Page 14 of 28
Docket No. 26-08-03 Page 12 expressly stating that the above provision addresses the metering and billing configuration for Buy-All projects and is not an eligibility requirement. Id.3 In the Year 3 proceeding, several stakeholders recommended expanding the Rooftop Project definition to allow a project to utilize multiple rooftops located at the same Project Site. Year 3 Decision, p. 60; Interrog. Resp. CAE-6. At that time, the EDCs were open to a modified definition but proposed instead limiting rooftop projects to a set of rooftops served by the same Revenue Meter; the Authority accepted the EDCs’ proposed redlines. Year 3 Decision, p. 61. The EDCs state that their proposal was intended to maintain “a clear relationship between the project and the applicable electric service and metering arrangement.” Interrog. Resp. CAE-6. However, the EDCs would not oppose modifying the Rooftop Project definition to allow a set of rooftops located at the same Project Site to qualify without requiring that the rooftops be served by the same Revenue Meter. Interrog. Resp. CAE-7. The EDCs note that, for Buy-All projects, the Production Meter serves as the Revenue Meter for purposes of Program billing and settlement, so the presence of multiple customer Revenue Meters on the underlying building or site does not necessarily mean that the project itself is measured or settled through multiple Revenue Meters. Id. Accordingly, the EDCs recommend that “any such revision clearly establish the applicable eligibility criteria and distinguish the physical location of the project from the electric service and metering arrangements associated with the site.” The Authority finds that the EDCs’ proposed revision to Section 8.1.1 of the Program Manual will improve the clarity of metering and billing arrangements applicable to Buy-All projects. Additionally, the Authority determines that modifying the definition of “Rooftop Project” by allowing a project to be installed on top of a set of rooftops located on a single Project Site will further the intent of General Statutes § 16-244z(f) to maximize solar systems on underutilized rooftop space. The EDCs shall modify the Program Manual accordingly and may propose language to distinguish the physical location of the project from the site’s electric service and metering arrangements. With the addition of the changes discussed above, the Authority finds that the EDCs’ proposed changes to the program documents will further the Program Objectives by improving clarity for participants and approves the EDCs’ proposed redline changes to the program documents. The EDCs shall file updated clean and redlined program 3 The EDCs’ propose the following revision: “8.1.1. Projects shall be equipped with a Production Meter to measure the amount of energy produced from Customer Projects, which will be located at or behind the EDC’s Delivery Point. In addition, there is a Revenue Meter that measures energy exports and imports to and from the distribution system. For Buy-All Projects, the Production Meter shall also serve as the EDC Revenue Meter for purposes of associated billing, and no separate Revenue Meter shall be required. This provision addresses the metering and billing configuration for Buy-All Projects and is not an eligibility requirement.” Interrog. Resp. CAE-5.Page 15 of 28
Docket No. 26-08-03 Page 13 documents, incorporating all direction in this Decision, for review and approval in the instant proceeding by January 1, 2027. V. CONCLUSION AND ORDERS A. CONCLUSION In this Decision, the Authority explores and approves several changes to the NRES Program to better serve the Program Objectives. The Decision provides several additional clarifications for stakeholders and approves price caps for applications received in calendar year 2027. The Decision also provides rulings to Motion Nos. 3, 4, and 5. B. EXISTING AND NEW ORDERS For the following Orders, the Company shall file an electronic version through the Authority’s website at www.ct.gov/pura. Submissions filed in compliance with the Authority’s Orders must be identified by all three of the following: Docket Number, Title and Order Number. Compliance with orders shall commence and continue as indicated in each specific Order or until the Company requests and the Authority approves that the Company’s compliance is no longer required after a certain date. All Orders requiring Authority review and approval shall be submitted as a motion. The below standing orders are a summation of prior orders related to the NRES Program that continue to apply. In some instances, the Authority has amended those standing orders with redline edits. The below new orders apply on a going forward basis. 1. Standing Orders 1. Reference Decision, June 30, 2021, Docket No. 20-07-01, p. 43: For Program Years 2 through Year 6, the Authority directs the EDCs to hold two solicitations annually and to submit for the Authority’s review and approval the RFP schedules for the following year in the appropriate annual review docket, discussed in Section III.K [of the 20-07-01 Decision]. 2. Reference Decision, June 30, 2021, Docket No. 20-07-01, Order No. 15, p. 53: No later than April 1, 2022, and at least monthly thereafter [until the NRES Program stops accepting new bid submissions], each EDC shall post a list to their website that shows the most current small zero emission application queue. The project list shall anonymize project data, but include the bid number, proposed project size, and the date the bid was received, and the total small zero emission megawatts remaining for the given calendar year. 3. Reference Decision, June 30, 2021, Docket No. 20-07-01, Order No. 16, p. 53: Starting August 1, 2022, [and annually thereafter until the NRES Program stops accepting new bid submissions,] the EDCs shall submit in the relevant annual program review docket (Docket No. 22-08-03, 23-08-03, etc.) bid preferences and price caps for the subsequent program year. [The bid preferences shall be submitted for Authority review and approval. The bid price caps shall be submitted as compliance utilizing the methodology discussed and approved in Section IV.B.Page 16 of 28
Docket No. 26-08-03 Page 14 of this Decision. Since the results of the Year 2 August solicitation will not be available when the price caps are filed, the EDCs shall use the results of the penultimate August solicitation (i.e., for Year 3, the Year 1 August solicitation), in addition to the most recent February solicitation, when determining the bid price caps.] 4. Reference Decision, June 30, 2021, Docket No. 20-07-01, Order No. 17, p. 53: No later than January 1, 2023, the EDCs shall create a webpage that provides summary data for the Non-Residential Tariffs Program consistent with the direction provided in Section III.L.2., including data fields determined in consultation with DEEP and the CGB. Such data shall be updated not less than quarterly. Ultimately, such webpage shall live on the EnergizeCT website and include all data relevant to the programs authorized in this Decision and the Residential Interim Decision, in an easily understood and digestible form. 5. Reference Decision, Nov. 3, 2021, Docket No. 21-08-03, p. 25: Not less than annually [until the NRES Program stops accepting new bid submissions], the Authority will publicly release summary statistics for the Program. Similarly, the EDCs shall only include summary installed cost data via the online data portal developed pursuant to Order No. 17 of the Non-Residential Tariff Decision. The Authority retains the right to modify this requirement in future Program years. 6. Reference Decision, June 30, 2021, Docket No. 20-07-01, Order No. 18, p. 53: In filing a motion seeking approval of the [partially executed tariff agreements] from each Non-Residential Tariffs Program solicitation, each EDC shall provide a narrative summary of such solicitation as outlined in Section III.L.3 of the Decision (Summary Report). Such a motion shall be filed in the annual program review docket opened the previous year (e.g., a motion seeking approval of projects selected in Program Year 1 in 2022 should be filed in Docket No. 21-08-03). Additionally, reference Docket No. 21-08-03, Motion No. 42, dated June 22, 2022, p. 3: At the conclusion of the rolling award notification process, submit as part of its compliance filing for Order No. 18, a listing of all [partially executed tariff agreements] for which award acceptance documentation has been ultimately completed. Additionally, reference Docket No. 21-08-03, Final Decision, dated November 3, 2021, p. 16: Further, each EDC shall submit the results of the February solicitation upon completion, requesting the Authority to issue an interim approval of the results. Finally, each EDC shall file the solicitation results for the entire Program Year, inclusive of both the February and August solicitations, no later than December 31 of the solicitation year. Both the results of the February and August solicitations shall be filed as motions for Authority review and approval in the prior year’s Annual Review proceeding. For example, the projects selected through the Year 1 Non-Residential Tariff Program solicitation should be filed as a motion in this proceeding, Docket No. 21-08-03. 7. Reference Decision, June 30, 2021, Docket No. 20-07-01, Order No. 19, p. 53: Not [later] than 60 days after the Authority’s approval of the selected bids [in eachPage 17 of 28
Docket No. 26-08-03 Page 15 NRES solicitation], each EDC shall provide the Program Summary Data as outlined in Section III.L.3 of the [20-07-01] Decision. Such data shall be filed in the docket through which the Authority approved the selected bids. 8. Reference Decision, June 30, 2021, Docket No. 20-07-01, Order No. 20, p. 53-54: Not [later] than 60 days after the Authority’s approval of the selected bids, the EDCs shall compile load data on customers that bid into the program. The data shall include the underlying tariff, customer class, and interval data as available. Such data shall be filed in the docket through which the Authority approved the selected bids. 9. Reference Decision, Nov. 3, 2021, Docket No. 21-08-03, p. 15: Pursuant to General Statutes § 16-244z(a)(2), each EDC is required to file projects, selected through the competitive procurement authorized in the Non-Residential Tariff Decision, for Authority approval “[not] later than July 1, 2022, and annually thereafter.” 10. Reference Decision, Nov. 3, 2021, Docket No. 21-08-03, p. 16: Each EDC shall file the solicitation results for the entire Program Year, inclusive of both the February and August solicitations, no later than December 31 of the solicitation year. Both the results of the February and August solicitations shall be filed as motions for Authority review and approval in the prior year’s Annual Review proceeding. For example, the projects selected through the Year 1 NonResidential Tariff Program solicitation should be filed as a motion in this proceeding, Docket No. 21-08-03. 11. Reference Decision, June 30, 2021, Docket No. 20-07-01, p. 46: Based on the Authority’s experience with the LREC/ZREC RFPs, the Authority orders the EDCs to inform the Authority, on the first day of issuance, that disqualified bidders and winning bidders have been notified in the applicable annual program review docket. Such notification shall take the form of a sample notification provided to disqualified bidders (e.g., an anonymized email sent to disqualified bidders) and winning bidders (e.g., an anonymized email sent to winning bidders) filed as compliance in the annual review docket initiated pursuant to Section III.K [of the 20-07-01 Decision.] [Further, the notification to disqualified or unselected bidders shall inform bidders of the process for obtaining performance assurance fee refunds, including a link to any refund forms or payment websites. Such email shall also include a warning that a performance assurance fee refund before the Authority’s final acceptance of the EDCs’ chosen bids will result in bid withdrawal from the solicitation in which the bid was first received.] 12. Reference Decision, Nov. 9, 2022, Docket No. 22-08-03, Order No. 14, p. 40: No later than [September 14], 2022, and annually thereafter for the duration of the NRES Program, the EDCs shall file as compliance with the Authority updated an updated netting bid price cap calculator, as described in Section IV.B. of this Decision, using retail rates from the past 12 months. [Moreover, since the resultsPage 18 of 28
Docket No. 26-08-03 Page 16 of the Year 2 August solicitation will not be available when the calculator is filed, the EDCs shall use the results of the penultimate August solicitation (i.e., for Year 3, the Year 1 August solicitation), in addition to the most recent February solicitation, when determining the Netting bid price caps.] 13. Reference Decision, Nov. 9, 2022, Docket No. 22-08-03, Order No. 18, p. 41: No later than February 1, 2023, and annually thereafter [until the NRES Program stops accepting new bid submissions], the EDCs shall hold at least one informational webinar with Program stakeholders on the NRES bidding solicitation process. Additionally, [prior to the start of] each solicitation cycle, and annually thereafter, the EDCs shall hold at least one bidders’ conference [prior to the start of each] solicitation window (beginning in February and August). [The EDCs shall also review how to successfully submit an interconnection application, the NRES interconnection process, guidelines, and all acceptable configurations for both Netting and Buy-All projects during each bidders’ conference.] At least 30 days’ notice shall also be provided to Program stakeholders prior to each bidders’ conference on the Program website. The EDCs shall file as compliance with the Authority the dates and information related to the webinar and bidders’ conferences at least 10 days before each event is held. 14. Reference Decision, Nov. 9, 2022, Docket No. 22-08-03, Order No. 21, p. 42: No later than August 1, 2023, and at least annually thereafter until the NRES Program is no longer active, the EDCs shall file for Authority review, modification, and approval, recommended programmatic changes, and updated Program Manual (both a redline and clean version), guidelines, and other resources to reflect the most recent program information and Authority orders and/or rulings. Such recommended changes and associated program documents shall be accompanied by a narrative document explaining how the recommended changes better achieve the Program Objectives. The Authority further directs the recommended programmatic changes, and the updated rules, guidelines, and other resources to be filed in the appropriate annual review docket (e.g., changes to be enacted starting in 2024 should be filed in Docket No. 23-08-03). 15. Reference Decision, Nov. 9, 2022, Docket No. 22-08-03, Order No. 22, p. 42: No later than 60 days prior to a change made to the methodology used in developing capacity maps, the EDCs shall provide notice of the upcoming change on the relevant webpage in order to alert project developers and relevant stakeholders. 16. Reference Decision, Feb. 22, 2023, Docket No. 22-08-01, 2022 Clean and Renewable Energy Program Data and Report, pp. 4-5: No later than January 5, 2024, and annually thereafter [until the NRES Program stops accepting new bid submissions], the EDCs shall provide an updated Frequently Asked Question document and Fact Sheet for the NRES Program that reflects the program modifications as directed in the most recent Final Decision issued through the NRES Program Annual Review proceeding, Docket No. XX-08-03.Page 19 of 28
Docket No. 26-08-03 Page 17 17. No later than August 1, 2024, and annually thereafter [until the NRES Program stops accepting new bid submissions], each EDC shall file as compliance in the most recent annual review docket (i.e., in 2024, Docket No. 24-08-04) a NRES Interconnection Report. The Report shall consist of a summary of the state of interconnection for all approved NRES projects to date and shall include, at a minimum, (1) the interconnection status of each NRES project; (2) the EDC interconnection approval due date for each project per approved interconnection guidelines; (3) the number of days from when all required interconnection materials were submitted to the utility for each project to interconnection approval, or to when the data was pulled for the report, if interconnection approval has not been granted; (4) the date for which data was pulled for the report; (5) the project attrition rate; (6) a list of the most common reasons for interconnection delays; and (7) EDCproposed solutions for each of the most common reasons delaying interconnection. 18. No later than August 1, 2024, and annually thereafter [until the NRES Program stops accepting new bid submissions], the EDCs shall file in the current annual review docket (i.e., in 2024, Docket No. 24-08-03) the average annual customer savings for each kilowatt of solar installed for all Distressed Municipality projects using the information provided by the Consumer Protection and Disclosure Form. 19. No later than August 1, 2025, and annually thereafter for the duration of the NRES Program, the Authority directs each EDC to file in the most recent NRES annual review docket (i.e., in 2025, Docket No. 25-08-03) an updated proposed nonrefundable application fee to cover the administrative costs associated with running the NRES Program, based on the most recent application numbers and administrative cost data. The filing shall include a total estimate of all NRES administrative costs for the prior year, in addition to the total nonrefundable fees collected by each EDC via NRES Program applications. 20. As soon as practicable after approval, the ombudsman shall file as compliance any approved extension requests, including whether each request was granted or denied, in the NRES annual review docket related to the solicitation year in which the project was selected (e.g., Docket No. 22-08-03 if the project was selected in Year 2 of the Program, i.e., calendar year 2023). The ombudsman shall also annually file a summary of any extension request denials in the relevant NRES proceeding by August 1. 21. No later than seven calendar days after the full MW capacity for the school category has been reached [in each Program year], if the full capacity is awarded prior to the end of the August solicitation, the EDCs shall file as compliance with the Authority in the most recent annual review proceeding a notification once the school category capacity has been filled, as well as make prominent updates to any informational webpages associated with the NRES solar carveout offering.Page 20 of 28
Docket No. 26-08-03 Page 18 2. New Orders 22. No later than January 1, 2027, the EDCs shall file for Authority review and approval in this proceeding updated NRES Program documents, including the Program Manual and an updated Netting Calculator, incorporating all of the approved modifications authorized in this Decision. Such filing shall include both a clean and a redlined version of all NRES Program documents.Page 21 of 28
APPENDIX A: List of Docket Participants Eric Annes Department of Energy and Environmental Protection Ten Franklin Square New Britain, CT 06051 DEEP/BETP Bernadette Antaki Michaud Law Group, LLC 515 Centerpoint Drive, Suite 503 Middletown, CT 06457 Solar Alliance for Virtual Energy Bernadette Antaki Michaud Law Group, LLC 515 Centerpoint Drive, Suite 503 Middletown, CT 06457 Melin Energy, LLC Obinna Anugweje, Esq. Staff Attorney Department of Energy & Envrionmental Protection 10 Franklin Square Nw Britain, CT 06051 Prabisha Bhandari Office of Consumer Counsel 10 Franklin Square New Britain, CT 06051 Cal Brown Sustainable Energy Advanage, LLC Sergio Carrillo Connecticut Green Bank 845 Brook Street, Building #2 Rocky Hill, CT 06067 Emma Cimino Acting Commissioner Department of Energy and Environmental Protection 79 Elm Street Hartford, CT 06106-5127 DEEP/BETP OCC SEA, LLC CT Green Bank DEEPPage 22 of 28
Docket No. 26-08-03 Page 2 Claire E. Coleman Consumer Counsel Office of Consumer Counsel 10 Franklin Square New Britain, CT 06051 OCC Amanda De Vito Trinsey, Esq. Couch White, LLP 540 Broadway P.O. Box 22222 Albany, NY 12201-2222 CIEC Jordan Garfinkle Sr. Policy Manager, NE Bloom Energy Corporation 4353 N 1st Street San Jose, CA 95134 Bloom Energy Corp. William Gary National Fuel Cell Research Center University of Californai, Irvine Irvine, CA 92697 Nat'l Fuel Cell Research Ctr Dylan J. Gillis Michaud Law Group, LLC 515 Centerpoint Drive, Suite 503 Middletown, CT 06457 TRITEC Americas, LLC Dylan J. Gillis Michaud Law Group, LLC 515 Centerpoint Drive, Suite 503 Middletown, CT 06457 Solar Alliance for Virtual Energy David Giordano Federal & State Government Relations Doosan Fuel Cell America, Inc. 195 Governor's Highway South Windsor, CT 06074 Doosan Fuel Cell America, Inc.Page 23 of 28
Docket No. 26-08-03 S. Jay Goodman, Esq. Partner Couch White, LLP 540 Broadway P.O. Box 22222 Albany, NY 12201 Page 3 CIEC Justin Gundlach Institute of Policy Integrity at NYU School of Law 139 MacDougal Street, 3rd. Floor New York, NY 10012 IPI at NYU School of Law Jeffrey Hintzke Greenskies Clean Energy, LLC 127 Washington Avenue West Building, Garden Level North Haven, CT 06743 Greenskies Clean Energy, LLC Lee D. Hoffman Pullman & Comley, LLC 90 State House Square Hartford, CT 06103 Gravity Renewables, Inc. Alexandrea Isaac, Esq. Senior Legal Counsel FuelCell Energy, Inc. 3 Great Pasture Road Danbury, CT 06810 FuelCell Energy, Inc. Keenia Joseph Spark Energy, LLC 12140 Wickchester Lane, Suite 100 Houston, TX 77079 Spark Energy, LLC Sean Kehoe Associate Attorney General Office of the Attorney General 165 Capitol Avenue Hartford, CT 06106 AG
As listed on the current system
Draft Decision, 10/27/2026 [26-08-03]