  1. Page 6 of 15

    and storage in another. A bidder could still submit a single bid, which the Authority would evaluate and procure within separate categories. Tranches would permit a more equitable comparison across consistent technologies and help ratepayers pay the lowest reasonable price for the relevant resource. This approach could allow developers to prepare complete bids rather than modifying their prices to account for the per-kW compensation or in an attempt to underbid solar-only projects. Adoption of tranches would raise the question of how much capacity to procure for each. The Authority could set aside a fixed amount to procure from each tranche, procuring all projects priced below avoided costs, whether solar-only or paired solar and storage, until the budget caps are reached. Alternatively, the Authority could first procure paired solar and storage projects, then accept solar-only projects until the budget caps thresholds are met. OCC recommends against fixing allocations for any tranches at this time. Once actual bids are available, the Authority could then compare pricing across categories and decide whether the differences warrant different treatments. G. Whether the EDCs should have discretion to adjust the targeted period for individual projects to align with specific system demands OCC does not oppose giving the EDCs some discretion to adjust the targeted period for individual projects, particularly where an EDC is targeting specific constrained locations. Massachusetts offers such an example, where utilities have sought to increase load between 11:00 AM and 3:00 PM to absorb excess solar generation near certain substations. 15 Similar discretion could be exercised in Connecticut, pursuant to published and standardized criteria. Without that structure, project-specific adjustments risk inconsistent treatment across the EDCs and potentially complicate the bid comparison upon which competitive solicitation relies. Any adjustments should, therefore, be disclosed in the annual program review.16 15 Massachusetts Energy Efficiency Advisory Council, ConnectedSolutions Update, slide 11, https://maeeac.org/wp-content/uploads/Connected-Solutions-Update-For-Posting-v25523139.pdf 16 OCC Comments, Feb. 4, 2026
  2. Page 7 of 15

    H. Relevant operational aspects and lessons learned from similar programs in other jurisdictions, such as Hawaii and Nevada OCC is not aware of any state that requires a competitive bidding process for both solar and storage. There are examples of solar-only competition, but the battery programs known to OCC use a standard offer approach. OCC recommends that the Authority treat the experience of standard offer storage programs elsewhere as informative on potential program mechanics, including how designated periods are defined, how performance is measured, and how compliance is verified. Those programs may help inform compensation levels, which should be capped using Connecticut-specific avoided costs.17 In this section, OCC offers some preliminary findings from other jurisdictions but notes that none of these programs serve as a true analogue to Connecticut’s NRES or SCEF programs. The salient difference is that most of the customer-facing DER programs described use tariffs or administratively determined incentive structures rather than selecting each participating project through a competitive solicitation. i. Summary of Lessons Learned from Jurisdictional Practices • All three states in this section value energy exports at less than retail rates. • The export rates in other states generally provide incentives to optimize storage charge and discharge through shorter netting intervals and distinct compensation structures for self-consumption and export. • Compensation rates based on $/kWh can appropriately incent storage without $/kW compensation. • Administratively-set, regularly updated adjustment factors can be used to approximate export forecasts, simplifying developer bids made under netting programs. ii. Hawaii Hawaii has adopted a multi-part payment framework by recognizing the value of energy exports and battery performance individually. The Hawaii Public Utilities Commission launched 17 Id
  3. Page 8 of 15

    its Smart DER and Bring Your Own Device (“BYOD”) tariffs in April 2024.18 Under Smart DER, exported energy receives time-varying compensation, with higher rates during the evening peak and lower rates during solar-heavy daytime hours. BYOD provides participating battery customers with additional compensation for providing grid services. The structure is conceptually similar to the proposed MPF for Connecticut, even though the programs are not direct procurement analogues. Smart DER puts the time signal in the $/kWh export rate, while BYOD separately recognizes the ability of a battery to provide dependable power when needed. Under the initial BYOD Level 1 design, participants committed a specified amount of battery capacity for a two-hour daily period.19 For example, a customer could receive Smart DER compensation for energy exported during the evening peak while separately receiving BYOD compensation for committing a specified amount of battery capacity during a two-hour period. This provides one instance of treating the value of delivered energy and the value of dependable battery capability as separate products rather than trying to capture both in one single payment. Hawaii’s implementation also highlights several operational issues that can affect whether compensated battery capacity delivers the intended system value. Hawaiian Electric found that some batteries participating in the predecessor Battery Bonus or Scheduled Dispatch Program did not always operate as expected. Certain systems shifted into manufacturercontrolled “Storm Watch” charging during severe weather, while some could only begin scheduled discharge at 15-minute increments. Hawaiian Electric also used AMI data to identify non-performing systems, directed 50 customers 20 to correct performance, and applied monthly penalties where continued noncompliance warranted them. All identified customers had returned to compliance by the end of 2024. Hawaii supports separating energy value from batteryperformance value but highlights that payment design is only one part of ensuring batteries perform as intended. Dispatch precision, metering, device controls, verification, and treatment of 18 Public Utilities Commission of The State Of Hawaii, Docket No. 2019-0323, Summary of Instituting a Proceeding to Investigate Distributed Energy Resource Policies Pertaining to the Hawaiian Electric Companies https://puc.hawaii.gov/wp-content/uploads/2023/12/DPS-Phase-3-Decision-and-Order-Summary.pdf ,p. 1-2, April 1, 2024 19 Id, p. 2-3 20 Hawai‘i Public Utilities Commission, Docket No. 2019-0323, Instituting a Proceeding to Investigate Distributed Energy Resource Policies Annual CER Program Review Report, https://www.hawaiianelectric.com/documents/products_and_services/customer_renewable_programs/custo mer_energy_resource_equipment/2024_annual_cer_report.pdf , March 31, 2025
  4. Page 9 of 15

    non-performance determine whether promised capacity actually provides system value. Those lessons are particularly relevant to the discussions in Connecticut regarding compensation of storage as a capacity resource. One important distinction is that, while Hawaii’s Smart DER and BYOD programs are tariff-based, Hawaii does use competitive procurement for renewable generation, storage, and aggregated DER grid services.21 However, those procurements do not provide a direct example of comparing individual solar-only and solar-plus-storage projects under a tariff program like Connecticut’s proposed NRES and SCEF successors. iii. Nevada Nevada’s practices regarding export rate compensation and netting intervals provide useful information for Connecticut’s NRES Netting discussion. Under NRS § 704.7732, qualifying customer-generators receive a credit for excess electricity, with the credit based on a percentage of the retail rate that would otherwise apply when the electricity is exported. The credit decreases as capacity thresholds are reached. The statutory tiers stepped down the credit from 95% to 88%, then to 81%, and ultimately to 75%22 of the applicable retail rate. Tier 4, at 75% of the retail rate, is now the open tier with no capacity limit.23 Nevada’s approach to compensation creates a distinction between self-consumption and exports.24 Solar used onsite avoids a retail-priced purchase, while excess generation sent to the grid receives the discounted export credit. Storage can therefore have value even without a separate battery incentive by allowing customers to retain solar generation for later use rather than exporting it below the retail rate. Nevada also illustrates why the netting interval matters separately from the export rate. Beginning October 1, 2025, new net-metering customers in northern Nevada are billed using 15- 21 State of Hawaii Public Commission, RFP DOCKET NO. 2017-0352, Renewable Energy Procurement https://puc.hawaii.gov/energy/renewable-energy-procurement/ 22 NRS 704.7732, Utility required to provide customer-generator with credit for excess electricity; amount of credit; monthly report of cumulative installed capacity of certain net metering systems https://www.leg.state.nv.us/nrs/nrs23 Public Utilities Commission of Neveda, Net Metering in Nevada https://www.puc.nv.gov/renewables/net-metering-in-nevada/ 24 NRS 704.7732, https://www.leg.state.nv.us/nrs/nrs-704.html#NRS704Sec7732
  5. Page 10 of 15

    minute netting.25 Within each interval, NV Energy compares generation and consumption, and any remaining export is credited at 75% of the applicable retail rate. The distinction matters even though the nominal export rate remains 75%. Under broader netting (e.g., monthly netting), generation produced earlier may offset consumption occurring later. Shorter-interval netting reduces that opportunity, meaning more generation can be treated as an export while later consumption is purchased at retail rates. For example, if a customer exports 10 kWh of solar generation in the afternoon and later consumes 10 kWh in the evening, monthly netting may allow those amounts to offset. Under 15-minute netting, the afternoon generation may instead receive the 75% export credit while the evening consumption is purchased at the full retail rate. A battery could reduce that difference by storing the afternoon generation for later use. Nevada law also recognizes the connection between time-varying rates and storage. NRS § 704.772526 supports greater use of energy storage by providing time-variant rate structures with rates that vary based on when electricity is consumed from or supplied to the grid. Nevada shows that below-retail rate compensation and shorter-interval netting can and likely should be considered together. The export rate determines the value of an exported kWh, while the netting interval determines whether that kWh is treated as an export. iv. California California provides a different model for recognizing the time-dependent value of solar and storage. Under the Net Billing Tariff (“NBT”), adopted by the California Public Utilities Commission (“CPUC”) in Decision 22-12-056,27 exported electricity is no longer compensated at the full retail rate. Instead, export credits are based on values derived from the CPUC Avoided Cost Calculator (“ACC”), which reflects costs such as energy, generation capacity, transmission 25 NVEnergy, Net Metering and Energy Storage Interconnection Handbook https://www.nvenergy.com/publish/content/dam/nvenergy/brochures_arch/cleanenergy/handbooks/SolarGenerations -Handbook.pdf ,p. 21. 26 NRS 704.7725, Utility required to submit request to Commission to establish time-variant rate schedule designed to expand use of energy storage systems; review and approval or denial of request by Commission https://www.leg.state.nv.us/nrs/nrs-704.html#NRS704Sec7725 27 PUBLIC UTILITIES COMMISSION OF THE STATE OF CALIFORNIA, Order Instituting Rulemaking to Revisit Net Energy Metering Tariffs Pursuant to Decision 16-01-044, and to Address Other Issues Related to Net Energy Metering. https://docs.cpuc.ca.gov/PublishedDocs/Published/G000/M500/K043/500043682.PDF , December 15, 2022, p. 59-60
  6. Page 11 of 15

    and distribution capacity, and other system benefits. The resulting export values vary by month and hour.28 This approach places much of the storage incentive directly into the energy price. Solar exports during the middle of the day generally receive lower compensation, while exports during evening periods may receive significantly more compensation. For example, a customer may receive relatively little for exporting excess solar generation during the middle of the day, but a battery allows that same energy to be stored and exported later in the evening when the applicable export value is higher. The price signal therefore rewards not just the amount of energy exported, but the time it is delivered to the grid. CPUC’s 2025 Grid Modernization Report29 states that the share of new behind-the-meter solar installations paired with storage increased from roughly 13% to 69% 30 following implementation of the NBT. CPUC attributes the new framework to creating more granular price signals for shifting solar production into higher-value hours. California also provides useful considerations for the NRES Netting discussion. The NBT uses no temporal netting; imports are charged at retail rates while exports are separately credited at the applicable export rate. 31 CPUC recognized that this makes prospective project savings harder to estimate because the result depends on the timing of customer load and solar production. Rather than requiring perfect forecasts, CPUC adopted standardized netting adjustment factors that developers can use as a proxy when estimating customer exports under no-netting treatment. Those factors are updated annually. 32 California offers two potential takeaways. First, time-dependent system value can be reflected directly through granular $/kWh compensation rather than through a separate $/kW payment. Second, its adjustment-factor methodology provides a useful precedent for the forecasting problem created by instantaneous netting. Connecticut could similarly consider standardized assumptions or profiles when evaluating NRES Netting bids. 28 Id, December 15, 2022, pp. 141-142 California Public Utilities Commission, California’s Grid Modernization Report To The Governor and Legislature, https://www.cpuc.ca.gov/-/media/cpuc-website/divisions/office-of-governmental-affairsdivision/reports/2025/californias-grid-modernization-report-2025--volume-i.pdf , December 2025, pp. 10 30 Id, p. 10 31 Public Utilities Commission of The State Of California, Item# 23 (Rev. 1) Agenda Id# 22685, Energy Division Resolution E 5324 https://docs.cpuc.ca.gov/PublishedDocs/Published/G000/M535/K542/535542694.PDF ,p. 2-4 32 Public Utilities Commission of The State Of California, Order Instituting Rulemaking to Revisit Net Energy Metering Tariffs Pursuant to Decision 16-01-044, and to Address Other Issues Related to Net Energy Metering https://docs.cpuc.ca.gov/PublishedDocs/Published/G000/M500/K043/500043682.PDF ,p. 3-4 29
  7. Page 12 of 15

    II. NRES SUCCESSOR PROGRAM NETTING TARIFF I. Instantaneous netting and export compensation below the retail rate OCC supports netting on an instantaneous basis.33 Instantaneous netting allows for payments that more accurately reflect the value of the generation provided, which matters especially when solar is paired with storage. OCC supported the same transition in the residential context for the same reasons: monthly kWh-based netting lets consumers offset high-cost peak consumption with low-value midday exports.34 Instantaneous netting also depends on interval metering. OCC continues to recommend that the Authority confirm AMI readiness by service territory and customer class and consider transitional or hybrid approaches where the enabling infrastructure is not yet uniformly available.35 OCC supports an export rate set below the full retail rate. The full retail rate is likely well above the value of the generation provided, and reducing compensation below this value appropriately recognizes cost causation principles.36 Export rates should be set using avoided costs as a price cap, and the EDCs should be required to estimate and provide the average hourly avoided costs used to determine that cap. J. Implementation of instantaneous netting within a continued competitive solicitation process Under an instantaneous netting program, procuring solar and storage generation within a competitive solicitation process is challenging. The EDCs may need to compare proposals that contain a variety of different hourly prices and different hourly generation profiles. The export generation profiles could vary significantly across bidders based on (1) the customer’s PV and storage system sizing relative to onsite loads, (2) incentives provided by the export tariff, (3) onsite consumption, and (4) demand response participation impacting onsite consumption. The 33 15-Minute increments may be considered as acceptable for instantaneous netting, if meter capabilities and utility billing infrastructure precludes measuring in shorter intervals. 34 Id p.2, (OCC “supports the transition from monthly to instantaneous netting, which better reflects real-time system conditions and reduces peak cost shifting,” whereas monthly netting “allowed customers to offset high-cost peak consumption with low-value midday exports, increasing cost for non-participants and decreasing grid benefits”). 35 OCC Written Comments, p. 2–3, Feb. 4, 2026 (noting concern regarding “Advanced Metering Infrastructure (AMI) readiness and uneven deployment across service territories” and recommending that the Authority “consider transitional or hybrid approaches until enabling infrastructure is uniformly available”, citing Docket No. 24-10-04; Docket No. 17-10-46RE04; Docket No. 11-02-03. 36 OCC Written Comments, Docket No. 25-02-14, p. 1, July 31, 2025
  8. Page 13 of 15

    customer export profiles might change not only daily, but also weekly or monthly. The export profile of a school with multiple vacations including summer vacations, for example, differs from that of a business with a consistent consumption pattern seven days a week, 365 days a year. OCC recommends the Authority adopt a simplified bidding strategy as follows. First, the EDCs prepare common time-differentiated per-MWh price caps based on hourly avoided costs. Then, competitive bids are structured as an overall single-value percentage discount from the EDC-established price caps. This would eliminate the need to forecast bidders’ export and onsite-consumption behavior. OCC believes that bidding projects are best equipped to anticipate their own export and onsite consumption behaviors and account for them in their bid formulations. The Authority could choose a level of granularity for the time-differentiated price caps that balances precision with simplicity. For example, price caps could vary by season or by month, and within each period they could be set hourly or on a coarser on-peak and off-peak basis. However, the more that the price caps are aggregated, the greater the chance that they deviate from avoided costs. There is also a question of whether the price caps, and therefore any associated bids, should change each year of the program term to reflect changes in future avoided costs. Price caps that are set for the full program term are more likely to deviate from actual avoided costs. Under OCC’s proposed approach, all bids would retain the same relative hourly price curve since they would be proportional to the EDC’s hourly avoided cost values. As NRES is designed to provide a net benefit to the grid and to ratepayers, the relative hourly value of exports should be derived from grid value rather than supply-side costs. Ratepayers are agnostic about export and onsite consumption profiles under a net-billing tariff as both behaviors provide cost-effective value to the grid. Single-value percentage discount bids from the set price caps enable a straightforward bid evaluation process where the bids with the largest discount values are awarded. One project may bid a 5% discount off established price caps, for example, while a more competitive project may bid a 10% discount. Thus, the projects that export energy at the most cost-effective rate at any hour will be selected.
  9. Page 14 of 15Match

    III. RESIDENTIAL INCENTIVE ADDER IMPLEMENTATION OCC believes that further analysis is needed to determine the most cost-effective approach to administer residential incentive adders, as previous increases in residential incentive adders have not clearly demonstrated a corresponding increase in residential solar deployment rates. The design and magnitude of the adder should be informed by a benefit-cost analysis and rate and bill impact analysis to mitigate the risk of overcompensating participating customers. Such analysis should also consider the effectiveness of economically distressed municipality adders in reaching the intended customers in those municipalities.37 To eliminate the need for dedicated production meters, the Authority proposes two alternative methods of administering residential incentive adders: (1) a fixed per-kW incentive and (2) a per-kWh incentive based on energy exports recorded at the revenue meter. OCC does not support the fixed per-kW incentive because it would not accurately reflect the system’s performance and benefits contributed to the grid, unless payouts are predicated on the system having non-zero export generation. Between the two options, OCC prefers administering the residential incentive adders using a per-kWh incentive based on energy exports. This approach would provide compensation that is more aligned with the value of the grid benefits. OCC is concerned, however, that this method would discourage onsite consumption of produced energy. If PURA could tie the per-kWh export incentive to a peak window, that may mitigate some of this concern. Otherwise, OCC generally continues to favor residential incentive adders based on total production, with transparent customer pricing and strict disclosure requirements so that participants know the incentives.38 OCC also cautions against the use of one-time upfront incentives as they expose ratepayers to unnecessary risk. An upfront incentive was administered in the ESS program until 2025 and has since been significantly reduced due to the unrecoverable cost of recipient nonperformance. 39 37 Eversource Written Comments, Docket No. 26-06-04, p. 10, August 26, 2026. OCC Written Comments, Docket No. 25-02-14, p. 3, May 9, 2025 (emphasizing “the importance of transparent customer pricing and a simple and accessible application process,” together with “stringent customer disclosure requirements that ensure customers are receiving accurate information and are made aware of available adders and federal incentives”) 39 Final Decision, Docket No. 25-08-05, p. 9, December 16, 2025. 38
  10. Page 15 of 15

    IV. CONCLUSION OCC appreciates the opportunity to submit these comments and thanks the Authority and stakeholders for their continued work on this docket. Respectfully submitted, STATE OF CONNECTICUT OFFICE OF CONSUMER COUNSEL CLAIRE E. COLEMAN CONSUMER COUNSEL By: /s/ Paschaline Poku Paschaline Poku, Esq. Staff Attorney Alex Wang Economist Anubhav Kumaria Research Analyst CERTIFICATE OF SERVICE I do hereby certify that on this day the foregoing document was filed with the Public Utilities Regulatory Authority, and copies thereof were served upon each person designated on the official service list in this proceeding in accordance with R.C.S.A. § 16-1-15. Dated at New Britain, Connecticut this 2nd day of October 2026. /s/Paschaline Poku Paschaline Poku, Esq. Commissioner of the Superior Court

As listed on the current system

Written Comments - 10/02/2026 [26-06-04] (Office Of Consumer Counsel)