recover the same labor costs twice through both the existing and successor programs by allocating the same staffing hours to both the predecessor and successor solar programs. As the RRES, NRES, and SCEF Programs are phased out and the successor programs are implemented, the Authority expects the EDCs to transition personnel and associated responsibilities from the existing programs to the successor programs, as appropriate. To the extent that personnel currently administering the existing programsPage 42 of 63
Docket No. 26-06-04 Page 40 can perform work associated with the successor programs as their prior responsibilities diminish, the associated labor costs shall not be treated as incremental merely because the work is performed under a new program. The EDCs must demonstrate that any labor costs claimed for recovery reflect additional staffing or additional labor expenses attributable to the successor programs, rather than the reassignment of existing resources or the continuation of costs already recovered through another cost mechanism. This requirement is necessary to prevent double recovery of costs and ensure that ratepayers are not charged additional amounts for work that existing personnel can perform within their current staffing resources. In their RAM filings, the EDCs shall separately identify incremental labor costs by program, describe the activities performed, identify the basis for determining the incremental costs, and explain how they accounted for the transition of responsibilities from the existing programs. The Authority will review these costs under the same standards of reasonableness and prudence applicable to all other program expenditures. VI. CONCLUSION AND ORDERS A. CONCLUSION In this Interim Decision, the Authority establishes the general framework for renewable energy tariffs for residential customers, non-residential customers, and community solar projects for the EDCs to ensure that such programs can take effect on January 1, 2028, pursuant to sections 1, 2, and 3 of Public Act No. 26-127. The Authority also directs the EDCs to develop and submit additional information for consideration in the remainder of this proceeding. B. ORDERS For orders requiring a filing, the Company shall file an electronic version through the Authority’s website at www.ct.gov/pura. Submissions filed in compliance with the Authority’s orders must be identified by: Docket Number, Title, and Order Number. Compliance with orders shall commence and continue as indicated in each specific order or until the Company requests and the Authority approves that the Company’s compliance is no longer required after a certain date. Unless otherwise provided or determined by the Authority, filings submitted in compliance with an order shall constitute satisfaction of the order. Filings requiring Authority approval must be filed as a motion. 1. No later than January 1, 2027, the EDCs shall initiate and lead a working group (MPF Working Group) to further develop a MPF Report, which shall be filed for further stakeholder feedback and Authority consideration in the remainder of this docket. The EDCs shall invite, at a minimum, the Clean Energy Parties, ConnSSA, OCC, DEEP, and CGB to participate in the MPF Working Group. 2. No later than March 1, 2027, the EDCs shall jointly file, as compliance, an updated inverter data proposal. The proposal shall include, at a minimum: (1) a discussion of methods to continue REC reporting when inverter data becomes unavailable,Page 43 of 63
Docket No. 26-06-04 Page 41 including when an API connection is lost because a company ceases operations; and (2) options for establishing automated data collection and management procedures, with associated cost and implementation timeline estimates. 3. No later than April 1, 2027, the EDCs shall jointly file, for review and approval, a comprehensive MPF Report based on the results of the working group process. The MPF Report shall include the following, at a minimum: (1) proposed performance criteria and settlement procedures, including the methodology for calculating per-kW payments; (2) a proposed per-kW payment rate based on a Connecticut-specific BCA, including the assumptions, methodology, and system benefits used to derive the rate, and a proposed methodology for updating the payment level over time; (3) a methodology for establishing the designated performance period, including consideration of seasonal and locational needs, and the extent to which projectspecific periods are appropriate; (4) proposed conditions, limitations, and notice requirements governing any changes to project-specific peak periods after project selection; (5) proposed metering and data requirements, storage charging restrictions, and verification requirements for ensuring that compensated energy is eligible for Class I renewable energy certification; (6) sizing requirements for paired PV and energy storage resources to ensure that projects meet the program’s proposed operational objectives; (7) a project revenue and operating model that includes historical weather and daily solar production data, battery charging and discharging behavior, and adjustable per-kW and per-kWh compensation inputs, to evaluate project performance and economics used under alternative program parameters; (8) an assessment of EDC implementation requirements for the recommended proposal; (9) an evaluation of interactions with potential storage participation in wholesale markets, flexible interconnection, and other relevant programs or rates, including potential duplication of ratepayer-funded benefits; and (10) a proposed program manual establishing the applicable program requirements and administrative procedures. The filing shall identify areas of consensus and non-consensus among working group participants and shall include any comments or alternative proposals submitted by participants. The EDCs shall also describe the working group’s process, the issues considered, and the rationale for any recommendations on which consensus was not achieved. 4. No later than January 1, 2028, the EDCs shall implement the necessary billing and IT modifications to establish two tariff options for the RRES successor program: (1) a netting tariff with instantaneous netting and (2) a flat buy-all tariff. Both tariffs shall have terms of up to 20 years. To preserve flexibility in the ultimate export rate determination, the EDCs shall implement billing system updates such that the export compensation rate may be either linked to existing bill components or programmed as an independent value that can be updated over time. The EDCsPage 44 of 63
Docket No. 26-06-04 Page 42 shall complete implementation of billing updates such that customers can apply to the program and begin receiving compensation under the residential successor netting tariff beginning on January 1, 2028. 5. No later than January 1, 2028, the EDCs shall implement the necessary billing and IT modifications to establish two tariff options for the successor NRES Program: (1) a netting tariff with instantaneous netting and (2) a flat buy-all tariff. Both tariffs shall have terms of up to 20 years. In establishing a flat buy-all tariff, the EDCs shall allow for the potential incorporation of a multipart payment framework for the successors to the NRES and SCEF Programs. To preserve flexibility in the ultimate netting export rate determination, the EDCs shall implement billing system updates such that the export compensation rate may be either linked to existing bill components or programmed as an independent value that can be updated over time. The EDCs shall complete implementation of updates such that the application and interconnection portals for the non-residential successor tariffs may open beginning on January 1, 2028. 6. No later than January 1, 2028, the EDCs shall implement billing system changes, if necessary, to allow for separate low-income and MFAH buy-all compensation rates. 7. All prudently incurred, uncapitalized costs associated with the implementation and administration of the successor residential, non-residential, and community solar programs shall be eligible for recovery through the RAM, specifically the NBFMCC rate mechanism, in the proceeding associated with the year in which the costs were incurred (i.e., for 2028 costs, Docket No. 28-01-03 for Eversource and Docket No. 28-01-04 for UI). a. Any fees collected in connection with the programs shall offset program costs. b. Each EDC shall separately identify the costs and revenues associated with each individual program – residential, non-residential, and community solar – in its applicable RAM filing. c. For each program, the EDC shall provide data for the previous calendar year and itemize, at a minimum: (1) REC revenues, if applicable, which shall be used to offset program administration costs; (2) cash compensation and billing credit compensation costs associated with each tariff under each program; (3) EDC administrative costs, broken out to the greatest practicable level of detail, including IT and billing costs, incremental staffing costs, marketing costs, and other administrative expenses; (4) any fees collected, which shall be used to offset program administration costs; and (5) net program costs or revenues based on the foregoing categories. d. Further, in their RAM filings, the EDCs shall separately identify incremental labor costs by program, describe the activities performed, identify the basis for determining the incremental costs, and explain how they accounted for the transition of responsibilities from the existing programs.Page 45 of 63
Docket No. 26-06-04 Page 43 e. All incurred costs will be subject to a full prudence review. The EDCs bear the burden of proof of the reasonableness and prudence of all program expenditures. 8. All prudently incurred, capitalized costs associated with the implementation and administration of the successor residential, non-residential, and community solar programs shall be eligible for recovery through a future EDC base distribution rate case. All costs will be subject to a full prudence review. The EDCs bear the burden of proof of the reasonableness and prudence of all costs incurred.Page 46 of 63
Docket No. 26-06-04 – Appendix A Page i Participant Ross Abbey United States Solar Corporation 100 N. 6th Street, Suite 410B Minneapolis, MN 55403 Representing United States Solar Corporation Eric Annes Department of Energy and Environmental Protection Ten Franklin Square New Britain, CT 06051 DEEP/BETP Bernadette Antaki Michaud Law Group, LLC 515 Centerpoint Drive, Suite 503 Middletown, CT 06457 World Energy Services, LLC Bernadette Antaki Michaud Law Group, LLC 515 Centerpoint Drive, Suite 503 Middletown, CT 06457 Viridi Parente, Inc. Bernadette Antaki Michaud Law Group, LLC 515 Centerpoint Drive, Suite 503 Middletown, CT 06457 TRITEC Americas, LLC Bernadette Antaki Michaud Law Group, LLC 515 Centerpoint Drive, Suite 503 Middletown, CT 06457 Triad Advanced Energy Development, LLC Bernadette Antaki Michaud Law Group, LLC 515 Centerpoint Drive, Suite 503 Middletown, CT 06457 Solar Alliance for Virtual Energy Bernadette Antaki Michaud Law Group, LLC 515 Centerpoint Drive, Suite 503 Middletown, CT 06457 Silver Brook Energy, LLC Bernadette Antaki Michaud Law Group, LLC 515 Centerpoint Drive, Suite 503 Middletown, CT 06457 Nevar CompanyPage 47 of 63
Docket No. 26-06-04 – Appendix A Page ii Bernadette Antaki Michaud Law Group, LLC 515 Centerpoint Drive, Suite 503 Middletown, CT 06457 Melin Energy, LLC Bernadette Antaki Michaud Law Group, LLC 515 Centerpoint Drive, Suite 503 Middletown, CT 06457 Kinsley Energy Systems, LLC Bernadette Antaki Michaud Law Group, LLC 515 Centerpoint Drive, Suite 503 Middletown, CT 06457 Ion Solar Pros, LLC Obinna Anugweje, Esq. Staff Attorney Department of Energy & Envrionmental Protection 10 Franklin Square Nw Britain, CT 06051 DEEP/BETP Jeanne Armstrong Senior Regulatory Council Solar Energy Industries Association Solar Energy Industries Association Emily Basham Connecticut Green Bank 75 Charter Oak Avenue, Suite 1-103 Hartford, CT 06106 CT Green Bank Andy T. Bauer Portland Clean Energy 256 Old Marlborough Turnpike Portland, CT 06480 Portland Clean Energy Greg Berger CPower Jeff Bishop Managing Director Key Capture Energy 150 State Street Salt Lake City, UT 84111 CPower Key Capture EnergyPage 48 of 63
Docket No. 26-06-04 – Appendix A Page iii David M. Bodendorf Senior Environmental Engineer Materials Innovation and Recycling Authority 200 Corporate Place, Suite 202 Rocky Hill, CT 06067 Materials Innovation and Recycling Authority Julian Boggs Manager, Regulatory & Policy Affairs Key Capture Energy 25 Monroe Street, 3rd. Floor Albany, NY 12210 Key Capture Energy Michael Borkowski Community Power Group Carole Briggs, Esq. Deptartment of Agriculture/Office of the Commissioner 450 Columbus Boulevard, Suite 701 Hartford, CT 06103 Community Power Group Ed Brolin RWE Clean Energy Ed Brolin Vice President, Policy & Regulatory Affairs Clean Energy Collective 27B Midstate Drive, Suite 106 Auburn, MA 01501 RWE Clean Energy Sean Burke BlueWave Project Development, LLC 116 Huntington Avuenue, Suite 601 Boston, MA 02116 BlueWave Development, LLC Richard W. Caperton Senior Director, Regulatory Affairs and Market Development Arcadia Power 1121 14th Street NW, Suite 300 Washington, DC 20005 Arcadia Power Michelle Carpenter Turning Point Energy 999 18th Street, Suite 3000 Denver, CO 80202 Turning Point Energy Department of Agriculture/Office of the Commissioner Clean Energy Collective