Compliance Filing, Order No. 1

5. Annual Compliance Filings – Additional Filings (Program Materials)

Compliance filingFiled by Avangrid13 files
Part of docket 26-08-01Open
  • Electric
2026 Clean and Renewable Energy Program Data and Report

Files13

Search terms highlighted
Eversource rate increase is on 8 pages of the text below, highlighted. Go to the first matchClear highlighting
Words on different pages
Words on different pages
Words on different pages

Text of 2026-11-16 UI Attachment 3 - Shared Clean Energy Facility Program Program Materials #26-08-01.pdf

Extracted from the file · 147 pages · 342,741 characters

8 pages match
  1. Page 52 of 203

    The United Illuminating Company Docket No. 26-08-01 UI Attachment 5 ESS Program Manual and Additional Information Page 52 of 203 replacing Fossil Fuel Generators, and Small Business Customers. Definitions and limitations for each customer class are defined below39. Table 12: Legacy Program Upfront Incentive Priority Customer Adder Upfront Incentive Adder Customer Category +25%: Non-Residential Small Business Critical Facilities Customers Replacing Fossil Fuel Generators Grid Edge +50%: Residential Grid Edge Customers on the Grid Edge Customers on the Grid Edge are defined as (1) the top ten percent of circuits with the highest number of outages per customer during major storms since July 1, 2012, and (2) the top ten percent of circuits with the longest outages due to major storms since July 1, 2012. A map of circuits that meet grid edge criteria can be found in the Program’s website. Critical Facilities As of January 1, 2024 Critical Facilities shall be defined by the revised definition according to Gen. Stat. § 16-243y(a)(2)40. EDCs will confirm applicant’s qualification as a critical facility as part of the application process. Commercial and Industrial Customers Replacing Fossil Fuel Generators This category applies to C&I customers who are replacing an existing fossil fuel generators with an energy storage system of comparable size. Customers must demonstrate their plan to decommission the fossil fuel generator(s) with a Decommissioning Plan. A template Decommissioning Plan is included in Appendix F. Decommissioning Plans are subject to review and approval by Program Administrators in order to qualify for the Upfront Incentive adder. Customers must fully decommission the existing fossil fuel generator and may not sell or otherwise redeploy the fossil fuel generator. The Program Administrators reserve the right to audit and inspect the customer’s site to ensure the generator has been decommissioned. Small Business Customers Small business customers are commercial and industrial customers with less than 200 kW annual peak demand. Hybrid Incentives Hybrid projects are defined as those where a single BESS will be interconnected to a single utility account where the building is used for both multifamily affordable housing (MFAH) and other 39 Priority Customers that applied to ESS prior to January 1, 2023 may participate in ISO-NE Forward Capacity Markets with approval from Program Administrators. See ESS Program Manual dated January 2, 2022 for more information. 40 Critical Facilities Definition to be used as of January 1, 2024 https://www.cga.ct.gov/2023/act/pa/pdf/2023PA-00157-R00HB-06853PA.pdf 51
  2. Page 53 of 203

    The United Illuminating Company Docket No. 26-08-01 UI Attachment 5 ESS Program Manual and Additional Information Page 53 of 203 nonresidential activities. The method used to calculate Hybrid project Upfront Incentives is as follows: 1. PAs will review all available consumption and demand data to determine a proportion of the consumption and/or demand to be applied to each use case (ex: 40% MFAH, 60% C&I). 2. The C&I incentive portion will be calculated based on the proportion of the demand and/or consumption attributable to the commercial operations (ex: if 60% C&I, then the kW / kWh ratings of the BESS and the customer’s annual peak demand will be multiplied by 60% and entered into the then-current C&I incentive calculator). 3. The Residential portion will be calculated based on the remaining proportion of the BESS at the then-current incentive level for MFAH (ex: in the above case, 40% of the BESS kW and kWh entered into the low-income residential incentive calculator). The Residential portion cannot exceed $16,000 per residential unit. 4. The C&I and Residential incentive portions will be totaled for a final approved Upfront Incentive amount but cannot exceed 50% of the total project cost. 6.2. Passive Dispatch Sec 6.2 applies only to Legacy Program customers enrolled in Passive Dispatch. CGB, in consultation with the EDCs, is responsible for developing the guidelines governing Passive Dispatch. 41 Legacy customers that received an Upfront Incentive (Residential Customers, Commercial – Fully Enrolled Customers, and Priority Customers, collectively “Passive Dispatch Participants”) must participate in the Passive Dispatch portion of the Program. 42 This requires setting the BESS to automatically store and dispatch energy through the BESS to reduce demand during summer peak periods (see Table 3). Typically, Passive Dispatch participants will not need to take any action for their BESS to respond to a Passive discharge event, as the BESS shall be pre-programmed to participate in Passive events according to the Program schedule. The residential BESS participating in Energy Storage Solutions will be required to have capability to export to the grid in order to maximize benefits to the grid.43 The conditions that allow for exemption will be detailed in separate Program materials as the factors affecting those conditions evolve. As part of the Application process, the Program Administrators will require all Passive Dispatch Participants to sign the Data Release and Terms & Conditions Agreement (see Appendix B and G) asserting compliance with the Passive Dispatch guidelines. Customers may deviate from Passive Dispatch parameters (without penalty) only under the following circumstances: During emergency events as determined by the relevant EDC. During Active Dispatch events as determined by the relevant EDC. 41 Authority, Order No. 3 in Docket No. 21-08-05. “No later than October 1, 2021, the Program Administrators shall also develop and file for the Authority’s review and approval rules guiding the distribution of the upfront incentive payment to participating electric storage system owners in Docket No. 21-08-05 consistent with the direction provided in Section III.C.” 42 If such customers seek to receive the upfront incentive and/or the upfront incentive adder. 43 Unless exception is granted, as detailed in Sec. 4 (Customer Enrollment Process) 52
  3. Page 54 of 203

    The United Illuminating Company Docket No. 26-08-01 UI Attachment 5 ESS Program Manual and Additional Information Page 54 of 203 During severe weather events as determined by the relevant EDC or by the BESS Operator, Aggregator, or OEM where there is a high likelihood of a grid outage Approved BESS Operators, Aggregators, or OEMs participating in Passive Dispatch must report all Passive Dispatch event hours during which their batteries were unable to perform due to an OEMtriggered severe storm event occurring within an uncanceled Passive Dispatch period. Such reports shall be submitted to the Program Administrators after the end of the Program’s Passive Dispatch season by October 15 of each year. As supporting evidence, Approved BESS Operators, Aggregators or OEMs must provide clear rationale and relevant data (e.g., National Weather Service alerts for the specific dates when the battery did not perform) to justify the cancellation of the Passive Dispatch hour. During Passive Dispatch events, Passive Dispatch Participants are required to discharge down to 20% of the BESS rated capacity. The Passive Dispatch window is 3 hours in duration. For example: a fully-charged BESS with 15 kWh rated energy capacity will have a maximum of 12 kWh available for Passive Dispatch and 3 kWh for reserve. During Passive Dispatch, the BESS will discharge at an average rate of 4 kWh per hour for the 3-hour duration. This is illustrated in the chart below: Figure 1: 15 kWh Battery Passive Dispatch 6.2.1. Legacy Passive Dispatch Season Performance and Claw Back Passive Dispatch Participants will be required to participate in Passive Dispatch events for ten (10) full years beginning on the date their system is connected to its respective DERMS. Participants who enroll partway through a Passive Dispatch season will not be penalized for partial participation. Rather, they will participate in the remainder of the season for Year 1, and in the beginning of the season for Year 11, totaling 10 full seasons of participation. Exiting from Energy Storage Solutions before the end of this period, or non-performance in Passive events during this period, will result in 53
  4. Page 55 of 203

    The United Illuminating Company Docket No. 26-08-01 UI Attachment 5 ESS Program Manual and Additional Information Page 55 of 203 non-compliance with Program requirements and the system owner will be required to return a prorated portion of the un-earned incentive. The claw back evaluation process will commence at the end of each summer season. The evaluation will determine whether a participating BESS scored greater than 90% for the Passive Dispatch season.44 Passive Dispatch participants are expected to make all efforts to have their BESS perform in compliance with Passive Dispatch rules. Program Administrators may periodically audit BESS that consistently perform below expectations (whether or not they comply with the Passive Dispatch Season Performance calculation below) to ensure ratepayer benefits are maximized. Table 13 [continued on the next page] describes the formula that will be used to determine each Legacy Participant’s Passive Dispatch Season Performance. 44 Legacy Passive Dispatch Participants are expected to dispatch 80% of available energy over the 3-hour Passive Dispatch window as uniformly as possible in accordance with the Passive Dispatch Season Performance criteria. 54
  5. Page 56 of 203

    The United Illuminating Company Docket No. 26-08-01 UI Attachment 5 ESS Program Manual and Additional Information Page 56 of 203 Table 13: Legacy Passive Dispatch Season Performance Formula Purpose Formula Component To ensure participants still receive credit for dispatching less than the required amount and to relax the Program’s uniform dispatch requirements, values may be less than 1 but no greater than 2. These values will then be summed across all Passive Dispatch event hours. An optimal score would be 1 for each hour 45. Σ (the energy discharged during a Passive Dispatch called event hour) / ((1/3) * (system’s available capacity at the start of the respective Passive Dispatch event – 20% of nameplate capacity)) To fully incentivize peak reduction through Active Dispatch participation46. (all Active Dispatch event hours called to replace a cancelled Passive Dispatch event in which a BESS discharged at least some portion of its available energy) [The allowable range for each Passive Dispatch hour’s score is 0 to 2 and scores that calculate as greater than 2 will be capped at 2.] + + To ensure participants are not penalized for Passive events canceled by the Program Administrators. (all Passive Dispatch hours cancelled by the Program Administrators that were not replaced by an Active Dispatch event) + To prevent penalties for OEMtriggered storm events that are beyond the customer’s control, allowing system usage during power outages. (all Passive Dispatch event hours called, and all Active Dispatch event hours called to replace a Passive Dispatch event, in which a battery could not perform because it was responding to an OEMtriggered severe storm event, provided the dispatch hour was not also cancelled by the Program Administrators) / To include all possible Passive Dispatch hours, if no events were canceled. (total possible Passive Dispatch hours in a given season) 45 The total score for this component is the sum of all individual scores from all Passive event hours unaffected by other formula components. Energy storage systems enrolled in Passive Dispatch should discharge 1/3 of their available energy during each Passive Dispatch event hour. For example, the system should discharge approximately 26.67% of its energy per hour (80%/3), assuming the system is fully charged at the start of the Passive event and accounting for the Program’s 20% reserve requirement, in order to earn full credit (three points) for the event. However, if the same system only discharges 13.34% of its nameplate capacity during the first Passive Dispatch hour, it would receive a score of 0.5 for that hour instead of a score of one. 46 As long as a system contributes any amount of energy back to the grid during each Active Dispatch event hour that replaces a canceled Passive Dispatch event, the system will receive full participation credit for those hours under the Passive Dispatch event participation formula. 55
  6. Page 57 of 203

    The United Illuminating Company Docket No. 26-08-01 UI Attachment 5 ESS Program Manual and Additional Information Page 57 of 203 The first Formula Component is used to score each Passive Dispatch hour in each season and is expressed mathematically below: 1 ( 3∗ ℎ ℎ ℎℎ ℎ − (0.2 ∗ )) Note: If score calculated above is greater than 2, the score will be capped at 2. The entire calculation used to score Passive Dispatch Season Performance is: ℎ = + + + A = Sum of Passive event scores for season B = Passive Dispatch hours replaced by Active events C = All Passive Dispatch hours canceled by the Program Administrators that were not replaced by an Active Dispatch event D = All Passive Dispatch event hours called, and all Active Dispatch event hours called to replace a Passive Dispatch event in which a battery could not perform because it was responding to an OEM-Triggered Severe Storm event, provided the Dispatch hour was not also canceled by the Program Administrators E = Total potential Passive Dispatch hours for the season Passive Dispatch Season Performance values less than 90% will trigger a claw back. When the claw back is triggered, the system owner will be responsible for a Violation Fee47 as follows: 1 − ℎ 0.9 ∗ ( ∗ 0.1) For systems that are owned by the participant (i.e. not owned by a third party), the Program Administrators may first contact the BESS Operator or OEM to investigate the cause of noncompliance. The BESS Operator or OEM can opt to pay the Violation Fee on behalf of the participant, though it is not required. For systems that are owned by a third-party, the Program Administrators will contact the system owner directly. In the event that Violation Fees are not paid as described above, available performance incentive payouts will be swept by CGB until the cost of the Violation Fee is recovered. If a clawback fee cannot be fully offset in the same Program year, the remaining amount shall roll forward to the next Program year and be deducted from any applicable performance incentives until the obligation is satisfied. If no performance incentive payouts are available to be swept or if a project’s clawback fee remains unpaid after reasonable collection efforts through performance incentives over multiple Program years, the Authority may authorize direct collection from the system owner via outreach or legal means at a later date. 47 For legacy systems enrolled mid-season, the period between the beginning of the season and enrollment in the program will not be assessed as “non-compliance” in the first year. 56
  7. Page 58 of 203

    The United Illuminating Company Docket No. 26-08-01 UI Attachment 5 ESS Program Manual and Additional Information Page 58 of 203 If the system owner is able to demonstrate a valid reason for non-compliance (e.g. equipment or software failure beyond the system owner’s control), they may appeal the Violation Fees to CGB directly. The Program Administrators are prohibited from unilaterally waiving any upfront incentive clawback fees. All clawback fee waivers require review and approval from the Public Utilities Regulatory Authority (PURA). To facilitate this process, the Program Administrators must submit all recommended clawback fee waivers to PURA for approval annually by November 1. Detailed examples of Passive Dispatch Season Performance and Violation Fees are provided at www.energystorageCT.com/contractor-resources. Passive Dispatch Participants will also be automatically enrolled in Active Dispatch. If a pattern of consistent non-performance of a particular BESS OEM, Operator, or Aggregator is identified, the Program Administrators will work with that party to improve performance. In the event that the OEM, Operator, or Aggregator is unable to improve performance due to technical issues, the Program Administrators reserve the right to suspend the OEM, Operator, or Aggregator per the process outlined in Section 4. 6.3. Calculation of Upfront Incentive Sec 6.3 applies only to Legacy Program customers enrolling in Passive Dispatch. The calculation of the Upfront incentive is primarily based on the nameplate energy capacity (kWh) of the BESS, with some limiting factors. The upfront residential incentive is calculated based on the minimum of the following three formulas: Residential Formula 1: BESS rated energy capacity (kWh) * [Applicable $/kWh rate at time of incentive application]48 Residential Formula 2: 50% of BESS total installed cost Residential Formula 3: Maximum per-residential unit incentive of $16,00049 The upfront C&I incentive is calculated based on the minimum of the following two formulas: C&I Formula 1: BESS rated energy capacity (kWh) * [Rate applicable to demand tier]50. C&I Formula 2: 50% of BESS total installed cost C&I systems are limited in power (kW) eligible to receive an upfront incentive to 150% of the customer’s annual peak demand or 2 MW, whichever is greater. The following illustrative examples demonstrate how incentive calculations work. These examples assume Residential Step 1 incentive rates from Table 8 and Commercial & Industrial 0-50MW Capacity Block incentive rates from Table 10. For additional examples and a calculator tool, along with the latest incentive rates and schedule, please visit the Energy Storage Solutions website. Example 1 - In the case of a 5 kW, 13.5 kWh battery with an installed cost of $20,000, for a standard Residential Customer: 48 kWh level as determined depending on the project type and incentive level as provided in Table 8. Residential Formula 3 does not apply to Multifamily Affordable Housing installations 50 kWh level as determined depending on the project type and incentive level as provided in Table 10. 49 57
  8. Page 59 of 203

    The United Illuminating Company Docket No. 26-08-01 UI Attachment 5 ESS Program Manual and Additional Information Page 59 of 203 13.5 kWh * $250/kWh, or $3,375 50% of $20,000, or $10,000 Maximum incentive of $16,000 The customer would receive an upfront incentive of $3,375. Example 2 – In the case of two batteries that add up to 15.2 kW, 36 kWh with an installed cost of $30,000, for a grid-edge Residential Customer: 36 kWh * $250/kWh, or $9,000 + 50% adder = $13,500 50% of $30,000, or $15,000 Maximum incentive of $16,000 The customer would receive an upfront incentive of $13,500. Example 3 – In the case of two batteries that add up to 10 kW, 27 kWh with an installed cost of $30,000, for a low-income Residential Customer: 27 kWh * $600/kWh, or $16,200 50% of $30,000, or $15,000 Maximum incentive of $16,000 The customer would receive an upfront incentive of $15,000. Example 4 – In the case of a 250 kW, 675 kWh battery for a medium-sized Commercial customer with an annual peak demand of 240 kW and an installed cost of $378,000 (Tranche 3 Step 1) 675 kWh * $159.25/kWh, or $107,494 50% of $378,000, or $189,000 The customer would receive an upfront incentive of $107,494. Example 5 – In the case of a 3 MW, 10 MWh battery for a large-sized Commercial grid-edge customer with an annual peak demand of 2 MW and an installed cost of $2,500,000 (Tranche 3 Step 1) 10,000 kWh * $91/kWh, or $910,000 +25% grid-edge adder = $1,137,500 50% of $2,500,000, or $1,250,000 The customer would receive an upfront incentive of $1,137,500 Example 6 – In the case of a 1.4 MW, 5 MWh battery for a small-sized Commercial small business customer with an annual peak demand of 180 kW and an installed cost of $1,950,000 (Tranche 3 Step 1) System is > 150% of customer’s peak demand, but < 2 MW. Incentive cap not exceeded. Tiered incentive calculation51 + 25% small business adder = $741,406 50% of $1,950,000, or $975,000 51 Use current ESS Calculator available at www.energystorageCT.com/contractor-resources for a detailed breakdown of the tiered incentive calculation. 58
  9. Page 60 of 203

    The United Illuminating Company Docket No. 26-08-01 UI Attachment 5 ESS Program Manual and Additional Information Page 60 of 203 The customer would receive an upfront incentive of $741,406 Example 7 – In the case of a 3 MW, 15 MWh battery for a large-sized Commercial customer with an annual peak demand of 750 kW and an installed cost of $3,500,000 (Tranche 3 Step 1) System is not capable of dispatching 80% of its capacity in a 3-hour Passive Dispatch window System is > 150% of customer’s peak demand and > 2 MW, exceeding incentive cap 150% of peak demand = 1.125 MW. Capped system size is 2 MW The project must be redesigned and resubmitted. For Eligible BESS Equipment that was approved prior to the Passive Dispatch window changing from 5 hours to 3 hours, (“Legacy Eligible BESS Equipment”), customers may apply for a prorated upfront incentive that is calculated based on the portion of the BESS that can comply with the current Passive Dispatch rules. Example 8 – In the case of a 5 kW, 30 kWh battery for a residential customer, the battery is not capable of discharging 80% of its nameplate capacity in 3 hours for 90% seasonal participation due to the limitation of the inverter size. The customer may enroll up to 20.83 kWh of capacity: 5 kW * 3 hours / 80% discharge / 90% minimum participation = 20.83. This formula may also be stated as [Inverter Size] * 4.166 for the minimum threshold of participation, or [Inverter Size] * 3.75 to allow 10% buffer for missed Passive Dispatch events. 6.4. Calculation of Enrollment Incentive (Effective 4/1/26) Sec 6.4 applies only to Construct 5 customers enrolling on or after 4/1/26. The calculation of the Enrollment Incentive is based on the nameplate energy capacity (kWh) of the BESS. Both residential and commercial Enrollment Incentives are calculated based on the following rates: Customer Category Enrollment Incentive Rate* Residential (Non-Grid Edge) $30/kWh Residential (Grid Edge) $130/kWh Commercial (Non-Priority) Commercial (Priority) N/A $10/kWh *Enrollment incentives are defined based on rated energy capacity (kWh) For additional examples and a calculator tool, along with the latest incentive rates and schedule, please visit the Energy Storage Solutions website. Example 1 - In the case of a 5 kW, 13.5 kWh battery for a standard non-grid edge residential customer: 59
  10. Page 61 of 203

    The United Illuminating Company Docket No. 26-08-01 UI Attachment 5 ESS Program Manual and Additional Information Page 61 of 203 13.5 kWh * $30 The customer would receive an upfront incentive of $405. Example 2 - In the case of a 5 kW, 13.5 kWh battery for a grid edge residential customer: 13.5 kWh * $130 The customer would receive an upfront incentive of $1,755. Example 3 - In the case of a 7 MW, 15 MWh battery for a grid edge commercial customer: 15,000 kWh * $10 The customer would receive an upfront incentive of $150,000. 6.5. Active Dispatch Sec 6.1 applies to both Legacy Program customers and Construct 5 Customers. Sec 6.5 applies to all customers enrolling in Energy Storage Solutions, including those enrolled after April 1, 2026. Active Dispatch Participants will be enrolled and eligible to participate in Active events for ten (10) full years beginning on the date their system is connected to its respective DERMS. Customers can enroll at any time. A customer who enrolls part way through a season may participate in the remainder of the season for Year 1, and in the beginning of the season for Year 11, totaling 10 full seasons of participation. Exiting from Energy Storage Solutions Active Dispatch before the end of this period or declining events will not yield any violation. When an Active Dispatch event is called, the Passive Dispatch event for that day is cancelled. In the situation that an Active Dispatch event is called by the EDCs during the Passive Dispatch hours, the Active Dispatch shall take precedence over the Passive Dispatch event. Table 14: Summer and Winter Active Dispatch Parameters Season Dates Number of Events Event Duration Timing Summer June 1 – September 30 30-60 1 - 3 hours 12:00 PM to 9:00 PM Winter November 1 – March 31 1-5 (Legacy) 1-10 (Construct 5) 1 - 3 hours 12:00 PM to 9:00 PM The incentive rate tied to performance during Active Dispatch events for each option is shown in Table 15 and Table 16. Table 15: Active Dispatch Performance Incentive for Legacy Customers (1/1/22 – 3/31/26) BESS Performance Period Years 1 – 5 Years 6 – 10 Summer Performance Incentive ($/kW)* $200 $115 Winter Performance Incentive ($/kW)* $25 $15 60

Text of 2026-11-16 UI Attachment 5 - EV Program Materials and Additional Information #26-08-01.pdf

Extracted from the file · 2 pages · 6,256 characters

Text of 2026-11-16 UI Attachment 6 - Annual RPS Compliance Report - Cover Ltr #26-08-01.pdf

Extracted from the file · 2 pages · 3,261 characters

Text of 2026-11-16 UI Attachment 6 - Annual RPS Compliance Report RPS Template Exhibit A #26-08-01.xlsx

Sheet names, column headings and text cells; numbers left out

Text of 2026-11-16 UI Attachment 6 - Annual RPS Compliance Report RPS Template Exhibit B C and D #26-08-01.xlsx

Sheet names, column headings and text cells; numbers left out

Text of 2026-11-16 UI Attachment 6 - Annual RPS Compliance Report RPS Template Exhibit E #26-08-01.xlsx

Sheet names, column headings and text cells; numbers left out · first 300,000 characters

Text of 2026-11-16 UI Attachment 6 - Annual RPS Compliance Report RPS Template Exhibit F #26-08-01.pdf

Extracted from the file · 1 page · 528 characters

Text of 2026-11-16 UI Attachment 7 - Exhibit Y Ten Year Cost History - BETP-001 #26-08-01.xlsx

Sheet names, column headings and text cells; numbers left out

Text of 2026-11-16 UI Attachment 8 - CEOP-VRO Program Materials #26-08-01.pdf

Extracted from the file · 2 pages · 4,800 characters