Compliance Filing, Order No. 1

5. Annual Compliance Filings – Additional Filings (Program Materials)

Compliance filingFiled by Avangrid13 files
Part of docket 26-08-01Open
  • Electric
2026 Clean and Renewable Energy Program Data and Report

Files13

Search terms highlighted
Eversource rate increase is on 8 pages of the text below, highlighted. Go to the first matchClear highlighting
Words on different pages
Words on different pages
Words on different pages

Text of 2026-11-16 UI Attachment 3 - Shared Clean Energy Facility Program Program Materials #26-08-01.pdf

Extracted from the file · 147 pages · 342,741 characters

8 pages match
  1. Page 114 of 203

    The United Illuminating Company Docket No. 26-08-01 UI Attachment 5 ESS Program Manual and Additional Information Page 114 of 203 Decommissioning Contact Provide the contact information for the party responsible for decommissioning: Contact Full Name _________________________________________________ Company Name ___________________________________________________ Contact Email _____________________________________________________ Address Line 1 _________________________________Address Line 2_______________ City ______________________________ State ________ ZIP ______________ Check below: ☐ I attest that the fossil fuel generator described above will be fully decommissioned and not resold or redeployed. ☐ I attest that I will make reasonable effort to ensure that materials are recycled or safely disposed of, and that any hazardous materials (i.e.: fuel, e-waste) are disposed of in accordance with all applicable laws and environmental regulations. ☐ I attest that I will provide the Program Administrators (via the Eligible Contractor or Third-Party Owner) with documentation confirming the decommissioning and safe disposal of the fossil fuel generator, including but not limited to photographs, inspection reports, invoices, and/or receipts. Upfront Incentive funds will not be disbursed to the Eligible Contractor or Third-Party Owner until complete documentation of decommissioning has been demonstrated to the Program Administrators. Customer Signature ______________________________________ Customer Contact Full Name _______________________________ Customer Company _______________________________________ 113
  2. Page 115 of 203

    The United Illuminating Company Docket No. 26-08-01 UI Attachment 5 ESS Program Manual and Additional Information Page 115 of 203 Appendix G: Direct Payment Beneficiary Form Direct Payment Beneficiary Form For Energy Storage Solutions Performance Incentives By default, eligible seasonal Active Dispatch Performance Incentives earned by Battery Energy Storage Systems (BESS) participating in Energy Storage Solutions are paid to the utility account holder associated with the BESS. Alternatively, customers may direct Performance Incentives to another party as stated below. This form is optional and should only be completed by Energy Storage Solutions customers who wish to designate a portion or all of their Energy Storage Solutions Active Dispatch Performance Incentives to another party. Eversource or United Illuminating will direct the seasonal Active Dispatch Performance Incentives earned by your Battery Energy Storage System (BESS) based on the information entered below. *All Fields are Required HOST CUSTOMER Host Customer First Name Host Customer Last Name Host Customer Address Line 1 Host Customer Address Line 2 Host Customer City / State / Zip Host Customer Utility Host Customer Utility Account Holder Name Host Customer Utility Account Number Eversource UI PAYMENT BENEFICIARY Third-Party System Owner Financial Institution Payment Beneficiary Type (Select One) Other: ____________________________________ Payment Beneficiary Company Name Payment Beneficiary Address Payment Beneficiary City/State/Zip Payment Beneficiary Phone Payment Beneficiary Email Has a W-9 Form for this Payment Beneficiary been provided previously? Yes No 114
  3. Page 116 of 203

    The United Illuminating Company Docket No. 26-08-01 UI Attachment 5 ESS Program Manual and Additional Information Page 116 of 203 By completing and signing this form, Host Customer consents that: HOST CUSTOMER WILL RECEIVE ____% OF SEASONAL PERFORMANCE INCENTIVE PAYMENTS PAYMENT BENEFICIARY WILL RECEIVE ____% OF SEASONAL PERFORMANCE INCENTIVE PAYMENTS PAYMENTS WILL BE MADE (CHECK ONE): ___ ONCE ANNUALLY ___ TWICE ANNUALLY Host Customer Signature _____________________________________________ Host Customer Full Name _____________________________________________ Date ______________ Payment Beneficiary Representative signature is not required unless box below is checked. Check this box only if Host Customer is changing Seasonal Performance Incentive Payment percentages from a previous submission. Payment Beneficiary Representative signature is required only if this form is being resubmitted to modify a previously submitted version. Payment Beneficiary Representative Signature _____________________________________ Payment Beneficiary Representative Full Name _____________________________________ Date ______________ 115
  4. Page 117 of 203

    The United Illuminating Company UI Attachment 5 Docket No. 26-08-01 ESS Program Manual and Additional Information Connecticut Energy Storage Solutions – Year 6 Evaluation, Measurement, and Verification (EM&V) Report Prepared for: Submitted by: Customized Energy Solutions Ltd. 1528 Walnut St, 22nd floor Philadelphia, PA 19102 August 1, 2026 Page 117 of 203
  5. Page 118 of 203

    The United Illuminating Company UI Attachment 5 Docket No. 26-08-01 ESS Program Manual and Additional Information Page 118 of 203 Table of Contents Executive Summary................................................................................................................ 4 1. Introduction .................................................................................................................... 9 1.1. Program Background and Objectives ....................................................................... 9 1.2. Overview of Program Design .................................................................................. 10 1.3. Annual Report Requirements and Objectives ......................................................... 15 1.4. Program Metrics Overview .................................................................................... 15 2. Data Sources and Data Review ...................................................................................... 15 2.1. Data from Program Administrators ........................................................................ 16 2.2. Telemetry Data ..................................................................................................... 16 2.3. Data Review ......................................................................................................... 17 2.4. Findings and Recommendations ........................................................................... 18 3. Program Tracking Metrics .............................................................................................. 18 3.1. Program Tracking Categorization ........................................................................... 18 3.2. Program Tracking Metrics ...................................................................................... 21 3.3. Findings and Recommendations ........................................................................... 42 4. Program Evaluation Metrics ........................................................................................... 43 4.1. Program Evaluation Metrics................................................................................... 43 4.2. Findings and Recommendations ........................................................................... 59 5. Benefit-Cost Analysis .................................................................................................... 60 5.1. Benefit-Cost Model – Design and Use .................................................................... 60 5.2. Benefit-Cost Model Inputs .................................................................................... 63 5.3. BCA Metrics ......................................................................................................... 70 5.4. Findings and Recommendations ........................................................................... 75 6. Key Findings and Recommendations ............................................................................. 75 6.1. Key Findings ......................................................................................................... 76 6.2. Recommendations ............................................................................................... 76 List of Tables Table ES-1. Count of Participants by Project Status, Customer Type, and Utility ........................ 6 Table ES-2. Total Power Capacity (MW) by Project Status ......................................................... 7 Table ES-3. Progress Made Toward Program Capacity Goals ..................................................... 8 Table 1-1. ESS MW Goals by Tranche ..................................................................................... 10 Table 1-2. Residential Upfront Incentive Levels (Legacy) ........................................................ 11 Table 1-3. Commercial Upfront Incentive Levels (Legacy)....................................................... 11 Table 1-4. Updated Passive Dispatch Scoring Methodology .................................................... 12 Table 1-5. Construct 5 Enrollment Incentives ........................................................................ 13 Table 1-6. Construct 5 Performance Incentives...................................................................... 14 Table 1-7. Active Dispatch Parameters .................................................................................. 14 Table 2-1. Data Availability and QC Findings and Recommendations ...................................... 18 Table 3-1. Project Stage Categories ....................................................................................... 19 Table 3-2. Residential Project Categories .............................................................................. 20 Table 3-3. Commercial Project Categories ............................................................................ 21 Table 3-4. ESS Participants (Number and Percentage of Total) ................................................ 22 Table 3-5. Share of Low-Income & Underserved Residential Participants ................................ 23 1|Pa ge
  6. Page 119 of 203

    The United Illuminating Company UI Attachment 5 Docket No. 26-08-01 ESS Program Manual and Additional Information Page 119 of 203 Table 3-6. Indication of Participation in the ISO-NE FCM for C&I Participants .......................... 24 Table 3-7. Project Approval Rates .......................................................................................... 25 Table 3-8. Average Days to Approve and Complete Project Application ................................... 26 Table 3-9. Share of Energy Storage Paired with PV .................................................................. 27 Table 3-10. Total Allocated Power Capacity (kW) by Project Status .......................................... 28 Table 3-11. Total Allocated Energy Capacity (kWh) by Project Status ....................................... 29 Table 3-12. Average Project Size ............................................................................................ 30 Table 3-13. Number of Systems and Batteries by Manufacturer .............................................. 31 Table 3-14. Number of Approved or Completed Applications by Contractor ............................ 32 Table 3-15. Program Administrative Costs ($) ......................................................................... 34 Table 3-16. Estimated Upfront Incentives Encumbered by Project Status ($) ........................... 35 Table 3-17. Average Total Project Upfront Incentive for Legacy Projects ($/Participant) ............ 36 Table 3-18. Average Total Project Upfront Incentive for Construct 5 Projects ($/Participant) ..... 37 Table 3-19. Average Project Cost ($/Participant) ..................................................................... 38 Table 3-20. Total Installed Costs Allocated to Participants by Project Status ($) ...................... 39 Table 3-21. Average Total Energy Storage System Costs ($/kWh and $/kW) ............................. 40 Table 3-22. Average Battery-Only Costs ($/kWh and $/kW) ..................................................... 42 Table 3-23. Program Tracking Metrics Findings and Recommendations .................................. 42 Table 4-1. Residential Program Evaluation Metrics by Active Event Date-Summer 2025 Season 45 Table 4-2. Residential Program Evaluation Metrics by Active Event Date-Winter 2025-2026 Season ................................................................................................................................ 47 Table 4-3. Residential Program Evaluation Metrics by Passive Event Date Summer 2025 ......... 47 Table 4-4. C&I Program Evaluation Metrics by Active Event Date - Summer 2025 Season ......... 49 Table 4-5. C&I Program Evaluation Metrics by Active Event Date – Winter 2025-2026 Season .. 51 Table 4-6. C&I Program Evaluation Metrics by Passive Event Date Summer 2025 ..................... 52 Table 4-7. Evaluation Metrics by Seasonal Peak Event ............................................................ 54 Table 4-8. Peak Targeting Percentages ................................................................................... 55 Table 4-9. Active Events on Top 30 Load Days by Season ........................................................ 56 Table 4-10. Battery Performance Metric ................................................................................. 57 Table 4-11. Emissions Evaluation Metrics .............................................................................. 58 Table 4-12. Outage Metrics ................................................................................................... 58 Table 5-1. BCA Cost Tests ..................................................................................................... 62 Table 5-2. Project Size and Cost Assumptions ....................................................................... 64 Table 5-3. Residential and C&I Legacy Upfront Incentive Levels ($/installed kWh) ................... 65 Table 5-4. Assumed Residential and C&I Enrollment Incentive Levels ($/installed kWh) .......... 65 Table 5-5. Average System Max Expected Peak Reduction ...................................................... 67 Table 5-6. Program Deployment Targets (MW) ........................................................................ 67 Table 5-7. Projected Program Enrollment (MW) ...................................................................... 68 Table 5-8. Actual (through 2025) and Projected Program Administration Costs ($) ................... 69 Table 5-9. Benefits Inputs Sources ........................................................................................ 70 Table 5-10. BCA Findings and Recommendations .................................................................. 75 List of Figures Figure 3-1. Average Total Energy Storage System by Application Year ($/kWh) .......................... 41 Figure 5-1. Overall Program BCA ........................................................................................... 72 2|Pa ge
  7. Page 120 of 203

    The United Illuminating Company UI Attachment 5 Docket No. 26-08-01 ESS Program Manual and Additional Information Page 120 of 203 Figure 5-2. Residential Program BCA ..................................................................................... 73 Figure 5-3. C&I Program BCA ................................................................................................ 74 Figure 5-4. Overall Program BCA - AESC Counterfactual 6 ...................................................... 75 3|Pa ge
  8. Page 121 of 203Match

    The United Illuminating Company UI Attachment 5 Docket No. 26-08-01 ESS Program Manual and Additional Information Page 121 of 203 Executive Summary The Energy Storage Solutions (ESS) program, administered by the Connecticut Green Bank, Eversource, and the United Illuminating Company (UI), collectively known as the Program Administrators (PAs), provides incentives to support the development and beneficial operation of behind-the-meter (BTM) energy storage systems in Connecticut. In this report, filed in Docket No. 26-08-05, the Annual Energy Storage Solutions Program Review – Year 6 proceeding, Customized Energy Solutions, Inc. (CES) provides an evaluation of the Program, including program enrollment through June 30, 2026, battery performance through March 31, 2026, benefit cost analysis, and resulting findings and recommendations. This report is the first to be issued since the implementation of Construct 5, as directed by PURA in its Final Decision in Docket No. 26-08-05 – these changes are reflected in the report. Year 6 represents a critical transition period for the ESS Program, reflecting both significant growth in residential deployment and the implementation of Construct 5 program modifications directed by PURA. It is challenging to draw conclusions about the implications of the transition to Construct 5, given how recently it was implemented. At the same time, some early indications are concerning: for example, as of the completion of this report, no new commercial applications have been filed under Construct 5. Given how much commercial projects are projected to contribute to the programs’ overall MW deployment goals, any slowdown in the commercial pipeline will challenge the ability of the program to achieve these program-level goals. As of June 30, 2026, the ESS Program has enrolled 1,885 participants (see Table ES-1), up from 1,000 as of the same date last year. The number of completed projects has nearly tripled, from 462 to 1,398, while the number of approved projects has decreased modestly, from 533 to 487. For residential projects, this decrease is attributable to the number of projects reaching complete status exceeding the number of new enrollments; for commercial projects, canceled projects also contribute to the decrease. Eversource territory accounts for roughly 81% of participants (1,553) and United Illuminating (UI) territory for roughly 19% (370); UI's share is driven substantially by a single affordable multifamily hybrid project, counted as 161 participants. On a capacity basis, submitted, approved, and completed projects total 155.4 MW, of which 21.8 MW (14%) is residential, and 133.6 MW (86%) is C&I. The MW volume of completed projects has also roughly tripled, driven almost exclusively by residential projects. Measured against the Program's 2030 capacity goals, completed residential capacity (17.6 MW) represents 11.7% of the 150 MW residential goal, while completed C&I capacity (1.3 MW) represents just 0.3% of the 430 MW C&I goal, reflecting the continued stagnation of the commercial pipeline discussed below. The performance of enrolled projects during program events also continues to improve, as outlined in Section 4. The Program Administrators have worked with OEMs to substantially improve residential battery performance, yielding improved participation rates, higher state of charge at the beginning of events, and increased percent of available energy discharged during the event. Because performance is driven largely by how OEMs respond to dispatch signals, targeted improvement with a small number of high-volume OEMs has meaningfully improved program-wide results. These improvements are particularly important because the value of distributed battery storage depends not only on installed capacity, but also on the ability of enrolled resources to reliably respond during periods of system need. These improvements have been seen in both active and passive event performance. The Program Administrators have also made progress improving the quality of telemetry data, though data quality challenges, for both enrollment and telemetry data, persist. Continued improvement in telemetry accuracy and data completeness will remain important to ensure reliable performance verification and accurate 4|Pa ge
  9. Page 122 of 203

    The United Illuminating Company UI Attachment 5 Docket No. 26-08-01 ESS Program Manual and Additional Information Page 122 of 203 quantification and reporting of program benefits. The program continues to evolve with the rollout of the Construct 5 incentive structure, effective April 1, 2026. CES also updated the Program's benefit-cost analysis (BCA). The overall program Ratepayer Impact Measure (RIM) is 1.55, indicating the program continues to provide a net benefit to ratepayers, though this is a modest decrease from the BCA analysis filed in last year’s EM&V report (1.69), driven primarily by changes in projected MW deployment and assumed project costs. The residential BCA shows improvement across all tests: the residential RIM increased to 1.18 and the Participant Cost Test (PCT) improved to 0.81, driven principally by changes (namely, improvements) in projected performance during active events. As with any prospective analysis, the results remain sensitive to assumptions regarding future battery deployment, event performance, avoided system costs, and project economics. Several challenges warrant continued attention. The commercial (C&I) pipeline remains stymied by both a dearth of new applications and the slow pace of approved projects reaching commercial operation, leaving the program far short of its C&I capacity goal. The program also continues to fall short of its target of 40% participation by residential Low-Income and Underserved customers; a single affordable multifamily project accounts for a significant share of the Low-Income participants counted to date. Given current deployment trends, achieving the Program’s 580 MW by 2030 target may require additional program design modifications, market interventions, or other adjustments. At the same time, any additional changes must be weighed against the value of program stability. Overall, Year 6 demonstrates continued progress in residential adoption, meaningful improvements in battery performance during dispatch events, and continued evidence of program cost-effectiveness. However, achieving the Program's long-term objectives will require increased C&I deployment, continued improvement in battery performance and telemetry quality, broader participation among Low-Income and Underserved customers, and successful implementation of Construct 5 enhancements. The tables below, which consider cumulative program capacity through June 30, 2026, provide summary enrollment statistics. More detailed discussion of evaluated metrics, findings, and recommendations is provided in the body of this report. 5|Pa ge
  10. Page 123 of 203

    The United Illuminating Company UI Attachment 5 Docket No. 26-08-01 ESS Program Manual and Additional Information Page 123 of 203 Table ES-1. Count of Participants by Project Status, Customer Type, and Utility Utility Eversource Customer Type Project Status as of June 30, 2026 Submitted Approved Completed Total 23 (10\0\13) 139 (1\106\32) 1055 (132\612\311) 1217 (143\718\356) Residential Standard 133 (7\103\23) 175 (11\134\30) Residential Underserved 9 (4\0\5) 33 (0\31\2) 69 (0\56\13) 101 (0\87\14) Residential Low-Income 0 (0\0\0) 32 (0\31\1) 32 (14\0\18) 204 (1\168\35) 1257 (139\771\347) 1493 (154\939\400) Residential Subtotal 0 (0\0\0) 8 (0\8\0) 4 (0\4\0) 12 (0\12\0) Small C&I 0 (0\0\0) 17 (0\17\0) 0 (0\0\0) 17 (0\17\0) Medium C&I 0 (0\0\0) 28 (0\28\0) 3 (0\3\0) 31 (0\31\0) Large C&I 0 (0\0\0) 53 (0\53\0) 7 (0\7\0) 60 (0\60\0) C&I Subtotal 32 (14\0\18) 257 (1\221\35) 1264 (139\778\347) 1553 (154\999\400) Eversource Subtotal 5 (4\0\1) 19 (0\18\1) 97 (30\65\2) 121 (34\83\4) Residential Standard Residential Underserved 1 (0\0\1) 27 (0\26\1) 34 (11\22\1) 62 (11\48\3) Residential Low-Income 0 (0\0\0) 175 (0\175\0) 0 (0\0\0) 175 (0\175\0) Residential Subtotal 6 (4\0\2) 221 (0\219\2) 131 (41\87\3) 358 (45\306\7) 0 (0\0\0) 2 (0\2\0) 0 (0\0\0) 2 (0\2\0) Medium C&I 0 (0\0\0) 2 (0\2\0) 3 (0\3\0) 5 (0\5\0) Large C&I 0 (0\0\0) 5 (0\5\0) 0 (0\0\0) 5 (0\5\0) United IlluminatingSmall C&I C&I Subtotal 0 (0\0\0) 9 (0\9\0) 3 (0\3\0) 12 (0\12\0) 6 (4\0\2) 230 (0\228\2) 134 (41\90\3) 370 (45\318\7) UI Subtotal Total Number of Residential Participants Total Number of C&I Participants 38 (18\0\20) 425 (1\387\37)1388 (180\858\350)1851 (199\1245\407) Total Number of Participants 38 (18\0\20) 487 (1\449\37)1398 (180\868\350)1923 (199\1317\407) 0 (0\0\0) 62 (0\62\0) 10 (0\10\0) 72 (0\72\0) Note: Values in parentheses are reported as Only Active participants \ Active & Passive participants \ Construct 5 participants, respectively. “Total” column represents the sum of submitted, approved, and completed projects, excluding any cancelled and pipeline projects, as defined in Section 3.1.1. The hybrid project, detailed in Section 3.1.5, is counted as 161 participants under United Illuminating’s Residential Low-Income and 1 participant under United Illuminating’s Large C&I. All other applications are counted as one participant each. Note that the values in this and most tables in this report include projects transferred from ConnectedSolutions, as discussed in Section 3.2. Source: Customized Energy Solutions analysis of Connecticut Green Bank program tracking data through June 30, 2026. 6|Pa ge

Text of 2026-11-16 UI Attachment 5 - EV Program Materials and Additional Information #26-08-01.pdf

Extracted from the file · 2 pages · 6,256 characters

Text of 2026-11-16 UI Attachment 6 - Annual RPS Compliance Report - Cover Ltr #26-08-01.pdf

Extracted from the file · 2 pages · 3,261 characters

Text of 2026-11-16 UI Attachment 6 - Annual RPS Compliance Report RPS Template Exhibit A #26-08-01.xlsx

Sheet names, column headings and text cells; numbers left out

Text of 2026-11-16 UI Attachment 6 - Annual RPS Compliance Report RPS Template Exhibit B C and D #26-08-01.xlsx

Sheet names, column headings and text cells; numbers left out

Text of 2026-11-16 UI Attachment 6 - Annual RPS Compliance Report RPS Template Exhibit E #26-08-01.xlsx

Sheet names, column headings and text cells; numbers left out · first 300,000 characters

Text of 2026-11-16 UI Attachment 6 - Annual RPS Compliance Report RPS Template Exhibit F #26-08-01.pdf

Extracted from the file · 1 page · 528 characters

Text of 2026-11-16 UI Attachment 7 - Exhibit Y Ten Year Cost History - BETP-001 #26-08-01.xlsx

Sheet names, column headings and text cells; numbers left out

Text of 2026-11-16 UI Attachment 8 - CEOP-VRO Program Materials #26-08-01.pdf

Extracted from the file · 2 pages · 4,800 characters

As listed on the current system

Compliance Filings, 11/16/2026 [26-08-01] Order No.1 / Avangrid / 5. Annual Compliance Filings – Additional Filings (Program Materials)

This filing on the current system (opens in a new tab)